HomeMy WebLinkAboutPW Rossi Pump Station Rehabilitation ProjectSAN RAFAEL
THE CITY WITH A MISSION
Agenda Item No: 5.i
Meeting Date: January 17, 2017
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works —�
Prepared by: Bill Guerin, City Manager Approval:
Director of Public Works (SG)
File No.: 08.06.62
TOPIC: ROSSI STORMWATER PUMP STATION REHABILITATION PROJECT
SUBJECT: ACCEPT COMPLETION OF THE ROSSI STORMWATER PUMP STATION REHABILITATION
PROJECT (CITY PROJECT NO. 11191), AUTHORIZE THE CITY CLERK TO FILE THE NOTICE OF
COMPLETION, AND
ADOPT A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN RAFAEL AUTHORIZING
THE CITY MANAGER TO EXECUTE AN AMENDMENT TO THE PROFESSIONAL SERVICES
AGREEMENT WITH CONSOLIDATED CM FOR ADDITIONAL INSPECTION SERVICES IN
CONNECTION WITH THE ROSSI STORMWATER PUMP STATION REHABILITATION PROJECT
AND TO INCREASE THE COMPENSATION BY $15,520, FOR A TOTAL NOT -TO -EXCEED
AMOUNT OF $90,520.
RECOMMENDATION: Accept completion of the project, authorize the City Clerk to file the Notice of
Completion, and adopt the resolution to amend the professional services agreement with Consolidated
CM.
BACKGROUND: The Rossi Stormwater Pump Station, located adjacent to 555 Francisco Boulevard East,
was originally constructed in 1952 by the California Department of Transportation (Caltrans). The 64
year old pump consisting of a concrete structure and three pumps had deteriorated beyond repair. The
failure of this pump station could have resulted in significant flooding on Francisco Boulevard East. On
December 20, 2010, the City Council authorized the Director of Public Works to enter into an agreement
with CSW/Stuber-Stroeh Engineering Group, Inc. to design the Rossi Stormwater Pump Station
Rehabilitation project.
The project was advertised in accordance with San Rafael's Municipal Code on August 21, 2015, and
sealed bids were publicly opened and read aloud on October 6, 2015. On November 16, 2015, the City
Council adopted a resolution authorizing the City Manager to enter into an agreement with the low
bidder, Valentine Corporation. As part of this project, the existing structure (concrete and supporting
beams) and equipment (pumps and electrical) were replaced. In addition, several civil improvements
were constructed, including widening the sidewalk in front of the pump station from 4 feet to 6.5 feet.
FOR CITY CLERK ONLY
File No.: 4-1-673 x 4-1-678 (file full copies in both)
Council Meeting: 01/17/2017
Disposition: Resolution 14262
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
On March 7, 2016, the City Council adopted a resolution authorizing the City Manager to enter into a
professional services agreement with Consolidated CM to provide inspection services associated with
the Rossi Stormwater Rehabilitation Project.
Construction commenced on May 6, 2016. The project was completed on November 9, 2016. All work
was completed within the number of Working Days allowed.
ANALYSIS: Prior to construction, it was anticipated that Consolidated CM would only provide inspection
services on a part-time basis (four hours per day). During construction, it was determined that there
were a number of days where full-time inspection (eight hours) was necessary. Examples include coffer
dam installation and removal, concrete pours, pile drilling, electrical panel installation, pump startup
and testing. The proposed resolution authorizes the City Manager to execute an amendment to the
existing professional services agreement with Consolidated CM to include an additional $15,520 to the
agreement to compensate Consolidated CM for the additional required services, increasing the total
contract amount to $90,520. Due to the nature and timing of the construction, it was not practical or
cost effective to delay the project to amend the inspection services contract. Additionally, the project
finished under the allocated budget amount.
Pursuant to Civil Code Section 3093 the City is required to record a Notice of Completion upon
acceptance of the improvements by the City. This acceptance initiates a time period during which
project subcontractors may file Stop Notices seeking payment from the City from the funds owed to the
Contractor for the project work. Staff recommends acceptance of the project and recordation of the
Notice of Completion.
FISCAL IMPACT: Construction was completed within the original authorized budget of $1,885,392.00.
