HomeMy WebLinkAboutPW Rotary Manor Culvert Replacement PPTRotary Manor Culvert Replacement Project
December 5, 2022Slide 1
Rotary Manor
Senior Community
Blue Lines = Storm Drainage System
Rotary Manor Culvert Replacement Project:
CEQA Mitigated Negative Declaration
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 2
Public Hearing Overview
•Project Summary
•CEQA Mitigated Negative Declaration
–Potentially Significant Impacts
–Comments Received
•Hearing any additional public comments
•Vote on Resolution Items
–Adopt the Initial Study/Mitigated Negative Declaration and
Mitigation Monitoring and Reporting Program
–Authorize staff to proceed with final design
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 3
Rotary Manor
Senior Community
Blue Lines = Storm Drainage System
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 4
San Rafael Creek
Downtown
Canal
Rotary Manor
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 5
8’x6’ Reinforced
Concrete Box Culvert
Arch Corrugated
Metal Pipe
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 6
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 7
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 8
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 9
CEQA: Mitigated Negative Declaration
Initial Study Completed
-Determine any potentially significant environmental impacts
Public Review Period
-October 26 to November 30, 2022
-Noticed in Marin IJ and mailers sent to owners/occupants within a
300-ft radius
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 10
CEQA: Potentially Significant Impacts
1.Biological Resources
2.Tribal Cultural Resources
3.Cultural Resources
4.Noise
5.Mandatory Findings of Significance
All potential impacts can be reduced to less than
significant
Mitigation Measures
-Preconstruction biological survey
-Environmental awareness training provided to contractor
-Procedures to be followed if cultural resources are found
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 11
CEQA: Comments Received
One comment letter received from State Fish & Wildlife
1.Obtain regulatory permits
2.Suggest potential impacts to certain special-status plants
and foothill yellow-legged frog is more than unlikely
Staff will continue to work with State Fish & Wildlife thru their
review of the submitted permit application
Rotary Manor Culvert Replacement Project
December 5, 2022Slide 12
Next Steps
1.Finalize Design
2.Obtain Regulatory Permits
3.Estimated Construction Start: Spring 2023