SAN RAFAEL Agenda Item No: 4.d
THE CITY WITH A MISSION Meeting Date: August 21, 2017
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works
Prepared by: Bill Guerin, City Manager Approval:
Director of Public Works
File No.: 16.06.85
TOPIC: COMPLETION OF 2015-16 STREET RESURFACING
SUBJECT: ACCEPT COMPLETION OF THE STREET RESURFACING 2015-2016 PROJECT (CITY PROJECT
NO. 11275), AND AUTHORIZE THE CITY CLERK TO FILE THE NOTICE OF COMPLETION
RECOMMENDATION: Accept completion of the project and authorize the City Clerk to file the Notice of
Completion.
BACKGROUND: The Street Resurfacing 2015-2016 project included the resurfacing of 24 streets (three
miles):
No.
Street
Treatment
Begin
End
1.
Canada Court
Micro -surface
Corrillo Drive
End
2.
Cortes Court
Micro -surface
Duran Drive
End
3.
Duran Drive
Full Width Grind and Overlay
Del Ganado Road
De La Guerra Road
4.
Duxbury Cove
Overlay
Spinnaker Point Drive
End
5.
Falmouth Cove
Full Width Grind and Overlay
Catalina Boulevard
End
6.
Gloucester Cove
Full Width Grind and Overlay
Catalina Boulevard
End
7.
Hetherton Street
Full Width Grind and Overlay
Mission Street
Second Street
8.
Hingham Cove
Micro -surface
Spinnaker Point Drive
End
9.
Hyannis Cove
Overlay
Catalina Boulevard
End
10.
Las Gallinas Avenue
Micro -surface
Merrydale Road
Corrillo Drive
11.
Las Huertas Court
Micro -surface
Las Gallinas Avenue
End
12.
Nantucket Cove
Overlay
Catalina Boulevard
End
13.
Narragansett Cove
Overlay
Spinnaker Point Drive
End
14.
Newport Way
Overlay
Spinnaker Point Drive
End
FOR CITY CLERK ONLY
File No.: 4-1-683
Council Meeting: 08/21/2017
Disposition: Accepted completion
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
Oleander Drive
Micro -surface
Patricia Way
Overlay
Plymouth Cove
Full Width Grind and Overlay
Portsmouth Cove
Overlay
Rockport Cove
Overlay
Salem Cove
Overlay
Spinnaker Point Drive
Overlay
Walter Place
Micro -surface
Warner Court
Full Width Grind and Overlay
Whitewood Drive
Full Width Grind and Overlay
Las Gallinas Avenue
Las Colindas Road
Catalina Boulevard
Spinnaker Point Drive
Spinnaker Point Drive
Spinnaker Point Drive
Canal Street
Corrillo Drive
Woodland Avenue
Las Pavadas Avenue
Los Gamos Road
End
End
End
End
End
Bedford Cove
End
End
Las Colindas Road
Based on state and local requirements, when a street, roadway or highway is altered or resurfaced, curb
ramps must be provided where pedestrian walkways intersect the altered street. This project included
installation of 36 accessible curb ramps and associated storm drainage improvements.
The project was advertised in accordance with San Rafael's Municipal Code on July 8, 2016, and sealed
bids were publicly opened and read aloud August 2, 2016 at 10:30 AM. On August 15, 2016, the City
Council adopted a resolution authorizing the City Manager to enter into an agreement with the low
bidder, Ghilotti Construction Company in the amount of $1,663,185.70.
Construction commenced on September 19, 2016. The Contractor completed all work except the micro -
surfacing portion of the contract by December, 2016. Construction recommenced in May, 2017 when
Contractor micro -surfaced the remaining streets as weather and air temperatures are more favorable
for micro -surfacing operations in the summer months. The project was completed on June 15, 2017.
ANALYSIS: Pursuant to Civil Code Section 3093, the City is required to record a Notice of Completion
upon acceptance of the improvements by the City. This acceptance initiates a time period during which
project subcontractors may file Stop Notices seeking payment from the City from the funds owed to the
Contractor for the project work.
FISCAL IMPACT: The total project cost of $1,651,355.12 came in under the originally authorized budget
of $1,912,000. The funding sources and expenses, including design, advertisement, construction, and
inspection services are below.
Funding Sources:
Funding Sources Amount
Gas Tax Fund (Fund #206) $1,912,000
Total Available Funds $1,912,000
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 3
Expenses:
Design Costs
Amount
Curb Ramp Design (Robert A. Karn Agreement)
$45,320.00
Environmental Document, Topographic Survey, and Public Outreach
$9,023.20
Design Subtotal
$54,343.20
Construction Costs
Actual Construction Contract Amount Based on Measured Quantities*
$1,584,876.70
Contract Change Orders*
$43,761.85
Construction Inspection Services
$48,686.18
Materials Testing and Sampling
$4,529.20
Utility Reimbursements
-$84,842.01
Construction Subtotal*
$1,597,011.92
Total Project Expense
$1,651,355.12
*Includes the 5% retention to be paid 35 days after Notice of Completion is filed.
