SAN RAFAEL
THE CITY WITH A MISSION
Agenda Item No: 5.1
Meeting Date: December 19, 2016
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works
Prepared by: Bill Guerin, City Manager Approval: C
Director of Public Works
File No.: 06.01.225
TOPIC: ESSENTIAL FACILITIES DEMOLITION PROJECT — FIRE STATIONS 52 & 57
SUBJECT: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN RAFAEL
AUTHORIZING THE CITY MANAGER TO AWARD A CONSTRUCTION
CONTRACT FOR CITY OF SAN RAFAEL ESSENTIAL FACILITIES
DEMOLITION PROJECTS — FIRE STATIONS 52 & 57- TO CVE CONTRACTING
GROUP, INC., IN THE AMOUNT OF $293,000
RECOMMENDATION: Adopt the resolution authorizing the City Manager to award the construction
contract to CVE Contracting Group, Inc., dba Central Valley Environmental.
BACKGROUND: Measure E passed on November 5, 2013 extending for 20 years an existing 0.5% sales
tax and increasing it by 0.25%. In 2014, the City hired Mary McGrath Architects and Kitchell to create a
comprehensive and operationally forward -thinking Essential Facilities Strategic Plan for the City of San
Rafael. The plan would guide the City through the replacement and/or seismic upgrade of the City's
essential facilities to ensure their ability to serve the community in the event of a major earthquake or
other potential disasters.
The Strategic Plan determined that Fire Stations 52 & 57 were past their useful life and should be
replaced at their existing locations. To achieve increased capacity, both stations will be enlarged to allow
the placement of paramedic ambulances. Additionally, because Fire Station 52 is the training site for the
Fire Department, the new facility will include replacement of a training classroom and tower.
The purpose of this Council item is to award a contract for the demolition of Fire Stations 52 & 57. The
work will include the demolition of the buildings and their foundations, a 5 -story training tower, a buried
concrete water tank, fencing, asphalt pavement, tree removal, utility removal and the abatement of
hazardous materials.
ANALYSIS: The project was advertised in accordance with San Rafael's Municipal Code on November
17, 2016 and November 23, 2016. On December 9, 2016 at 2:00 PM the following bids were received
and read aloud. Bid summary is as follows:
FOR CITY CLERK ONLY
File No.: 4-1-694 x 12-22
Council Meeting: 12/19/2016
Disposition: Resolution 14252
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
BIDDER
CVE Contracting Group
Silverado Contractors
Bay Area Engineering
AMOUNT
$293,000.00
$487,900.00
$292,883.00 (non-responsive)
The City received 3 -bids with Bay Area Engineering, Inc. as the apparent low bidder. After review of
their bid packages by Public Works, Kitchell and outside legal counsel, it was determined that the bid
from Bay Area Engineering Inc. was incomplete and deemed non-responsive. Staff have reviewed the
other bids and find them to be complete and in compliance with the contract documents. Based on this
review, staff and the City's consultant team recommend that the City Council authorize the City Manager
to award the Demolition contract for Station 52 & 57 to CVE Contracting, Inc., as the lowest responsive
and responsible bidder, in the amount of $293,000.00.
PUBLIC OUTREACH: City staff have met with neighbors near the project sites throughout the year to
explain the project designs and provide them with a time frame for the temporary relocation of the police
and fire departments as well as the overall timeline for construction. They have also held open houses at
the existing fire stations and done considerable media outreach to update the public on the upcoming
projects.
FISCAL IMPACT: This project is supported by Measure E funds.
Funding Source
Funding Source
Measure E
Total Available Funds
Expenses
Amount
Note(s)
This project was listed in the City's Capital
$323,000.00 Improvement Program for Fiscal Year 16/17
$323,000.00
The demolition of fire stations 52 and 57 is a component of the overall Measure E project. To clarify this
specific project, only the demolition expenses are shown below.
Category
Construction -02
Construction -02
Subtotal Construction
CIJ 9WIX113
Amount
Note(s)
$293,000.00 Contract with CVE Contracting Group, Inc.
$30,000.00 Contingency (approximately 10%)
$323,000.00
Adopt the resolution awarding the contract to CVE Contracting Group, Inc. in the amount of
$293,000.00, in a form approved by the City Attorney, and authorizing a $30,000.00 project
contingency.
2. Do not award the contract, reject all bids, and direct staff to rebid the project. If this option is
chosen, rebidding will delay construction and will incur added cost to the City for the additional
time during which the Fire Department is relocated to temporary facilities.
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 3
ACTION REQUIRED: Adopt the resolution awarding the contract to CVE Contracting Group, Inc. in
the amount of $293,000.00, in a form approved by the City Attorney, and authorizing a $30,000.00
project contingency.
ATTACHMENTS:
• Resolution
• Agreement
RESOLUTION NO. 14252
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN RAFAEL
AUTHORIZING THE CITYMANAGER TO AWARD A CONSTRUCTION CONTRACT
FOR CITY OF SAN RAFAEL ESSENTIAL FACILITIES DEMOLITION PROJECT —FIRE
STATIONS 52 AND 57, TO CVE CONTRACTING GROUP, INC. IN THE AMOUNT OF
$293,000.00.
WHEREAS, on the 9th day of December, 2016, pursuant to due and legal notice
published in the manner provided by law, inviting sealed bids or proposals for the work
hereinafter mentioned, as more fully appears from the Affidavit of Publication thereof on file in
the office of the City Clerk of the City of San Rafael, California, the City Clerk of said City did
publicly open, examine, and declare all sealed bids or proposals for doing the following work in
said City, to wit:
"SAN RAFAEL ESSENTIAL FACILITIES DEMOLITION PROJECT
FIRE STATIONS 52 AND 57"
City Project No. 11214, 11292, 11293
in accordance with the plans and specifications therefore on file in the office of said City Clerk;
and
WHEREAS, the bid of CVE Contracting Group, Inc., dba Central Valley Environmental
(CVE Contracting), at the unit prices stated in its bid was and is the lowest and best bid for said
work and said bidder is the lowest responsive and responsible bidder.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF SAN RAFAEL
RESOLVES as follows:
1. The bid of CVE Contracting Group, Inc. is hereby accepted at said unit prices and
the contract for said demolition work is hereby awarded to CVE Contracting
Group, Inc., at the unit prices mentioned in said bid.
2. The City Manager and the City Clerk of said City are authorized and directed to
execute the contract with CVE Contracting Group, Inc., in a form approved by the
City Attorney, for said work and to return the bidder's bond upon the execution of
said contract.
3. There are sufficient funds in the Measure E Fund for this project.
4. A contingency in the amount of $30,000 is authorized for this specific project.
5. The City Manager is hereby authorized to take any and all such actions and make
changes as may be necessary to accomplish the purpose of this resolution.
I, ESTHER C. BEIRNE, Clerk of the City of San Rafael, hereby certify that the
foregoing resolution was duly and regularly introduced and adopted at a regular meeting of the
City Council of said City held on Monday, the 19th day of December, 2016 by the following
vote, to wit:
AYES: COUNCILMEMBERS: Bushey, Gamblin & Mayor Phillips
NOES: COUNCILMEMBERS: None
ABSENT: COUNCILMEMBERS: Colin and McCullough
atj�L- '
ESTHER C. BEIRNE, City Clerk
File No.: 06.01.225
00 52 13 - AGREEMENT
THIS AGREEMENT, dated this 4 day of 1 , 2017, by and between
CVE Contracting Group, Inc. DBA Central Valley Environmental
[Name of Contractor] whose place of business is located at:
4263 N. Selland Ave. Fresno, Ca. 93722
[Address of Contractor]
("Contractor'), and the CITY OF SAN RAFAEL ("Owner') acting under and by virtue of the authority
vested in the City of San Rafael by the laws of the State of California.
WHEREAS, City of San Rafael, by its Resolution No. I adopted on the / ZO day of
4 c6r(Se-P) 2of(q awarded to Contractor the following contract:
CITY OF SAN RAFAEL ESSENTIAL FACILITIES DEMOLITION PROJECT —
FIRE STATIONS 52 AND 57
NOW, THEREFORE, in consideration of the mutual covenants hereinafter set forth, Contractor
and City of San Rafael agree as follows:
Article 1. Work
1.1 Contractor shall complete all Work specified in the Contract Documents, in accordance with the
Specifications, Drawings, and all other terms and conditions of the Contract Documents.
Article 2. City of San Rafael Representative and Construction Manager
2.1 City of San Rafael has designated Bill Guerin Director of Public Works will act as City of San
Rafael Representative(s), who will represent City of San Rafael in performing City of San Rafael
duties and responsibilities and exercising City of San Rafael rights and authorities in Contract
Documents. City of San Rafael may change the individual(s) acting as City of San Rafael
Representative(s), or delegate one or more specific functions to one or more specific City of San
Rafael Representatives, including without limitation engineering, architectural, inspection and
general administrative functions, at any time with notice and without liability to Contractor. Each City
of San Rafael Representative is the beneficiary of all Contractor obligations to City of San Rafael,
including without limitation, all releases and indemnities.
2.2 City of San Rafael has designated Kitchell to act as Construction Manager (CM). City of San
Rafael may assign all or part of the City of San Rafael Representative's rights, responsibilities and
duties to Construction Manager. City of San Rafael may change the identity of the Construction
Manager at any time with notice and without liability to Contractor.
2.3 All notices or demands to City of San Rafael under the Contract Documents shall be submitted to
the City of San Rafael 's Representative at:
Kitchell — Raaj Patel, Project Manager
c/o The City of San Rafael,
1400 Fifth Avenue, San Rafael, CA 94901
or to such other person(s) and address(es) as City of San Rafael shall provide to Contractor.
City of San Rafael AGREEMENT 00 52 13 - 1 of 5
Essential Facilities Demolition
Project — Fire Stations 52 and 57
Article 3. Contract Time and Liquidated Damages
3.1 Contract Time.
The Notice to Proceed is tentatively set to be issued on early January 2017.
Contractor shall immediately apply for necessary approvals and permits, prepare required
documents and submittals, and mobilize personnel and equipment to commence the City of San
Rafael Work within 10 calendar days from the date when the Notice to Proceed is issued. City of
San Rafael reserves the right to modify or alter the Commencement Date of the Work.
Contractor shall achieve Final Completion of the entire Work within 48 calendar days from the
date of notice to proceed.
3.2 Liauidated Damaaes.
City of San Rafael and Contractor recognize that time is of the essence of this Agreement and
that City of San Rafael will suffer financial loss in the form of contract administration expenses
(such as project management and consultant expenses), if all or any part of the Work is not
completed including consequential loss of use and disruption of normal operations within the
times specified above, plus any extensions thereof allowed in accordance with the Contract
Documents. Consistent with Article 15 and 16 of Section 00 72 13 (General Conditions),
Contractor and City of San Rafael agree that because of the nature of the Project, it would be
impractical or extremely difficult to fix the amount of actual damages incurred by City of San
Rafael because of a delay in completion of all or any part of the Work. Accordingly, City of San
Rafael and Contractor agree that as liquidated damages for delay, Contractor shall pay City of
San Rafael
3.2.1 Not used.
3.2.2 $500.00 (Five Hundred Dollars) per day for each day that expires after the time specified
herein for the Contractor to achieve Substantial Completion of the entire Building
Construction Work as indicated in Section 00 31 13 (Preliminary Construction Schedule).
These measures of liquidated damages shall apply cumulatively and except as provided below,
shall be presumed to be the damages suffered by City of San Rafael resulting from delay in
completion of the Work.
3.3 Liquidated damages for damages as a result of delays shall cover administrative, overhead,
interest on bonds, and general loss of public use damages suffered by City of San Rafael as a
result of delay or costs of substitute facilities. Liquidated damages shall not cover the cost of
completion of the Work, damages resulting from defective Work, lost revenues or damages
suffered by others who then seek to recover their damages from City of San Rafael (for example,
delay claims of other contractors, subcontractors, tenants, or other third -parties), and defense
costs thereof.
Article 4. Contract Sum
4.1 City of San Rafael shall pay Contractor the Contract Sum for completion of Work in accordance
with Contract Documents as follows:
$293,000.00
TWO HUNDRED AND NINETY THREE THOUSAND AND 00/100
Article 5. Contractor's Representations
City of San Rafael AGREEMENT 00 52 13 - 2 of 5
Essential Facilities Demolition
Project — Fire Stations 52 and 57
In order to induce City of San Rafael to enter into this Agreement, Contractor makes the following
representations and warranties:
5.1 Contractor has visited the Site and has examined thoroughly and understood the nature and
extent of the Contract Documents, Work, Site, locality, actual conditions, as -built conditions, and
all local conditions, and federal, state and local laws and regulations that in any manner may
affect cost, progress, performance or furnishing of Work or which relate to any aspect of the
means, methods, techniques, sequences or procedures of construction to be employed by
Contractor and safety precautions and programs incident thereto.
5.2 Contractor has given City of San Rafael prompt written notice of all conflicts, errors, ambiguities,
or discrepancies that it has discovered in or among the Contract Documents and the written
resolution thereof through Addenda issued by City of San Rafael is acceptable to Contractor.
5.3 Contractor is duly organized, existing and in good standing under applicable state law, and is duly
qualified to conduct business in the State of California.
5.4 Contractor has duly authorized the execution, delivery and performance of this Agreement, the
other Contract Documents and the Work to be performed herein.
5.5 Contractor has listed the following Subcontractors pursuant to the Subcontractor Listing Law,
California Public Contracting Code §4100 et seq. in Section 00430
Article 6. Contract Documents
6.1 Contract Documents consist of the following documents, including all changes, addenda, and
modifications thereto:
The entirety of Division 00, including:
Document 00 51 00
Notice of Award
Document 00 52 13
Agreement
Document 00 55 00
Notice to Proceed
Document 00 65 19
Agreement and Release of Any and All Claims
Document 00 65 36
Guaranty
Document 00 72 13
General Conditions
Document 00 73 00
Special Conditions
Document 00 73 16
Insurance
Document 00 91 13
Addenda
The entirety of Specification Division 01 through Division 31, including:
Drawings and Specifications as attached and referred.
6.2 The Contract Documents may only be amended, modified or supplemented as provided in
Section 00 72 13 (General Conditions).
Article 7. Miscellaneous
7.1 Terms used in this Agreement are defined in Section 00 72 13 (General Conditions) and Section
0142 00 (References) and will have the meaning indicated therein.
7.2 It is understood and agreed that in no instance are the persons signing this Agreement for or on
behalf of City of San Rafael or acting as an employee, agent, or representative of City of San
Rafael, liable on this Agreement or any of the Contract Documents, or upon any warranty of
authority, or otherwise, and it is further understood and agreed that liability of the City of San
Rafael is limited and confined to such liability as authorized or imposed by the Contract
Documents or applicable law.
City of San Rafael AGREEMENT 00 52 13 - 3 of 5
Essential Facilities Demolition
Project — Fire Stations 52 and 57
7.3 Contractor shall not assign any portion of the Contract Documents, and may subcontract portions
of the Contract Documents only in compliance with the Subcontractor Listing Law, California
Public Contracting Code §4100 et seq.
7.4 In entering into a public works contract or a subcontract to supply goods, services or materials
pursuant to a public works contract, Contractor or Subcontractor offers and agrees to assign to
the awarding body all rights, title and interest in and to all causes of action it may have under
Section 4 of the Clayton Act (15 U.S.C. §15) or under the Cartwright Act (Chapter 2 [commencing
with Section 16700] of Part 2 of Division 7 of the Business and Professions Code), arising from
purchases of goods, services or materials pursuant to the public works contract or the
subcontract. This assignment shall be made and become effective at the time City of San Rafael
tenders final payment to Contractor, without further acknowledgment by the parties.
7.5 Copies of the general prevailing rates of per diem wages for each craft, classification, or type of
worker needed to execute the Contract, as determined by Director of the State of California
Department of Industrial Relations, are deemed included in the Contract Documents by reference
and on file at City of San Rafael office, and shall be made available to any interested party on
request. Pursuant to Section 1861 of the Labor Code, Contractor represents that it is aware of
the provisions of Section 3700 of the Labor Code which require every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that Code, and Contractor shall comply with such provisions before commencing the
performance of the Work of the Contract Documents.
7.6 Contractor and each of Contractor's subcontractors agree to complete and verify construction
reports on a form prescribed by the Division of the State Architect and to file the reports no less
than quarterly during construction as required by Title 24; at the completion of the Work; at the
suspension of work for a period of more than one month; whenever the services of Contractor or
any of Contractor's subcontractors are terminated for any reason; and at any time a special verified
report is required by the Division of the State Architect.
7.7 Should any part, term or provision of this Agreement or any of the Contract Documents, or any
document required herein or therein to be executed or delivered, be declared invalid, void or
unenforceable, all remaining parts, terms and provisions shall remain in full force and effect and
shall in no way be invalidated, impaired or affected thereby. If the provisions of any law causing
such invalidity, illegality or unenforceability may be waived, they are hereby waived to the end
that this Agreement and the Contract Documents may be deemed valid and binding agreements,
enforceable in accordance with their terms to the greatest extent permitted by applicable law. In
the event any provision not otherwise included in the Contract Documents is required to be
included by any applicable law, that provision is deemed included herein by this reference (or, if
such provision is required to be included in any particular portion of the Contract Documents, that
provision is deemed included in that portion).
7.8 This Agreement and the Contract Documents shall be deemed to have been entered into in the
County of Marin, State of California, and governed in all respects by California law (excluding
choice of law rules). The exclusive venue for all disputes or litigation hereunder shall be in Marin
County. Both parties hereby waive their rights under California Code of Civil Procedure Section
394 to file a motion to transfer any action or proceeding arising out of the Contract Documents to
another venue. Contractor accepts the Claims Procedure in Section 00700, Article 12,
established under the California Government Code, Title 1, Division 3.6, Part 3, Chapter 5.
City of San Rafael AGREEMENT 00 52 13 - 4 of 5
Essential Facilities Demolition
Project— Fire Stations 52 and 57
IN WITNESS WHEREOF the parties have executed this Agreement in quadruplicate the day and year
first above written.
OWNER:
CITY OF SAN RAFAEL
By:
MWON PDX
Jim S u , CityManag r Ot
By:
CONTRACTOR:
CVE Contracting Group, Inc. DBA Central Valley
Environmental - Tim Williamson
[Contractor's name]
By:
7
Sign ture
CEO
Title
-END OF SECTION-
Cl-ty 61-a1zic
Approved as to PnrrW
4 �2QL nrf
City of San Rafael AGREEMENT
Essential Facilities Demolition
Project- Fire Stations 52 and 57
005213-5of5
00 65 36 - GUARANTY
TO THE CITY OF SAN RAFAEL for construction of
City of San Rafael Essential Facilities Demolition Project — Fire Stations 52 and 57
The undersigned guarantees all construction performed on this Projects and also guarantees all material and
equipment incorporated therein.
Contractor hereby grants to City of San Rafael for a period of one year following the date of Notice of Completion,
or such longer period specified in the Contract Documents, its unconditional warranty of the quality and adequacy
of all of the Work including, without limitation, all labor, materials and equipment provided by Contractor and its
Subcontractors of all tiers in connection with the Work.
Neither final payment nor use or occupancy of the Work performed by the Contractor shall constitute an
acceptance of Work not done in accordance with this Guaranty or relieve Contractor of liability in respect to any
express warranties or responsibilities for faulty materials or workmanship. Contractor shall remedy any defects in
the Work and pay for any damage resulting therefrom, which shall appear within one year, or longer if specified,
from the date of Final Completion.
