HomeMy WebLinkAboutCC Resolution 9781 (Merrydale Overcrossing Project)RESOLUTION NO. 9781
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN
RAFAEL AUTHORIZING AMENDMENT TO THE AGREEMENT
WITH HARRIS & ASSOCIATES FOR AN ADDITIONAL $150,000
ON THE MERRYDALE OVERCROSSING PROJECT.
WHEREAS, an agreement was entered into with Harris & Associates for
construction management services for the Merrydale Overcrossing project; and
WHEREAS, extra time was required to complete the project due to heavy
amount of rains, and the number of changes made to the contract; and
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of
San Rafael to authorize the Director of Public Works to execute an Amendment to the
Agreement in a form to be approved by the City Attorney between the City of San Rafael
and Harris & Associates in an amount not to exceed $150,000.
I, JEANNE M. LEONCINI, Clerk of the City of San Rafael, hereby
certify that the foregoing resolution was duly and regularly introduced and adopted at a
regular meeting of the Council of said City on the 21s' day of January, 1997, by the
following vote, to wit:
AYES: COUNCILMEMBERS• Heller, Miller, Phillips & Vice—Mayor Cohen
NOES: COUNCILMEMBERS: None
ABSENT: COUNCILMEMBERS: Mayor Boro
H E6)41'r,City , lerk
AMENDMENT TO AGREEMENT
for
MERRYDALE OVERCROSSING PROJECT
PROJECT NO. 07.02.26.10.01
This Amendment to Agreement made and entered into this 21" day of January, 1997, by and between
the CITY OF SAN RAFAEL (hereinafter "CITY"), and HARRIS & ASSOCIATES, INC. (hereinafter
"CONTRACTOR").
RECITALS
WHEREAS, on March 7, 1994, the CITY accepted a proposal from CONTRACTOR for
construction management services for the Merrydale Overcrossing Project; and entered into an
Agreement; and
WHEREAS, under Section C of the subject Agreement, "Payment", the CITY
agreed to make payments of $678,509 to CONTRACTOR, as described in "Exhibit A"; and
WHEREAS, all other terms and conditions of subject Agreement remain unchanged;
AMENDMENT TO AGREEMENT
NOW, THEREFORE, the parties hereby agree as follows:
1. PAYMENT.
The payment by CITY to CONTRACTOR described under Section C, Exhibit A of the subject
Agreement shall be increased in an amount not to exceed $150,000. The total amount paid by CITY
to CONTRACTOR shall now not exceed $828,509.
IN WITNESS WHEREOF, the parties have executed this Agreement as of the day, month, and year
first above written.
COF AN RAF L
t: fi&?"� A
David M. Bernardi, P.E.
Director of Public Works
ATTEST:
C Clerk Jean q M. Leoncini
APPRO D
CI`T'Y Atto610y
CONTRAC AOR–HARRI & ASSOCIATES, INC.
By:
Name: 7"—n -
Title:
COPY
RECEIVED
DEC 16 1996
CITYIOF SCAN RAFAE
December 10, 1996
Mr. Dave Bernardi
Director of Public Works
Department of Public Works
City of San Rafael
P.O. Box 151560
San Rafael, California 94915-1560
Re: Merrydale Overcrossing
Dear Dave:
Harris & Associates
Engineers
Architects
Construction
Managers
The following changed conditions to the construction contract for the Merrydale Overcrossing project
have necessitated this request for a budget amendment to our agreement dated, March 7, 1994:
The original proposed budget for the CM & inspection services for the Merrydale
Overcrossing and the northbound onramp was based on a 15 month construction duration
from April 1, 1994 through June 30, 1995. The actual project duration is approaching 28
months (from Sept. 1, 1994 through December 31, 1996). We are projecting our continued
services through the end of December to closeout the project. This extension of time, in
part, is due to the following reasons.
2. The project has spanned through two winter seasons. The first winter season of 1994-1995
we provided as needed inspection services of the temporary stormwater protection facilities
during this agreed to winter suspension of work (from 1/1/95 through 5/8/95). The following
winter season of 1995-1996 proved inefficient for construction progress (40 rain days
impeded construction progress). We attempted to minimize our level of inspection and
administration effort, but we needed to be responsive to the contractor's work schedule.
3. To date there have been 38 change orders issued for $507,062 of additional work. These
changes include 34 additional days added to the contractor's contract requirement. A
possible 19 additional days may be considered for the required safety changes to the
northbound onramp. Currently our contract calendar day records reflect a contract
completion date of August 8, 1996 which includes the additional 34 days.
4. Of the 38 change orders, 17 of the change orders have been necessitated due to
changes requested by Caltrans or allowed by Caltrans specifications totalling
$414,939. These include:
CCO #1- Flagging
CCO #2- Structure seismic design changes
CCO #5- Right -of way delay due to surveying delay
CCO #7- Extension of time for holidays
CCO #9- Prepartions for winter suspension
220 Mason Circle Concord, California 94520 (510) 82.7 4900 FAX (5 10) 8214982
Mr. Dave Bernardi
Director of Public Works
Department of Public Works
City of San Rafael
October 29, 1996
Page 2
CCO #10- Modifications to detour plans
CCO #12- Maintain and repair detour
CCO #13- Add traffic control, signing, striping and k -rail for n/b on-ramp.
CCO #15- Revise lighting and traffic signal plans
CCO #23- Provide for right-of-way obligations
CCO #25- Install changes required for stormwater pollution prevention
CCO #28- Provide temporary detours in lieu of median crossovers
CCO #30- Remove unsuitable materials
CCO #32- Install irrigation backflow preventers
CCO #33- Drainage modifications and unsuitable materials
CCO #35- Install conduit for irrigation controllers
CCO #38- Modify drainage systems on the n/b on-ramp
5. Caltrans materials testing procedures did not allow for prompt response for concrete
quality assurance tests. Harris retained Signet Testing Laboratories to assist in
these concrete sampling and testing procedures. To date approximately $6,000 has
been expended for these services which were not budgeted for in our agreement.
I request your approval of a budget amendment of $150,000.00 to complete our project services.
This amendment will allow us to substantially complete and prepare a proposed final estimate and
final report by December 31, 1996. In addition, approximately $20,000 will remain as contingency
for Hams' services to assist the City in outstanding project issues beyond the first of the new year.
Very truly yours,
HARRIS & ASSOCIATES
Gregory C
Vice Pres
93065
cc: Jim Parmley
Chuck Flynn
Harris & Associates