Agenda Item No: 5.h
Meeting Date: January 17, 2017
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works P�_
Prepared by: Bill Guerin, City Manager Approval:
Director of Public Works (SG)
File No.: 16.01.264
TOPIC: COMPLETION OF RETAINING WALL PROJECT
SUBJECT: ACCEPT COMPLETION OF THE BROOKDALE AVENUE RETAINING WALL PROJECT, CITY
PROJECT NO. 11214, AND AUTHORIZE THE CITY CLERK TO FILE THE NOTICE OF
COMPLETION
RECOMMENDATION: Accept completion of the project and authorize the City Clerk to file the Notice of
Completion.
BACKGROUND: Brookdale Avenue is a one-way loop off of Lincoln Avenue and adjacent to the Irwin
Creek to the north. The area next to the roadway experienced erosion due to the close proximity of
Irwin Creek as it meanders downstream. The creek bank erosion caused instability in the original
stacked rock retaining wall that held up a portion of Brookdale Avenue, and caused the roadway to
subside. In order to support the roadway and allow access to properties, a Cast-in—Drilled Hole (CIDH)
retaining wall system was constructed adjacent to the roadway. This type of repair includes the
installation of closely spaced piles with a concrete cap. If future erosion continues in this area from the
creek, this type of repair can accommodate the installation of a tieback system that will further support
the roadway. In addition, 300 feet of Brookdale Avenue was resurfaced as part of this project.
The project was advertised in accordance with San Rafael's Municipal Code on June 27, 2016, and sealed
bids were publicly opened and read aloud on July 21, 2016, at 10:30 AM. On August 15, 2016, the City
Council adopted a resolution authorizing the Public Works Director to enter into an agreement with the
low bidder, Valentine Corporation. Construction commenced on October 31, 2016. The project was
completed on December 21, 2016. All work was completed within the number of Working Days
allowed. Staff recommends acceptance of the project and recordation of the Notice of Completion.
FOR CITY CLERK ONLY
File No.: 4-1-682
Council Meeting: 01/17/2017
Disposition: Approved staff recommendation
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
ANALYSIS: Pursuant to Civil Code Section 3093 the City is required to record a Notice of Completion
upon acceptance of the improvements by the City. This acceptance initiates a time period during which
project subcontractors may file Stop Notices seeking payment from the City from the funds owed to the
Contractor for the project work.
FISCAL IMPACT: Construction was completed within the original authorized budget of $260,000. The
total project cost, including advertisement, construction, and City staff time are shown in the table
below.
Funding Source:
Project Funding Sources Allocation
Gas Tax Fund (Fund #206) $260,000
Total Available Funds $260,000
Design Costs
Amount
Environmental Document, Topographic Survey, and Geotechnical Report
$9,343.17
Design Subtotal
$9,343.17
Construction Costs
Actual Construction Contract Amount Based on Measured Quantities*
$190,575.52
Contract Change Orders*
$39,979.40
Materials Testing and Sampling
$759.60
Construction Subtotal*
$231,314.52
Total Project Expense
$240,657.69
*Includes the 5% retention to be paid 35 days after Notice of Completion is filed.
ACTION REQUIRED: Staff recommends that the City Council accept completion of the project and
authorize the City Clerk to file the Notice of Completion.
ATTACHMENT: Notice of Completion
Record Without. 'I--'C-
Per
--Per GC 27303 and,
'L When recorded mail to: 2017-0002611
(,
Recorded I REC FEE
City of San Rafael
Official Records I
County of I
Esther C. Beirne, City Clerk
RICHARDa11.nBENSON
1400 Fifth Avenue
Assessor -Recorder I
County Clerk I
P. O. Box 151560
1 t :45A11 19 -Jan -2017 1 Page 1 of 2
San Rafael, CA 94915-1560
SPACE ABOVE THIS LINE FOR RECORDER'S USE
CITY OF SAN RAFAEL
NOTICE OF COMPLETION OF IMPROVEMENT
TO ALL PERSONS WHOM IT MAY CONCERN:
0.00
NOTICE IS HEREBY GIVEN for and on behalf of the City of San Rafael, County of Marin, State of
California, that there has been a cessation of labor upon the work or improvement and that said work or
improvement was completed upon the 21" day of December, 2016 and accepted the 17th day of
January, 2017; that the name, address and nature of the title of the party giving this notice is as follows:
The City of San Rafael, 1400 Fifth Avenue, San Rafael, California, 94901, a municipal corporation, in
the County of Marin, State of California, within the boundaries of which said work or improvement was
made upon land owned by said City and/or over which said City has an easement; that said work or
improvement is described as follows:
BROOKDALE RETAINING WALL PROJECT
CITY PROJECT #11214
and reference is hereby made for a further description thereof to the plans and specifications approved
for said work or improvements now on file in the office of the City Clerk of said City, and said plans
and specifications are hereby incorporated herein by reference thereto; and that the name of the
Contractor who contracted to perform said work and make such improvement is
Valentine Corporation
I declare under penalty of perjury that the foregoing is true and correct.
Executed at San Rafael, California, on TA1411A M , 201-7 .
CITY OF SAN RAFAEL
A Municipal Corporation
By w�
BILL GUERIN
Director of Public Works
A notary public or other officer completing this certificate verifies
only the identity of the individual who signed the document to
which this certificate is attached, and not the truthfulness,
accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF MARIN
Subscribed and sworn to (or affirmed) before me on this / 9744 day of ��u atm' ,
20�, by Bill Guerin, proved to me on the basis of satisfactory evidence to be the person(s) who
appeared before me.
WITNESS my hand and official seal.
Signature e5-5tt'--A C • '��
ESTHER C. BEIRNE
San Rafael City Clerk
File: 16.01.264
�3t;
N RAF,q
ROUTING SLIP / APPROVAL FORM
INSTRUCTIONS: Use this cover sheet with each submittal of a staff report before approval
by the City Council. Save staff report (including this cover sheet) along
with all related attachments in the Team Drive (T:) 4 CITY COUNCIL
AGENDA ITEMS 4 AGENDA ITEM APPROVAL PROCESS -)� [DEPT -
AGENDA TOPIC]
Agenda Item #
Date of Meeting: 1/17/2017
From: Bill Guerin
Department: Public Works
Date: 12/22/2016
Topic: Completion of Retaining Wall Project.
Subject: Accept Completion of the Brookdale Retaining Wall Project, City Project No. 11214 and
Auhtorize the City Clerk to File the Notice of Completion.
Type: ® Resolution ❑ Ordinance
❑ Professional Services Agreement ❑ Other:
APPROVALS
® Finance Director
Remarks: MM - approved 12/30/16
® City Attorney
Remarks: LG -Approved 1/3/17.
® Author, review and accept City Attorney / Finance changes
Remarks: SG - accepted 1/6/2017
® City Manager
Remarks: