HomeMy WebLinkAboutPW Essential Facilities Project Management; KitchellAMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT
WITH KITCHELL CEM INC. FOR PROJECT AND
CONSTRUCTION MANAGEMENT SERVICES
THIS AMENDMENT to Professional Services Agreement is made and entered into this
.� day of - 12017, by and between the CITY OF SAN RAFAEL
(hereinafter "CITY"), and KITCHELL CEM INC., a California Corporation, (hereinafter
"CONTRACTOR").
RECITALS
WHEREAS, on July 20, 2015, the City of San Rafael approved an Essential Facilities
Strategic Plan, which included a total budget of $9,956,805 for design phase services for the
three Phase 1 projects (Public Safety Center (PSC) and Fire Stations 52 (FS 52) and 57 (FS 57))
of the Essential Facilities Strategic Plan. Within this overall budget, there was a line item
budgeted amount for design contingency of $515,658; and
WHEREAS, on October 1, 2015, in furtherance of the Essential Facilities Strategic Plan,
the CITY and CONTRACTOR entered into that certain "Agreement for Professional Services
for Project and Construction Management Services" on the Phase 1 Essential Facilities projects,
for an amount not -to -exceed $3,314,277; and
WHEREAS, the negotiated contract amount of the Agreement did not include any of the
design contingency funds budgeted for the Essential Facilities projects; and
WHEREAS, during the early design phase of the Phase 1 projects, in order to advance
numerous project objectives, the City Council's Facilities Subcommittee made certain strategic
decisions affecting the management of the projects, including separating the projects into two
parts for bidding purposes, and separating the demolition and hazardous materials abatement
portion of the projects from the construction phase; and
WHEREAS, the strategic decisions by the Facilities Subcommittee, while proving
valuable to the City, have resulted in a need for additional services by CONTRACTOR; and
WHEREAS, by Resolution No. 14332, adopted on May 15, 2017, the San Rafael City
Council approved an amendment to the Agreement to provide for the additional required
services, to be funded by a portion of the available design contingency funds;
AGREEMENT
NOW, THEREFORE, the parties hereby agree as follows:
1. Section 2 of the Agreement, entitled "DUTIES OF CONTRACTOR" is hereby
amended to additionally include the services described in CONTRACTOR's proposal letter
dated February 7, 2017, attached hereto as Exhibit A, and incorporated herein by reference.
2. Section 4 of the Agreement, entitled "COMPENSATION" is hereby amended to
include an additional amount of compensation to CONTRACTOR in the sum of up to $237,475
for additional services to be performed pursuant to this Amendment as described in Exhibit A
attached, thereby increasing the total contract compensation to a not -to -exceed amount of
$3,551,752.
2. Except as specifically amended herein, all of the other provisions, terms and
obligations of the Agreement between the parties shall remain valid and shall be in force after
this amendment.
IN WITNESS WHEREOF, the parties have executed this Amendment to Professional
Services Agreement as of the day, month and year first above written.
CITY OF SAN RAFAEL KITCHELL CEM INC.
By. 0
� i', JJ By.
JIM SCHUTZ, City Manager
Name of Corporate Officer: tip
ATTEST:
Title: Ste-- «CL— Slowl—
e,2gf t zz f G - Ae-412 ,
ESTHER C. BEIRNE, City Clerk
APPROVED AS TO FORM:
L a "L - in Qr-e7
ROBERT F. EPSTEIN, Cit.4Attordtk
13 CA h
:14, 4 Ey - �
February 7, 2017
Cristine Alilovich
Assistant City Manager
San Rafael City Hall
1400 Fifth Avenue, Room 203
San Rafael, California 94915-1560
Re: Fee Proposal for the Phase 1 Projects (Public Safety Center, Fire Station 52 and the Fire
Station 57) of the Essential Facilities Strategic Plan.
Dear Cristine Alilovich,
Below is fee proposal for the added scope of services incurred by Kitchell for the Phase 1 Projects (Public Safety
Center, Fire Station 52 and the Fire Station 57) of the Essential Facilities Strategic Plan.
