HomeMy WebLinkAboutCC Resolution 7938 (Merrydale Overcrossing)as follows:
RESOLUTION NO. 7938
A RESOLUTION AUTHORIZING THE SIGNING OF A
CONTRACT, LEASE OR AGREEMENT
THE CITY COUNCIL OF THE CITY OF SAN RAFAEL RESOLVES
THE DIRECTOR OF PUBLIC WORKS is authorized to exe-
cute, on behalf of the City of San Rafael, a Request of Increased
Compensation, Merrydale Overcrossing, dated March 2, 1989 by
Wilsey & Ham, a copy of which is hereby attached and by this
reference made a part hereof.
I, JEANNE M. LEONCINI, Clerk of the City of San Rafael,
California, hereby certify that the foregoing resolution was
duly and regularly introduced and adopted at a regular meeting
of the Council of said City held on the 3rd day of April, 1989,
by the following vote, to wit:
AYES: COUNCILMEMBERS:Boro, Breiner, Frugoli, Thayer & Mayor Mulryan
NOES: COUNCILMEMBERS:None
ABSENT: COUNCILMEMBERS:None
J N1M. LEONCM , City Clerk
pL 793'
1729-0301-10
July 28, 1989
Mr. Lloyd Strom
Department of Public Works
City of San Rafael
1400 Fifth Avenue
San Rafael, CA 94915-0060
Re: Merrydale O.C. Project
Request for Additional Authorization
Dear Lloyd:
ENGINEERING AND PLANTTING SERVICES
Public Improvements • !And D ecclopuncnt • TramparWtion
355 Lakeside Drive, Suite 200
Foster City, California 94404
(4 IS) 349-2151
Telecopier: (415) 345-4921
We have and will be incurring extra costs due to the reasons set
forth below. This work falls into the following categories:
1. Scettrini Widenina
Due to the requested widening of Scettrini Drive at the eastern
end of the project, several base sheets have been revised to
reflect this change. The design to accommodate this widening
includes retaining wall design, additional geotechnical borings
and recommendations, storm drain system revisions and revisions
to the required right-of-way and easements documents.
Coordination efforts with Las Gallinas Sanitary District are
necessary for the force main which crosses the retaining wall
area.
Requested Authorization $33,200
2. Northbound On -Ramp Storm Drain Svstem
Due to the lack of cover between the existing storm drain system
and the proposed ramp at the northern end of the ramp it has
necessitated a considerable amount of additional hydrology, storm
drain calculations and additional field surveys. Approximately
700 feet of reinforced concrete box culvert has been designed
with special inlet and pipe connection details to solve this
cover problem not identified by Caltrans in its original design.
Requested Authorization $23,000
3. Additional Ricrht-of-Wav Coordination
We have responded to questions and requests by Pat Semple, an
appraiser working on the project. As part of this additional
coordination, we have: met with Pat Semple and Ed Dunne to
discuss the right-of-way requirements map, staked the right-of-
way and easement limits in the cemetery for a meeting between Pat
Semple and the owners, and have transmitted plan information to
the engineering representatives of the cemetery and Great Western
July 28, 1989
Page Two.
Savings and Loan. We expect that this coordination will continue
during the appraisal process.
Requested Authorization $7,000
4. Additional Utilitv Coordination
We have been responding to requests by the utilities for the
checking of preliminary information, explanations of the project
plans and transmittals of additional information as requested.
Requested Authorization $6,000
5. Las Gallinas Vallev Sanitary Sewer Relocation Desian
We have been asked by the Las Gallinas Valley Sanitary District
to do the relocation design of their facility which is in
conflict with the approach retaining walls on Merrydale Road. As
discussed earlier with the City, we are planning on doing this
design which will be included in our utility relocation plans.
Requested Authorization $3,000
6. Las Gallinas Stripina and Sianalization
The signalization at the Las Gallinas/Merrydale Road Intersection
as shown on the approved GAD drawing will be revised as
requested. This also will require the restriping of
approximately 1400 feet of Las Gallinas to channelize for this
signalization.
In order to make the striping alignment work at the Las
Gallinas/Merrydale intersection, the eastern Las Gallinas
curbline south of Merrydale Road will need to be pulled back
(easterly) 3 feet. This will require additional geometrics and
grading, design another typical section to address this area,
additional field surveys and design of landscaping and irrigation
to be reconstructed in kind.
Requested Authorization $10,400
7. Additional Landscanina
As discussed by letter with the submittal of the Landscape Design
Report, Caltrans has requested additional landscape design beyond
what was originally required for the slopes adjacent to Civic
Center Dr. within 101 right-of-way.
Requested Authorization $5,700
8. Pac Bell Manhole Access Structure
Pac Bell has agreed to construction of a vehicle access structure
to its existing manhole in Civic Center Drive through the Civic
Center Dr. retaining wall in lieu of reconstructing and
July 28, 1989
Page Three.
relocating its facility. In addition to the vehicle access
structure under Civic Center Dr., a drive access and landscaped
modification will be required to the existing improvements in
Civic Center Plaza. Additional field surveys will be required to
locate the existing improvements in order to design the required
modifications.
Requested Authorization $36,500
9. Excanded Hiahwav Liahtina
The original concept was to provide street lighting at the
Merrydale intersections with Las Gallinas and Civic Center Dr.
Subsequently, it was requested that street lighting be extended
for the full length of Merrydale and for several hundred feet of
Civic Center Dr.
Requested Authorization $8,500
10. Preparation of Stakina Notes and
Loa of Borinas
Our original contract did not include contemplate preparation of
staking notes to be used by the contractor for construction
staking and preparation of a log of borings sheet which presents
the results of the soils boring taken in the field.
Requested Authorization $9,700
11. Northbound On -Ramp Modifications
During Caltrans' recent review -of the project plans they have
advised that the geometrics of the northbound on-ramp will have
to be changed from those previously prepared by Caltrans and
given to the City and Wilsey & Ham. This change will require a
complete redo of the design and plans including the storm drain
system, retaining wall and will likely require further
modifications to Redwood Highway. The exact costs to complete
this major redesign cannot be determined with certainty until
further studies are undertaken and Caltrans approves the revised
geometrics. Therefore, the following Requested Authorization is
considered a best estimate available at this time based on the
anticipated need to revise or completely redo approximately 18
sheets or about 20% of the total sheets.
If Caltrans should, after further consideration, decide not to
require this change we will only bill the City our actual charges
to this account which are approximately $500 as of this date.
Requested Authorization $70,000
July 28, 1989
Page Four.
12. Expanded Prosect Complexity and Duration
The Civic Center Dr. retaining wall, with the addition of the Pac
Bell vault has become more complex to design and detail on the
drawings.
With the additional design features added to the project along
with extended review times will extend the completion date of the
project ready for bidding and construction by an estimated 4
months adding additional time and charges for overall
coordination and supervision.
Additional meetings and review comments are anticipated from
Caltrans due to changes of its project personnel.
Together the foregoing items have and will increase our cost
significantly.
Requested Authorization $20,000
Based on the foregoing we hereby request authorization to
increase our budget by $233,000 to a new total of $646,000 by
returning a signed copy of this letter to us for our files.
As soon as authorization is received our subconsultants can
proceed with the Pac Bell vault, Scettrini retaining wall and
Wilsey & Ham can proceed with its portion of the remaining work
to keep the project moving towards approval.
Very truly yours,
WILSEY & HAM
R. T. Calhoun
Vice President
RTC/kmg
ws:RTCLtr\1729Strom
APPROV D: C TY F/� /S RAFAEL Q
By:
Title:
Date:
PROJECT RECAP
Merrydale Overcrossing
A. Items Reimbursable By Caltrans
2. North Bound On -Ramp Storm Drain System $23,000
11. North Bound On -Ramp Modifications $70,000
Subtotal A = $93,000
B. Items Reimbursable By Utilities
5. Las Gallinas Valley Sanitary Sewer Relocation Design $ 3,000
8. Pac Bell Manhole Access Structure $36,500
Subtotal B = $39,500
C. Extra Work Outside of Original Scope
1. Scettrini Widening $33,200
6. Las Gallinas Striping & Signalization $10,400
7. Additional Landscaping $ 5,700
9. Expanded Highway Lighting $ 8,500
10. Preparation of Staking Notes and Log of Borings $ 9,700
Subtotal C = $67,500
D. Extra Work Within Original Scope
3. Additional Right of Way Coordination $ 7,000
4. Additional Utility Coordination $ 6,000
12. Expanded Project Complexity $20,000
Subtotal D = $33,000
Total Request For Authorization = $233,000