The total project cost, including advertisement, construction, and City staff time are shown in the table
below.
Funding Source:
Project Funding Sources Allocation Notes
Stormwater Fund (Fund No. 205) $1,885,392.00
Total Available Funds $1,885,392.00
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Paee: 3
Expenses:
Design Costs
Design
Permits
Document Reproduction (i.e. Advertisement)
Design Subtotal
Construction Costs
Actual Construction Contract Amount Based
on Measured Quantities*
Contract Change Orders*
Construction Design Support and Electrical
Engineering
Telemetry and Programming
Materials Testing and Sampling
Construction Inspection
Construction Inspection
PG&E Electrical Services
Construction Subtotal*
Amount I Notes
$158,973.75 CSW/Stuber-Stroeh
$2,963.00 Various regulatory permits
$4,429.52
$166,366.27
$1,342,869.01 Awarded to Valentine Corporation
$54,232.43 Contingency
$29,016.24 CSW/Stuber-Stroeh Agreement
$28,264.00
Telstar Agreement
$3,186.40
Concrete testing and pile drilling observation
$75,000.00
Consolidated CM: Previously Authorized
$15,520.00
Consolidated CM: Proposed Authorization
$56,396.41
Engineering and construction fees
$1,604,484.49
Total Project Expense 1 $1,770,850.76
*Includes the 5% retention to be paid 35 days after Notice of Completion is filed.
ACTION REQUIRED: Staff recommends that the City Council:
1. Accept completion of the project and authorize the City Clerk to file the Notice of Completion;
and
2. Approve the resolution authorizing the City Manager to execute an amendment to the
professional services agreement with Consolidated CM, to include additional inspection services
and compensation therefore in the amount of $15,520, increasing the total not -to -exceed
amount under the agreement to $90,520.
ATTACHMENTS:
1. Notice of Completion; and
2. Resolution authorizing the City Manager to execute an amendment to the professional services
agreement with Consolidated CM for addition inspection services.
RESOLUTION NO. 14262
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN RAFAEL
AUTHORIZING THE CITY MANAGER TO EXECUTE AN AMENDMENT TO THE
PROFESSIONAL SERVICES AGREEMENT WITH CONSOLIDATED CM FOR
ADDITIONAL INSPECTION SERVICES IN CONNECTION WITH THE ROSSI
STORMWATER PUMP STATION REHABILITATION PROJECT, AND TO INCREASE
THE COMPENSATION BY $15,520 FOR A TOTAL NOT -TO -EXCEED AMOUNT OF
$90,520
WHEREAS, the City Council adopted Resolution No. 14076 on March 7, 2016
authorizing the City Manager to enter into a Professional Services Agreement with
Consolidated CM to perform construction inspection services for the Rossi Stormwater Pump
Station Rehabilitation project for an amount not -to -exceed $75,000 (the "Agreement"); and
WHEREAS, the City needed additional construction inspection services during
construction of the Rossi Stormwater Pump Station; and
WHEREAS, the City received a proposal from Consolidated CM, Inc. for additional
inspection services, in an amount not -to -exceed $15,520; and
WHEREAS, Funds in the amount of $15,520 will be appropriated from Stormwater
Fund 205;
WHEREAS, staff has reviewed the proposal and found it to be complete and within
industry standards;
NOW, THEREFORE, BE IT RESOLVED that the City Council hereby
approves and authorizes the City Manager to execute an amendment to the Agreement
with Consolidated CM, in the form attached hereto as Exhibit "A" and incorporated herein
by reference, subject to final approval as to form by the City Attorney, adding inspection
services and increasing the compensation payable, in an additional amount not to exceed
$15,520, for a total contract cost not to exceed $90,520.
BE IT FURTHER RESOLVED that the Director of Public Works is hereby
authorized to take any and all such actions and make changes as may be necessary to
accomplish the purpose of this resolution.
I, ESTHER C. BEIRNE, Clerk of the City of San Rafael, hereby certify that the
foregoing resolution was duly and regularly introduced and adopted at a regular meeting of the
City Council of said City held on Monday, the 17th day of January, 2017 by the following vote, to
wit:
AYES:
COUNCILMEMBERS:
Bushey, Colin, Gamblin, McCullough & Mayor Phillips
NOES:
COUNCILMEMBERS:
None
ABSENT:
COUNCILMEMBERS:
None
ESTHER C. BEIRNE, City Clerk
File No.: 08.06.62
AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT WITH
CONSOLIDATED CM TO PERFORM ADDITIONAL CONSTRUCTION INSPECTION
SERVICES AND INCREASE THE COMPENSATION FOR THE ROSSI
STORMWATER PUMP STATION REHABILITATION PROJECT
This Amendment to the Professional Services Agreement by and between the CITY OF
SAN RAFAEL (hereinafter "CITY"), and CONSOLIDATED CM, a corporation (hereinafter
"CONTRACTOR"), is made and entered into as of the .2[j >.*day of -<L
201 G' 'ECU YED
RECITALS OEC 1 2016
PUBLIC WORKS DEPT,
CITY OF SAN RAFAEL
WHEREAS, pursuant to City Council Resolution No. 14076 adopted on March 7, 2016,
the CITY and CONTRACTOR entered into a Professional Services Agreement for construction
inspection services for the Rossi Stormwater Pump Station Rehabilitation project for an amount
not -to -exceed $75,000 (the "Agreement"); and
WHEREAS, CITY now has a need for additional inspection services during
construction of the Rossi Stormwater Pump Station, and desires CONTRACTOR to perform
this additional work under the Agreement, for an additional contract amount not -to -exceed
$15,520;
AMENDMENT TO AGREEMENT
NOW, THEREFORE, the parties hereby amend the Agreement as follows:
1. Section 2 of the Agreement, entitled "DUTIES OF CONTRACTOR" is hereby
amended to include the services set forth in CONTRACTOR's proposal for additional services
dated November 2, 2016, attached hereto as Exhibit "1" and incorporated herein by reference.
2. Section 4 of the Agreement, entitled "COMPENSATION" is hereby amended to
include an additional amount of compensation to CONTRACTOR in the sum of $15,520 for the
services set forth in Exhibit "1" to this Amendment, thereby increasing the total contract
compensation to a not -to -exceed amount of $90,520.
3. Except as specifically amended herein, all of the other provisions, terms and
obligations of the Agreement between the parties shall remain valid and shall be in force after
this amendment.
IN WITNESS WHEREOF, the parties have executed this Amendment of the day,
month, and year first above written.
CITY OF SAN RAFAEL
JI S HUTZ, City a ager
ATTEST:
ESTHER C. BEIRNE, City Clerk
APPROVED AS TO FORM:
CONSOLIDATED CM
� 1
Name: Scott Ritter
Title: Sr. Vice President
La-j,jjL,( nom-
ROBERT F. EPSTEIN, Qity Attey
2
November 2,20 16
City of San Rafael
I I I Morphew Street
P.O. Box ISI 560
San Rafael, CA 949I5 -I560
Attn: Ms. Stephanie Gindlesperger P.E.
Subject Inspection Services for the Rossi Pump Station
Augmentation Request Rev. I
Dear Ms. Gindlesperger,
-1
CON�OL1D�TED
J _. J
Professional Construction Management
Exhibit 1
Thank you for the opportunity to work with you on the Rossi Pump Station. As you know Consolidated CM
has been providing inspection services on this pump station project and we are now nearing completion, however
our budget is nearly expired and it appears the project will not finish up until about the first week of November.
We had initially planned on approximately half time support for this project, and after reviewing records it
appears that for the most part this was accomplished, however there were some periods of time where eight hours
a day rather than four were required to support the project. This request for budget augmentation is based on
the understanding that any additional hours utilized for inspection were provided at your request, if that was not
the case and these hours expended were not authorized, please let me know and we will reduce this request
according.
Augmentation Request
As of this date Consolidated CM has expended the base budget amount for our inspection services. As of this
date the project is nearly complete and should require only 3 or 4 more days of inspection. We have expended
and additional 82 hours through October 28, 20I6 and we estimate that an additional 40 hours will be utilized
to complete the project. This equates to I22 hours at $I25/hour for a total augmentation request of $I5,250.
Please feel free to contact me at our Oakland office 5I0.208.I720 ext. I06 or on my cell 5I0.9I0.2402.