We anticipate the scope of services for this proposal to be consistent with the scope identified in the current
contract. Below is list of additional activities for the Phase 1 projects. The attached spreadsheet shows the
breakdown of the hours and rates.
1. Bid Phase for Early Demolition Projects:
The Kitchell fee proposal dated April 12, 2017 for the separation of the Bid Phase of the Early Haz-Mat and
Demolition was approved by the Facilities Subcommittee on April 15, 2016 in the amount of $46,800.
2. Extended Preconstruction Phase Management for Public Safety Center Project:
The fee and proposed staffing to provide the above scope of services is as follows:
The Kitchell staffing fee proposal included in the original contract dated October 1, 2015 had Programming/Design
and Bid Phase Management for the Phase 1 projects from October 2016 through to January 2017. The PSC
design schedule was extended during the conceptual and schematic design phases due to numerous design
iterations, DRB and PC comments, extended CEQA process and to incorporate the Value Engineering cost saving
ideas into the design. The current timeline to complete the Public Safety Center Pre -Construction activities Is
August 2017. We are forecasting requiring Project Director time of 16 hours per month and Senior Project Manager
time of 100 hours per month for seven additional months. This equates to an add request of $139,160.
3. Splitting the Bid Phase for the Early Demolition of Public Safety Center:
The fee and proposed staffing to provide the above scope of services is as follows:
The April 12, 2016 change proposal for Early Haz-Mat and Demolition was accounting for bidding all three
demolition projects together as one bid package with actual demolition work for Fire Stations 52 and 57 to be
concurrent and Fire Station 51/Blue Houses to be separate. The FSC approved separation of the bid phases for
Fire Station 51 and Blue Houses to incorporate deconstruction as an add alternate into the demolition scope. Due
to this change, Kitchell will incur additional costs to manage this added bid process. We are forecasting requiring
Project Director time of 16 hours per month, Senior Project Manager time of 32 hours per month and Project
Manager time of 225 hours. This equates to an add request of $51,515.
In total the additional services described in items 1, 2 and 3 above equate to a total amount of $237,475.
Reasonable and customary reimbursable expenses would be submitted separately to the above costs consistent
with the current contract.
Thank you for the opportunity to provide these services. If you have any questions, please do not hesitate to
contact me at this office.
Sincerely,
Bill a al
Project Director
Kitchell CEM
2450 Venture Oaks Way I Suite 500 1 Sacramento, California 95833 1 Phone 916.648.9700 1 Fax 916 648.6534 1 www.kitcliell.com
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Cindy Ray
Extension: 5326
Contractor Name: Kitchell CEM Inc.
Contractor's Contact: Bill Johal
Contact's Email: bjohal@kitchell.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1 Project Manager
a. Email PINS Introductory Notice to Contractor
Click here to
❑
enter a date.
b. Email contract (in Word) & attachments to City
Click here to
Atty c/o Laraine.Gittens@cityofsanrafael.org
enter a date.
❑
2 City Attorney
a. Review, revise, and comment on draft agreement
6/5/2017
® LAG
and return to Project Manager
6/6/2017
® LAG
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
3 Project Manager
Forward three (3) originals of final agreement to
6/7/2017
❑
contractor for their signature
4 Project Manager
When necessary, * contractor -signed agreement
❑ N/A
agendized for Council approval
*PSA > $20,000; or Purchase > $35,000; or
Or
❑
Public Works Contract > $125,000
Click here to
Date of Council approval
enter a date.
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
5 Project Manager
Forward signed original agreements to City
06/16/17
Attorney with printed copy of this routing form
6 City Attorney
Review and approve hard copy of signed
r� 117
agreement
4
/ +
7 City Attorney
Review and approve insurance in PINS, and bonds
/�7
(for Public Works Contracts)
/
8 City Manager/ Mayor
Agreement executed by Council authorized official
�l
9 City Clerk
Attest signatures, retains original agreement and
`
(
forwards copies to Project Manager
t-7
14-3 ,ss3