HomeMy WebLinkAboutCC Resolution 8378 (Merrydale Overcrossing)as follows: RESOLUTION NO. 8378 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN RAFAEL AUTHORIZING THE SIGNING OF A "REQUEST FOR ADDITIONAL AUTHORIZATION AND COST INCREASES" IN THE MERRYDALE OVERCROS- SING DESIGN CONTRACT WITH WILSEY & HAM IN THE AMOUNT OF $77,200. THE CITY COUNCIL OF THE CITY OF SAN RAFAEL RESOLVES The Director of Public Works is authorized to execute, on behalf of the City of San Rafael, a 'Request for Additional Authorization and Cost Increases' in the amount of $77,200 with Wilsey & Ham for additional design services in the Merrydale Overcrossing Project. I, JEANNE. M. LEONCINI, Clerk of the City of San Rafael, hereby certify that the foregoing resolution was duly and regularly introduced and adopted at a regular meeting of the Council of said City on Monday, the 15th day of April, 1991, by the following vote, to wit: AYES: COUNCILMEMBERS: Boro , Thayer & Vice -Mayor Brei ner NOES: COUNCILMEMBERS: None ABSENT: COUNCILMEMBERS: Shippey and Mayor Mul ryan JE M. LEONC NI, City Clerk uil q 11 A 1729-03-02 January 9, 1991 Mr. Lloyd Strom Department of Public Works City of San Rafael 1400 Fifth Ave. San Rafael, CA 94915-0060 Re: Merrydale Road Overcrossing Request for Increased Authorization Dear Lloyd: MAI I R "%, _0M as "em 4 1 ENGINEERING A\TD PLANNING SERVICES Public Improvement. • 1 and Ikcelolnnent • Thamsportation 355 Lakeside Drive, Suite 200 Foster City, California 94404 (415) 349-2151 RECEIVE Teleeopier: ( 415) 345-4921 PUBLIC WORKS DE CITY OF PAN RAFT "Ir,•:iei As you are aware, the final plans for the Merrydale Overcrossing project were submitted to Caltrans in mid-December with an ex- pected approval shortly. As discussed in our November 20 letter to you, we have performed extra work and have incurred extra costs above and beyond our most recent amendment due to the rea- sons set forth below. The work and requests for authorization are broken down and summarized as follows: 1. Right of Wav Appraisal Map At the outset of the right-of-way process and throughout the project, it was agreed to by all parties concerned that a formal Caltrans right-of-way Appraisal Map would not be required. Since the State was not acquiring right-of-way, Caltrans did not require their formal appraisal map format. During the final stages of the project, the State reversed it's direction and required a formal appraisal map to be prepared. This caused a duplication of effort and an in- crease in costs over and above the contract requirements and previous direction. Request for Authorization $ 11,950 Mr. Lloyd Strom January 10, 1991 Page Two 2. Storm Drain Revisions for PG&E Because PG&E did not wish to relocate a 2" high pressure gas transmission line, extensive revisions were made to the Northbound on-ramp storm drain plans. This incurred added costs which otherwise would not have been required. This cost should be back charged to PG&E. Request for Authorization $ 8.000 3. Survev for Potholina Pac Bell The survey work was performed for the utility company in the area of the Civic Center Drive Wall. The utility company requested and (I assume) paid the City for the work. This amount, however, was deducted from the contract amount in our regular billings. This is an error which should be corrected by returning this amount to the total contract budget. Request for Authorization $ 3,900 4. Loa of Test Sheet Borinars for Scettrini Drive An additional requirement was imposed during the final stages to show the log of test borings for the Scettrini Drive retaining wall on plan sheet format. This sheet is in addi- tion to the log of test borings sheet prepared for the bridge area (discussed in our July 28, 1989 letter to you.) This resulted in additional coordination with Caltrans and AGS and the addition of another sheet to the contract plans. Request for Authorization $ 5,000 5. Survev for MMWD Reclaimed Waterline Proiect Our survey crew performed survey (including office support and computer) for the Marin Municipal Water Department who was planning the construction of a waterline on Merrydale Road. This survey was to show MMWD where the Merrydale project utilities are proposed in the field to avoid con- flicts with their project. Request for Authorization $ 3,200 Mr. Lloyd Strom January 9, 1991 Page Three 6. Revision to Las Gallinas Vallev Sanitary Sewer Design Based on the results of the survey performed for MMWD, the Water District requested a design revision of the sanitary sewer to facilitate the placement of their waterline. This design revision was performed at the direction of the City. Request for Authorization $ 1,750 7. Revisions to Contract Boilerplate in Specifications for an Encroachment Permit Job In June of this year, we were informed by Caltrans that because this project is not on Intergraph, it would not be administered by Caltrans. Per direction of the City, we revised the front end boilerplate contract information for City administration of the plans. Now the project has been converted back to Caltrans administered. This has added an additional cost for coordination and specification prepara- tion above and beyond our control. Request for Authorization $ 10,000 8. Separatina Job Estimate into the Overcrossina Costs and the Northbound On -Ramp Costs At the beginning of this year, we were requested by Caltrans to separate all construction costs into the above named cate- gories. Since the project was estimated together, this required additional time to segregate all quantities and prepare two estimates. Request for Authorization $ 850 9. NBOR Redesian In our Request for Authorization letter dated July 28, 1989, our estimate of fees for the redesign of the NBOR was $70,000 prior to beginning design. (See item 11 of that letter). Now that the design is complete, our costs have amounted to $79,532 for this redesign. Request for Authorization $ 9,550 Mr. Lloyd Strom January 9, 1991 Page Four 10. Utilitv Easements After completion of documents for the project easements and right-of-way, we were requested to prepare plats and descrip- tions of utility easements for PG&E poles, anchors and trenching. The preparation of these descriptions resulted in additional costs. Request for Authorization $ 2.100 11. Additional Utilitv Coordination Coordination with utilities continues to date. Requests by PG&E, PacBell and other utilities for computer information and other backup information as well as checking utility drawings has cost an additional amount over and above last authorization. Request for Authorization $ 5.900 12. Costs Incurred Because of Additional Contract Time A certain amount of costs are incurred in a contract for administration simply because of the time involved. These costs generally are incurred on a monthly basis, and include such items as billing, maintenance of books and project files, general (not technical) management of the project, etc. There are other non -quantifiable costs simply because of an increase in the time which the project is kept active. The most obvious of these would be phone calls and other minutia which detract from other work. Generally speaking, the addition of the Northbound on-ramp extended the time of design considerably beyond any normal expectations. Costs incurred because of delay generally amount to 1% per month. We feel this has been an added cost to us and therefore request an additional authorization. Request for Authorization $ 15,000 We have submitted our final plans to Caltrans for back check on December 13, 1990. The Caltrans Senior, Helena Culik-Caro (Lenka), has informed us that they anticipate to have their back check done by the end of January. At that time, we will bring the mylars up and go through any last minute items. The plans will then be sent to Sacramento for approval. Mr. Lloyd Strom January 9, 1991 Page Five At this time, the remaining original contract items consist of: 1.) minor revisions for finalization of plans, and; 2.) prepara- tion of the Resident Engineers file. For additional work re- quested above and beyond the original contract items listed above, we propose to bill the City on a time and materials basis on a separate account and invoicing. Examples of extra work now in progress includes: - Changes to Landscape Plans per Department of Fish and Game comments. - Coordination with PG&E on easement questions. - Placement of SSP's on computer disk. Based on the foregoing, we request the following: 1. Authorization to increase the project budget by $77,200 to a new total of $723,200. 2. Approval of our proposed accounting and billing of extra work performed after December 13, 1990. An interim budget of $25,000 is requested for the completion of any current or additional extra work. We trust that the foregoing is consistent with your records and understanding of the extra work performed since the last contract amendment. Upon approval, please sign and return a copy of this letter for our files. Very truly yours, Appr ved, C3� If.Sa n Rafael WILSEY & HAM By rL ,jyLGL.2 David M. Bernardi Title Director of Public Works ?Frank C. T esco, P.E. ice Pres2dent - Transportation FCT:lm C:\LYNN\TEDESCO\STROM Date April 15, 1991 ATTEST: .4' ' e""ne M. Le ncini City Clerk u -G O w HFlF-'%D 00 -1 O1 UIk+W NH 'o ro Fi 0 N FJ 0. . . . . . in H F-+ %0 J %D oIn p. o za cnEnEnwcntycnEn�i w y rt O O A•rt, mo mto m m m rr 0 9: ct to O a tlW11Fl- OWOM<:'<�rth�0�' C O rt H rt rt r- H W w o r- m H. `C Ul P) N rimrtr- z " Fl- In " In m 0 m O H O a P- rt 7o to w M r- Fl"< M "< 't3 0 O 0 H O '< m O rt r- O 00 d 'o rto 0 mwH_0 o m o MHrnn n w o a txjm o w m m O m o w w H H0f✓0)N0Wrt r- rtmmr-r- H r- Fi (n r• O r• rr W O rt o fn rtcmLQmti00z ro a 0 mmrt;Aort0o t-+tti0WF-J w A. FJ - m (n tr N 0 -� a 0 rt m rt Ho OMNC7nor<z (p t3i W rt* t1i M o O r• O r- a m rtN m 0 rtn 00:3 Hmb 0 01�< rtti n w mw r H_ N0) o nro 5 tI]t,7I F�NNw o (p (n 06) wort aN r -M m moa+ rt0 dOr•Oro Ftw mnw--a0"aM OOH OO Nm 00 Mr• Ha r- Wtnw ti w �w rt :7m zm Hto a rt 0 0 n H w rt F� Ia rt 0 CO rt w 6< Fl- m rt o o n Fu cn►ror Fw' O o N -v- d m r- rt • r - N rt w < o K LQ N to -M .P UI N -ca _M 4041). H W W 00 D7 1D F-' U1 00 %D O O OO UIO OO 00 00 is _M -n W in H F-+ %0 J %D O Fj 00 U1 U1 03 O ID Ul O Ul Ul O Ul O O O O 0 O _M 0 O O iLn Ln 0 0 O O tr 0 �< m CH_ C N- [r F✓ Fi r- N w tr m F_j N m tr w K m w 0 rt pi FS U1 a a o Cr N H m A z 00 Ort rt Fi H a0 0 rt, t9 0 x rt N m rt o N m M an 0 oV 0 rt F; a 0 rt H %D �o N 7d m 12 m N rt M O n H 0 0 m a En m ay rt 0 n r - N w rt O 0 0 0 rt N w Cr m N m .d w Fi w rt m a r' 0 rt 0 rt o' m M 0 Fj F� O E P_ 0 W 0 a rt m LQ O Fi r- m N oro < So m O n y O H N N � 0 k ro ro n O u. m 0 rt