Very truly yours,
Consolidated CMInG
Scott Ritter
Sr. Vice President
180 Grand Avenue, Suite 1520, Oakland, CA 94612 ccm@consolidatedcm.com
Phone: 510.208.1720 - www.consolidatedcm.com
Fax: 510.208.1721
Page 1 of 2
November 2, 20I6
City of San Rafael
I I I Morphew Street
P.O. Box IS 1560
San Rafael, CA 949I5 -I560
Attn: Ms. Stephanie Gindlesperger P.E.
Subject: Inspection Services for the Rossi Pump Station
Augmentation Request Rev. I
Dear Ms. Gindlesperger,
C040L4)�TED
.X a�
Professional Construction Management
Exhibit 1
Thank you for the opporrunity to work with you on the Rossi Pump Station. As you know Consolidated CM
has been providing inspection services on this pump station project and we are now nearing completion, however
our budget is nearly expired and it appears the project will not finish up until about the first week of November.
We had initially planned on approximately half time support for this project, and after reviewing records it
appears that for the most part this was accomplished, however there were some periods of time where eight hours
a day rather than four were required to support the project. This request for budget augmentation is based on
the understanding that any additional hours utilized for inspection were provided at your request, if that was not
the case and these hours expended were not authorized, please let me know and we will reduce this request
according.
Augmentation Request
As of this date Consolidated CM has expended the base budget amount for our inspection services. As of this
date the project is nearly complete and should require only 3 or 4 more days of inspection. We have expended
and additional 82 hours through October 28, 20I6 and we estimate that an additional 40 hours will be utilized
to complete the project. This equates to I22 hours at $I25/hour for a total augmentation request of $I5,250.
Please feel free to contact me at our Oakland office 510.208.1720 ext. I06 or on my cell S I0.9I0.2402.
Very truly yours,
Consolidated CM-Lnc
,J
Scout Ritter
Sr. Vice President
180 Grand Avenue, Suite 1520, Oakland, CA 94612 ccm@con5otidatedcm.com
Phone: 510.208.1720 - www.consotidaLedcm.com
Fax: 510.208.1721
Page 1 of 2
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Stephanie Gindlesperger
Extension: 3454
Contractor Name: Consolidated CM
Contractor's Contact: Scott Ritter
Contact's Email: ritter@consolidatedcm.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step RESPONSIBLE DESCRIPTION
DEPARTMENT
1 Project Manager a. Email PINS Introductory Notice to Contractor
2 City Attorney
3 Project Manager
4 Project Manager
PRINT
5 Project Manager
6 City Attorney
7 City Attorney
8 City Manager/ Mayor
9 City Clerk
b. Email contract (in Word) & attachments to City
Atty c/o Laraine.Gittens@cityofsanrafael.org
a. Review, revise, and comment on draft agreement
and return to Project Manager
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
Forward at least two originals of final agreement to
contractor for their signature
When necessary, * contractor -sinned agreement
agendized for Council approval
*PSA > $20,000; or Purchase > $35,000; or
Public Works Contract > $125,000
COMPLETED
DATE
N/A
12/9/2016
12/9/2016
12/9/2016
12/9/2016
❑ N/A
Or
Attest signatures, retains original agreement and
forwards copies to Project Manager
REVIEWER
Check/Initial
® SG
® SG
® LAG
l� LAG
70
/'�
1/17/2017
Date of Council approval
CONTINUE ROUTING PROCESS WITH HARD COPY
Forward signed original agreements to City
1/10/2017
Attorney with printed copy of this routing form
Review and approve hard copy of signed
l /7
agreement
Review and approve insurance in PINS a0d , and
bonds (for Public Works Contracts)f
Agreement executed by Council authorized official
Attest signatures, retains original agreement and
forwards copies to Project Manager
REVIEWER
Check/Initial
® SG
® SG
® LAG
l� LAG
70
/'�
Record Without Fee,
Per GC 27333 and
