HomeMy WebLinkAboutCC Resolution 7435 (General Plan Consulting)RESOLUTION NO. 7435
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF SAN RAFAEL
ADOPTING AN ADDENDUM TO THE CONTRACT OF
MOORE, IACOFANO, GOLTSMAN
(Hereinafter, Consultant)
WHEREAS, the City Council authorized the execution
of the original agreement with Consultant on April 7, 1986,
attached hereto and incorporated herein as Exhibit A; and
WHEREAS, City staff is in the process of amending
the City's General Plan and an integral part of said amendment
is the preparation of the General Plan maps and other General
Plan related graphics.
NOW, THEREFORE, BE IT RESOLVED, effective September
15, 1986, the City Council hereby adopts an addendum to the
original agreement with Consultant executed April 7, 1986.
Such addendum is fully set forth in Exhibit B, attached hereto,
and fully incorporated into the original agreement.
I, JEANNE M. LEONCINI, Clerk of the City of San Rafael,
hereby certify that the foregoing resolution was duly and regularly
introduced and adopted at a regular meeting of the Council
of said City on Mondav , the 15th day of September ,
1986, by the following vote, to wit:
AYES: COUNCILMEMBERS: Breiner, Frugoli, Nave & Mayor Mulryan
NOES: COUNCILMEMBERS: None
ABSENT: COUNCILMEMBERS: Russom
J&V M. LEONCINI, City Clerk
ft
RIGINAi
,�Z3r
EXHIBIT A
AGREEMENT FOR PROFESSIONAL PLANNING SERVICES
This AGREEMENT is made and entered into this 7th clay of Apr i1, 1986, by and
.,:wct,n the CITY OF SAN RAFAEL (hereinafter referred to as City) and MOORE
CYANO SND GOLTSMAN (hereinafter called Consultant).
Scope of Work:
In accordance with this Agreement, the Consultant agrees to provide
contract planning services for the Public Involvement Program for
revising the City of San Rafael General Plan as outlined in the schedule
drrd work tasks described in the attached Work Program (see Attachment
A). The Consultant agrees to be available to perform the work specified
in this Agreement in the time frames specified.
h. Direction:
The Consultant, in performance of the Scope of Work referred to above,
will work under the direction of the City's Planning Director or the
Director's appointed representative. It is understood and agreed that
the Consultant is, and at all times shall be, an independent contractor
and nothing contained herein shall be construed as making the
C,,nsultant, or any individual whose compensation for services is paid by
the Consultant, an agent or employee of the City, or authorizing the
Consultant to create or assume an obligation for or on behalf of the
City.
C . Payment:
Por the payments specified herein, which the City agrees to make, the
jonsultant will undertake the above noted work. Payment of contract
planning work shall be as follows:
i1) The Consultant shall receive $3,000 for three community workshops
after receipt and City staff review (within one week) of community
workshop summary report.
(2) The Consultant shall receive $14,000 after receipt and City staff
review (within one week) of survey summary report.
(3) Consultation (retainer) fees up to $3,000 shall be billed on a
monthly basis.
t4) Payments by the City shall be made within 15 days of receiving each
billing invoice.
D. Terms:
The terms of this Agreement shall be through December 31, 1986. Either
party may terminate, with or without cause, by giving the other party
thirty (30) days written notice. In the event of Agreement termination,
city shall pay Consultant all sums then due and unpaid under this
Agreement. Payment by City of such compensat-:n shall be considered
Full and final settlement for all work perforned by the Consultant under
this Agreement. All completed reports and o nzr documents and materials
described in Attachment A shall become the pr:certy of the City.
E. Arbitration
All claims or disputes between the CLIENT anc she CONSULTANT relating to
this Agreement shall be decided by arbitratic• in accordance with the
rules of the American Arbitration Associatior. conducted in Marin County
under the laws of the State of California. T,• decision of the
arbitrator shall be final and binding on the :.=,ties. In interpreting
the provisions of this Agreement, the arbitrE:.:r may make an award of
costs and fees, including attorney's fees ne::::sitated by arbritation.
F. Alterations:
This Agreement may be modified, as necessary. `or the successful and
timely completion of the services to be provi:,=d. Any alteration shall
be expressed in writing, as an amendment to t• -s Agreement, and shall be
approved by both parties. Amendments to Atta:^ment A may be made by
mutual agreement of Consultant and City's P12 -ring Director.
IN WITNESS WHEREOF, City and Consultant have cause: their authorized
representatives to execute this Agreement the day and v_-ir first written above.
ATTEST:
J:�NE M. LEONCINI City Clerk
APPROVED AS TO FORM:
GARY 7. R4GGHIANTI, City Attorney
ADPK)VED AS TO CONTENT:
.NNE C. MOORE, Planning Director
CITY 0= -,AN RAFAEL
c'
LAWREN:_ E. MULkYAN, Mayor
CONSUL71.%T
ATTACHMENT A
-nder the Scope of Services, the CONSULTANT will provide professional consulting
,.-vices to CITY for the Public Involvement Program of the City of San Rafael's
,rneral Plan Revision Project which are generally described as follows:
Conduct three (3) community workshops on the General Plan revision (Task 1);
�_rrpare and administer a community survey to sample public opinion regarding
.;eneral Plan issues (Task 2); assist City Planning Department staff on an as
needed basis in the preparation of graphic materials to aid public
understanding of the General Plan revision process (Task 3).
;J)L'C' is tasks and responsibilities for the CONSULTANT and CITY in the
" I til mance of this Agreement are described below:
. CnMMUNITY 14ORKSHOPS
1.1 Pre -workshop Planning
CONSULTANT will be responsible for preparing agendas for each community
workshop with input from City staff and chart graphics for use during
the workshops to aid discussions.
'.2 Communit Workshov Facilitation
Three (3� workshops are anticipated with staggered scheduling. The
agenda for each workshop will be devoted primarily to planning issue
identification during the early phases of the General Plan revision
process. The workshops will be facilitated and graphically recorded by
the CONSULTANT.
1.3 Post -workshop Reporting
A written workshop report will be prepared by the CONSULTANT summarizing
the results of the three workshops. A draft of the report for City
staff review will be available the week of April 14, 1986. CONSULTANT
will furnish CITY with a camera-ready copy of the report for
reproduction within one week following receipt of City staff comments.
'!MUNITY SURVEY
gyre cJ,nmunity survey will: (i) provide information from representative
,seomr.nts and interest groups in the community; and (ii) involve a large
rumher of people in the planning process who might otherwise not have the
,)II-tunity to participate in the community workshops.
Survey Desiqn
� stratified sample based on owner/renter status, neighborhood and other
socio-economic and geographical variables will be devised to insure
balanced community representation. Draft questions will be. assembled by
the CONSULTANT based on major General Plan issue areas identified by
City staff.
2.2 Pilot Survey
A pilot survey will be conducted to test survey length, question
phraseology and response quality.
4.3 Survey Administration
Survey will be administered to a stratified sample of community
residents and business owners through face-to-face interviews. The
estimated sample size is 600. The number of questions on the survey is
estimated to be 30.
I Survey Analysis
Completed surveys will be computer tabulated; major findings will hr -
presented in a memorandum using text, graphs and tables. A draft
memorandum for City staff review will be available the week of April 14,
1986. CONSULTANT will furnish CITY with a camera-ready copy of the
report for reproduction within one week following receipt of City staff
comments.
PEPORTS AND MEDIA PRODUCTION
NSULTANT will assist City staff in the design and production of project
.:sletters, press releases and press packages, 35mm slides, presentation
:iraphics and exhibits, flyers, etc., on an as needed basis. CONSULTANT will
a. se provide CITY with copies of the memorandums described in Tasks 1 and 2,
-equested to do so by the CITY, on a direct cost basis. Work on Task 3,
which will only be perfoi7red at the request of staff on an as needed basis,
;11 be billable at the rates stated below, but will not exceed $3,000.
Principal .............. $55/person-hour.
Professional Staff ..... $40/person-hour.
EXHIBIT B
A D D E N D U M
CONSULTING SERVICES AGREEMENT BETWEEN THE CITY OF SAN RAFAEL
AND MOORE, IACOFANO, GOLTSMAN, FOR THE CITY OF SAN RAFAEL
GENERAL PLAN REVISION PUBLIC INVOLVEMENT PROGRAM
A. SCOPE OF SERVICES
TASK 5: GENERAL PLAN MAP PRODUCTION
5.1 Map Production Schedule
CONSULTANT will prepare a General Plan map
production plan and schedule which details the
role of City staff and CONSULTANT staff in
producing each map, the method of reproduction
and timeline.
5.2 Supervision of Map Production
CONSULTANT will supervise map production
activities of City and CONSULTANT staff and the
print production process in order to insure
timely completion of maps in accordance with
the deadline established by City staff for
assembling the draft General Plan documents.
5.3 Map Production
CONSULTANT will produce camera-ready artwork
according to the production schedule developed
in Task 5.1. The maps to be produced by the
CONSULTANT are: base maps (6); total number of
maps at 11" x 17" is estimated to be
twenty-nine (29); total number of maps at 23" x
29" is estimated to be three (3).
5.4 Other General Plan -Related Graphics
CONSULTANT will produce camera-ready artwork
for other General Plan -related graphics as
directed by City staff and as shown in the Map
Production Schedule.
B. COMPENSATION AND BUDGET
For and in consideration of the services
provided by the
CONSULTANT as described in this Agreement, the
CONSULTANT shall be compensated as described below.
Estimated Budget
TASK 5: GENERAL PLAN MAP PRODUCTION
5.1 Map Production Plan . . . . .
. . $ 440.00
(1 Person -Day @ $55/Hour)
5.2 Supervision of Map Production
2,200.00
(5 Person -Days @ $55/Hour)
5.3 Map Production . . . . . . . .
. 10,440.00
(43.5 Person -Days @ $30/Hour)
5.4 Other General Plan -Related
Graphics . . . . . . . . . . .
. 480.00
(2 Person -Days @ $30/Hour)
ESTIMATED SUB -TOTAL . . . . . . . . . . .
. $13,560.00
Direct Costs
Photographic Services . . . . . . . . . . . 700.00
Graphic Supplies . . . . . . . . . . . . . 200.00
ESTIMATED TOTAL . . . . . . . . . . . . . . $14,460.00
The maximum financial obligation of the City of San
Rafael for all services provided under this Agreement
has been estimated at $14,460 and will not be exceeded
without prior written approval by the duly authorized