Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutPW Francisco Blvd MUP____________________________________________________________________________________
FOR CITY CLERK ONLY
Council Meeting: 5/21/2018
Disposition: Accepted Report and Provided direction to staff
Agenda Item No: 7.b
Meeting Date: May 21, 2018
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Prepared by: Bill Guerin,
Public Works Director
City Manager Approval: ______________
TOPIC: FRANCISCO BLVD. WEST MULTI-USE PATHWAY
SUBJECT: UPDATE REGARDING NEGOTIATIONS WITH SMART AND ITS CONTRACTOR
STACY WITBECK HERTZOG FOR ISSUANCE OF A CHANGE-ORDER TO
CONSTRUCT THE MULTI-USE PATH FROM ANDERSEN DRIVE TO RICE DRIVE
RECOMMENDATION: Accept the report and provide direction to staff.
BACKGROUND: Sonoma Marin Area Rail Transit (SMART) is moving forward with its Larkspur
Extension project, which will extend the rail service from downtown San Rafael to Larkspur Landing.
SMART competitively awarded a design/build contract to Stacy Witbeck Hertzog (SWH) and has begun
their construction with work at Andersen Drive and in the Bettini Transit Center. SMART anticipates
completing the work at Andersen Drive in early/mid-June and will shift its construction activities to the
Francisco Blvd West “flip” in mid-June. The construction phase of the Larkspur Extension is anticipated
to be complete by the end of 2018 with commercial operations estimated to begin after rail testing
sometime in 2019.
In connection with the March 2017 Memorandum of Understanding between the City and SMART for
cooperation on the Larkspur Extension project, the City, anticipating the need to create a Multi-Use
Path (MUP), obtained assurance, by letter dated March 17, 2017 from SMART’s General Manager
Farhad Mansourian, that so long as all design, studies, approvals and funding for the MUP project are
in place, then upon request by the City, SMART will accommodate a change order to integrate the MUP
into SMART's Larkspur Extension project construction schedule, if doing so will not interfere with the
Larkspur Extension Project completion.
The City is working to incorporate a Multi-Use Path (MUP) adjacent to the new rail line. On November
6, 2017 the San Rafael City Council authorized the City Manager to execute an agreement with BKF
Engineers to finalize the design of the Second to Andersen MUP. The final design is complete. In
addition, three permits were required to construct in the adjacent waterway. Two of the permitting
agencies including the Corps of Engineers, and the California State Water Resources Control Board
have provided the permits required to allow work in the waterway. California Department of Fish and
Wildlife has committed to provide the last remaining permit on or before September 24.
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
The completed design was provided to SWH in order for SW H to develop a construction cost proposal.
SWH will provide three separate estimates;
• A cost proposal for the entire path from Andersen Drive to Second Street,
• A cost proposal for a segment of the project from Andersen Drive to Rice Drive and,
• A cost proposal to place structural steel only from Rice Drive to Irwin Street.
Funding in an amount of approximately $4.35 million has been collected through sources from TAM,
MTC, the City of San Rafael, and Marin County. In addition, staff has been notified that a grant
application to the Bay Area Air Quality Management District is pending approval and will provide an
additional $248,400 to the project, bringing the total funding available to $4.6 million. The path from
Andersen to Rice Drive must be put in place while SMART is constructing their rail project because of
its proximity to the rail line. Rice to Second is adjacent to the realigned Francisco Boulevard West
(FBW), away from the SMART tracks, and can be constructed later without the added challenges and
cost associated with construction adjacent to active rail operations. SMART’s current realignment
design of FBW and Rice will still allow cyclists to utilize the roadway while pedestrians will be able to
use the adjacent sidewalk until the new MUP is constructed.
On April 16, 2018, Council approved the pursuit of a second Urban Greening grant application in an
amount of up to $1.86 million. The results of that grant request are expected in November 2018 and
could be the source of funds for a second phase of construction.
The design for the MUP from Andersen to Rice includes steel sheet piles to support the pathway, which
represents a significant portion of the construction cost. Because steel fabrication is a long lead item,
the City Council approved the advanced purchase of structural steel at the May 7, 2018 Council
meeting.
Staff will update the Council on the status of the MUP project, the cost of the path, and the status of
negotiations with SMART and its contractor. Staff is seeking direction from the Council regarding
whether or not to continue the steel purchase approved on May 7, 2018 in order to allow the
construction of the MUP from Andersen Drive to Rice Drive to happen this year.
RECOMMENDED ACTION:
Accept the report and provide direction to staff.
TRANSPORTATION ALTERNATIVES FOR MARIN 187 E. BLITHEDALE AVENUE MILL VALLEY CA 94941
TEL: 415.389.5040 X24 FAX: 415.389-5044
May 18, 2018
San Rafael City Council
1400 Fifth Avenue
San Rafael, CA 94901
VIA EMAIL
RE: 1. FRANCISCO BLVD. WEST MULTI-USE PATHWAY
2. UPDATE REGARDING NEGOTIATIONS WITH SMART AND ITS
CONTRACTOR STACY WITBECK HERTZOG FOR ISSUANCE OF A
CHANGE-ORDER TO CONSTRUCT THE MULTI-USE PATH FROM
ANDERSEN DRIVE TO RICE DRIVE
Dear Mayor Phillips and City Council:
This packet is submitted regarding Agenda Item 7(b), the Francisco Blvd. West Multi-
Use Pathway, for discussion at the May 21, 2018 City Council Meeting.
Transportation Alternatives for Marin (TAM) is a non-profit corporation whose mission is
to champion sustainable mobility. This mission is advanced through the study and
promotion of national and international best practices including integrating modalities,
model community programs, funding, design standards, education, safety and
maintenance.
I. FUNDING THE PATHWAY. Marin County’s voters have twice voted to tax
themselves to build the Multiuse Pathway (“MUP”) between Andersen Drive and 2nd
Street (the “Pathway”): Regional Measure 2 and SMART/Measure Q.
1. Regional Measure 2
You will find attached “A Group” Exhibits, which provide background on Regional
Measure 2.
A. Exhibit “A-1” is an excerpt of Regional Measure 2 (“RM2”) with relevant sections
highlighted. Please note the language in the red box in the lower right hand
corner of Exhibit “A-1,” which shows that the Andersen Drive to 2nd Street portion
of the North-South Greenway was to be funded by RM2.
The RM2 language directly identifies the Pathway as “right-of-way approaches
for the bicycle and pedestrian access to connect the San Rafael Transit Center
with the Larkspur Ferry Terminal.”
B. Exhibit “A-2” summarizes the MTC’s actions on its 2014 programming of Marin’s
remaining $40 million RM2 funds. The excerpted language includes both the
Programming and Allocation Committee and the Amendments to Regional
Measure Capital Projects. Please note the language:
a. “…Fund elements… [to include] Multi-purpose bike/pedestrian pathway”
in the “SMART Larkspur Extension.” This language describes the Multi-
use Pathway from Andersen Drive to 2nd Street.
TRANSPORTATION ALTERNATIVES FOR MARIN 187 E. BLITHEDALE AVENUE MILL VALLEY CA 94941
TEL: 415.389.5040 X24 FAX: 415.389-5044
Mayor Phillips and City Council
May 18, 2018
Page 2
b. The MTC’s recommended funding of the Andersen Drive to 2nd Street
Pathway is what all the bicycle references were for. RM2 specifically
includes language in support of the Multi-use bike/pedestrian Pathway in
the San Rafael to Larkspur Operating segment of SMART.
C. Conclusion: RM2 included the Andersen Drive to 2nd Street Multi-Use Pathway.
The reason the MTC allowed the RM2 funds to be switched from Larkspur-Corte
Madera to the Pathway is that the Andersen Drive to 2nd Street MUP is a RM2
project.
2. SMART / Measure Q
You will find attached “B Group” Exhibits, which provide background on Measure Q,
the SMART funding legislation.
A. Measure Q was the fourth attempt to pass SMART (more accurately a Marin rail
project) if one includes the 1990 (approximately) rail project put before voters.
(SMART—before it was SMART--was included in 1998 Measure’s A and B,
which both lost. The next attempt to pass a Marin-Sonoma rail project, the first
time as SMART, was Measure R in 2006.
B. When Measure R failed in 2006, SMART conducted some sophisticated surveys
and research and found that Marin’s voters in particular were interested in the
Pathway, and would support the measure (and push it over the required 2/3rds
majority) IF THE BICYCLE AND PEDESTRIAN PATHWAY WERE INCLUDED
IN 100% OF THE PROJECT, AND FULLY FUNDED.
C. Exhibit “B-1”compares key points of Measure R and Measure Q. The primary
discernable difference from what was on the ballot for smart in 2008 versus 2006
is that the smart Pathway was increased from approximately 50% to 100% of the
rail line from Larkspur to Cloverdale, and the funding for the bicycle path
increased from $46 million to $91 million.
D. SMART’s Measure Q ¼ cent sales tax was passed in 2008. Exhibit “B-2”
highlights key information in Measure Q and its Expenditure Plan regarding the
SMART Pathway:
Measure Q, including the 2008 Expenditure Plan, passed with the Pathway
included in 100% of the smart project, and was to be funded with $91 million of
measure q funds.
E. The “Cal Park Hill Rail Tunnel and right-of-way approaches for the bicycle and
pedestrian access to connect the San Rafael Transit Center with the Larkspur
Ferry Terminal” Pathway described in RM2 is a subset of the same Pathway that
is described in Measure Q, passed 4 years after RM2.
TRANSPORTATION ALTERNATIVES FOR MARIN 187 E. BLITHEDALE AVENUE MILL VALLEY CA 94941
TEL: 415.389.5040 X24 FAX: 415.389-5044
Mayor Phillips and City Council
May 18, 2018
Page 3
II. THE BIG PICTURE
1. San Rafael, Larkspur, Marin County, the Transportation Authority of Marin, the
Metropolitan Transportation Commission, Caltrans AND THE VOTERS OF
MARIN, have planned for and funded an integrated Multi-Modal transportation
system by connecting San Rafael, and the San Rafael Transit Center, to the
Larkspur transit hub, as overviewed in Exhibit “C – Marin’s National Multi-Modal
Transportation Model.” Over the last 30 years the investment in this area years has
been to build a multi-modal system for cars, buses, a train, a ferry system, bicycles,
and pedestrians. MARIN’S MULTI-MODAL PLANS FOR THIS AREA ARE A
NATIONAL MODEL OF SUSTAINABLE, INTER-MODALITY.
2. If the Pathway from Andersen Drive to Rice Drive is not built at the same time the
train goes in, the Greenway in this section may never be built. All of the investment
made to date would be wasted. The complete vision and dream of the North-South
Greenway, now 40 years in the making, would be destroyed. (The North South
Greenway was first described in the 1974 County Bikeway Plan as the top priority
route, then called the “Redwood Route” that basically follows the railroad right of
way.)
3. SMART is not going to pay for the Pathway.
a. No matter how much we complain, no matter what we say, no matter what
San Rafael does, SMART is not going to pay for the Pathway. That is clear.
b. We cannot stop a plan 40 years in the making, with 100s of millions of dollars
of investment, because SMART is not going to pay for the Andersen Drive to
2nd Street Pathway. That amounts to tilting at windmills while abandoning a
HUGE community investment, for which voters have twice taxed themselves.
San Rafael must take action to complete the Multi-Modal System, to preserve
investment, enact the will of the people, enhance local and regional
sustainable mobility, and improve Marin’s quality of life.
c. At present San Rafael has agreed to contribute $200,000 to this Pathway
segment. If San Rafael does not use the funding that the voters and
taxpayers have directed be used for the Andersen Drive to 2nd Street
Pathway, when the time to build ANY Pathway in this area arrives, San
Rafael would be expected to contribute 20% of the project cost. Consider it
for a moment. That means if San Rafael does not make the Pathway a reality
now, in the future it would cost the City over $1 million (based on the
CURRENT cost quotes of $6 million X 20% = $1.2 million - $200,000 =
$1,000,000.) Any suggestion to not build this Pathway NOW is NOT in San
Rafael’s interest.
TRANSPORTATION ALTERNATIVES FOR MARIN 187 E. BLITHEDALE AVENUE MILL VALLEY CA 94941
TEL: 415.389.5040 X24 FAX: 415.389-5044
Mayor Phillips and City Council
May 18, 2018
Page 4
4. Current Status. San Rafael has already done the heavy lifting. The City has:
a. Done a Feasibility Study to confirm the Pathway could be built with the rail.
b. Completed 30% engineering of the Pathway and received a cost estimate of the
Pathway from Andersen Drive to 2nd Street.
c. Received environmental approvals.
d. Completed 100% of the engineering drawings.
e. Raised $4.35 million of the estimated $4.5 million for building the Pathway.
f. Received commitment for the environmental permits from all permitting agencies.
5. Recommendations
a. Accept the staff report.
b. Continue the steel purchase as approved by the City Council May 7, 2018.
c. Wait for the cost estimates from SWH.
d. Put in a Change Order for the reduced road width project from Rice to
2nd Street. Rather than build a sidewalk to be taken out, build 8’ of the Preferred
Alternative from the west curb of the Preferred Alternative W. Francisco plans.
This will cost the same or less than the Planned Alternative, will reduce the cost
of putting in the Preferred Alternative, and will provide a paved sidewalk rather
than a concrete sidewalk, which would be taken out when the Preferred
alternative is put in. Note:
(1) The Preferred Alternative is the alternative with a 12’ multi-use pathway
and two 13’ travel lanes for cars on W. Francisco from Rice to 2nd Street.
(2) The Planned Alternative (the one SMART is planning to build right now)
has two 12’ travel lanes W. Francisco from Rice to 2nd Street, each with 2’
shoulders, and a 6’ sidewalk.
e. Direct staff after receiving the cost estimates in (c) and (d), above.
WTB-TAM has been working on the North South Greenway since 1993. We first worked
with SMART on the engineering plans for the SMART Pathway alignment from Andersen
Drive to 2nd Street in 2003. We are encouraged by the community’s and San Rafael’s
clear vision and continued commitment to this prized public asset: the safe, separate,
and continuous North-South Greenway (see Exhibit “D”).
Thank you for your consideration.
Respectfully submitted,
Patrick M. Seidler
President
(10)Sonoma-Marin Area Rail Transit District (SMART) Extension to Larkspur
or San Quentin. Extend rail line from San Rafael to a ferry terminal at Larkspur
or San Quentin. irty-ve million dollars ($35,000,000). Up to ve million dollars
($5,000,000) may be used to study, in collaboration with the Water Transit Authority,
the potential use of San Quentin property as an intermodal water transit terminal. e
project sponsor is SMART.
(11)Greenbrae Interchange/Larkspur Ferry Access Improvements. Provide
enhanced regional and local access around the Greenbrae Interchange to reduce trac
congestion and provide multimodal access to the Richmond-San Rafael Bridge and
Larkspur Ferry Terminal by constructing a new full service diamond interchange at
Wornum Drive south of the Greenbrae Interchange, extending a multiuse pathway
from the new interchange at Wornum Drive to East Sir Francis Drake Boulevard
and the Cal Park Hill rail right-of-way, adding a new lane to East Sir Francis
Drake Boulevard and rehabilitating the Cal Park Hill Rail Tunnel and right-of-way
approaches for bicycle and pedestrian access to connect the San Rafael Transit Center
with the Larkspur Ferry Terminal. Sixty-ve million dollars ($65,000,000). e project
sponsor is the Marin County Congestion Management Agency.
(c)If the voters approve a toll increase in 2004 pursuant to Section 30921 , the
authority shall, consistent with the provisions of subdivisions (d) and (f), fund the projects
described in this subdivision and in subdivision (d) that shall collectively be known as the
Regional Trac Relief Plan by bonding or transfers to the Metropolitan Transportation
Commission. ese projects have been determined to reduce congestion or to make
improvements to travel in the toll bridge corridors, from tollv revenues of all bridges:
30914. (a) In addition to any other authorized expenditures of toll bridge revenues,
the following major projects may be funded from toll revenues of all bridges:
Section 309.14 (a - f)
Excerpted from the
STREETS AND HIGHWAYS CODE
SECTION 30910-30922
REGIONAL MEASURE 2 - 2004
EXCERPTED LANGUAGE
SMART FUNDING
MARIN’S 4 PROJECTS
ese projects have been determined to reduce congestion
If Regional
Measure 2
passes...
Already
allocated to
SMART
1. TAM has said
this cannot be
done
4. Cal Park Hill
Tunnel Opened
in 2010, and
Phase I Central
Marin Ferry
Connection
Completed 2016
4. Original
language
in Regional
Measure 2:
Andersen to
2nd is included
in the plan
The requests to fund the construction and tasks necessary to build the North South
Greenway from Wornum Drive to the Central Marin Ferry Connection falls within the
funding directive of Regional Mearure 2. The north South Greenway is the “multiuse
pathway” mentioned here in the legisltaruive language.
2. Phase II
Central
Marin Ferry
Connection
. . .
. . .
. . .
3. Completed
years ago by
Larkspur
EXHIBIT "Ͳϭ"
Metropolitan Transportation Commission
Programming and Allocations Committee
February 12, 2014
Agenda Item 3a
May 14, 2014
Agenda Item 3a.i
Amendments to Regional Measure 2 Capital Projects
MTC Resolution No. 3801, Revised
EXHIBIT "A-2"
SMART PATHWAY 100% OF THE RAILWAY PROJECT
GETS VOTERS TO APPROVE THE SMART
1/4 CENT TAX IN MEASURE Q
2006
Measure R
2008
Measure Q
III. Expenditure Plan and Project Details
* * *
A. Project Description
* * *
5. Bicycle/Pedestrian Pathway:
SMART proposes a bicycle/pedestrian pathway along
the SMART rail corridor linking the 14 rail stations.
The proposed bicycle/pedestrian pathway includes a
combination of Class 1 and Class 2 pathways.
The construction of the bicycle/pedestrian pathway is
proposed both on and off the SMART right-of-way
depending on physical and environmental constraints
and available rights-of-way.
SMART proposes to fund approximately 57% of the
pathway construction.
Completion of the entire pathway would require the
identification of additional revenues.
I. Executive Summary: SMART
Expenditure Plan
The Sonoma-Marin Area Rail Transit District (SMART) proposes a 1/4-
cent sales tax measure for Sonoma and Marin Counties in order to pay
for the construction and operation of a passenger train system and
ancillary bicycle/pedestrian pathway along the existing, publicly owned
Northwestern Pacific Railroad. The SMART project will extend from
Cloverdale in Sonoma County to Larkspur in Marin County. (See Figure
1)
* * *
III. Expenditure Plan and Project Details
* * *
B. Project Components: Capital Improvements
* * *
5. Provide Funding for a Bicycle/Pedestrian Pathway:
SMART will Provide a bicycle/pedestrian pathway along the
SMART rail corridor linking the 14 train stations and on-going
annual maintenance of the pathway.
TABLE 2: Anticipated Costs and Revenues Over 20 Years
Project Capital Costs
Bicycle/Pedestrian Pathway Along
Approximately 50% of the SMART Railway
TABLE 1: SMART Project Costs (All costs in 2008 dollars)
Project Capital Costs
Bicycle/Pedestrian Pathway Along
100% of the SMART Railway
Voter Support for Measure Q
County: Yes No
Votes % Votes %
Marin County 83.805 62.79% 49.665 37.21%
Sonoma County 162.242 73.7% 58.016 26.3%
Totals: 246.047 69.6% 107.681 30.4%
Voter Support for Measure R
County: Yes No
Votes % Votes %
Marin County 59.774 57.51% 44.168 42.49%
Sonoma County 118.382 70.1% 50.505 29.6%
Totals: 178.156 65.3% 94.673 34.7%
I. Executive Summary: SMART
I. Executive Summary:SMART
Expenditure Plan
The Sonoma-Marin Area Rail Transit District (SMART) proposes a 1/4-cent sales tax
measure for Sonoma and Marin Counties in order to pay for the construction and
operation of a passenger train system and ancillary bicycle/pedestrian pathway along
the existing, publicly owned Northwestern Pacific Railroad.The SMART project will
extend from Cloverdale in Sonoma County to Larkspur in Marin County. (See Figure 1)
$46 Million $91 Million
EXHIBIT "BͲϭ"
SONOMA-MARIN AREA RAIL TRANSIT DISTRICT MEASURE Q
Q MFASURR Q, To rnlieve traffic, YESfight global warming and increase
transportation o)llions, shall Sono-NOma-Marin Area Rail Transit District be
authorized to rovide two-way passenger train service
every 30 minutes during weekday rush hours, weekend
service, a bicycle/_p_edestrian pathway linking the sta-
tions, and connections to ferry/bus service, by levying
a ¼-cent sales tax for 20 years, with an annual spend-
ing cap, independent audits/oversight, and all funds
supporting these environmentally responsible trans-
portation alternatives in Marin and Sonoma Counties?
COUNTY COUNSEL'S IMPARTIAL ANALYSIS OF MEASURE Q
The Sonoma-Marin Area Rail Transit District ("SMART')
is a rail district created by the Legislature in 2003 to evaluate, plan, and implement passenger rail and associated
rail transit facilities and services from Cloverdale in Sono
ma County to a ferry terminal in Marin County that connects to San Francisco. The geographic area of the district
includes all of Sonoma and Marin counties. The District is authorized, with the approval of the voters,
to propose a special tax to implement this service. The
District has adopted an ordinance proposing a quarter-cent transactions and use tax ($0.0025 on every $1 spent), to be
imposed on retail sales in Sonoma and Marin Counties,
beginning April 1, 2009. Proceeds of the tax would provide funding for the design, construction, implementation,
operation, financing, maintenance and management of the rail system and a bicycle/pedestrian pathway from Cloverdale in Sonoma County to Larkspur in Marin County. An
Expenditure Plan for the tax revenues is inco orated into the pro osed sales tax ordinance. The revenue from the tax
can only be spent on project elements listed in the Expen
diture Plan, including but not limited to: 1.We ekday and weekend i;,assenger rail service.·*2.A parallel bicycle/pedestrian pathway.
3.Fourteen rail stations from Cloverdale to Larkspur (9 inSonoma County, 5 in Marin County).
4.Rehabilitation and upgrading of the existing Northwest
ern Pacific Railroad (NWP) corridor from Cloverdale toLarkspur, including new passenger train passing sidings.5.A maintenance facility in either Cloverdale or Windsor. 6.Shuttle service at selected rai l stations.The tax would be collected in the same manner as sales tax
is ClllTently collected, would begin on April 1, 2009, andwould continue in effect for twenty (20) years.
The District is empowered under state law to issue bonds
to fund all or part of the construction of the project, so thatwork can begin sooner. The bonds would be repaid overtime from the tax revenue collected. The ordinance also
establishes an appropriations (spending) limit for SMART.The ordinance must be approved by two-thirds of the vot
ers voting on the question in order for the special tax to go
into effect.
s/PATRICK K. FA ULKNER s/STEVEN WOODSIDE
EXCERPTSOF MEASURE Q
ORDINANCE NO. 2008-01
AN OR DINANCE OF THE SONOMA-MARIN AREA
RAIL TRANSIT DISTRICT IMPOSING A RETAIL
TRANSACT IONS AND USE TAX TO BE ADMINIS
TERED BY THE STATE BOARD OF EQUALIZATION;
ADOPTING AN EXPENDITURE PLAN; AND ESTAB
LISHING AN ANNUAL APPROPRIATIONS LIMIT
FOR THE SONOMA -MARIN AREA RAIL TRANSIT
DISTRICT.
BACKGROUND FINDINGS:
The Sonoma-Marin Area Rail Transit District (SMART )
was created to provide a passenger rail system along the
N orthwestem Pacific Railroad within Sonoma and Marin
Counties. The entire 75-mi le corridor is publicly owned
and can be used toyrovid�assenger rail service. SMART
will provide passenger rail service and a bicycle/pedestrian pathway to 14 rail stations in Sonoma and Marin Counties.
SMART is committed to providing service with the most
environmentally clean passenger rail vehicle possible.
SMART requires this measure in order to provide match
ing revenues to existing state and federal transportation grants, to bond for the construction of the project, and to
provide funding for the on-going operation and mainte
nance of the project.
Section 1. TITLE. This ordinance shall be known as
the Sonoma-Marin Passenger Rail Act. The Sonoma
Marin Area Rail Transit District hereinafter shall be called
"District." This ordinance sh all be applicable in the incor
porated and unincorporated territory of the Counties of
Sonoma and Marin, which shall be referred to herein as ''District."
Section 2. OPERATIVE DATE. "Operative Date"
means the first day of the first calendar quarter commenc
ing more than 110 days after the effective date of this ordinance, as set forth below.
Section 3. PURPO SE. This ordinance is adopted to
achieve the following, among other purposes, and directs
that the provisions hereof be interpreted in order to accom
plish those plllposes:
A.To provide funding for the design, construction,
implementation, operation, financing, maintenance and
management of a passenger rail system and a bicycle/ *
pedestrian pathway connecting the 14 rail stations from
Cloverdale to Larkspur.
B.To impose a retail transactions and use tax in
accordance with the provisions of Part 1.6 (commencing
with Section 7251) of Division 2 of the Revenue and Taxation Code and Section 105115 of the Public Utilities
Code which authorizes the District to adopt this tax ordi
nance which shall be operative if a two-thirds majority of
the electors voting on the measure vote to approve the
imposition of the tax at an election called for that purpose.
* * *
Marin County Counsel
SMM-1
Sonoma County Counsel
[Emphasis Added]
EXHIBIT "B-2"
SMM-8
SONOMA-MARIN AREA
RAIL TRANSIT DISTRICT
2008 EXPENDITURE
PLAN
July 2008
I. Executive Summary: SMART
Expenditure Plan
SMART's proposed '/4-cent sales tax measure
would relieve traffic, fight global warming and
increase transportation options, by providing
two-way passenger train service every 30
minutes during weekday rush hours, weekend
service, a bicycle/pedestrian pathway linking the * stations, and connections to ferry/bus service,
by levying a 1/4-cent sales tax for 20 years, with
an annual spending cap, independent
audits/oversight, and all funds supporting these
environmentally responsible transportation
alternatives in Marin and Sonoma Counties.
Passage of this measure allows SMART to
access other state, regional, and federal funds
for the provision of passenger train service that
are currently unavailable to Sonoma and Marin
residents.
This measure would raise approximately $890
million over a 20-year period or approximately
$45 million a year. The proceeds of the tax
would be allocated to the design, construction,
implementation, operation, financing,
maintenance and management of a passenger
train system and a bicycle/pedestrian pathway * connecting the proposed train stations.
SMM·9
In 2006 SMART certified an Environmental
Impact Report (EIR) analyzing the potential
environmental impacts of the proposed
passenger train and pathway corridor. The
report's findings included:
The train and pathway project is the
environmentally superior alternative to the
congested 101 freeway.
The proposed project would reduce
greenhouse gases.
Up to 1.5 million car trips would be removed
from Highway 101 annually.
Energy use is reduced thereby reducing
dependence on fossil fuels.
The pathway provides another clean
transportation option linking the train
stations, along with health and recreational
benefits.
Replacement of waterway bridges and
culverts with modern structures would
significantly improve drainage along the train
corridor and eliminate seasonal flooding.
More recently, a Supplemental EIR was
prepared to evaluate:
Potential addition of weekend passenger train
service;
Potential use of lighter-weight train vehicles;
Potential alternative locations for the
Novato South Station; and
The cumulative impact due to a change in
the level of future freight rail service
operating in the SMART corridor.
See www.sonomamarintrain.ora to view the
environmental documents.
II. SMART Expenditure Plan Background
A. SMART District Role and Purpose
On January 1, 2003, the SMART District was
established by the California Legislature through
the enactment of AB 2224. The SMART District
includes both Sonoma and Marin Counties and
was created for the purpose of providing a
unified and comprehensive structure for the
ownership and governance of a passenger rail
system within Sonoma and Marin Counties. The
goal of SMART is to provide passenger train
service along the existing publicly-owned
railroad right-of-way.
B. Rail Corridor Ownership and
Management
The primary asset of SMART is the NWP rail
right-of-way and properties contained within that
right-of-way along the railroad corridor extending
from Healdsburg in Sonoma County to Corte
Madera in Marin County. (See Figure 1). This
right-of-way is a significant public asset and is to
be managed for the public's use and benefit via
the restoration of passenger train service and
the development of a pathway linking the train
stations.
SMM-10
Figure 1
SMM·11
SMART is managed by a General Manager, who
is appointed by and reports to the SMART Board
of Directors. SMART adopts an annual budget
documenting all revenues and expenditures.
Upon passage of this measure, SMART will
prepare a Strategic Plan, under the direction of
the SMART Board of Directors, and will update
the plan at least every five years. The Strategic
Plan will provide detailed annual revenue and
cost assumptions for project implementation and
operation. SMART will also prepare a five-year
Short Range Transit Plan documenting service
and funding assumptions. Prior to initiating train
service, SMART will prepare a Start-Up Plan
and an Emergency Preparedness Plan one year
in advance of scheduled service. The Start-Up
Plan will include implementation requirements,
schedule assumptions, staffing, and
maintenance and operations requirements. The
Emergency Preparedness Plan will be
developed in coordination with local jurisdictions
and emergency responders and will address
response protocols and procedures along the
corridor.
A Citizens Oversight Committee will be
established by the SMART Board to provide input
and review on the Strategic Plan and
subsequent updates. The committee will be
composed of citizens from the SMART District,
appointed by the Board.
C. Community Outreach
SMART's community outreach efforts have
included monthly public Board meetings, public
hearings, special ad hoc meetings and hundreds
of presentations to community, business and
special issue groups. SMART maintains. an
agency website with regular postlngs of project
documents, a project hotline with phone
numbers in both Sonoma and Marin counties and
has provided regular email updates on the
project's development to over 2,200 email
recipients each year.
III. Expenditure Plan and Project Details
A. Project Description
The SMART passenger train project will upgrade
the existing NWP right-of-way, to provide
passenger train service from Cloverdale to
Larkspur, with convenient linkages to bus,
ferries, and shuttle feeder routes and direct
connections to the bicycle/pedestrian pathway.
Fourteen stations are planned, nine in Sonoma
County and five in Marin County. Proposed
station sites include: Cloverdale, Healdsburg,
Windsor, Santa Rosa (two stations), Rohnert
Park, Cotati, Petaluma (two stations), Novato
(two stations), Marin Civic Center, San Rafael
and Larkspur.
Two-way train service is proposed at 30 minute
frequencies, operating in the weekday a.m. and
p.m. commute periods, along with one mid-day
train. Weekend train service is also proposed
with four, two-way round trips per day on
Saturdays and Sundays.
B. Project Components; Capital
Improvements
4. Implementing Other Needed Improve-
ments: Two tunnels will be upgraded for train
service. The CalPark Hill Tunnel, between San
Rafael and Larkspur, will be funded 50% by
SMART and 50% by Marin County. The CalPark
Hill Tunnel will include both train and pathway
improvements . The Puerto Suello Hill Tunnel,
located north of San Rafael, will be upgraded for
passenger rail service.
All public crossings will be upgraded along the
rail line.
A new signal and dispatch system will be
provided along the rail line to control train
operations in accordance with state and federal
operating rules and requirements.
The replacement of old railroad bridges and
trestles will provide significant improvements In
drainage and aid in the elimination of seasonal
fiooding along the corridor.
5. Providing Funding for a Bicycle/
Pedestrian Pathway: SMART will provide a
bicycle/pedestrian pathway along the SMART *
rail corridor linking the 14 train stations and on-
gOing annual maintenance of the pathway.
6. Providing for Connecting Shuttle
Services: Peak hour shuttle service is proposed
for selected train stations. SMART has
proposed nine shuttle routes serving selected
stations during peak commute periods. Maps
showing the shuttle routes are included as part
of White Paper #9 and can be found on the
district's website at www.sonomamarintrain.ora.
7. Building a Needed Maintenance Facility:
A maintenance facility will be constructed to
provide rail car maintenance and storage.
8. Implementing Quiet Zones: SMART has
committed to funding Quiet Zones in urban
areas along the corridor, which would allow
crossings to operate without train horns.
* * •
[Emphasis Added]
[Intentionally Left Blank]
SMART 2008
EXPENDITURE PLAN
v. Implementing Guidelines
The following is a list of guidelines for implementation of this Expendi-
ture Plan:
1. A Citizens Oversight Committee will be established by the
SMART Board to provide input and review on the Strategic Plan
and subsequent updates [Emphasis Added]
* * *
8. If additional funds become available , the SMART Board will priori-
tize completion of the bicycle/pedestrian pathway.
* * *
MARIN’S NATIONAL
MULTI-MODAL TRANSPORTATION MODEL
North-South Greenway
Gap Closure Project
SMART Train
Larkspur Station
Cal Park Hill Tunnel
North-South Greenway
San Rafael to Larkspur
SMART Rail
Andersen Drive to 2nd Street
North-South Greenway San Rafael
Transit Center
SMART 1st Operating
Segment San Rafael to
Sonoma County Airport
LARKSPUR FERRY LARKSPUR FERRY LARKSPUR FERRY
TERMINAL
LARKSPUR FERRY
TERMINAL
Larkspur Ferry t
o San Francisco
San Francisco
Larkspur Ferry t
o San Francisco
Larkspur Ferry t
o Larkspur Ferry t
o San Francisco
DOWNTOWN
SAN RAFAEL
DOWNTOWN
SAN RAFAEL
Puerto Suello Hill
North-South Greenway
Segment
CANALCANAL
EXHIBIT "C"
THE NORTH-SOUTHGREENWAY
© Transportation Alternatives for Marin – 2018 – v11.5
Ferry Landing
Transit Center
Major Roads
State Highways
U.S. Freeways
North-South Greenway/SMART Pathway/
Being planned and built
Greenway Tunnels
North-South Greenway
North-South Greenway Sections to be Built
Approximate Altitude Contour of North-South Greenway
SMART PATHWAY
CAL PARK TUNNEL & PATHWAY
ALTO TUNNEL REHABILITATION/REOPENING
Digital Simulation
GOLDEN GATE BRIDGE BEGINNING OF THE
NORTHSOUTH GREENWAY
RENDERING OF ANDERSEN TO 2ND LEGACY PATHWAY
RENDERING OF ANDERSEN TO 2ND LEGACY PATHWAY
RENDERING OF ANDERSEN TO 2ND LEGACY PATHWAY
EXHIBIT “D”