If within one year after the date of Final Completion, or such longer period of time as may be prescribed by laws
or regulations, or by the terms of Contract Documents, any Work is found to be defective, Contractor shall
promptly, without cost to City of San Rafael and in accordance with City of San Rafael written instructions, correct
such defective Work. Contractor shall remove any defective Work rejected by City of San Rafael and replace it
with Work that is not defective, and satisfactorily correct or remove and replace any damage to other Work or the
work of others resulting therefrom. If Contractor fails to promptly comply with the terms of such instructions, or in
an emergency where delay would cause serious risk of loss or damage, City of San Rafael may have the
defective Work corrected or the rejected Work removed and replaced. Contractor shall pay for all claims, costs,
losses and damages caused by or resulting from such removal and replacement. Where Contractor fails to
correct defective Work, or defects are discovered outside the correction period, City of San Rafael shall have all
rights and remedies granted by law.
Inspection of the Work shall not relieve Contractor of any of its obligations under the Contract Documents. Even
though equipment, materials, or Work required to be provided under the Contract Documents have been
inspected, accepted, and estimated for payment, Contractor shall, at its own expense, replace or repair any such
equipment, material, or Work found to be defective or otherwise not to comply with the requirements of the
Contract Documents up to the end of the guaranty period.
All abbreviations and definitions of terms used in this Agreement shall have the meanings set forth in the Contract
Documents, including, without means of limitation, Section 014200 (References and Definitions).
The foregoing Guaranty is in addition to any other warranties of Contractor contained in the Contract Documents,
and not in lieu of, any and all other liability imposed on Contractor under the Contract Documents and at law with
respect to Contractor's duties, obligations, and performance under the Contract Documents. In the event of any
conflict or inconsistency between the terms of this Guaranty and any warranty or obligation of the Contractor
under the Contract Documents or at law, such inconsistency or conflict shall be resolved in favor of the higher
level of obligation of the Contractor.
CVE Contracting Group, Inc. DBA Central Valleu Environmental 4263 N. Selland Ave.
F' Vure�
Address
Fresno, Ca. 93722
Sig City/State/Zip
Tim Williamson - CEO 1/4/2017
Name and Title Date
-END OF SECTION -
City of San Rafael GUARANTY 00 65 36 - 1 of 1
Essential Facilities Demolition
Project — Fire Stations 52 and 57
Central Vallev Office
3443 W. Gettysburg Avenue Fresno, CA 93722
P: (559) 222-1149 1 F: (559) 222-1174
TO:
Northern California/Bav Area Office
35500 S. Welty Road Vernalis, CA 95385
P: (209) 239-9676 1 F: (209)-629-8837
CONTRACTOR'S LICENSE #: 905631 A, B, C-21, C-22, ASB, IHAZ
Serving Entire Northern California, Bay Area, and San Joaquin Valley
Transmittal Sheet
FROM.
Bill Guerin Dustin Drake
COMPANY- DATE.
City of San Rafael January 5, 2017
RE:
Contract Documents
❑ URGENT ■ FOR REVIEW ❑ PLEASE COMMENT ❑ PLEASE REPLY ❑ PLEASE RECYCLE
NOTES COMMENTS.
Bill,
Enclosed are the following:
(2) copies of the signed agreement
(2) copies of the signed guaranty
The performance and payment bond
Our insurance cert for the project.
Please let me know if you need anything else.
Thank you,
Dustin Drake
CVE Demolition
(559) 288-7588
4263 N. Selland Ave. Fresno, Ca. 93722 — Phone: (559) 222-1149 — Fax: (559) 222-1174
Email- dustind@cvecorp.com
RECEIVED
JAN 0 6 2017
lSAFEGn OFN RAAL
Bond No.: 106574061
Premium: $4,835.00
00 61 13 - CONSTRUCTION PERFORMANCE BOND
THIS CONSTRUCTION PERFORMANCE BOND ('Bond") is dated 1/4/2017 , is in the penal
sum of
Two Hundred Ninety Three Thousand Dollars and 00/100 ($293.000.00)
[which is one
hundred percent of the Contract Price], and is entered into by and between the parties listed below to
ensure the faithful performance of the Construction Contract listed below. This Bond consists of this page
and the Bond Terms and Conditions para raphs 1 througgh 12, attached to this page. Any singular
reference &E Contracting Group, Inc. dba Uentral alley Environmen�I`'COntraClor ),
Travelers Casualty and Surety Comvanv of America ("Surety"), City of San Rafael ("City of San Rafael") or
other party shall be considered plural where applicable.
CONTRACTOR:
CVE Contracting Group, Inc. dba Central Valley Environmental
Name
4263 N. Selland Ave.
Address
Fresno, CA 93722
City/State/Zip
CONSTRUCTION CONTRACT:
CITY OF SAN RAFAEL
SURETY:
Travelers Casualty and Surety Company of America
Name
11070 White Rock Road, Suite 130
Principal Place of Business
Rancho Cordova. CA 95670
City/State/Zip
Located at San Rafael, California.
Two Hundred Ninety Three Thousand Dollars and 001100
DATED January 4 20 17 in the Amount of $ ($293,000.00) (the "Penal Sum")
CONTRACTOR AS PRINCIPAL
Company: (Corp. Seal)
CVE Contr • Inc. coral Valley Environmental
Signature:
Name and Titl 1 I' �/ /�i•��
SURETY
Company: (Corp. Seal)
Travelers Casualty and Sure ompany o America
Signature:
v
Name and Title yman, torn -Fact
v
BOND TERMS AND CONDITIONS
1. Contractor and Surety, jointly and severally, bind themselves, their heirs, executors,
administrators, successors and assigns to City of San Rafael for the complete and proper
performance of the Construction Contract, which is incorporated herein by reference.
2. If Contractor completely and properly performs all of its obligations under the Construction
Contract, Surety and Contractor shall have no obligation under this Bond.
3. If there is no City of San Rafael Default, Surety's obligation under this Bond shall arise after:
3.1 City of San Rafael has declared a Contractor Default under the Construction Contract
pursuant to the terms of the Construction Contract; and
3.2 City of San Rafael has agreed to pay the Balance of the Contract Sum:
City of San Rafael CONSTRUCTION PERFORMANCE BOND 00 61 13 - 1 of 4
Essential Facilities Demolition
Project — Fire Stations 52 and 57
3.2.1 To Surety in accordance with the terms of this Bond and the Construction Contract;
or
3.2.2 To a contractor selected to perform the Construction Contract in accordance with the
terms of this Bond and the Construction Contract.
4. When City of San Rafael has satisfied the conditions of paragraph 3, Surety shall promptly (within
30 days) and at Surety's expense elect to take one of the following actions:
4.1 Arrange for Contractor, with consent of City of San Rafael, to perform and complete the
Construction Contract (but City of San Rafael may withhold consent, in which case the
Surety must elect an option described in paragraphs 4.2, 4.3 or 4.4, below); or
4.2 Undertake to perform and complete the Construction Contract itself, through its agents or
through independent contractors; provided, that Surety may not select Contractor as its
agent or independent contractor without City of San Rafael consent; or
4.3 Undertake to perform and complete the Construction Contract by obtaining bids from
qualified contractors acceptable to City of San Rafael for a contract for performance and
completion of the Construction Contract, and, upon determination by City of San Rafael of
the lowest responsible bidder, arrange for a contract to be prepared for execution by City of
San Rafael and the contractor selected with City of San Rafael concurrence, to be secured
with performance and payment bonds executed by a qualified surety equivalent to the
bonds issued on the Construction Contract; and, if Surety's obligations defined in
paragraph 6, below, exceed the Balance of the Contract Sum, then Surety shall pay to City
of San Rafael the amount of such excess; or
4.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor
and with reasonable promptness under the circumstances, and, after investigation and
consultation with City of San Rafael, determine in good faith its monetary obligation to City
of San Rafael under paragraph 6, below, for the performance and completion of the
Construction Contract and, as soon as practicable after the amount is determined, tender
payment therefore to City of San Rafael with full explanation of the payment's calculation.
If City of San Rafael accepts Surety's tender under this paragraph 4.4, City of San Rafael
may still hold Surety liable for future damages then unknown or unliquidated resulting from
the Contractor Default. If City of San Rafael disputes the amount of Surety's tender under
this paragraph 4.4, City of San Rafael may exercise all remedies available to it at law to
enforce Surety's liability under paragraph 6, below.
If Surety does not proceed as provided in paragraph 4, above, then Surety shall be deemed to be
in default on this Bond ten days after receipt of an additional written notice from City of San
Rafael to Surety demanding that Surety perform its obligations under this Bond. At all times City
of San Rafael shall be entitled to enforce any remedy available to City of San Rafael at law or
under the Construction Contract including, without limitation, and by way of example only, rights
to perform work, protect work, mitigate damages, and advance critical work to mitigate schedule
delay, or coordinate work with other consultants or contractors.
Surety's monetary obligation under this Bond is limited by the Amount of this Bond identified
herein as the Penal Sum. This monetary obligation shall augment the Balance of the Contract
Sum. Subject to these limits, Surety's obligations under this Bond are commensurate with the
obligations of Contractor under the Construction Contract. Surety's obligations shall include, but
are not limited to:
6.1 The responsibilities of Contractor under the Construction Contract for completion of the
Construction Contract and correction of defective work;
City of San Rafael CONSTRUCTION PERFORMANCE BOND 0061 13 - 2 of 4
Essential Facilities Demolition
Project — Fire Stations 52 and 57
6.2 The responsibilities of Contractor under the Construction Contract to pay liquidated
damages, and for damages for which no liquidated damages are specified in the
Construction Contract, actual damages caused by non-performance of the Construction
Contract including, but not limited to, all valid and proper back charges, offsets, payments,
indemnities, or other damages;
6.3 Additional legal, design professional and delay costs resulting from Contractor Default or
resulting from the actions or failure to act of the Surety under paragraph 4, above (but
excluding attorney's fees incurred to enforce this Bond).
7. No right of action shall accrue on this Bond to any person or entity other than City of San Rafael
or its successors or assigns.
Surety hereby waives notice of any change, alteration or addition to the Construction Contract or
to related subcontracts, purchase orders and other obligations, including changes of time. Surety
consents to all terms of the Construction Contract, including provisions on changes to the
Contract. No extension of time, change, alteration, modification, deletion, or addition to the
Contract Documents, or of the work required there under, shall release or exonerate Surety on
this Bond or in any way affect the obligations of Surety on this Bond.
Any proceeding, legal or equitable, under this Bond shall be instituted in the courts of the County
of Marin. Communications from City of San Rafael to Surety under paragraph 3.1 of this Bond
shall be deemed to include the necessary agreements under paragraph 3.2 of this Bond unless
expressly stated otherwise.
10. All notices to Surety or Contractor shall be mailed or delivered (at the address set forth on the
signature page of this Bond), and all notices to City of San Rafael shall be mailed or delivered as
provided in Section 00 52 13 (Agreement). Actual receipt of notice by Surety, City of San Rafael
or Contractor, however accomplished, shall be sufficient compliance as of the date received at
the foregoing addresses.
11. Any provision in this Bond conflicting with any statutory or regulatory requirement shall be
deemed deleted here from and provisions conforming to such statutory requirement shall be
deemed incorporated herein.
12. Definitions.
12.1 Balance of the Contract Sum: The total amount payable by City of San Rafael to Contractor
pursuant to the terms of the Construction Contract after all proper adjustments have been
made under the Construction Contract, for example, deductions for progress payments
made, and increases/decreases for approved modifications to the Construction Contract.
12.2 Construction Contract: The agreement between City of San Rafael and Contractor
identified on the signature page of this Bond, including all Contract Documents and
changes thereto.
12.3 Contractor Default: Material failure of Contractor, which has neither been remedied nor
waived, to perform or otherwise to comply with the terms of the Construction Contract
including, but not limited to, "default" or any other condition allowing a termination for cause
as provided in Section 00 72 13 (General Conditions).
12.4 City of San Rafael Default: Material failure of City of San Rafael, which has neither been
remedied nor waived, to pay Contractor progress payments due under the Construction
Contract or to perform other material terms of the Construction Contract, if such failure is
the cause of the asserted Contractor Default and is sufficient to justify Contractor
termination of the Construction Contract.
City of San Rafael CONSTRUCTION PERFORMANCE BOND 0061 13 - 3 of 4
Essential Facilities Demolition
Project — Fire Stations 52 and 57
-END OF SECTION -
City of San Rafael CONSTRUCTION PERFORMANCE BOND 0061 13 - 4 of 4
Essential Facilities Demolition
Project — Fire Stations 52 and 57
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
Civil Code § 1189
A notary public or other officer completing this certificate verifies only the identity of the
individual who signed the document to which this certificate is attached, and not the
truthfulness, accuracy, or validity of that document.
State of California )
ss
County of Fresno )
On l ZD— , before me, Bonnie Gonzalez, Notary Public, personally appeared
Cody Lyman , who proved to me on the basis of satisfactory evidence to be the person{}
whose name{4 is4r-e subscribed to the within instrument and acknowledged to me that
he/she/theyexecuted the same in his/4efA4eif authorized capacity4es4, and that by
his/4"F/44e4 signaturek4 on the instrument the personk4, or the entity upon behalf of which
the persons} acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
(Seal)
Signature _
Bonnie�onzalezQNotary Public J
a.�. c.r..
ES7iIPP°GONZALEZ f
J -
NOTtRY PUBLIC - CALIFORNIA
C0PAf:41SSI0i4 # 20331113
-=?
My Comm. E:cP. July '12, 2017 6
(Seal)
Signature _
Bonnie�onzalezQNotary Public J
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT CIVIL CODE: § 1189
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of Calif o �^ )
County of�
On ' �~ before me,--,—, Wou) `t a�nd
Date t
ert Name T'tle f the Officer
personally appeared I l [Y1
Name(s) of Signer(s)
who proved to me on the basis of satisfactory evidence to be the person(g) whose name* is/aie
subscribed to the within instrument and acknowledged to me that he/trjr4 executed the same in
his/hqr/thKr authorized capacity(i�Q, and that by his/*/th*ir signature(K6n the instrument the persortA,
or the entity upon behalf of which the person acted, executed the instrument.
TIFFANY L. FARLEY
Commission # 2139413 Z
< Notary Public -California Z
Z
Fresno County
MM Comm. Expires Jan 7, 2020
Place Notary Seal Above
I certify under PENALTY OF PERJURY under the laws
of the State of California that the foregoing paragraph
is true and correct.
WITNESS my hand and official seal.
Sign ture
"y e �jj A
Sign e of Nof4y Publi
_�)
OPTIONAL
Though this section is optional, completing this information can deter alteration of the document or
fraudulent reattachment of this form to an unintended document.
Description of Attached Document nn
Title or Type of Document: 7n��1 PP r;--, f ,N1f At 0 T,'A
Document Date: I _H —i Number of Pages: y
Signer(s) Other Than Named Above:
Capacity(ies) Cl1 "d lbSig r(s)
Signer's Name: 1 i M MM'i
orporate Officer — Title(s): Tf,0.� -
G Partner — ❑ Limited ❑ General
❑ Individual ❑ Attorney in Fact
❑ Trustee ❑ Guardian or Conservator
n Other:
Signer Is Representing:
Signer's Name:
❑ Corporate Officer — Title(s):
❑ Partner — ❑ Limited ❑ General
❑ Individual ❑ Attorney in Fact
❑ Trustee ❑ Guardian or Conservator
❑ Other:
Signer Is Representing:
©2016 National Notary Association - www.NationalNotary.org - 1 -800 -US NOTARY (1-800-876-6827) Item #5907
Bond No.: 106574061
Premium: Included in
Performance Bond
00 61 16 - CONSTRUCTION LABOR AND MATERIAL PAYMENT BOND
THIS CONSTRUCTION LABOR AND MATERIAL PAYMENT BOND ("Bond") is dated 1/4/2017
is in the penal sum of
Two Hundred Ninety Three Thousand Dollars and 00/100 ($293,000.00)
[one hundred percent of the Contract Price], and is entered into by and between the parties listed below
to ensure the payment of claimants under the Construction Contract listed below. This Bond consists of
this page and the Bony gyp ancd Cyoltions, paragraphs 1 through 13, attached to this page. Any
E ontrac ing roup, nc. a
singular reference to Central VauevEnvirnnmeniai ("Contractor"),
Travelers Casualty and Surety Company of America ("Surety"), the City of San Rafael ("City of San
Rafael") or other party shall be considered plural where applicable.
CONTRACTOR:
CVE Contracting Group, Inc. dba Central Valley Environmental
Name
4263 N. Selland Ave.
Address
Fresno, CA 93722
City/State/Zip
CONSTRUCTION CONTRACT:
SURETY:
Travelers Casualty and Surety Company of America
Name
11070 White Rock Road, Suite 130
Principal Place of Business
Rancho Cordova, CA 95670
City/State/Zip
City of San Rafael Essential Facilities Demolition Project — Fire Stations 52 and 57
at San Rafael, California.
Two Hundred Ninety Three Thousand Dollars and 00.' 100
DATED January4 20 17 in the Amount of $(6293,000.00) (the 'Penal
Sum")
CONTRACTOR AS PRINCIPAL
Company: eal
CVE Contr tin (Corp.Grou7 nc. d ,a Central Valley Environmental
Signature: �/'
Name and Title: r
SURETY PPaai�ll
Cor trpanl�rs Casualty ancFSGre ompany of merica
Signature: _
.�
Name and Title: Codv Lvman, ttorne n -Fact
BOND TERMS AND CONDITIONS
Contractor and Surety, jointly and severally, bind themselves, their heirs, executors,
administrators, successors and assigns to City of San Rafael and to Claimants, to pay for labor,
materials and equipment furnished for use in the performance of the Construction Contract, which
is incorporated herein by reference.
With respect to City of San Rafael, this obligation shall be null and void if Contractor:
2.1 Promptly makes payment, directly or indirectly, for all sums due Claimants; and
2.2 Defends, indemnifies and holds harmless City of San Rafael from all claims, demands,
liens or suits by any person or entity who furnished labor, materials or equipment for use
in the performance of the Construction Contact, provided City of San Rafael has promptly
notified Contractor and Surety (at the address set forth on the signature page of this
Bond) of any claims, demands, liens or suits and tendered defense of such claims,
demands, liens or suits to Contractor and Surety, and provided there is no City of San
Rafael Default.
City of San Rafael CONSTRUCTION LABOR AND MATERIAL PAYMENT BOND 00 61 16 - 1 of 3
Essential Facilities Demolition
Project — Fire Stations 52 and 57
3. With respect to Claimants, this obligation shall be null and void if Contractor promptly makes
payment, directly or indirectly through its Subcontractors, for all sums due Claimants. If
Contractor or its Subcontractors, however, fail to pay any of the persons named in Section 3181
of the California Civil Code, or amounts due under the Unemployment Insurance Code with
respect to Work or labor performed under the Contract, or for any amounts required to be
deducted, withheld, and paid over to the Employment Development Department from the wages
of employees of Contractor or Subcontractors pursuant to Section 13020 of the Unemployment
Insurance Code, with respect to such Work and labor, then Surety shall pay for the same, and
also, in case suit is brought upon this Bond, a reasonable attorney's fee, to be fixed by the court.
4. Consistent with the California law, Civil Code §8000, et seq., Surety shall have no obligation to
Claimants under this Bond unless the Claimant has satisfied all applicable notice requirements.
5. Surety's total obligation shall not exceed the amount of this Bond, and the amount of this Bond
shall be credited for any payments made in good faith by Surety under this Bond.
6. Amounts due Contractor under the Construction Contract shall be applied first to satisfy claims, if
any, under any Construction Performance Bond and second, to satisfy obligations of Contractor
and Surety under this Bond.
7. City of San Rafael shall not be liable for payment of any costs, expenses, or attorney's fees of
any Claimant under this Bond, and shall have under this Bond no obligations to make payments
to, give notices on behalf of, or otherwise have obligations to Claimants under this Bond.
8. Surety hereby waives notice of any change, including changes of time, to the Construction
Contract or to related subcontracts, purchase orders and other obligations. Surety further hereby
stipulates and agrees that no change, extension of time, alteration or addition to the terms of the
Construction Contract, or to the Work to be performed there under, or materials or equipment to
be furnished there under or the Specifications accompanying the same, shall in any way affect its
obligations under this Bond, and it does hereby waive any requirement of notice or any such
change, extension of time, alteration or addition to the terms of the Construction Contract or to
the Work or to the Specifications or any other changes.
9. Suit against Surety on this Bond may be brought by any Claimant, or its assigns, at any time after
the Claimant has furnished the last of the labor or materials, or both, but, per Civil Code §9558,
must be commenced before the expiration of six months after the period in which stop notices
may be filed as provided in Civil Code §8508.
10. All notices to Surety or Contractor shall be mailed or delivered (at the address set forth on the
signature page of this Bond), and all notices to City of San Rafael shall be mailed or delivered as
provided in Section 00 52 13 (Agreement). Actual receipt of notice by Surety, City of San Rafael
or Contractor, however accomplished, shall be sufficient compliance as of the date received at
the foregoing addresses.
11. This Bond has been furnished to comply with the California Law including, but not limited to, Civil
Code §9500, et seq. Any provision in this Bond conflicting with said statutory requirements shall
be deemed deleted here from and provisions conforming to such statutory or other legal
requirements shall be deemed incorporated herein. The intent is that this Bond shall be
construed as a statutory bond and not as a common law bond.
12. Upon request by any person or entity appearing to be a potential beneficiary of this Bond,
Contractor shall promptly furnish a copy of this Bond or shall permit a copy to be made.
13. Definitions.
City of San Rafael CONSTRUCTION LABOR AND MATERIAL PAYMENT BOND 0061 16 - 2 of 3
Essential Facilities Demolition
Project — Fire Stations 52 and 57
13.1 Claimant: An individual or entity having a direct contract with Contractor or with a
Subcontractor of Contractor to furnish labor, materials or equipment for use in the
performance of the Contract, as further defined in California Civil Code §8004. The intent
of this Bond shall be to include without limitation in the terms "labor, materials or
equipment' that part of water, gas, power, light, heat, oil, gasoline, telephone service or
rental equipment used in the Construction Contract, architectural and engineering
services required for performance of the Work of Contractor and Contractor's
Subcontractors, and all other items for which a stop notice might be asserted.
13.2 Construction Contract: The agreement between City of San Rafael and Contractor
identified on the signature page of this Bond, including all Contract Documents and
changes thereto.
13.3 City of San Rafael Default: Material failure of City of San Rafael Administrative Office,
which has neither been remedied nor waived, to pay the Contractor as required by the
Construction Contract, provided that failure is the cause of the failure of Contractor to pay
the Claimants and is sufficient to justify termination of the Construction Contract.
-END OF SECTION -
City of San Rafael CONSTRUCTION LABOR AND MATERIAL PAYMENT BOND 0061 16 - 3 of 3
Essential Facilities Demolition
Project — Fire Stations 52 and 57
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
Civil Code § 1189
A notary public or other officer completing this certificate verifies only the identity of the
individual who signed the document to which this certificate is attached, and not the
truthfulness, accuracy, or validity of that document.
State of California )
ss
County of Fresno )
On before me, Bonnie Gonzalez, Notary Public, personally appeared
Codv Lvman , who proved to me on the basis of satisfactory evidence to be the person{}
whose names} is/afe subscribed to the within instrument and acknowledged to me that
he/`h executed the same in his/4efA42FF authorized capacitykie4, and that by
his/ e4 signature(4 on the instrument the personjs}, or the entity upon behalf of which
the person{s4 acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
ty
BONNIE GONZAI
NOTARY PUBLIC - CALIFORNIA �
COM".41SSIOil # 203311©
FRESNO COl.1NiY �
n^My Comm. Exp. July '12, 2017
(Seal)
Signature., _ (94Y1p�k0C
Bonnie onzalez, Notary Public
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
CIVIL CODE § 1189
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California )
County of
On I '-'r i before me,'_1.k1� �%.(� ��,rU►litV
Date ( r In ert Name and Title d� the OfficeVUY r
personally appeared
Name(s) of Signer(s)
who proved to me on the basis of satisfactory evidence to be the person
whose name is%a'
subscribed to the within instrument and acknowledged to me that he/ )Q
executed the same in
his/h(r/tFi�yr authorized capacity), and that by his/P1@r1tN r signature on thcSinstrument the person
or the entity upon behalf of which the personKacted, executed the instrument.
TIFFANY L. FARLEY
Commission # 2139413 =
-� Notary Public - California
Fresno County
MV Comm. Expires Jan 7, 2020
Place Notary Seal Above
I certify under PENALTY OF PERJURY under the laws
of the State of California that the foregoing paragraph
is true and correct.
WITNESS my hand and official seal.
Signture_
Sig0a-1of Notary u lic
OPTIONAL
Though this section is optional, completing this information can deter alteration of the document or
fraudulent reattachment of this form to an unintended document.
Description of Attached Doigyme t ,n, II ,
Title or Type of Do�ume t: bkr4 A'I� //d D, PG(�1T1/VI/fT-
Document Date. ( `� Number of Pages:
Signer(s) Other Than Named Above:
Capacity(les) C g�mdl by Signers -
Signer's Name: )�f i/ �l y C
/ccorporate Officer — Title(s):
❑ Partner — Limited Gen ral
❑ Individual ❑ Attorney in Fact
❑ Trustee ❑ Guardian or Conservator
F-1 Other:
Signer Is Representing:
Signer's Name:
❑ Corporate Officer — Title(s)-
El Partner — Limited General
❑ Individual ❑ Attorney in Fact
❑ Trustee ❑ Guardian or Conservator
❑ Other:
Signer Is Representing:
©2016 National Notary Association • www.NationalNotary.org - 1 -800 -US NOTARY (1-800-876-6827) Item #5907
i
TRAVELERSAj
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
POWER OF ATTORNEY
Farmington Casualty Company St. Paul Mercury Insurance Company
Fidelity and Guaranty Insurance Company Travelers Casualty and Surety Company
Fidelity and Guaranty Insurance Underwriters, Inc. Travelers Casualty and Surety Company of America
St. Paul Fire and Marine Insurance Company United States Fidelity and Guaranty Company
St. Paul Guardian Insurance Company
Attorney -In Fact No. 227966
Certificate No. 006955490
KNOW ALL MEN BY THESE PRESENTS: That Farmington Casualty Company, St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance
Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety Company, Travelers Casualty and Surety Company of America, and United States
Fidelity and Guaranty Company are corporations duly organized under the laws of the State of Connecticut, that Fidelity and Guaranty Insurance Company is a
corporation duly organized under the laws of the State of Iowa, and that Fidelity and Guaranty Insurance Underwriters, Inc., is a corporation duly organized under the
laws of the State of Wisconsin (herein collectively called the "Companies"), and that the Companies do hereby make, constitute and appoint
John C. Day, Steven P. Edwards, Lyn Genito, Bonnie Gonzalez, and Cody Lyman
of the City of ._,_,__,,..Fresno State of_.... California their true and lawful Attorney(s)-in-Fact,
each in their separate capacity if more than one is named above, to sign, execute, sea] and acknowledge any and all bonds, recognizances, conditional undertakings and
other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of
contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
IN WITNESS WHEREOF, the Companies have caused this instrument to be signed and their corporate seals to be hereto affixed, this 25th
day of August 2016
Farmington Casualty Company
Fidelity and Guaranty Insurance Company
Fidelity and Guaranty Insurance Underwriters, Inc.
St. Paul Fire and Marine Insurance Company
St. Paul Guardian Insurance Company
St. Paul Mercury Insurance Company
Travelers Casualty and Surety Company
Travelers Casualty and Surety Company of America
United States Fidelity and Guaranty Company
�°t4� j �,1N1Yt� FIRe 6 4 ;'N � �� •.•{ 1Hsuq `E � Tr aHo sua"�' Y
O
Q' 0.PON .Y4 .'iii G,P •t
�ti0 ._. A,�,m iW it�FPORAlf::i^•. aP '� S ��4Rn
Z „t 9 8 Z_ y 977 '" ® i j d a: _-_ W tiARTFORD< FN9TFOF�,
ct�S 1.1iJ�1 T ".. S
SEA'o t CONN. ^� Cay' 1896
�• �n 1.`;
w.wn� NY4
State of Connecticut
City of Hartford ss.
By:O
Robert L. Raney, Senior Vice President
On this the 25th day of August 2016 before me personally appeared Robert L. Raney, who acknowledged himself to
be the Senior Vice President of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters, Inc., St. Paul
Fire and Marine Insurance Company, St. Paul Guardian Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety Company, Travelers
Casualty and Surety Company of America, and United States Fidelity and Guaranty Company, and that he, as such, being authorized so to do, executed the foregoing
instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer.
Sot,
In Witness Whereof, I hereunto set my hand and official seal My Commission expires the 30th day of June, 2021. Marie C. Tetreault. Notary Public
58440-5-16 Printed in U.S.A.
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: C1464" t� tuvw F'r
Project Manager: Click here to enter text.;�(erfv►
Extension: Click here to enter text.
Contractor Name: Click here to enter text. L V15 Cc-nf"r�-r
Contractor's Contact: Click here to enter text. D +k S'n D�
Contact's Email: Click here to enter text. 61 Us V, (A C-e-ve. e_ c.
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step RESPONSIBLEI
DESCRIPTION
COMPLETED
DEPARTMENT
DATE
1 Project Manager
a. Email PINS Introductory Notice to Contractor
Click here to
enter a date.
b. Email contract (in Word) & attachments to City
Click here to
Atty c/o Laraine.Gittens@cityofsanrafael.org
enter a date.
2 City Attorney
a. Review, revise, and comment on draft agreement
Click here to
and return to Project Manager
enter a date.
b. Confirm insurance requirements, create Job on
Click here to
PINS, send PINS insurance notice to contractor
enter a date.
3 Project Manager
Forward three (3) originals of final agreement to
Click here to
contractor for their signature I
enter a date.
4 Project Manager
When necessary, * contractor -sinned agreement
❑ N/A
agendized for Council approval
*P5A > $20,000; or Purchase > $35,000; or
Or
Public Works Contract > $125,000
r<
Date of Council approval
Clich re toenter
a date.
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
5 Project Manager
Forward signed original agreements to City
Attorney with printed copy of this routing form
6 City Attorney
I Review and approve hard copy of signed I
�7
agreement
�/
7 City Attorney
I Review and approve insurancq in PINS, and bonds
`r'e""`t `i``"'`/'r
/
17
(for Public Works Contracts) PrNs.
8 City Manager/ Mayor
I Agreement executed by Council authorized official
9 City ClerkI Attest signatures, retains original agreement and
forwards copies to Project Manager 1 .2-11 /t7
REVIEWER
Check/Initial
El
El
ROUTING SLIP / APPROVAL FORM
INSTRUCTIONS: Use this cover sheet with each submittal of a staff report before approval
by the City Council. Save staff report (including this cover sheet) along
with all related attachments in the Team Drive (T:) � CITY COUNCIL
AGENDA ITEMS 4 AGENDA ITEM APPROVAL PROCESS 4 [DEPT -
AGENDA TOPIC]
Agenda Item #
Date of Meeting: 12/19/2016
From: Bill Guerin
Department: Public Works
Date: 12/5/2016
Topic: ESSENTIAL FACILITIES DEMOLITION PROJECT — FIRE STATIONS 52 AND 57.
Subject: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN RAFAEL
AUTHORIZING THE CITY MANAGER TO AWARD A CONSTRUCTION CONTRACT FOR CITY
OF SAN RAFAEL ESSENTIAL FACILITIES DEMOLITION PROJECT — FIRE STATIONS 52 AND
57, TO CVE CONTRACTING GROUP, INC. IN THE AMOUNT OF $293,000.00
Type: ® Resolution ❑ Ordinance
❑ Professional Services Agreement ❑ Other: Staff Report
APPROVALS
® Finance Director
Remarks: Van Bach -approved -after RL change the funding to match exp.
® City Attorney
Remarks: Approved with changes to the Staff Report and Resolution. ETD. 12/14/16
❑ Author, review and accept City Attorney / Finance changes
Remarks:
® City Manager
Remarks: