HomeMy WebLinkAboutCC Resolution 9239 (Engineering Services for Freitas Parkway Impr)FOLLOWS:
RESOLUTION NO. 9239
A RESOLUTION AUTHORIZING THE SIGNING OF
A SECOND AMENDMENT TO AN AGREEMENT
WITH CH2M HILL FOR PROFESSIONAL ENGINEER-
ING SERVICES FOR THE FREITAS PARKWAY
INTERCHANGE IMPROVEMENTS
THE CITY COUNCIL OF THE CITY OF SAN RAFAEL RESOLVES AS
The Director of Public Works and the City Clerk are hereby authorized
to execute, on behalf of the City of San Rafael, an amendment to an agreement with
CH2M HILL for the "Freitas Parkway Interchange Improvements." Said amendment
shall be in a form approved by the City Attorney, and is for the purpose of
conducting an "Alternatives Study," a proposal for which is hereby attached and by
this reference made a part of this resolution.
I, JEANNE. M. LEONCINI, Clerk of the City of San Rafael. hereby
certify that the foregoing resolution was duly and regularly introduced and adopted
at a regular meeting of the Council of said City on Monday, the 17th day of October,
1994, by the following vote, to wit:
AYES: COUNCILMEMBERS: Cohen, Heller, Thayer, Zappetini & Mayor Boro
NOES: COUNCILMEMBERS: None
ABSENT: COUNCILMEMBERS: None
JEAIME M. LEONC NI, City Clerk
ORIGINAI
9}a
City of San Rafael • Department of Public Works
AMENDMENT NO. 2
TO THE STANDARD AGREEMENT FOR
PROFESSIONAL SERVICES WITH CH2MHILL CALIFORNIA, INC.
FOR THE
FREITAS PARKWAY/US 101 INTERCHANGE r9PROVEMENTS
Date of Agreement
This Amendment No. 2 is made and entered into this 17th day of
October, 1994 by and between the City of San Rafael, a municipality in
the County of Marin, State of California (hereinafter called CITY) and
CH2M Hill California, Inc.. a corporation in the State of California
(hereinafter called Consultant).
Names and Addresses of Agreeing Parties
City of San Rafael CH2M Hill California, Inc.
Dept. of Public Works P. O. Box 12681
P. O. Box 151560 Oakland, CA 94604-4046
San Rafael, Ca. 94915-1560 Attn: Steve Castleberry
This Amendment No. 2 shall amend the previous Agreement dated June 18,
1993 and Amendment No. 1 dated July 23, 1994 as per Attachment A,
"Proposal for Freitas Parkway/Highway 101 Interchange Alternatives Study" as
submitted by the Consultant and approved by the City by Resolution No. 9239.
ATTEST:
JkANNE M. LEONCI
City Clerk
PF SAN_ RAFA
M. BERNARDI
Director of Public Works
-1
14
APPROVED O FORM: CH2MHILL CALIF
LGI'�T. RA66HMAM O' RAN
City Attorney Manager, Transportation
E v E0
;IU'V _ 71994
e.lu; 1-11 t.L
5AN FKANGISGO
Attachment A
Proposal for
Freitas Parkway/Highway 101 Interchange Alternatives Study
This scope of work covers C112M HILL's involvement in conducting a cooperative process to
address freeway access issues at Freitas Parkway/ Highway 101 in the City of San Rafael.
The objective of this work is to define project goals, develop evaluation criteria, develop
alternatives and prepare a recommendation to the City for approval. The deliverable for the
project will be a Recommendation and Summary Report as outlined below.
Task 1: Proiect Advisory Team Workshops
The City will be responsible for selecting and appointing Advisory Team members. It is
understood the Team will comprise 10-15 people representing various stakeholders who have
an interest in access at the project location. Four workshops are to be held. C112M HILL will
schedule, plan, facilitate, and record these workshops and coordinate the workshop logistics.
Technical support to these workshops is described under Task 3-4. Each workshop is
anticipated to run 4 hours and will be attended by 3-5 CH2M HILL professional staff
(including technical personnel). The general outline of the workshops are as follows:
Advisory Team Workshop 1:
Introductions and role of Project Advisory Team
Review, discussion and definition of problem statement
Discussion of evaluation criteria and weighting factors
Advisory Team Workshop 2:
Review and discuss final evaluation criteria and weighting factors
Brainstorm and discuss alternative concepts (assume approximately 10)
Preliminary Screening
Advisory Team Workshop 3:
Presentation of alternative concepts ranking
Discussion of alternatives ranking
Review of design alternatives
Advisory Team Workshop 4:
Presentation of engineering and cost data
Discussion of Advisory Team recommendation
Selection of preferred design alternative
Task 2: Recommendation and Summary Report
The results of the Advisory Team process will be summarized in a report to the City. Twenty
copies of the report will be submitted to the City.
COF
Task 3: Engineering Evaluation
It is assumed that all traffic volumes used for evaluating the alternatives will be provided by
the City. CH2M HILL's tasks are described as follows:
Task 3-1 Initial Data Collection
CH2M HILL will prepare the basic engineering information needed to support the Advisory
Team. The intent of this task is to give the Team information required to understand the
problems and constraints and thereby improve the quality of alternatives developed. This
information will include an aerial photograph of the project area, profiles and cross sections,
and a summary of relevant traffic data.
Task 3-2 Alternative Concept Development
Between the second and third Advisory Team workshops, CH2M HILL will investigate up to
ten alternative design concepts. For each alternative concept, we will develop plan
geometrics, approximate design profiles, and conceptual opinions of construction cost. The
intent of this evaluation is to identify possible fatal flaws in the alternatives and give the
Advisory Team the technical information necessary to further screen the alternatives. It is
anticipated development of the alternative geometrics will be an iterative process with both
the City and Caltrans. The geometrics will reviewed as they are developed.
Task 3-3 Refine Alternative Development
Between the third and fourth Advisory Team workshops, CH2M HILL will further refine
geometrics for up to three alternatives. The purpose of this task is to confirm geometric and
cost assumptions made in Task 3-2. In addition, additional profiles will be developed of
critical geometric elements, such as curb returns, to confirm that Caltrans and City design
standards can be met.
Task 3-4 Advisory Team Workshop Technical Support
Each workshop will be attended by the project engineer and geometrician to provide technical
support to the Advisory Team. In addition, graphics materials as required for each workshop
will be prepared.
Freitas Parkway/Highway 101 Access Study
Task 1: Meeetings
Task 2: Recommendation and Summary Report
O'Halloran
Hours
Dollars
O'Halloran
48
$6,480
Regos
92
$6,440
Eichhorn
80
$8,000
Office
40
$2,400
Task 1 Labor Subtotal
6
$23,320
Task 2: Recommendation and Summary Report
O'Halloran
6
$810
Regos
24
$1,680
Eichhom
12
$1,200
Office
16
$960
Task 2 Labor Subtotal
60
$4,650
Task 3: Engineering Evaluation
Task 3.1: Initial Data Collection
Angleman 8 $800
Task 3.2 Alternative Concept Development
Angleman
204
$20,400
Ragland
12
$1,440
Castleberry
8
$960
Task 3.3 Refined Alternative Development
Angleman
60
$6,000
Ragland
6
$720
Task 3.4 Technical Support
Angleman
32
$3,200
Castleberry
16
$1,920
Task 3 Labor Subtotal $35,440
Labor Subtotal $63,410
Expenses
Graphics/Production $4,000
Misc $5,200
Expense Subtotal $9,200
Total $72,610