HomeMy WebLinkAboutOrdinance 1562 (Spinnaker on the Bay Project)CLERK'S CERTIFICATE
I, JEANNE M. LEONCINI, Clerk of the City of San Rafael, and
Ex -officio Clerk of the Council of said City, do hereby certify that
the foregoing Charter Ordinance No. 1562 entitled:
"AN ORDINANCE OF THE CITY OF SAN RAFAEL AMENDING THE DEVELOPMENT
STANDARDS FOR SPINNAKER ON THE BAY AS DESCRIBED IN EXHIBIT "A"
TO ORDINANCE 1515 ADOPTED BY REFERENCE, BY SECTION 14.15.020 OF THE
MUNICIPAL CODE OF SAN RAFAEL, RECLASSIFYING CERTAIN REAL PROPERTY
FROM P -C (PLANNED COMMUNITY) TO P -D (PLANNED DEVELOPMENT) DISTRICT SO
THAT EXHIBIT "A" REFLECTS CURRENT GENERAL PLAN POLICIES, MODIFICATIONS
TO THE SPINNAKER ON THE BAY PROJECT RESULTING FROM SUCH POLICIES, AND
MODIFICATIONS REVISING PROJECT DESIGN FEATURES"
is a true and correct copy of an ordinance of said City and was
introduced at a REGULAR
meeting of the City Council
of the City of San Rafael, held on the 17TH
day of
APRIL 19 89 published as required by City Charter in the
MARIN INDEPENDENT JOURNAL a newspaper published in the City
of San Rafael and passed and adopted as an ordinance of said City at
a REGULAR
held on the FIRST
vote, to wit:
meeting of the City Council of said City
day of MAY 19 89, by the following
AYES: COUNCILMEMBERS: Boro, Breiner, Frugoli, Thayer & Mayor Mulryan
NOES: COUNCILMEhIBERS: None
ABSENT: COUNCIUIEMBERS: None
WITNESS my hand and the official seal
of the City of San Rafael this
2nd day of May
19 89.
JEANN EONCIN*,:Ly�Ie
ORDINANCE NO. 1562
AN ORDINANCE OF THE CITY OF SAN RAFAEL
AMENDING THE DEVELOPMENT STANDARDS FOR
SPINNAKER ON THE BAY
AS DESCRIBED IN EXHIBIT "A" TO ORDINANCE 1515
ADOPTED BY REFERENCE, BY SECTION 14.15.020 OF
THE MUNICIPAL CODE OF SAN RAFAEL, RECLASSIFYING
CERTAIN REAL PROPERTY FROM P -C (PLANNED COMMUNITY)
TO P -D (PLANNED DEVELOPMENT) DISTRICT
SO THAT EXHIBIT "A" REFLECTS CURRENT
GENERAL PLAN POLICIES, MODIFICATIONS TO THE
SPINNAKER ON THE BAY PROJECT RESULTING FROM SUCH POLICIES,
AND MODIFICATIONS REVISING PROJECT DESIGN FEATURES
THE COUNCIL OF THE CITY OF SAN RAFAEL DO ORDAIN AS FOLLOWS:
DIVISION 1. Ordinance 1515, adopted by reference
Section 14.15.020 of San Rafael Municipal Code, is amended
so that it reflects the revised development standards described
in Exhibit "A" attached hereto. Property affected by said
amendment is located at Catalina and Bellam Boulevards, San
Rafael, Assessor's Parcel numbers 9-010-17, 18, 19, 20, 21;
9-100-01, 04; 9-142-13, 24, 26, 53, and is particularly described
in Exhibit "B" attached hereto.
DIVISION 2. Any development of said property shall
be subject to the conditions outlined in Exhibit "A" ("Amended
Development Standards for Spinnaker on the Bay") attached hereto.
DIVISION 3. If any section, subsection, sentence,
clause or phrase of this ordinance is for any reason held to
be invalid, such holding or holdings shall not affect the validity
of the remaining portions of this ordinance. The Council declares
that it would have passed this ordinance and each section,
subsection, sentence, clause and phrase thereof, irrespective
of the fact that any one or more sections, subsections, sentences,
clauses or phrases be declared invalid.
DIVISION 4. This ordinance shall be published once
in full before its final passage in a newspaper of general
circulation, published and circulated in the City of San Rafael,
and shall be in full force and effect thirty (30) days after
its final passage.
Attest: yy��
JEA -Pl. LEONCINI, City Clerk
LAWRENCE E. MULRYAN, Mayor
GRIGINAI
ORDINANCE NO. 1562
The foregoing Ordinance No. 1562 was read
and introduced at a regular meeting of the City Council of
the City of San Rafael on the 17th day of April ,
1989, and ordered passed to print by the following vote, to
wit.
AYES: COUNCILMEMBERS: Boro, Breiner, Frugoli, Thayer & Mayor Mulryan
NOES: COUNCILMEMBERS: None
ABSENT: COUNCILMEMBERS: None
and will come up for adoption as an Ordinance of the City of
San Rafael at a regular meeting of the Council to be held on
the 1st day of May , 1989.
JE NWk,,M. LEONCIN,�Cityk
EXHIBIT "A"
Development Standards:
(a) This P -D zoning shall permit a residential project consisting of 207
single-family dwellings and 40 multifamily below market rate
units upon the 28.93 acres of existing land fill and dredge spoils.
The 20 -acre lagoon and 16.6 -acre diked wetland/marsh shall remain as
"private reserve" for parks/open space/conservation and are not
approved for development. A note stating the above shall appear on
the final map to make clear the status of these areas. The shoreline
levee is approved as a shoreline access band. The levee and offshore
submerged tidelands shall be dedicated as part of the first
subdivision and design review action for the proposed project. To
ensure that there is a transition in density and unit design, the two
acres immediately south of the Spinnaker Point townhouse development
(fronting Catalina Boulevard) shall be developed at a maximum density
of 10 du -acre with maximum 2 -story units.
(b) Geology/Soils
1. No filling of the 20 -acre lagoon or the 16.6 -acre diked
wetland/marsh shall be permitted under this planned development
zoning.
2. All land filling and grading shall be in compliance with the
measures identified in the soils report prepared for the proposed
project by Harding and Lawson Associates, dated September 6, 1983
and listed on pages 25 and 26 of the draft Environmental Impact
Report for Spinnaker on the Bay.
3. Buildings, patios, fenced yards, balconies, roof overhangs and
architectural features shall be set back a minimum of 50 feet
measured from the highest waterline of the lagoon (-1.0 MSL) or a
minimum of 10 feet from the top of bank at finished grade (+7.0
MSL), whichever is greater. Prior to tentative map or design
approval, the applicant shall be required to provide a report
prepared by a qualified biologist substantiating that such a
setback will not result in significant indirect wildlife impacts
associated with endangered species. All construction and grading
for seismic safety shall be to the satisfaction of the soils
engineer and City Engineer.
4. Imported fill for raising existing land fill and spoils area
shall be limited to that necessary to comply with City flood
protection standards. A use permit shall be obtained from the
City for all filling/grading activities.
5. A comprehensive erosion and sediment control plan shall be
submitted prior to issuance of grading permits. The plan shall
include areas for stockpiling and a watering/sprinklering plan to
minimize dust generation.
6. A truck route for importing fill mterials shall be established by
the City Engineer prior to issuance of a grading permit. Bonding
for wheel loads shall be required.
7. Hours of operation for grading and importing materials shall be
limited to between 7:30 a.m. to 3:30 p.m., Monday through Friday
in order to limit noise and traffic impacts.
8. Any necessary street cleaning as a result of spills fill material
shall be the responsibility of the developer. Failure to clean
up the debris in the public right-of-way could result in a stop
work order by the City of San Rafael.
9. Prior to issuance of a grading permit by the Public Works
Department, the limit line of land fill shall be staked and
fenced in the field. The purpose of staking and fencing shall
ensure that there is no filling of existing lagoon and wetland
areas and to identify the jurisdictional limits of the U.S. Army
Corps of Engineers.
(c) Hydrology/Drainage
1. Prior to issuance of a grading permit, the applicant shall design
and implement an erosion control plan to prevent sediment from
entering the lagoon during construction. The plan shall include
provisions for items such as sediment detention basins and traps,
silt fences and/or hay bales, temporary seeding of dirt piles and
distributed soils areas, and watering of loose soil areas on
windy days. The plan shall be approved and enforced by the City
of San Rafael.
2. In order to provide the benefits of areawide flood plain
management, the construction of an interconnector pipeline may be
required from the existing Spinnaker lagoon to adjoining
properties. The necessity for and details of this interconnector
shall be determined by the Public Works Department at the time of
the first design review or tentative map. An easement shall be
reserved through the development area to accommodate this
improvement. The easement shall be located and sized to the
satisfaction of the Public Works Department.
(d) Water Quality
1. Graded slopes shall be directed away from the lagoon and wetland
areas. All runoff from the development except that from the
lagoon and levee banks shall be routed into an enclosed drainage
system designed with sediment and grease traps to collect urban
runoff. Ongoing maintenance of the on-site drainage system shall
be incorporated into the CC&Rs of the homeowners' association.
2. A detailed water management plan for the lagoon and wetland shall
be submitted at the time of the first Design Review application
or at the time of Tentative Map review. The plan shall take
into consideration the following goals:
a) Continual flood control;
b) Maintenance of water quality;
c) Regulation of water levels;
d) Control of siltation;
e) Management of the protective habitat area for wildlife; and
f) Enforcement of mosquito abatement measures.
The plan shall include detailed calculations and information on
the timing for cleaning and flushing the lagoon and wetland
areas, schedule for monitoring water levels and water quality,
the amount of water necessary to offset evaporation, and water
necessary to maintain a relatively fresh water lagoon. Ongoing
management of the program shall be conducted by a professional
firm or agency experienced with biological and water quality
management, with the City governing management for flood control.
An advisory committee consisting of members representing wildlife
interests, City Public Works Department staff, Mosquito Abatement
and homeowners' association representatives who are members of a
special maintenance district shall be appointed by the City to
oversee the goals and objectives of the ongoing management plan.
The plan shall also determine a mechanism for private funding of
maintenance such as through homeowners' association dues or
preferably formation of a special district.
3. The general mosquito abatement measures identified on pages 40
and 41 of the draft EIR for Spinnaker on the Bay shall be
implemented through the ongoing water management program
identified in condition (f-2) above. The specific measures shall
be the least impacting to wildlife values and productivity of the
lagoon wetland areas. The specific measures shall be reviewed
and approved by the Marin/Sonoma Mosquito Abatement District.
4. Prior to issuance of the first building permits for this project,
the developer shall be responsible for providing a general
cleanup of the existing lagoon and wetland areas. This general
cleanup would include removal of all debris and repair of the
existing flap gate located at the south end of the wetland, east
of Murphy's Rock, and any other reasonable measures to the
satisfaction of the City of San Rafael. The City will consult
with the various wildlife agencies/organizations for assistance
and guidance.
(e) Air Quality
1. The developer shall provide water facilities and employ all
measures necessary and as required by the Department of Public
Works to reduce dust generation from grading operations.
2. As grading is completed on various portions of the project site,
these portions of the site shall be hydroseeded or landscaped, as
required by the Public Works and Planning Departments' use and
grading permits.
(f) 1. A minimum setback of 50 feet from the highest waterline of the
lagoon (-1.0 MSL) or 10 feet measured from the top of bank at
finished grade (+7.0 MSL), whichever is greater, shall be
provided to all buildings, patios, fenced yards, balconies, roof
overhangs and architectural features. The protective fence can
be located downslope from the top of bank at finished grade, with
the precise location determined at the time of design review.
2. A sufficient and specially designed edge treatment shall be
required around the south edges of the lagoon and wetland
adjacent to the development to mitigate indirect impacts to the
Salt Marsh Harvest Mouse. The edge treatment shall include dense
landscaping and a 4 -foot -high vinyl clad cyclone -type or similar
transparent fence shall also be required along the northern and
southern edges of the wetland to eliminate pedestrian access
along the dikes within the existing wetland area. Landscaping
within the setback area, along with consideration of
incorporating all or part of the existing berm, shall be
determined at the time of design review.
3. A corridor between the Canalways and Spinnaker wetlands can be
provided by lowering the levee separating the two wetlands and
providing an elevated bridge for shoreline band access. This
corridor shall be provided only if the Canalways site is
developed and the shoreline levee (east of the Canalways site) is
improved to Title 18, Flood Protection Standards. Design and
installation of these corridor improvements shall be the
responsibility of the Canalways developer. Prior to issuance of
building permits for Phase I, the applicant shall agree in a form
acceptable to the City Attorney not to protest installation of
this corridor, if the Canalways development occurs.
4. No dedication or enhancement of the lagoon and wetland areas are
required as part of this planned development zoning. However,
ongoing maintenance and cleanup responsibilities listed as part
of these development standards shall be required to maintain this
currently productive wildlife habitat area.
(g) Traffic/Circulation
1. Traffic mitigation fees for East San Rafael transportation
improvements shall be estimated at the time of use permit and
design review for each phase of this development. The fees shall
be based on trip generation rates of 1.0 trips per dwelling unit
over 1,000 square feet in size and .85 trips per dwelling unit
for units less than 1,000 square feet in size.
2. Bellam Boulevard shall be extended and dedicated to the City of
San Rafael. The road right-of-way shall be reduced to 60 feet
wide east of Catalina Boulevard. The road right-of-way shall
extend eastward and shall terminate at the east end of the
adjacent City -owned parcel in a cul-de-sac bulb. The City or any
other future developer of the adjacent City -owned parcel to the
southwest shall be required to participate in the right-of-way
dedication and costs for improving the extended Bellam Boulevard.
If the East San Rafael Neighborhood Plan recommends a City park
at the east end of the Spinnaker site, a roadway shall be
designed to extend 500 feet west of the eastern edge of the
spoils area. The right-of-way shall be located entirely on the
subject property and shall be designed with two travel lanes, two
sidewalks, two parking lanes, and two bicycle lanes to the
satisfaction of the Public Works Department. Access from the
extended Bellam Boulevard to the adjacent Canalways site shall be
granted provided that a "payback provision" for Bellam Boulevard
improvements be required of the Canalways' developer. A one -foot
wide non -access strip shall be established between the Bellam
Boulevard right-of-way and the Canalways site. The non -access
strip shall not be removed for access to Canalways until pay back
has occurred.
3. Catalina Boulevard shall be extended and dedicated to the City of
San Rafael at a 60 -foot -wide right-of-way width as indicated on
the development plan dated March 20, 1989. There shall be a
minimum of 150 feet between the Catalina Boulevard/Bellam
Boulevard intersection and the Playa del Rey/Bellam Boulevard
intersection.
4. Roadways within the project shall have a 20 -foot minimum
unobstructed width. If parallel parking is allowed on one side
or both sides, the width shall be no less than 28 or 36 feet,
respectively. Private bicycle paths shall be incorporated into
the design of the roadways.
5. All turning radii for interior roadways within the project must
be a minimum of 45 feet to accommodate the largest fire trucks.
6. Emergency roadway access shall be designed throughout the entire
project to the satisfaction of the City Police and Fire
Departments.
(h) Noise
1. All proposed units shall be designed with noise attenuation
measures to mitigate potential noise impacts. A noise analysis
shall be submitted to the City for review and evaluation prior to
issuance of any building permits.
2. Prior to issuance of the first building permit, the developer
shall agree in a form acceptable to the City Attorney to pay a
proportionate share of costs necessary to attenuate noise from
Bellam Boulevard traffic upon the 24 Bahia de Rafael condominiums
adjacent to Bellam Boulevard. The need for any such improvements
is to be identified in a noise study currently underway as part
of the East San Rafael Neighborhood Plan. Such attenuation
measures shall be required if it is concluded by the noise study
that noise levels along the affected portion of Bellam Boulevard
will reach 65dB LDN as a result of increased traffic generated by
the proposed project and other projects anticipated in the area.
3. If noise mitigation is determined not to be necessary, all
written agreements shall become null and void.
4. All grading equipment shall be adequately muffled to minimize
potential noise impacts to the surrounding area.
(i) Land Use/Affordable Housing Element
1. Each phase of the project shall provide a mix of floor plan
types.
2. Prior to issuance of building permits, an affordable housing
package agreement and property management plan shall be submitted
to the City for review and approval by the City Council.
Consistent with current General Plan policies, a minimum of 40
below market rate rental units must be provided on-site with the
247 -unit project. Nineteen of the below market rate units shall
be available to low income households as defined by the General
Plan. The remaining 21 units shall be available to moderate
income households as identified by the General Plan. Phase I,
consisting of 111 units total, with 24 below market rate units,
shall provide a minimum of 11 units to low income households and
13 units to moderate income households as defined by the General
Plan. All below market rate units shall remain so for a minimum
of 40 years. The agreement/plan shall provide for management of
the program by a suitable entity such as the County Housing
Authority, or Ecumenical Association for Housing, and for overall
management of the site.
(j) Open Space/Parks
1. The proposed project shall be subject to in -lieu park dedication
fees consistent with the San Rafael Recreation Element and
Ordinance 1558. A 50% fee credit for Phase I equal to
approximately $101,014 shall be granted for dedications and
improvements to the Shoreline Band. Fees shall be assessed at
the time of use permit, design review and/or subdivision
approvals for each phase of the development.
2. In conjunction with the extension of Bellam Boulevard, a bicycle
path shall be installed on both sides of the public street
consistent with the City's Recreation Element. This bicycle path
shall connect with the shoreline band access.
3. Public parking shall be provided at the east end of Bellam
Boulevard, to service shoreline band access. The public parking
that is provided shall be no less than seven vehicle spaces or as
required by the East San Rafael Neighborhood Plan.
4. Prior to issuance of building permits for the first phase of
development, Assessor's Parcel Numbers 9-142-13, 9-142-53, and 9-
142-24 shall be dedicated in -fee for open space purposes. These
parcels encompass the shoreline levee, 100 -foot -wide shoreline
band, and offshore submerged tidelands. The shoreline band and
levee shall be dedicated in -fee to the City of San Rafael while
the offshore submerged tidelands shall be dedicated to the State
of California. In addition, the applicant shall dedicate to the
City a 30 -foot wide parcel along the site's southern boundary for
the purpose of providing access to Shoreline Park. All dedicated
parcels shall be improved pursuant to the to -be -adopted Shoreline
Master Plan.
5. The specific design for each phase of development shall include
view corridors to the lagoon and/or wetland areas consistent with
the project EIR and the East San Rafael Neighborhood Plan. These
view corridors shall be incorporated into the use permit and
design review for each phase of development. The view corridor
locations required are as follows:
a) A view corridor shall be provided from Catalina Boulevard
toward the lagoon between the existing Spinnaker Point
townhouse units and the proposed project;
b) A view corridor shall be provided from Bellam Boulevard
toward the lagoon in the proximity of the recreation center;
and
c) A view corridor shall be provided at the end of Bellam
Boulevard eastward toward the shoreline band and offshore
island.
(k) Public Services/Utilities
1. Fire flows must meet the requirements of the Fire Department and
will be based on the type of building contruction, percentage of
exterior openings and the distance between units.
2. To allow faster response by emergency vehicles, an identifier
board with a map showing the interior road system shall be placed
at each entrance to the project, subject to design review
approval.
3. Each entry road shall identify the unit numbers and each unit
number shall be visible from the street and illuminated at night.
4. To the greatest extent possible, unit entryways shall be visible
from the street/interior circulation ways.
5. Detailed project landscaping plans shall be submitted at the time
of design review for each phase. Landscaping shall be designed
to provide adequate screening of the buildings and parking from
public streets, yet provide adequate visibility and sight
distance at driveway entrance ways for proper surveillance by the
Police Department.
6. All security hardware on units shall be to the satisfaction of
the Police Department.
7. Water conserving devices in all interior plumbing fixtures shall
be installed to the satisfaction of the Marin Municipal Water
District.
8. Drought -tolerant vegetation shall be provided in all landscape
areas.
9. The 50 -foot wide setback/buffer required along the edge of the
lagoon and wetland shall be designed with landscaping that has
been reviewed and approved by a biologist experienced in habitat
landscaping and edge treatment of wetland areas.
10. The landscape and irrigation plan for each phase shall consider
an efficient drip irrigation system to minimize runoff and
erosion and to conserve water.
11. The San Rafael Fire Department shall review the tentative map and
reservoir sizing projected by the Marin Municipal Water District
to ensure adequate fire flow for East San Rafael. Given that
projected build out in the East San Rafael area will require
construction of a two million gallon water tank, the project may
be required to participate in the funding of construction of this
water tank. This determination shall be made by MMWD prior to
issuance of building permits for Phase I.
12. Depending on actual enrollments at Davidson Middle School and
elementary schools in the San Rafael School District, additional
classrooms may be required. The school district may assess a
"bedroom" tax on this and other residential development if there
is a demonstrated significant effect on school capacity. This
bedroom tax can be used to provide portable classrooms or
additional school facilities. The monies cannot be used for
maintenance or operating expenses.
(1) Urban Design
1. The project design theme, building materials and colors of all
phases of this development shall be compatible with the adjacent
Spinnaker Point townhouse development. This theme shall be
accompanied by a landscape plan with similar treatment as
landscaping at the Spinnaker Point development.
2. Street trees shall be installed along Bellam and Catalina
boulevards, spaced at 30-foot intervals. These trees shall be
installed in conjunction with the construction of the roadway
improvements. Variations in the intervals of tree planting may
be considered to provide flexibility and interest in the
streetscape.
3. In conjunction with the first phase of development, an entry
statement (i.e., specialized landscaping, monument-type
identification signs) shall be designed and installed along
Catalina Boulevard, which identifies the adjacent Spinnaker
townhouse development. A large entry statement (specialized
landscaping and monument-type identification sign for Spinnaker)
shall be incorporated into the landscape plan at the corner of
Bellam and Catalina boulevards.
4. This master plan shall permit a maximum building coverage of 35%.
Building coverage shall include residential structures, enclosed
recreational structures, parking structures, carports and
garages.
5. The individual buildings shall be designed in small clusters in
order to minimize mass, bulk, and repetition in design throughout
the complex.
6. Building setbacks from the property line along Bellam-Boulevard
and Catalina Boulevard shall be a minimum of 20 feet for front
yard setbacks and a foot for side yard setbacks.
(m) Other Standards
1. Each phase of construction shall be subject to use and
environmental and design review permit approvals.
2. Subsequent use, design review and/or subdivision permits for the
first phase of development shall be filed within the first 18
months of adoption of this P-D zoning. If such permit
applications are not filed within that specified time, a time
extension must be granted.
EXHIBIT "B"
DESCRIPTION:
All that certain real property situate in the City of San Rafael, County of Marin,
State of California, described as follows:
BEGINNING at the Southeasterly corner of Lot 6 in Block 19, as shown upon that
certain map entitled "Map of East San Rafael," recorded January 21, 1908 in Book 2
of Maps at Page 109, Marin County Records, being the Southeasterly corner of the
Lands of the San Rafael Redevelopment Agency commonly known as Pickleweed Park,
being also the Southwesterly corner of the parcel of Tidelands described in the
deed from P. J. Rowland et ux to A. B. Copeland, recorded November 24, 1953 in
Book 837 of Official Records at Page 406, Marin County Records; thence South
14021'00" West 1,297.88 feet, along the Easterly boundary of Block 30, as shown
upon said "Map of East San Rafael," to the TRUE POINT OF BEGINNING; thence leaving
said Easterly boundary along the Southerly boundary of that certain map entitled
"Map of San Rafael Cayes, Unit One, San Rafael, California," recorded December 24,
1963 in Book 12 of Maps at Page 55, Marin County Records, South 69032' East 516.67
feet; then North 20028' East 73.58 feet; thence along a tangent curve to the right
with a radius of 150 feet through a central angle of 103056'08" a length of 272.10
feet; thence along a tangent curve to the left with a radius of 265 -feet through a
central angle of 72056'22" a length of 337.36.feet; thence along a tangent curve
to the right with a radius of 200 -feet through a central angle of 84054'30" a
length of 296.38 feet; thence along a tangent curve to the left with a radius of
290 feet through a central angle of 25054'16" a length of 131.12 feet to a tangent
point; thence South 69032' East 172.67 feet to the Southeasterly corner of Lot 12,
as said lot is shown upon the aforementioned Map of San Rafael Cayes, Unit One;
thence along the Easterly boundary of said map North 20028' East 902.82 feet to a
point which lies South 69032' East 1,690.24 feet from the reference point of
beginning of this description; thence North 20028' East 17.56 feet; thence South
69032' East 14.91 feet; thence along a tangent curve to the right with a radius of
67.5 feet through a central angle of 61048'01" a length of 674.14 feet to a point
in the Northerly line of Tide Lot 17 in Section 2 T.1N. R6W. M.D.B. and M., as
shown upon that certain map entitled "Map No. 2 of Salt Marsh and Tide Lands
Situate in the County of Marin, State of California, 1870"; thence East 20.68
feet; thence South 1,320 feet to a point in the Southerly line of said Tide Lot
17; thence West 200 feet; thence Southwesterly 250 feet, more or less, to the most
Northerly corner of the Lands of Canalways as shown on that certain map entitled
"Record of Survey of A Portion of Section 2 « Section 11, T.1N., R.6W., Mount
Diablo Meridian" as filed April 9, 1969 in Book 8 of Surveys at Page 28, Marin
County Records; thence South 79025' blest 1,267.83 feet to the most Easterly corner
of the Lands of the City of San Rafael as described in deed from San Rafael Cayes,
Inc., a Corporation, to the City of San Rafael recorded March 7, 1968 in Book 2195
of Official Records at Page 214, Marin County Records; thence Northwesterly along
the Easterly boundary of said Lands of the City of San Rafael along a curve to the
right with a radius of 800 feet through a central angle of 50017'38" a length of
702.24 feet; thence along a tangent curve to the left with a radius of 600 feet
through a central angle of 33046'57" a length of 353.77 feet to a paint in the
Right -of -Way of Bellam Boulevard, said point being distant North 8005' East 61.95
feet from the intersection of the courses North 2003'00" West 92.28 feet and North
8005' East 36.90 feet at the Easterly line of Lot 1 of the map entitled "Map of
Bahia de Rafael Industrial Park" as recorded February 13, 1973 in Volume 15 of
Maps at Page 54 Marin County Records; thence North 8005' East 477.05 feet; thence
North 14021' East 388.62 feet to the True Point of Beginning.
Containing 72 Acres, more or less.