ACTION REQUIRED: Staff recommends that the City Council accept completion of the project and
authorize the City Clerk to file the Notice of Completion.
ATTACHMENTS: Notice of Completion
S� Sle Per GC 27383 r nd
ka
When recorded mail to:
City of San Rafael
Esther C. Beirne, City Clerk
1400 Fifth Avenue
P. O. Box 151560
San Rafael, CA 94915-1560
Il Ilkll illll'll'�Illllllkllllkllkilli III
201x-0038483
Recorded I REC FEE 0.00
Official Records I
County of I CONFORMED COPY 0.00
Marin I
RICHARD N. MIMI I
Assessor -Recorder I
County Clerk I
I
02:O8P11 12 -Sep -2017 I Page 1 of 2
SPACE ABOVE THIS LINE FOR RECORDER'S USE
CITY OF SAN RAFAEL
NOTICE OF COMPLETION OF IMPROVEMENT
TO ALL PERSONS WHOM IT MAY CONCERN:
NOTICE IS HEREBY GIVEN for and on behalf of the City of San Rafael, County of Marin, State of
California, that there has been a cessation of labor upon the work or improvement and that said work or
improvement was completed upon the 15`h day of June, 2017 and accepted the 21" day of August,
2017; that the name, address and nature of the title of the party giving this notice is as follows: The City
of San Rafael, 1400 Fifth Avenue, San Rafael, California, 94901, a municipal corporation, in the County
of Marin, State of California, within the boundaries of which said work or improvement was made upon
land owned by said City and/or over which said City has an easement; that said work or improvement is
described as follows:
STREET RESURFACING 2015-2016
CITY PROJECT #11275
and reference is hereby made for a further description thereof to the plans and specifications approved
for said work or improvements now on file in the office of the City Clerk of said City, and said plans
and specifications are hereby incorporated herein by reference thereto; and that the name of the
Contractor who contracted to perform said work and make such improvement is
Ghilotti Construction Company
I declare under penalty of perjury that the foregoing is true and correct.
Executed at San Rafael, California, on 5eVsEr-%be4- 8 , 2011 .
CITY OF SAN RAFAEL
A Municipal Corporation
By_ %�W ,
BILL GUERIN
Director of Public Works
A notary public or other officer completing this certificate verifies
only the identity of the individual who signed the document to
which this certificate is attached, and not the truthfulness,
accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF MARIN
Subscribed and sworn to (or affirmed) before me on this 9�- day of
20/;f , by Bill Guerin, proved to me on the basis of satisfactory evidence to be the person(s) who
appeared before me.
WITNESS my hand and official seal.
Signature f*.s7C� G . / I�
ESTHER C. BEIRNE
San Rafael City Clerk
File: 16.06.85
4 IftSAN RAFAEL STAFF REPORT APPROVAL
THE CITY WITH AMISSION ROUTING SLIP
Staff Report Author: Kevin McGowan Date of Meeting: 08/21/2017
Department: Public Works
Topic: STREET RESURFACING 2015-2016
Subject: ACCEPT COMPLETION OF THE STREET RESURFACING 2015-2016 PROJECT (CITY PROJECT NO. 11275),
AND AUTHORIZE THE CITY CLERK TO FILE THE NOTICE OF COMPLETION
Type: (check all that apply) ® Consent Calendar ❑ Public Hearing
❑ Discussion Item ❑ Resolution ❑ Ordinance
❑ Professional Services Agreement ❑ Informational Report
*If PSA, City Attorney approval is required prior to start of staff report approval process
Was agenda item publicly noticed? ❑ Yes ❑No I Date noticed: I ❑Mailed ❑Site posted ❑Marin IJ
Due Date Responsibility Description Completed
Date
FRIDAY
noon
8/4
MONDAY
morning
8/7
DEPARTMENT REVIEW
Director Director approves staff
report is ready for ACM,
City Attorney & Finance
review.
Assistant City Manager
City Attorney
Finance
CONTENT REVIEW
ACM, City Attorney &
Finance will review items,
make edits using track
changes and ask questions
using comments. Items will
be returned to the author
by end of day Wednesday.
8/8/2017
8/8/2017
8/8/2017
8/14/2017
Initial / Comment
❑X
BG
0
RW
0
LG
0
VB
0
N
0
LG
0
VB
DEPARTMENT REVISIONS
FRIDAY
Author
Author revises the report
8/11/2017
noon
based on comments
8/11
receives and produces a
final version (all track
changes and comments
removed) by Friday at
noon.
ACM, CITY ATTORNEY, FINANCE FINAL
APPROVAL
MONDAY
Assistant City Manager ACM, City Attorney &
8/14/2017
morning
Finance will check to see
8/14
their comments were
8/14/2017
City Attorney
adequately addressed and
sign -off for the City
8/14/2017
Manager to conduct the
Finance
final review.
TUES
City Manager
Final review and approval
Click here to
noon
enter a date.
8/15
Initial / Comment
❑X
BG
0
RW
0
LG
0
VB
0
N
0
LG
0
VB