SAN RAFAEL Agenda Item No:
THE CITY WITH A MISSION Meeting Date: March 20, 2017
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works
Prepared by: Bill Guerin, City Manager Approval:
Director of Public Works
File No.: 18.01.76
TOPIC: REGIONAL TRANSPORTATION SYSTEM ENHANCEMENTS PROJECT
SUBJECT: ACCEPT COMPLETION OF THE REGIONAL TRANSPORTATION SYSTEM ENHANCEMENTS
PROJECT (CITY PROJECT NO. 11237), AND AUTHORIZE THE CITY CLERK TO FILE THE
NOTICE OF COMPLETION
RECOMMENDATION: Accept completion of the project and authorize the City Clerk to file the Notice of
Completion.
BACKGROUND: Sonoma -Marin Area Rail Transit (SMART) completed construction of their initial
operating segment (IOS 1) in San Rafael and is planning passenger service to begin in 2017. SMART's IOS
1 segment terminates at the downtown rail station, which is located between Third and Fourth Streets.
In anticipation of SMART passenger service, the Public Works Department initiated the Regional
Transportation System Enhancements (RTSE) project to prepare San Rafael's downtown transportation
system for rail operations. The City's aging traffic signal system in the vicinity of the train station was
not equipped to work together with SMART's rail system. Upgrading the traffic signal systems to include
railroad pre-emption is essential for bicycle, pedestrian, and vehicular safety as well as overall efficiency
of the downtown roadway network. In addition to traffic signal upgrades, new curb ramps and sidewalk
widening were installed in 2016 to comply with Americans with Disabilities Act (ADA) requirements.
The project was originally advertised on July 31, 2015. On August 27, 2015, one sealed bid, submitted by
Ghilotti Bros., Inc. in the amount of $3,449,545 was publicly opened and read aloud. On September 8,
2015, the City Council rejected the one bid received and instructed staff to re -advertise the project.
The project was re -advertised in accordance with San Rafael's Municipal Code on September 14, 2015
and four sealed bids were publicly opened and read aloud on October 6, 2015 at 11:00 AM. On October
19, 2015, the City Council adopted a resolution authorizing the City Manager to enter into an agreement
with the low bidder, Ghilotti Bros., Inc in the amount of $2,748,357.00.
FOR CITY CLERK ONLY
File No.: 4-1-671
Council Meeting: 03/20/2017
Disposition: Approved and accepted
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
On January 4, 2016, the City Council adopted a resolution authorizing the City Manager to enter into a
professional services agreement with Park Engineering, Inc. to provide inspection services associated
with the RTSE Project.
Construction of new traffic signal and roadway improvements commenced on December 9, 2015 and
was completed on November 7, 2016. The contract work was completed within the number of working
days allowed. However, extensive coordination with AT&T was required at the very end of the project to
assure the City that the Contractor's work did not adversely affect the traffic signal systems on the west
end of downtown. This utility coordination with AT&T delayed the final Notice of Completion from
November 2016 to March 2017.
ANALYSIS: Pursuant to Civil Code Section 3093 the City is required to record a Notice of Completion
upon acceptance of the improvements by the City. This acceptance initiates a time period during which
project subcontractors may file Stop Notices seeking payment from the City from the funds owed to the
Contractor for the project work.
FISCAL IMPACT: The total project cost of $3,797,856 came in well under the originally authorized budget
of $4,600,000. The actual construction for the project involved some complex interactions with PG&E as
well as other utilities in order to install the signal poles and conduits across intersections. The design
and construction team worked closely together with the City's project engineer to modify the scope of
work, resulting in the project being delivered $802,144 under the original budget, while adapting to field
changes that were necessary to accomplish the work.
The funding sources and expenses, including design, advertisement, construction, material acquisition,
and inspection services are below.
Proiect Budget
Funding Sources
Amount
Note(s)
Federal Congestion Management and Air Quality
OBAG Grant
$1,900,000
(CMAQ) funds
Traffic Mitigation Funds, #246
$2,045,735
Gas Tax Funds, #206
$654,265
Total Available Funds
$4,600,000
Expenses
Category -Eden Expense Code
Amount
Note(s)
Already Charged Expenses
Design -01
$384,967.52
Kimley-Horn and Associates, Inc.
Construction -02
$3,986.15
Document Reproduction
Construction -02
$1,300.00
SMART Right -of -Entry Permit
Construction -02
$2,639,643.66
Ghilotti Brothers, Inc. Construction*
Construction -02
$9,601.64
DC Electric Group, Inc.
Construction -02
$37,598.90
Utility Work (PG&E and MMWD)
Construction -02
$104,153.56
Park Engineering, Inc. (Construction Inspection)
Construction Support Services (i.e., Materials
Testing, Native American Monitoring, and
Construction -02
$21,019.34
Archaeologist Monitoring)
Miscellaneous expenses (i.e., batteries, server
Equipment Purchase -07
$17,375.66
hardware, Marin IT staff time, etc.)
Equipment Purchase -07
$578,210.43
Econolite Control Products, Inc. (traffic signal
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 3
Category -Eden Expense Code Amount Note(s)
vendor)
Total Expenses $3,797,856.86
*Includes the 5% retention to be paid 35 days after Notice of Completion is filed.
The remaining budgeted funds of $802,144 will be utilized to add additional mast arm signals on the
west side of Hetherton Street at Mission Avenue and Fifth Avenue. Additional resurfacing is also
anticipated at Third Street and Irwin Street to improve safety aspects of that intersection. These two
smaller projects will be bid separately and should be in place in the next few months.
ACTION REQUIRED: Staff recommends that the City Council accept completion of the project and
authorize the City Clerk to file the Notice of Completion.
ATTACHMENTS: Notice of Completion
Record Without Fee,
Per GC 27383 and
CG
1z CL
recorded riiail tc;:
2 City of San Rafael
Esther C. Beirne, City Clerk
1400 Fifth Avenue
P. O. Box 151560
San Rafael, CA 94915-1560
I II Illilll IIIIIII�Iilll�lillil�llll II III
2017-0011845
Recorded I REC FEE 0.00
Official Records I
County of I COHFORHED COPY 0.00
Harin I
RICHARD N. BENSON I
Assessor -Recorder I
County Clerk I
I
01:50PIl 21-11ar-2017 I Page 1 of 2
SPACE ABOVE THIS LINE FOR RECORDER'S USE
CITY OF SAN RAFAEL
NOTICE OF COMPLETION OF IMPROVEMENT
TO ALL PERSONS WHOM IT MAY CONCERN:
NOTICE IS HEREBY GIVEN for and on behalf of the City of San Rafael, County of Marin, State of
California, that there has been a cessation of labor upon the work or improvement and that said work or
improvement was completed upon the 7 1 day of November, 2016 and accepted the 20'h day of March,
2017; that the name, address and nature of the title of the party giving this notice is as follows: The City
of San Rafael, 1400 Fifth Avenue, San Rafael, California, 94901, a municipal corporation, in the County
of Marin, State of California, within the boundaries of which said work or improvement was made upon
land owned by said City and/or over which said City has an easement; that said work or improvement is
described as follows:
REGIONAL TRANSPORTATION SYSTEM ENHANCEMENTS PROJECT
CITY PROJECT #11237
and reference is hereby made for a further description thereof to the plans and specifications approved
for said work or improvements now on file in the office of the City Clerk of said City, and said plans
and specifications are hereby incorporated herein by reference thereto; and that the name of the
Contractor who contracted to perform said work and make such improvement is
Ghilotti Bros., Inc.
I declare under penalty of perjury that the foregoing is true and correct.
Executed at San Rafael, California, on t ) '►-4 2► 1201-1
CITY OF SAN RAFAEL
A Municipal Corporation
By & ) .�
BILL GUERIN
Director of Public Works
A notary public or other officer completing this certificate verifies
only the identity of the individual who signed the document to
which this certificate is attached, and not the truthfulness,
accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF MARIN
Subscribed and sworn to (or affirmed) before me on this 2-1S? day of /` 4o2e-N ,
20_LT, by Bill Guerin, proved to me on the basis of satisfactory evidence to be the person(s) who
appeared before me.
WITNESS my hand and official seal.
Signature G
ESTHER C. BEIRNE
San Rafael City Clerk
File: 18.01.76
�Pta RAF,q�I
h
C'Tr WITH y
ROUTING SLIP / APPROVAL FORM
INSTRUCTIONS: Use this cover sheet with each submittal of a staff report before approval
by the City Council. Save staff report (including this cover sheet) along
with all related attachments in the Team Drive (T:) --> CITY COUNCIL
AGENDA ITEMS 4 AGENDA ITEM APPROVAL PROCESS 4 [DEPT -
AGENDA TOPIC]
Agenda Item #
Date of Meeting: 3/20/2017
From: Bill Guerin
Department: Public Works
Date: 3/15/2017
Topic: COMPLETION OF THE REGIONAL TRANSPORTATION SYSTEM
ENHANCEMENTS PROJECT
Subject: ACCEPT COMPLETION OF THE REGIONAL TRANSPORTATION SYSTEM
ENHANCEMENTS PROJECT (CITY PROJECT NO. 11237), AND AUTHORIZE THE CITY CLERK
TO FILE THE NOTICE OF COMPLETION
Type: ® Resolution ❑ Ordinance
❑ Professional Services Agreement ❑ Other:
APPROVALS
® Finance Director
Remarks: Approved -Van Bach 3/15/17
® City Attorney
Remarks: LG -approved 3/13/17 with changes shown.
® Author, review and accept City Attorney / Finance changes
Remarks:
® City Manager
Remarks:
FOR CITY CLERK ONLY
File No.:
Council Meeting:
Disposition: