HomeMy WebLinkAboutCM Security Services 2014to] .1- I% A IW&I 0 1 % /_
This Agreement is made and entered into this 6 day of October, 2014, by and between the
CITY OF SAN RAFAEL (hereinafter "CITY"), and Barbier Security Group, a corporation
authorized to do business in California (hereinafter "CONTRACTOR").
I x41 I Im im
WHEREAS, CITY operates the San Rafael Public Library ("LIBRARY") and other CITY
facilities; and
WHEREAS, CITY has a need for regular professional security services in connection with
the Downtown LIBRARYand occasionally at other CITY facilities; and
WHEREAS, CONTRACTOR has the expertise required to provide such services and is
willing to do so on the terms and conditions set forth in this Agreement.
NOW, THEREFORE, the parties hereby agree as follows:
PROJECT COORDINATION.
A. CITY. The City Manager shall be the representative of the CITY for all purposes
under this Agreement. The City Manager is the PROJECT MANAGER for the CITY, and said
PROJECT MANAGER shall supervise all aspects of the progress and execution of this Agreement.
B. CONTRACTOR'S Project Director. CONTRACTOR shall assign a single
PROJECT DIRECTOR to have overall responsibility for the progress and execution of this
Agreement for CONTRACTOR. Evan Barbier is hereby designated as the PROJECT
DIRECTOR for CONTRACTOR. Should circumstances or conditions subsequent to the
execution of this Agreement require a substitute PROJECT DIRECTOR, for any reason, the
CONTRACTOR shall notify the CITY within ten (10) business days of the substitution.
2. DUTIES OF CONTWTOR.
CONTRACTOR shall perform the duties and/or provide services as follows:
• CONTRACTOR shall provide one professionally trained security guard to be on the
premises of the Downtown Library ("Library") during all open hours (Sunday 1-5,
Monday 1-8, Tuesday/Wednesday/Thursday 10-8, Friday/Saturday 10-5), a total of 55
hours per week.
Rev. Date: 1/30/14
• Exceptions are days that the Library is closed for a holiday or other purpose (PROJECT
MANAGER will provide an annual calendar to CONTRACTOR), during which time no
service is required.
• Additionally, upon timely request, CONTRACTOR shall provide one or more
professionally trained security guards to be present on an ad hoc basis at other CITY
facilities and events at the times and for the duties to be arranged on a case-by-case
basis.
3. DUTIES OF CITY.
CITY shall pay the compensation as provided in Paragraph 4, and shall provide
CONTRACTOR with access to the LIBRARY or other CITY facilities as appropriate, and shall
otherwise cooperate as necessary for the performance of CONTRACTOR's services hereunder.
For the full performance of the services described herein by CONTRACTOR, CITY shall
pay CONTRACTOR as follows:
0 $24 per hour/per person for Library work, at 55 hours per week, excepting closed days for
which no compensation will be due;
0 $35-$40 per hour/per person for ad hoc work for other CITY facilities or departments such
as Community Services and Fire facilities;
0 Total payments for all Library work and ad hoc work provided pursuant to this Agreement
shall not exceed $ 100,000.
Payment will be made monthly upon receipt by PROJECT MANAGER of itemized
invoices submitted by CONTRACTOR.
The term of this Agreement shall commence on the date of this Agreement and shall end on
October 6, 2015. Upon mutual agreement of the parties, and subject to the approval of the City
Manager, the term of this Agreement may be extended for an additional period of six months.
A. Discretionary. Either party may terminate this Agreement without cause upon
thirty (30) days written notice mailed or personally delivered to the other party.
B. Cause. Either party may terminate this Agreement for cause upon fifteen (15) days
written notice mailed or personally delivered to the other party, and the notified party's failure to
cure or correct the cause of the termination, to the reasonable satisfaction of the party giving such
notice, within such fifteen (15) day time period.
C. Effect of Termination. Upon receipt of notice of termination, neither party shall
incur additional obligations under any provision of this Agreement without the prior written consent
Rev. date: 1/30/14 2
of the other.
D. Return of Documents. Upon termination, any and all CITY documents or
materials provided to CONTRACTOR and any and all of CONTRACTOR's documents and
materials prepared for or relating to the performance of its duties under this Agreement, shall be
delivered to CITY as soon as possible, but not later than thirty (30) days after termination.
1�11L�I�I a W4:1111] 0 1161411075 1 NON
The written documents and materials prepared by the CONTRACTOR in connection with
the performance of its duties under this Agreement, shall be the sole property of CITY. CITY may
use said property for any purpose, including projects not contemplated by this Agreement.
8. INSPECTION AND AUDIT.
Upon reasonable notice, CONTRACTOR shall make available to CITY, or its agent, for
inspection and audit, all documents and materials maintained by CONTRACTOR in connection
with its performance of its duties under this Agreement. CONTRACTOR shall fully cooperate
with CITY or its agent in any such audit or inspection.
9. ASSIGNABILITY.
The parties agree that they shall not assign or transfer any interest in this Agreement nor the
performance of any of their respective obligations hereunder, without the prior written consent of
the other party, and any attempt to so assign this Agreement or any rights, duties or obligations
arising hereunder shall be void and of no effect.
10. INSURANCE.
A. Scope of Coverage. During the term of this Agreement, CONTRACTOR shall
maintain, at no expense to CITY, the following insurance policies:
I. A commercial general liability insurance policy in the minimum amount of
one million dollars ($1,000,000) per occurrence/two million dollars ($2,000,000) aggregate, for
death, bodily injury, personal injury, or property damage.
2. An automobile liability (owned, non -owned, and hired vehicles) insurance
policy in the minimum amount of one million dollars ($1,000,000) dollars per occurrence.
3. If any licensed professional performs any of the services required to be
performed under this Agreement, a professional liability insurance policy in the minimum amount
of two million dollars ($2,000,000) per occurrence/four million dollars ($4,000,000) aggregate, to
cover any claims arising out of the CONTRACTOR's performance of services under this
Agreement. Where CONTRACTOR is a professional not required to have a professional license,
CITY reserves the right to require CONTRACTOR to provide professional liability insurance
pursuant to this section.
Rev. date: 1/30/14 3
4. If it employs any person, CONTRACTOR shall maintain worker's
compensation and employer's liability insurance, as required by the State Labor Code and other
applicable laws and regulations, and as necessary to protect both CONTRACTOR and CITY
against all liability for injuries to CONTRACTOR's officers and employees. CONTRACTOR'S
worker's compensation insurance shall be specifically endorsed to waive any right of subrogation
against CITY.
B. Other Insurance Requirements. The insurance coverage required of the
CONTRACTOR in subparagraph A of this section above shall also meet the following
requirements:
I. Except for professional liability insurance, the insurance policies shall be
specifically endorsed to include the CITY, its officers, agents, employees, and volunteers, as
additionally named insureds under the policies.
2. The additional insured coverage under CONTRACTOR'S insurance
policies shall be primary with respect to any insurance or coverage maintained by CITY and shall
not call upon CITY's insurance or self-insurance coverage for any contribution. The "primary and
noncontributory" coverage in CONTRACTOR'S policies shall be at least as broad as ISO form
CG20 0104 13.
3. Except for professional liability insurance, the insurance policies shall
include, in their text or by endorsement, coverage for contractual liability and personal injury.
4. The insurance policies shall be specifically endorsed to provide that the
insurance carrier shall not cancel, terminate or otherwise modify the terms and conditions of said
insurance policies except upon ten (10) days written notice to the PROJECT MANAGER.
5. If the insurance is written on a Claims Made Form, then, following
termination of this Agreement, said insurance coverage shall survive for a period of not less than
five years.
6. The insurance policies shall provide for a retroactive date of placement
coinciding with the effective date of this Agreement.
7. The limits of insurance required in this Agreement may be satisfied by a
combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall
contain or be endorsed to contain a provision that such coverage shall also apply on a primary and
noncontributory basis for the benefit of CITY (if agreed to in a written contract or agreement)
before CITY'S own insurance or self-insurance shall be called upon to protect it as a named
insured.
8. It shall be a requirement under this Agreement that any available insurance
proceeds broader than or in excess of the specified minimum insurance coverage requirements
and/or limits shall be available to CITY or any other additional insured party. Furthermore, the
Rev. date: 1/30/14 4
requirements for coverage and limits shall be: (1) the minimum coverage and limits specified in this
Agreement; or (2) the broader coverage and maximum limits of coverage of any insurance policy or
proceeds available to the named insured; whichever is greater.
C. Deductibles and SIR's. Any deductibles or self-insured retentions in
CONTRACTOR's insurance policies must be declared to and approved by the PROJECT
MANAGER and City Attorney, and shall not reduce the limits of liability. Policies containing any
self-insured retention (SIR) provision shall provide or be endorsed to provide that the SIR may be
satisfied by either the named insured or CITY or other additional insured party. At CITY's option,
the deductibles or self-insured retentions with respect to CITY shall be reduced or eliminated to
CITY's satisfaction, or CONTRACTOR shall procure a bond guaranteeing payment of losses and
related investigations, claims administration, attorney's fees and defense expenses.
D. Proof of Insurance. CONTRACTOR shall provide to the PROJECT
MANAGER or CITY'S City Attorney all of the following: (1) Certificates of Insurance
evidencing the insurance coverage required in this Agreement; (2) a copy of the policy
declaration page and/or endorsement page listing all policy endorsements for the commercial
general liability policy, and (3) excerpts of policy language or specific endorsements
evidencing the other insurance requirements set forth in this Agreement. CITY reserves the
right to obtain a full certified copy of any insurance policy and endorsements from
CONTRACTOR. Failure to exercise this right shall not constitute a waiver of the right to
exercise it later. The insurance shall be approved as to form and sufficiency by PROJECT
MANAGER and the City Attorney.
11. INDEMNIFICATION.
A. Except as otherwise provided in Paragraph B., CONTRACTOR shall, to the
fullest extent permitted by law, indemnify, release, defend with counsel approved by CITY, and
hold harmless CITY, its officers, agents, employees and volunteers (collectively, the "City
Indemnitees"), from and against any claim, demand, suit, judgment, loss, liability or expense of
any kind, including but not limited to attorney's fees, expert fees and all other costs and fees of
litigation, (collectively "CLAIMS"), arising out of CONTRACTOR'S performance of its
obligations or conduct of its operations under this Agreement. The CONTRACTOR's
obligations apply regardless of whether or not a liability is caused or contributed to by the active
or passive negligence of the City Indemnitees. However, to the extent that liability is caused by
the active negligence or willful misconduct of the City Indemnitees, the CONTRACTOR's
indemnification obligation shall be reduced in proportion to the City Indemnitees' share of
liability for the active negligence or willful misconduct. In addition, the acceptance or approval
of the CONTRACTOR's work or work product by the CITY or any of its directors, officers or
employees shall not relieve or reduce the CONTRACTOR's indemnification obligations. In the
event the City Indemnitees are made a party to any action, lawsuit, or other adversarial
proceeding arising from CONTRACTOR'S performance of or operations under this
Agreement, CONTRACTOR shall provide a defense to the City Indemnitees or at CITY'S
option reimburse the City Indemnitees their costs of defense, including reasonable attorneys'
fees, incurred in defense of such claims.
Rev. date: 1/30/14 5
B. Where the services to be provided by CONTRACTOR under this Agreement are
design professional services to be performed by a design professional as that term is defined
under Civil Code Section 2782.8, CONTRACTOR shall, to the fullest extent permitted by law,
indemnify, release, defend and hold harmless the City Indemnitees from and against any
CLAIMS that arise out of, pertain to, or relate to the negligence, recklessness, or willful
misconduct of CONTRACTOR in the performance of its duties and obligations under this
Agreement or its failure to comply with any of its obligations contained in this Agreement,
except such CLAIM which is caused by the sole negligence or willful misconduct of CITY.
C. The defense and indemnification obligations of this Agreement are undertaken in
addition to, and shall not in any way be limited by, the insurance obligations contained in this
Agreement, and shall survive the termination or completion of this Agreement for the full period
of time allowed by law.
12. NONDISCRIMINATION.
CONTRACTOR shall not discriminate, in any way, against any person on the basis of age,
sex, race, color, religion, ancestry, national origin or disability in connection with or related to the
performance of its duties and obligations under this Agreement.
CONTRACTOR shall observe and comply with all applicable federal, state and local laws,
ordinances, codes and regulations, in the performance of its duties and obligations under this
Agreement. CONTRACTOR shall perform all services under this Agreement in accordance with
these laws, ordinances, codes and regulations. CONTRACTOR shall release, defend, indemnify
and hold harmless CITY, its officers, agents and employees from any and all damages, liabilities,
penalties, fines and all other consequences from any noncompliance or violation of any laws,
ordinances, codes or regulations.
14. •. THIRDA•
CITY and CONTRACTOR do not intend, by any provision of this Agreement, to create in
any third party, any benefit or right owed by one party, under the terms and conditions of this
Agreement, to the other party.
15. NOTICES.
All notices and other communications required or permitted to be given under this
Agreement, including any notice of change of address, shall be in writing and given by personal
delivery, or deposited with the United States Postal Service, postage prepaid, addressed to the
parties intended to be notified. Notice shall be deemed given as of the date of personal delivery, or
if mailed, upon the date of deposit with the United States Postal Service. Notice shall be given as
follows:
Rev. date: 1130/14 6
TO CITY's Project Manager:
TO CONTRACTOR's Project Director:
16. INDEPENDENT CONTRACTOR.
Nancy Mackle
City of San Rafael
1400 Fifth Avenue
P.O. Box 151560
San Rafael, CA 94915-1560
Evan Barbier
369-B Third Street #440
San Rafael, CA 94901
For the purposes, and for the duration, of this Agreement, CONTRACTOR, its officers,
agents and employees shall act in the capacity of an Independent Contractor, and not as employees
of the CITY. CONTRACTOR and CITY expressly intend and agree that the status of
CONTRACTOR, its officers, agents and employees be that of an Independent Contractor and not
that of an employee of CITY.
17. ENTIRE AGREEMENT -- AMENDMENTS.
A. The terms and conditions of this Agreement, all exhibits attached, and all documents
expressly incorporated by reference, represent the entire Agreement of the parties with respect to the
subject matter of this Agreement.
B. This written Agreement shall supersede any and all prior agreements, oral or written,
regarding the subject matter between the CONTRACTOR and the CITY.
C. No other agreement, promise or statement, written or oral, relating to the subject
matter of this Agreement, shall be valid or binding, except by way of a written amendment to this
Agreement.
D. The terms and conditions of this Agreement shall not be altered or modified except
by a written amendment to this Agreement signed by the CONTRACTOR and the CITY.
E. If any conflicts arise between the terms and conditions of this Agreement, and the
terms and conditions of the attached exhibits or the documents expressly incorporated by reference,
the terms and conditions of this Agreement shall control.
18. SET-OFF AGAINST DEBTS.
CONTRACTOR agrees that CITY may deduct from any payment due to
CONTRACTOR under this Agreement, any monies which CONTRACTOR owes CITY under
any ordinance, agreement, contract or resolution for any unpaid taxes, fees, licenses, assessments,
unpaid checks or other amounts.
19. WAIVERS.
Rev. date: 1/30/14
The waiver by either party of any breach or violation of any term, covenant or condition of
this Agreement, or of any ordinance, law or regulation, shall not be deemed to be a waiver of any
other term, covenant, condition, ordinance, law or regulation, or of any subsequent breach or
violation of the same or other term, covenant, condition, ordinance, law or regulation. The
subsequent acceptance by either party of any fee, performance, or other consideration which may
become due or owing under this Agreement, shall not be deemed to be a waiver of any preceding
breach or violation by the other party of any term, condition, covenant of this Agreement or any
applicable law, ordinance or regulation.
The prevailing, party in any action brought to enforce the terms and conditions of this
Agreement, or arising out of the performance of this Agreement, may recover its reasonable costs
(including claims administration) and attorney's fees expended in connection with such action.
21. CITY BUSINESS LICENSE / OTHER TAXES.
CONTRACTOR shall obtain and maintain during the duration of this Agreement, a CITY
business license as required by the San Rafael Municipal Code CONTRACTOR shall pay any and
all state and federal taxes and any other applicable taxes. CITY shall not be required to pay for any
work performed under this Agreement, until CONTRACTOR has provided CITY with a
completed Internal Revenue Service Form W-9 (Request for Taxpayer Identification Number and
Certification).
22. APPLICABLE LAW.
The laws of the State of California shall govern this Agreement.
IN WITNESS WHEREOF, the parties have executed this Agreement as of the day, month
and year first above written.
NANCY MACKLE, ity Manager
Rev. date: 1/30/14
R, FounderoVAN �BARB�IE
Barbier Security Group
ESTHER C. BEIRNE, City Clerk
APPROVED AS TO FORM:
FET
Lu A=3% -
ROBERT F. EPSTEIN, City ttorney
Rev. date: 1/30114
Exhibit A
Scope of Work for Security Services
Provided by Barbier Security to the City of San Rafael
Introduction
Barbier Security will provide security services to various sites for the City of San Rafael,
including:
• 55 hours per week for the San Rafael Public Library
Ad hoc work for other City facilities or departments such as Community Services and
Fire
Scope of Work
Barbier Security will provide one security guard, or more upon request, at the rates specified in
the contract. All planning, scheduling, coordination, and general training for security guards is
the responsibility of Barbier Security. City of San Rafael will provide additional training and
information on site specific needs and policies. Barbier Security must ensure it has adequate
resources to provide adequate security staff per agreements with the City. Barbier Security will
provide the City with information about security incidents and coordinate with staff when
appropriate.
Period of Performance
The period of performance for security services is one year (365 days) beginning on October 6,
2014 through October 5, 2015. Any modifications or extensions will be coordinated between the
City and Barbier Security for review and discussion.
Below is the process for getting your professional services agreements/contracts finalized and
executed. Please attach this "Completion Checklist and Routing Slip" to the front of your
contract as you circulate it for review and signatures. Please use this form for all professional
services agreements/contracts (not just those requiring City Council approval).
This process should occur in the order presented below.
Step
Responsible
Description
Completion
Department
Date
I
City Attorney
Review, revise, and comment on draft
agreement.
2
Contracting Department
Forward final agreement to contractor for
their signature. Obtain at least two signed
originals from contractor.
J
Contracting Department
Agendize contractor -signed agreement for
Council approval, if Council approval
necessary (as defined by City Attorney/City
Ordinance*).
4
City Attorney
Review and approve form of agreement;
bonds, and insurailee ceqificates and
endorsements.+
111, 1
5
City Manager / Mayor or
Agreement executed by Council authorized
Department Head
official.
6
City Clerk
City Clerk attests signatures, retains original
agreement and forwards copies to the
t\
contracting department.
To be completed by Contracting Department:
Project Manager: Sarah Houghton, Library Director
Project Name: Professional Services Agreement with Barbier Security
Agendized for City Council Meeting of (if necessary): October 6, 2014 (approved.)
If you have questions on this process, please contact the City Attorney's Office at 485-3080.
* Council approval is required if contract is over $20,000 on a cumulative basis.