When recorded mail to:
City of San Rafael
Esther C. Beirne, City Clerk
1400 Fifth Avenue
P. O. Box 151560
San Rafael, CA 94915-1560
2017-0002614
Recorded I REC FEE
Official Records I
County of I
Harin I
RICHARD 11. BENSON I
Assessor -Recorder I
County Clerk I
I
11:46A11 19 -Jan -2017 I Page 1 of 2
SPACE ABOVE THIS LINE FOR RECORDER'S USE
CITY OF SAN RAFAEL
NOTICE OF COMPLETION OF IMPROVEMENT
TO ALL PERSONS WHOM IT MAY CONCERN:
NOTICE IS HEREBY GIVEN for and on behalf of the City of San Rafael, County of Marin, State of
California, that there has been a cessation of labor upon the work or improvement and that said work or
improvement was completed upon the 9th day of November, 2016 and accepted the 17t1i day of
January, 2017; that the name, address and nature of the title of the party giving this notice is as follows:
The City of San Rafael, 1400 Fifth Avenue, San Rafael, California, 94901, a municipal corporation, in
the County of Marin, State of California, within the boundaries of which said work or improvement was
made upon land owned by said City and/or over which said City has an easement; that said work or
improvement is described as follows:
ROSSI STORMWATER PUMP STATION REHABILITATION PROJECT
CITY PROJECT NO. 11191
and reference is hereby made for a further description thereof to the plans and specifications approved
for said work or improvements now on file in the office of the City Clerk of said City, and said plans
and specifications are hereby incorporated herein by reference thereto; and that the name of the
Contractor who contracted to perform said work and make such improvement is
Valentine Corporation
I declare under penalty of perjury that the foregoing is true and correct.
Executed at San Rafael, California, on 14tj DA All it , 20 M .
CITY OF SAN RAFAEL
A Municipal Corporation
By /-X12.
X L'/
BILL GUERIN
Director of Public Works
0.00
A notary public or other officer completing this certificate verifies
only the identity of the individual who signed the document to
which this certificate is attached, and not the truthfulness,
accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF MARIN
Subscribed and sworn to (or affirmed) before me on this /fir" day of '� M uuOC-41
20rj, by Bill Guerin, proved to me on the basis of satisfactory evidence to be the persons j who
appeared before me.
WITNESS my hand and official seal.
Signature :- ,
ESTHER C. BEIRNE
San Rafael City Clerk
File: 08.06.62
k
ROUTING SLIP / APPROVAL FORM
INSTRUCTIONS: Use this cover sheet with each submittal of a staff report before approval
by the City Council. Save staff report (including this cover sheet) along
with all related attachments in the Team Drive (T:) 4 CITY COUNCIL
AGENDA ITEMS --> AGENDA ITEM APPROVAL PROCESS 4 [DEPT -
AGENDA TOPIC]
Agenda Item #
Date of Meeting: 1/17/2017
From: Bill Guerin
Department: Public Works
Date: 12/29/2016
Topic: Rossi Stormwater Pump Station Rehabilitation Project.
Subject: ACCEPT COMPLETION OF THE ROSSI STORMWATER PUMP STATION
REHABILITATION PROJECT (CITY PROJECT NO. 11191), AUTHORIZE THE CITY CLERK TO
FILE THE NOTICE OF COMPLETION, AND
ADOPT A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN RAFAEL
AUTHORIZING THE CITY MANAGER TO EXECUTE AN AMENDMENT TO THE
PROFESSIONAL SERVICES AGREEMENT WITH CONSOLIDATED CM FOR ADDITIONAL
INSPECTION SERVICES IN CONNECTION WITH THE ROSSI STORMWATER PUMP STATION
REHABILITATION PROJECT AND TO INCREASE THE COMPENSATION BY $15,520, FOR A
TOTAL NOT -TO -EXCEED AMOUNT OF $90,520.
Type: ® Resolution ❑ Ordinance
❑ Professional Services Agreement ❑ Other:
APPROVALS
® Finance Director
Remarks: MM - 12/30/16: approved subject to resolving the question I have in the Fiscal
Impact section.
® City Attorney
Remarks: LG -Approved 1/3/17.
M Author, review and accept City Attorney / Finance changes
Remarks: SG - Accepted 1/6/2017
® City Manager
Remarks:
FOR CITY CLERK ONLY
File No.:
Council Meeting:
Disposition: