RESOLUTION NO. 14630
RESOLUTION OF THE SAN RAFAEL CITY COUNCIL AUTHORIZING THE CITY
MANAGER TO EXECUTE AN AGREEMENT FOR PROFESSIONAL SERVICES WITH
FEHR & PEERS ASSOCIATES, INC. TO SERVE AS TRANSPORTATION TECHNICAL
CONSULTANT FOR THE GENERAL PLAN 2040, WITH A TWO-YEAR TERM AND TWO
OPTIONAL ONE-YEAR EXTENSIONS FOR A TOTAL CONTRACT AMOUNT UP TO
$273,000.
(Term of Agreement: from January 22, 2019 to January 22, 2021)
WHEREAS, on March 5, 2018, the City Council adopted Resolution No. 14478, which
initiated the preparation of General Plan 2040 and accepted the Final Work Program; and
WHEREAS, on August 9, 2018, the City issued a competitive Request for Proposals for
General Plan 2040 Technical Support and Downtown Precise Plan; and
WHEREAS, a selection committee comprised of staff and a General Plan 2040 Steering
Committee member was formed to review submitted proposals; and
WHEREAS, the City received one proposal on or before the September 5th, 2018 filing
deadline for the Transportation analysis scope for General Plan 2040 Technical Support and
Downtown Precise Plan; and
WHEREAS, the selection committee conducted a thorough and objective review of the
received Transportation analysis scope proposals; and
WHEREAS, the selection committee recommended the proposal submitted by Fehr & Peers
Associates, Inc.as qualified and meeting the City’s requirements after consideration of both the review
of Transportation analysis scope proposal and in-person interview; and
WHEREAS, the City does not have existing staff persons dedicated to long range planning
efforts or the staffing capacity amongst existing staff to conduct an Transportation analysis for the
General Plan 2040; and
WHEREAS, the City was awarded grant funding from the Metropolitan Transportation
Commission to provide financial support for the creation of a Downtown Precise plan as part of this
contract; and;
WHEREAS, the City has sufficient funds in the General Plan Special Revenue Fund #218 to
be appropriated for FY18/19 to support this contract for the duration of the contract; and;
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of San Rafael
hereby authorizes as follows:
1.An amount of $89,250 shall be appropriated for FY18/19 from the General Plan Special
Revenue Fund #218.
Page 2 of 2
2.The City Manager to sign the Professional Services Agreement with Fehr & Peers Associates,
Inc. attached hereto as Exhibit 1, subject to final approval as to form by the City Attorney, for
services as Transportation Technical Consultant for the San Rafael General Plan 2040 Update
project, with a Term of January 22, 2019 to January 22, 2021, with up to two optional one (1)
year extensions, for a total base contract amount up to $260,000 and an additional five (5)
percent of the total base contract, or $13,000, available upon approval of the City Manager for
a total contract amount not to exceed $273,000.
I, LINDSAY LARA, Clerk of the City of San Rafael, hereby certify that the foregoing resolution was
duly and regularly introduced and adopted at a regular meeting of the City Council of said City held on
Tuesday, the 22nd day of January 2019, by the following vote, to wit:
AYES:
NOES:
ABSENT:
COUNCILMEMBERS: Bushey, Colin, Gamblin & Mayor Phillips
COUNCILMEMBERS: None
COUNCILMEMBERS: McCullough
______________________________
LINDSAY LARA, City Clerk
Exhibit 1: Professional Services Agreement between City of San Rafael and Fehr &
Peers Associates, INC., with
Exhibit A to Exhibit 1 San Rafael General Plan 2040 – Transportation Consultant Scope of
Work for Fehr & Peers Associates, INC., January 22, 2019.
AGREEMENT FOR PROFESSIONAL SERVICES
FOR GENERAL PLAN 2040 TRANSPORTATION TECHNICAL
CONSULTING SERVICES
This Agreement is made and entered into this __ day of _______ , 2019, by
and between the CITY OF SAN RAFAEL (hereinafter "CITY"), and FEHR & PEERS
ASSOCIATES, INC. (hereinafter "CONTRACTOR").
RECITALS
WHEREAS, on March 5, 2018, CITY'S City Council adopted Resolution No. 14478,
which accepted the Final Work Program and initiated the preparation of General Plan 2040; and
WHEREAS, the CITY does not have existing staff persons dedicated to long range
planning efforts or the staffing capacity amongst existing staff to conduct a Transportation analysis
for the General Plan 2040, and CONTRACTOR has the expertise to do so;
AGREEMENT
NOW, THEREFORE, the parties hereby agree as follows :
I. PROJECT COORDlNA TION.
A. CITY'S Project Manager. '.The-Barry Miller is hereby designated the PROJECT
MANAGER for the CITY and said PROJECT MANAGER shall supervise all aspects of the progress
and execution of this Agreement.
B. CONTRACTOR'S Project Director. CONTRACTOR shall assign a single
PROJECT DIRECTOR to have overall responsibility for the progress and execution of this
Agreement for CONTRACTOR. Bob Grandy is hereby designated as the PROJECT DIRECTOR
for CONTRACTOR. Should circumstances or conditions subsequent to the execution of this
Agreement require a substitute PROJECT DIRECTOR, for any reason, the CONTRACTOR shall
notify the CITY within ten (10) business days of the substitution.
2. DUTIES OF CONTRACTOR.
CONTRACTOR shall perform the duties and/or provide technical services for the General
Plan 2040, as specified in the "Work Plan" dated January 8, 2019 attached hereto as Exh ibit "A" and
incorporated herein by reference.
3. DUTIES OF CITY.
CITY shall pay the compensation as provided in Section 4 of this Agreement. CITY shall
also provide a work space for CONTRACTOR, background information, oversight and direction,
network computer access and other materials necessary for CONTRACTOR to perform their duties.
4. COMPENSATION.
For the full performance of the services described herein by CONTRACTOR, CITY shall
pay CONTRACTOR a total base contract amount not to exceed $260,000 for time and materials as
described in Exhibit A. An additional five (5) percent of the total base contract, or $13 ,000 may be
added to the budget upon approval of the City Manager for a total contract amount not to exceed
$273,000.
Payment will be made monthly upon receipt by PROJECT MANAGER of itemized invoices
submitted by CONTRACTOR.
5. TERM OF AGREEMENT.
The term of this Agreement shall be for 2 year(s) commencing on approval of this contract
and ending on January 22nd , 2021. Upon mutual agreement of the parties , and subje ct to the approval
of the City Manager the term of this Agreement may be extended for two additional periods of up to
one year.
6. TERMINATION.
A. Discretionary. Either party may terminate this Agreement without cause upon thirty
(30) days written notice mailed or personally delivered to the other paity.
B. Cause. Either paity may terminate this Agreement for cause upon fifteen (15) days
written notice mailed or personally delivered to the other party, and the notified party's failure to cure
or correct the cause of the termination, to the reasonable satisfaction of the paity giving such notice ,
within such fifteen (15) day time period.
C. Effect of Termination. Upon receipt of notice of t e rmination, neither party s hall
incur additional obligations under any provision of this Agreement without the prior written consent
of the other.
D. Return of Documents. Upon te rmination, any and all CITY documents or materials
provided to CONTRACTOR and any and a ll of CONTRACTOR's docume nts and materials
prepared for or relating to the pe rformance of its duties under this Agreement, shall be delivered to
CITY as soon as possible, but not later than thi1ty (30) days after termination.
7. OWNE RSHIP OF DOCUMENTS.
The written documents and materials prepared by the CONTRACTOR in connection with
2
the performance of its duties under this Agreement, shall be the sole prope11y of CITY. CITY may
use said prope1ty for any purpose, including projects not contemplated by this Agreement.
8. INSPECTION AND AUDIT.
Upon reasonable notice, CONTRACTOR shall make available to CITY, or its agent, for
inspection and audit, all documents and materials maintained by CONTRACTOR in connection with
its performance of its duties under this Agreement. CONTRACTOR shall fully cooperate with
CITY or its agent in any such audit or inspection.
9. ASSIGNABILlTY.
The parties agree that they shall not assign or transfer any interest in this Agreement nor the
performance of any of their respective obligations hereunder, without the prior written consent of the
other party, and any attempt to so assign this Agreement or any rights, duties or obligations arising
hereunder shall be void and of no effect.
10. INSURANCE.
A. Scope of Coverage. During the term of this Agreement, CONTRACTOR shall
maintain, at no expense to CITY, the following insurance policies:
1. A commercial general liability insurance policy in the minimum amount of
one million dollars ($1,000,000) per occun-ence/two million dollars ($2,000,000) aggregate, for death,
bodily injury, personal injury, or property damage.
2. An automobile liability (owned, non-owned, and hired vehicles) insurance
policy in the minimum amount of one million dollars ($1,000,000) dollars per occurrence.
3. If any licensed professional performs any of the services required to be
perfon-ned under this Agreement, a professional liability insurance policy in the minimum amount of
one million dollars ($1,000,000) per occurrence/two million dollars ($2,000,000) aggregate, to cover
any claims arising out of the CONTRACTOR's performance of services under this Agreement.
Where CONTRACTOR is a professional not required to have a professional license, CITY reserves
the right to require CONTRACTOR to provide professional liability insurance pursuant to this
section.
4. If it employs any person, CONTRACTOR shall maintain worker's
compensation insurance, as required by the State of California, with statutory limits, and
employer's liability insurance with limits of no less than one million dollars ($1,000,000) per
accident for bodily injury or disease. CONTRACTOR's worker's compensation insurance shall
be specifically endorsed to waive any right of subrogation against CITY.
B. Other Insurance Requirements. The insurance coverage required of the
CONTRACTOR in subparagraph A of this section above shall also meet the following requirements:
3
1. Except for professional liability insurance or worker's compensation
insurance, the insurance policies shall be specifically endorsed to include the CITY, its officers,
agents, employees, and volunteers, as additional insureds (for both ongoing and completed
operations) under the policies.
2. The additional insured coverage under CONTRACTOR'S insurance policies
shall be "primary and non contributory" with respect to any insurance or coverage maintained by
CITY and shall not call upon CITY's insurance or self-insurance coverage for any contribution. The
"primary and noncontributory" coverage in CONTRACTOR'S policies shall be at least as broad as
ISOformCG20010413.
3. Except for professional liability insurance or worker's compensation
insurance, the insurance policies shall include, in their text or by endorsement, coverage for
contractual liability and personal injury.
4. By execution of this Agreement, CONTRACTOR hereby grants to
CITY a waiver of any right to subrogation which any insurer of CONTRACTOR may acquire
against CITY by vi1tue of the payment of any loss under such insurance. CONTRACTOR
agrees to obtain any endorsement that may be necessary to effect this waiver of subrogation, but
this provision applies regardless of whether or not CITY has received a waiver of subrogation
endorsement from the insurer.
5. If the insurance is written on a Claims Made Form, then, following termination
of this Agreement, said insurance coverage shall survive for a period of not less than five years.
6. The insurance policies shall provide for a retroactive date of placement
coinciding with the effective date of this Agreement.
7. The limits of insurance required in this Agreement may be satisfied by a
combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall
contain or be endorsed to contain a provision that such coverage shall also apply on a primary and
noncontributory basis for the benefit of CITY (if agreed to in a written contract or agreement) before
CITY'S own insurance or self-insurance shall be called upon to protect it as a named insured.
8. It shall be a requirement under this Agreement that any available insurance
proceeds broader than or in excess of the specified minimum insurance coverage requirements and/or
limits shall be available to CITY or any other additional insured party. Fmthermore, the requirements
for coverage and limits shall be: (I) the minimum coverage and limits specified in this Agreement; or
(2) the broader coverage and maximum limits of coverage of any insurance policy or proceed s
available to the named insured; whichever is greater. No represe ntation is made that the minimum
Insurance requirements of this agreement are sufficient to cover the obligations of the
CONTRACTOR under this agreement.
C. Deductibles and SIR's. Any deductibles or self-insured retentions in
CONTRACTOR's insurance policies must be declared to and approved by the PROJECT
MANAGER and City Attorney, and shall not reduce the limits of liability. Policies containing any
4
self-insured retention (SIR) provision shall provide or be endorsed to provide that the SIR may be
satisfied by either the named insured or CITY or other additional insured party. At CITY's option,
the deductibles or self-insured retentions with respect to CITY shall be reduced or eliminated to
CITY's satisfaction, or CONTRACTOR shall procure a bond guaranteeing payment of losses and
related investigations , claims administration , attorney's fees and defense expenses.
D. Proof oflnsnrance. CONTRACTOR shall provide to the PROJECT MANAGER
or CITY'S City Attorney all of the following: (I) Ce1tificates oflnsurance evidencing the insurance
coverage required in this Agreement; (2) a copy of the policy declaration page and/or endorsement
page listing all policy endorsements for the commercial general liability policy, and (3) excerpts of
policy language or specific endorsements evidencing the other insurance requirem e nts set forth in this
Agreement. CITY reserves the right to obtain a full ce1tified copy of any insurance policy and
endorsements from CONTRACTOR. Failure to exercise this right shall not constitute a waiver of
the right to exercise it later. The insurance shall be approved as to form and sufficiency by PROJECT
MANAGER and the City Attorney.
11. INDEMNIFICATION.
A. Except as otherwise provided in Paragraph B., CONTRACTOR shall, to the fullest
extent permitted by law, indemnify, release, defend with counsel approved by CITY, and hold
harmless CITY, its officers, agents, employees and volunteers (collectively, the "City
Indemnitees"), from and against any claim, demand, suit, judgment, loss , liability or expense of
any kind, including but not limited to attorney's fees, expe1t fees and all other costs and fees of
litigation, (collectively "CLAIMS"), arising out of CONTRACTOR'S performance of its
obligations or conduct of its operations under this Agreement. The CONTRACTOR's obligations
apply regardless of whether or not a liability is caused or contributed to by the active or passi ve
negligence of the City Indemnitees. Howev er, to the extent that liability is caused b y the active
negligence or willful misconduct of the City lndemnitees, the CONTRACTOR's
indemnification obligation shall be reduced in propo1tion to the City Indemnitees' share o f
liability for the active negligence or willful misconduct. ln addition, the acceptance or approval
of the CONTRACTOR's work or work product by the CITY or any of its directors, officers or
employees shall not relieve or reduce the CONTRACTOR's indemnification obligations. In the
event the City Indemnitees are made a party to any action, lawsuit, or other adversarial proceeding
arising from CONTRACTOR'S performance of or operations under this Agreement,
CONTRACTOR shall provide a defense to the City lndemnitees or at CITY'S option reimburse
the City Indemnitees their costs of defense, including reasonable attorneys' fees , incurred in
defense of such claims.
B. Where the services to be provided by CONTRACTOR under this A greem e nt are
design profe ssional services to be performed by a design professional as that term is defined under
Civil Code Section 2782.8, then, to the extent permitted by law including without limitation, Civil
Code s ections 2782, 2782.6 and 2782.8, CONTRACTOR s hall indemnify and hold harmless the
CITY and its officers, officia ls, and e mployees (collectively City Indemnitees) from and against
damages, liabilities or costs (including incidental damages. Court costs , reasonable attorney 's fees
as may be determined by the Co urt, litigation expenses and fee s of expe rt witnesse s incurred in
connection therewith and costs of investigation) to the extent they are caused by the negligen ce ,
5
recklessness, or willful misconduct of CONTRACTOR, or any subconsultants, or s ubcontractor
or anyone directly or indirectly employed by them, or anyone for whom they are legally liable
(collectively Liabilities). Such obligation to hold harmless and indemnify any inde mnity shall not
apply to the extent that such Liabilities are caused in part by the negligence or willful misconduct
of such City Indemnitee.
C. The defense and indemnification obligations of this Agreement are unde1taken in
addition to , and shall not in any way be limited by, the insurance obli gatio ns contained in thi s
Agreement, and shall s urvive the termination or completion of this Agreement for the full period
ohime allowed by law.
12. NONDISCRIMINATION.
CONTRACTOR shall not discriminate, in any way, against any person on the basis of age,
sex, race, color, religion, ancestry, national origin or disability in connection with or related to the
performance of its duti es and obligations under this Agreement.
13. COMPLIANCE WITH ALL LAWS .
CONTRACTOR shall observe and comply with all applicable federal, state and local laws,
ordinances, codes and regulations, in the performance of its duties and obligations under this
Agreement. CONTRACTOR shall perfmm all services under this Agreement in accordance with
these laws, ordinances, codes and regulations. CONTRACTOR shall release, defend, indemnify
and hold harmless CITY , its officers, agents and employees from any and all damages, liabilities,
penalties, fines and all other consequences from any noncompliance or violation of any laws,
ordinances, codes or reg ulations.
14. . NO THIRD PARTY BENEFICIARIES.
CITY and CONTRACTOR do not intend , by a ny provision of thi s Agreement, to create in
any third party, any benefit or right owed by one party, under the terms and conditions of this
Agreement, to the other party.
15. NOTICES.
All notices and other communications required or permitted to be given under this Agreement,
including any notice of change of address, shall be in writing and given by personal d e li very, or
deposited with the United States Postal Service, postage prepaid , addressed to the parties intended to
be notified. Notice s hall be deemed given as of the date of personal delivery, or if m a iled, upon the
date of deposit with the United States Postal Service. Notice shall be given as follows:
TO CITY's Proj ect Manager:
6
Barry Miller
City of San Rafael
1400 Fifth Avenue
P.O. Box 151560
San Rafael, CA 94915-1560
TO CONTRACTOR's Project Director: Bob Grandy
Fehr & Peers Associates, Inc.
332 Pine St., 4th Floor
San Francisco, CA 94104
16. INDEPENDENT CONTRACTOR.
For the purposes, and for the duration, of this Agreement, CONTRACTOR, its officers,
agents and employees shall act in the capacity of an Independent Contractor, and not as employees of
the CITY. CONTRACTOR and CITY expressly intend and agree that the status of
CONTRACTOR, its officers, agents and employees be that of an Independent Contractor and not
that of an employee of CITY.
17. ENTIRE AGREEMENT --AMENDMENTS.
A. The terms and conditions of thi s Agreement, all exhibits attached, and all documents
expressly incorporated by reference, represent the entire Agreement of the pa11ies with respect to the
subject matter of this Agreement.
B. This written Agreement shall supersede any and all prior agreements, oral or written,
regarding the subject matter between the CONTRACTOR and the CITY.
C. No other agreement, promise or statement, written or oral, relating to the subject
matter of this Agreement, shall be valid or binding, except by way of a written amendment to this
Agreement.
D. The terms and conditions of this Agreement shall not be altered or modified except
b y a written amendment to this Agreement s igned by the CONTRACTOR and the CITY.
E. If any conflicts ari s e between the term s a·nd conditions of this Agreement, and the
terms and conditions of the attached exhibits or the documents expressly incorporated by refe rence ,
the terms and conditions of this Agreement shall control.
18. SET-OFF AGAINST DEBTS.
CONTRACTOR agrees that CITY may deduct from any payment due to CONTRACTOR
under thi s Agreement, any monies which CONTRACTOR owes CITY under any ordinance,
agreement, contract or resolution for any unpaid taxes, fees , licenses, assessments, unpaid checks or
other amounts .
19 . WAIVE RS.
The waiver by e ither pa11y of any breach or violation of any term , c ovenant or conditi o n of
thi s Agreement, or of an y ordinance, law or regulation , s hall not be deemed to be a wai ver of an y
7
other term, covenant, condition, ordinance, law or regulation, or of any subsequent breach or violation
of the same or other term, covenant, condition, ordinance, law or regulation. The subsequent
acceptance by either patty of any fee, performance, or other consideration which may become due or
owing under this Agreement, shall not be deemed to be a waiver of any preceding breach or violation
by the other party of any term, condition, covenant of this Agreement or any applicable law, ordinance
or regulation.
20. COSTS AND A TIORNEY'S FEES.
The prevailing party in any action brought to enforce the terms and conditions of this
Agreement, or arising out of the performance of this Agreement, may recover its reasonable costs
(including claims administration) and attorney's fees expended in connection with such action.
21. CITY BUSINESS LICENSE/ OTHER TAXES.
CONTRACTOR shall obtain and maintain during the duration of this Agreement, a CITY
business license as required by the San Rafael Municipal Code CONTRACTOR shall pay any and
all state and federal taxes and any other applicable taxes. CITY shall not be required to pay for any
work performed under this Agreement, until CONTRACTOR has provided CITY with a completed
Internal Revenue Service Form W-9 (Request for Taxpayer Identification Number and Certification).
22. SURVIVAL OF TERMS.
Any terms of this Agreement that by their nature extend beyond the term (or termination) of
this Agreement shall remain in effect until fulfilled, and shall apply to both Patties' respective
successors and assigns.
23. APPLICABLE LAW.
The laws of the State of California shall govern this Agreement.
24. COUNTERPARTS AND ELECTRONIC SIGNATURE.
This Agreement may be executed in any number of counterparts, each of which shall be
deemed an original, but all of which together shall constitute one document. Counterpart signature
pages may be delivered by telecopier, email or other means of electronic transmission .
IN WITNESS WHEREOF, the parties have executed thi s Agreement as of the day , month
and year first above written.
CITY OF SAN RAFAEL CONTRACTOR
By:
JIM SCHUTZ , City Manager
8
ATTEST:
LINDSAY LARA, City Clerk
APPROVED AS TO FORM:
ROBERT F. EPSTEIN, City Attorney
9
[If Contractor is a corporation, add signature of second
corporate officer]
By:'711Qr ~A/J_ c~
Name: /'('Kif' /cfY\ fJ<J n ,1 e. / /'-/
l
Title: t r.{).
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-1
Purpose and Key Deliverables
We understand that the purpose of this transportation work plan is to provide a combined analysis of
the City of San Rafael General Plan Update and a Downtown Precise Plan in time for adoption of both
plans in 2020. CEQA clearance for both plans would be provided in a single combined document.
Community input for both plans would be facilitated through a single Steering Committee and a series of
workshops.
The primary transportation deliverables are summarized as follows.
▪State of Transportation White Paper
▪Travel Forecasting Methodology Memo
▪2040 Travel Forecasts
▪Downtown Precise Plan Multi-modal Access & Connectivity White Paper
▪Downtown Precise Plan Parking Policy White Paper
▪Transportation chapter of Combined CEQA Document
▪Required documentation for updated Traffic Mitigation Fee (Optional Task 5.3)
Approach
We understand that the City of San Rafael wishes to accomplish the following objectives as part of the
General Plan Update and Downtown Precise Plan process.
▪Develop Revised Transportation Policies
▪Identifying how the City will comply with SB 743, and how VMT and LOS will be applied in
future planning and CEQA efforts
▪Refine the NEW Marin County Travel Model being developed by TAM to use in the General
Plan and Precise Plan process
▪Screen General Plan Land Use and Circulation Alternatives against key transportation
metrics
▪Develop Circulation Element, Transportation Policies and Thresholds, and Analysis that
Allows for Future CEQA Streamlining (e.g., reducing transportation study requirements for
future projects that are consistent with the General Plan and Downtown Precise Plan)
▪Update Traffic Impact Fees
We will work with City staff and the Steering Committee to consider refinements to transportation
policies, with a focus on VMT and LOS. Key considerations are whether the City wishes to adopt a VMT
policy and VMT CEQA threshold prior to the General Plan and Precise Plan EIR process. Taking this step
would allow for future CEQA streamlining relative to VMT assessments, but would require an early
review and consideration of policy options.
This work plan includes a validation of base year for the new Marin County Travel Model being
developed by TAM for 40 road study segments. We understand the 2015 base year model will be
EXHIBIT A
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-2
completed by TAM and available by March 2019, which will allow for the validation to occur in April and
May, 2019.
Key transportation metrics that could be applied in the screening of General Plan Land Use and
Circulation Alternatives include relative citywide VMT as well as volume/capacity ratio for the 40 road
segments. These metrics would be developed for the 2040 horizon year using the new TAM model as
described above.
We will work with City staff during the early projects stages to identify actions that would maximize
future CEQA streamlining relative to transportation issues. Developing a financially constrained
circulation network (i.e., one that is fully funded) is a key action for future CEQA streamlining. We will
work with City staff to review projects identified in the 2020 General Plan that have not been
implemented, and determine which of those are reasonable candidates to be funded by 2040 given
revenues available to the City of San Rafael.
This work plan also includes a task to update the traffic mitigation fee program, since much of the data
generated during this process can be used to determine required fee adjustments.
Work Plan
Task 1. Reconnaissance
Establishing good working relationships with our clients, maintaining efficiencies, and staying on
schedule are important for the success of the Plan Update. Fehr & Peers will attend up to two kick-off
meetings with the Project team and key stakeholders to determine:
▪Data needs from the City and/or other relevant agencies
▪Points of contact for on-going collaboration and sharing key deliverables
▪Major transportation issues and improvements to be highlighted in the circulation element
▪Transportation analysis approach
▪Overall project administrative goals, including schedule, milestones, and on-going team
communication
Task 1 Deliverables
▪Draft and Final Work Plan to include the Scope of Work, Schedule, and Communication
Strategy
▪List of Major Transportation Issues and Related Key Community Values
▪List of Data Needs
Task 2. Participate in Community Engagement Program
Outreach is an important aspect to the General Plan, as the plan should reflect the goals and vision of
the City as well as key community values. As such, Fehr & Peers will participate in at least seven in-
person meetings with the General Plan project team to engage the San Rafael community.
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-3
Task 2 Activities
▪Participation in up to four in-person meetings with the General Plan Steering Committee
▪Participation in up to three in-person meetings for the community-wide workshops
▪An additional 10 staff hours to participate in other public and stake holder meetings for the
General Plan and Downtown Specific Plan
Task 3. Data Collection and Analysis to Support General Plan and EIR “Setting”
Fehr & Peers will prepare a transportation “White Paper” documenting existing conditions. Below
documents our approach in successfully completing this task.
Task 3.1 Traffic Counts
Fehr & Peers will work with the City to identify road segments where traffic counts are needed to
establish an adequate baseline for transportation planning purposes. Up to 40 road segments will be
included. The need for traffic counts at these segments will be determined and the City, or a third party
vendor to be retained by the City, will conduct the necessary AM and PM counts as needed. Based on
the traffic data, AM and PM peak hour LOS will be determined for the identified roadway segments.
Task 3.2 Inventory and Assessment of Conditions by Mode
Fehr & Peers will review the City of San Rafael’s Public Works’ GIS database to understand existing
conditions throughout the City of San Rafael. Existing conditions include but are not limited to:
signalized intersections, presence of medians and sidewalks, transit stop locations, and bicycle lanes. We
will collect historic roadway operating and maintenance cost data, road maintenance revenues, road
maintenance shortfall data, and historic transportation capital revenue data from City Public Works staff
for use in the financial constraint assessment and fee update. We will collect data on past efforts and
the current status of Transportation Demand Management (TDM) Plans for private companies in the
City of San Rafael from City Planning staff. Additionally, Fehr & Peers will collect and summarize
existing transit data including ridership, headway, and service for all transit providers in the City of San
Rafael. As directed by City staff, we will utilize existing data for this task.
Task 3.3 Baseline Modeling and Analysis
Fehr & Peers is currently working with the Transportation Authority of Marin to prepare a travel
demand forecasting model for the County of Marin. Fehr & Peers will use their experience with the TAM
model to understand the model’s suitability for General Plan application. As part of this task, Fehr &
Peers will prepare a technical memorandum outlining the model’s applicability and recommended
revisions including land use changes, trip types, and transportation infrastructure projects within the
City of San Rafael. The technical memorandum will also summarize household and employment data by
traffic analysis zone (TAZ) for comparison to existing and future projections.
As noted above, Fehr & Peers is currently working with TAM to validate the existing TAM activity-based
travel model. This work scope assumes that the validated base year model files will be available from
TAM by March 2019. Fehr & Peers will conduct a static validation check to see if the new model meets
the validation metrics in the 2017 RTP Guidelines for the 40 study roadway segments in the City of San
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-4
Rafael. If the static validation thresholds are not met for roadways in the City of San Rafael, Fehr & Peers
would conduct additional calibration and validation efforts for the City of San Rafael. We understand
that TAM will develop a 2040 horizon year model by June 2019 that will serve as the 2040 No Build
scenario (i.e., based on MTC Plan Bay Area 2040 growth) for this effort. We will obtain those model files
for application in Task 4.
Task 3.4 Transportation Issues Profile
A key element of Task 3 is to identify existing transportation issues. As part of this task, Fehr & Peers will
address several key policy topics, including the following:
●Complete Streets and Safety1
●Transportation Demand Management (past efforts and current status)
●Goods Movement
●Parking Polices and Management Program
●Emerging Transportation Considerations
●Financially Constrained Transportation System
The white paper will document existing collision data to document transportation issues related to
complete streets and safety. Fehr & Peers will identify collision hot spots and summarize existing
transportation collision patterns. Alternative approaches for addressing the Complete Streets and Safety
policy requirement will be described in the white paper, and may include a single focused policy to
develop and operate city streets based on a “complete streets” concept, methods to develop street
typologies that are tied to land use context, and/or identification of a multimodal analysis methodology.
The white paper will also describe options to incorporate Transportation Demand Management (TDM)
programs into the General Plan process that provide opportunities to utilize the new Downtown Transit
Center and SMART system to achieve Transportation, GHG, and Air Quality goals.
Emerging transportation considerations that will be discussed in the white paper include Transportation
Network Companies (TNCs like Uber and Lyft), shared transportation systems, enhanced technology and
information systems, and partial or fully autonomous vehicles. The potential effects of these emerging
technologies on roadway needs, transit ridership, VMT, parking, and curbside management will be
discussed.
Recent litigation and the 2017 General Plan Guidelines have caused agencies to increase the level of
analysis and policy considerations related to the need for transportation plans to be realistic based on
projected costs and available revenues. The white paper will describe policies and actions considered by
other agencies to address transportation funding shortfalls.
Task 3.5 Summary Report
Fehr & Peers will prepare a report describing existing transportation conditions to initiate the planning
process. The report will include road segment LOS analysis for the roadway segments identified in Task
3.1. It will provide a summary of existing conditions for all travel modes and highlight existing
1 The 2018 Marin County Safety Plan will be consulted as part of this task.
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-5
transportation issues in the City of San Rafael. The white paper will also include a summary of emerging
transportation trends and highlight how transportation is expected to evolve within the City of San
Rafael.
Task 3 Deliverables
▪TAM Model Review and Preliminary Analysis Technical Memorandum
▪State of Transportation White Paper
Task 4. Prepare and Analyze General Plan 2040 Transportation Forecasts
Fehr & Peers will work with the Project team to prepare and analyze 2040 transportation forecasts,
identify transportation improvements, strategies, polices, land use changes for mitigation.
Task 4.1 Calculate 2015-2040 Growth by Zone
We understand that City staff will perform the growth analysis exercise and provide 2040 land use
forecasts by model land use type, and that these forecasts will be consistent with 2040 citywide
population and employment control totals in MTC’s Plan Bay Area 2040 RTP/SCS. City staff will also
review the 2015 land use allocations in the TAM 2015 base year model. Fehr & Peers will provide model
land use and network information for City staff use. City staff will prepare growth calculations by TAZ,
which Fehr & Peers will use for base year (2015) and horizon year (2040) model calculations. City staff
will provide population, households, and employment for each TAZ for up to three land use alternatives.
City staff will provide electronic files detailing the preferred land use plan by TAZ that includes a
“crosswalk” from the General Plan designation to model land use types as well as population and
employment rates by acre, for the three land use alternatives. It is likely that each land use alternative
will include different assumptions for Downtown, based on the parallel process of developing land use
alternatives for the Downtown Precise Plan.
Task 4.2 Traffic Modeling and Analysis
Under Task 4.2, Fehr & Peers will use the 2040 travel model provided by TAM to develop 2040 forecasts
for citywide VMT and road segment volumes. For the three General Plan land use alternatives, only
forecasts for the 40 road segments will be developed; for the preferred General Plan land use
alternative, roadway segment forecasts will be developed for the 2040 No Project and 2040 Plus Project
scenarios. Model validation or calibration efforts are not included.
For the three General Plan land use alternatives, 2040 LOS will be determined for the 40 study road
segments. The number of travel lanes that would be required to meet current General Plan LOS
designations will be identified.
For the preferred General Plan land use alternative, Fehr & Peers will calculate LOS for the 40 road
segments identified through Task 3.1. The improvements required to meet current General Plan LOS
designations will be identified. After reviewing the road segment LOS results with City staff, we will
collaborate to identify locations for a focused operations assessment. The study budget includes
$10,000 for this focused traffic operations assessment. This information will be summarized in a matrix
for City staff review and comment.
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-6
To comply with SB 743, the City will need to make a series of decisions about how to change current
transportation impact analysis and shift to the use of VMT. The City will need to address questions
related to VMT analysis methodologies, thresholds, and feasible mitigation measures. As part of the
decision making process, we would work with staff to consider the following questions.
1.Does the City want to follow the VMT analysis recommendations developed by OPR for SB
743 implementation? If not, substantial evidence will be needed to support the City’s
preferred analysis approach, forecasting methodology, thresholds, etc.
2.How should VMT analysis methodology be coordinated across the air quality, energy,
greenhouse gas, and transportation sections of CEQA environmental documents for the
general plan and subsequent projects? OPR recommends that SB 743 VMT analysis focus on
automobile VMT only for individual land uses and trip types. In contrast, current practice for
estimating VMT for the other environmental subjects above is to account for all VMT
associated with a proposed project.
To help the City answer these questions, Fehr & Peers will prepare VMT per capita and/or VMT per
service population forecasts using the new TAM travel demand model. Because the TAM travel model
pivots off the MTC regional model, it meets OPR recommendations to base VMT calculations on the
regional travel model. It should be noted that VMT forecasts from the MTC model do not account for
trips made to or from locations outside the nine Bay Area counties, and adjustments should be made to
the final VMT forecasts to account for all trips as recommended by OPR.
LOS and VMT Analysis
We understand the City of San Rafael would like to explore its options with respect to measuring project
impacts and monitoring performance of its roadway network. These options could include continued
use of LOS on roads outside of Downtown and other transit-oriented zones for planning purposes, or a
citywide shift to VMT for all future traffic analysis. Therefore, we propose completing both a VMT
analysis, in compliance with SB 743, and LOS analysis as part of this project.
Based on the forecasts prepared as described above, Fehr & Peers will conduct roadway segment LOS
for the cumulative and cumulative plus project scenario to determine if changes in the current
circulation element network (i.e., number of travel lanes) are required to meet existing LOS thresholds.
Potential modifications to current LOS policy thresholds will also be discussed. As a result of the LOS
analysis described above, Fehr & Peers will identify future roadway modifications to meet the desired
transportation thresholds and metrics. We will prepare conceptual cost estimates for this list of
projects, either through updating previous cost estimates or preparing new ones, as described in Task
4.5 below. We will work with the City to determine the extent to which identified projects may be
added to a list of planned improvements or are determined infeasible due to fiscal constraints.
Task 4.3 Greenhouse Gas (GHG), Air Quality, and Noise Analyses
Fehr & Peers will prepare 2040 VMT forecasts for the preferred plan for distribution to the project team
for use in calculating impacts on GHGs, air quality, and noise. We will also provide a summary of the
methodology used to develop the VMT forecasts based on OPR SB 743 guidance, which differs from
common methods used to calculate GHG emissions (e.g., RTAC methods only account for one-half of
IX/XI trips in VMT calculations).
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-7
Task 4.4 Focused Analysis for the Downtown Precise Plan Area
Downtown Precise Plan Analysis
Fehr & Peers will prepare a multimodal analysis of the Downtown Plan Area. The focus of this effort will
be to identify transportation policies to support planned development in the Downtown Area including a
revised LOS policy and policies related to the allocation of future street right-of-way, commercial
loading, curbside management, travel demand management, and transportation management
strategies related to downtown facilities. This includes consideration of how transportation facilities will
be affected by emerging transportation trends such as Transportation Network Companies (Uber, Lyft,
etc.) and autonomous vehicles.
The white paper will document the Downtown Plan Area’s existing conditions based on available data,
including locations of signalized intersections, transit stops and ridership, bicycle network, and existing
traffic patterns. Additionally, using available data from City and/or transit agencies, we will include the
existing mode splits.
Downtown Parking Analysis and Policy Strategy
Fehr & Peers will develop a parking policy strategy based on a review of the recently completed
Downtown Parking and Wayfinding Study as well as the preferred General Plan land use study and
community input. The focus of the effort will be to identify parking and loading policies that both
support planned growth, are consistent with the General Plan vision, and account for current and
emerging transportation trends.
Task 4.5 Conceptual Planning Level Transportation Cost Estimates
Fehr & Peers will develop conceptual planning level cost estimates for the transportation projects
identified in Task 4.2. Our cost estimates will be developed using Caltrans cost data or other relevant
data from recent projects in the City (if available) or from other Bay Area projects. Costs will include an
estimate of construction costs, soft costs, and contingency based on the guidance in the Caltrans project
development manual or per direction from City staff.
For corridor improvements, we will develop costs on a lineal distance basis for typical corridor
improvements (e.g. roadway widening) based on the various corridor improvements identified in the
previous tasks. For intersection improvements, we will develop costs on a per location basis, likely
including a base cost of signal upgrades with roadway spot improvements (e.g. turn pocket installation
or widening at intersection approaches).
Our estimates will not include costs for right of way acquisition. We will document our assumptions for
cost components where applicable. Fehr & Peers will provide the City with our draft assumptions for
cost items and unit costs for review and concurrence prior to finalizing our cost estimates. A discussion
of likely funding shortfalls and the types of projects that should be eligible for TIF funding will be
included.
Task 4 Deliverables
▪2040 VMT and Network Forecasts for 3 Alternatives and the Preferred Plan
▪Downtown Multi-modal Access & Connectivity White Paper
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-8
▪Downtown Parking Analysis & Policy White Paper
▪Conceptual Planning Level Transportation Cost Estimates
Task 5. Participate in Drafting General Plan Transportation Element and EIR
Task 5.1 Transportation Element
We understand that we will not be responsible for preparing the Transportation Element of the General
Plan or the Transportation Section of the Downtown Precise Plan; however, we will assist the Consultant
team in developing polices and action programs for inclusion in the Plans. We have allocated
approximately eight hours of consultant time to review and provide comment on transportation policies
developed by City staff.
As part of our input, we anticipate providing input on LOS and VMT related policies. These policies
would focus on setting VMT reduction targets that could also be used as CEQA impact significance
thresholds and defining the range of potential feasible mitigation measures. The input will be informed
by community input on the Existing Conditions Report. This initial VMT information will demonstrate the
level of forecasted VMT reduction based on the projected population and employment growth in the
Land Use Element and the planned transportation network expansion in the Transportation Element.
This information is intended to help the City determine an appropriate level of VMT reduction for
mobile greenhouse gas emissions, mobile air pollutant emissions for air quality purposes, and individual
land use and transportation projects in compliance with SB 743.
General Plan guidance requires that the Transportation Element be financially constrained. We will
conduct this assessment in collaboration with City staff based on a combination of construction costs for
new improvements, deferred maintenance backlog, and ongoing operation and maintenance costs for
the entire transportation system (i.e., roadways, transit, lighting, utilities, etc.).
Task 5.2 General Plan and Precise Plan EIR
Fehr & Peers will prepare the Administrative Draft EIR for the General Plan and Precise Plan. The
transportation section for the ADEIR will cover topics related to the roadway, transit, bicycle, pedestrian,
and truck components of the transportation system. Based on comments received from City staff, we
will prepare the transportation section of the Draft EIR. We will provide input into this process as
needed to ensure the section is complete, accurate, and legally adequate.
Potential significant impacts will be measured based on changes to baseline conditions that occur under
the cumulative plus project scenario consistent with CEQA Guidelines Section 15125 (a) and considering
the City’s transportation impact significance thresholds. If possible, we recommend that thresholds for
the General Plan EIR be developed/confirmed by City staff prior to starting the environmental impact
analysis and be adopted according to CEQA Guidelines Section 15064.7. If the project schedule does not
allow for this approach, then we will apply the same thresholds used in previous City of San Rafael EIRs.
The potential compliance with SB 743 could complicate this approach if the City wants new SB 743
thresholds for the General Plan EIR. The approach to transit, bicycle, pedestrian, and truck impact
evaluation will be qualitative and generally rely on potential disruptions to these system components
that could be caused or exacerbated by the proposed project. At this time, the specific approach for
roadway network impacts is somewhat uncertain given the potential role of SB 743 compliance. As
Caltrans is now requesting VMT analysis instead of LOS analysis based on their interim SB 743 guidance,
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-9
we are including sufficient time for this task to include LOS analysis for the cumulative no project and
plus project scenarios for 40 road segments (with the exception of freeway facilities per the Caltrans
interim guidance noted above), as well as VMT analysis.
We will also address CEQA Guidelines Section 15125 (d) requiring an analysis that examines
inconsistencies between the currently adopted general plan and the proposed plan by comparing
transportation network performance differences between the cumulative no project and cumulative
plus project scenarios. These differences do not constitute impacts, as impacts will be determined as
described above, but the information is required to be disclosed for CEQA purposes.
Task 5 Deliverables
▪Draft polices for consideration in the Transportation Element of the General Plan and
Downtown Precise Plan
▪Prepare an admin draft, screencheck draft, and public review draft DEIR Transportation
Chapter for inclusion in the Combined General Plan/ Precise Plan EIR
Task 5.3 Traffic Mitigation Fee Update
Fehr & Peers will assist the City in development of an updated Traffic Mitigation Fee that can be
adopted concurrently with the General Plan. The Fee would facilitate development of the capital
projects identified in the General Plan and EIR, and provide a tool for assigning a fair share of future
improvement costs to future development. It would also reduce the need for (and scope of) future
traffic studies for projects that are consistent with the General Plan and Downtown Precise Plan.
The scope for this update to the Traffic Mitigation Fee includes both a nexus analysis and a fee
calculation. The revised traffic mitigation fees will be determined on a “per trip” basis. If desired, we will
work with City staff to identify fee districts that reflect the different trip making characteristics for land
uses based on their proximity to transit service, land use density, network characteristics (i.e.,
walkability), etc. If the City decides in the future to consider basing the fees on another metric such as
VMT, Fehr & Peers will develop a revised work plan and budget for that effort. For the nexus analysis,
we will develop a draft system of roadway improvements for review by City staff. After review by City
staff, we will conduct one additional model run to finalize the roadway network improvements and
generate final travel demand output for the nexus analysis. The information will be used to determine
the preliminary fair-share cost contribution from each district for the fee program’s selected
improvements as well as a preliminary list of potential existing deficiencies.
We will assist City staff in calculating the transportation impact fee based on the nexus analysis results.
As noted previously, we will identify the impact fee per trip based on the nexus analysis, cost estimates
prepared in Task 4.5, and available other funding identified in Task 3.2. This task includes the
development of up to three alternative impact fee structures to allow testing of how different
methodology can affect the distribution of cost between different land use types.
Task 6. Plan Adoption
Fehr & Peers will assist the Project team in preparing response to comments and attending public
hearing meetings.
City of San Rafael General Plan 2040 & Downtown Precise Plan
Transportation Technical Support
Attachment A
WORK PLAN
January 8, 2019 version
A-10
Task 6.1 Response to Comments
Fehr & Peers has assumed up to 16 staff hours to prepare responses to transportation related
comments on the Draft EIR.
Task 6.2 Public Hearings
Fehr & Peers will attend up to two public hearings before the Planning Commission and two hearings
before the City Council. Fehr & Peers will be available to present and/or respond to comments by City
Council, Planning Commission, and/or City staff as requested.
Task 6 Deliverables and Activities
▪16 staff hours to respond to EIR comments
▪Attendance at up to four public hearings for the Plan’s Adoption
Task 7. Project Management and Administration
Fehr & Peers will keep the Project Team informed over the course of the project as to the status of the
analysis as well as set-aside time for regular conference calls to provide updates on data requests,
analysis, etc. As such, we propose the inclusion of recurring coordination calls as needed. We have
assumed up to 18 check-in/coordination calls with the Consultant Project Manager over the course of
the Project. Further, we assume that we will prepare for and participate in up to four in-person
meetings with the Project team over the course of the study.
Task 7 Deliverables and Activities
▪Up to 18 check-in/coordination calls
▪Up to 4 in-person meetings
▪Monthly invoices and progress reports
San Rafael General Plan Update, Downtown Precise Plan, & Traffic Mitigation Fee Update
Budget for Transportation Services
January 8, 2019
Task
Staff Person Labor (hours & billing rates)
Total Key Staff
Principals Associate/QAQC Deputy Project
Manager
Senior
Engineer /
Planner
Engineer /
Planner GIS / Admin
$335 $240 $190 $165 $130 $135 Hours Cost
1.Reconnaissance 4 0 2 6 2 2 16 $3,240
2.Community Engagement 16 0 4 10 0 8 38 $8,850
3.Data Collection & Exiting
Setting 26 24 52 88 100 20 310 $54,570
4.2040 Transportation
Forecasts 22 28 64 106 220 22 462 $75,310
5.Draft Transportation Element
& EIR 12 0 24 56 200 0 292 $43,820
6.Plan Adoption 14 0 14 4 4 0 36 $8,530
7.Project Management &
Administration 32 0 0 0 0 48 80 $17,200
Traffic Mitigation Fee Update
(Task 5.3) 24 32 40 48 48 12 204 $39,100
Labor Totals 150 84 200 318 574 112 1,438 $250,620
Direct Costs (communications, travel, reproduction, etc.) $9,380
Total Budget $260,000