AGENDA ITEM NO.: 3
MEETING DATE: July 20, 2009
San Rafael Redevelopment Agency Agenda Report
Department: Economic Development
Prepared by: ->4'"�ej /,& Approved by: Y,
Nancy Mackie, Deputy City Manager Ke Nor off, Executive Director
SUBJECT: Resolution Approving a Request for a Postponement of the Construction Schedule to
Complete the Phase II Buildings for the San Rafael Corporate Center Project
RECOMMENDATION: Adopt the attached resolution approving a request for a postponement of the
commencement of construction of the final office building (791 Lincoln Avenue) and the eastern parking
garage (788 Lincoln Avenue) in the San Rafael Corporate Center development, pursuant to the Owner
Participation, Disposition and Development Agreement.
BACKGROUND: In 1998, the City Council and Redevelopment Agency Board approved the
development of the 406,000 -square -foot San Rafael Corporate Center on Lindaro and Second Streets in
Downtown. The City Council approved a Development Agreement and related land use and planning
approvals, and the Agency Board approved an Owner Participation, Disposition and Development
Agreement ("OPDDA") for the sale of the City Corporation Yard site to be included in the development.
The property is now owned by Seagate SR Corporate Center LLC (`Seagate"). The first phase of the San
Rafael Corporate Center has been constructed and is currently close to 90% occupied. The second phase
is approved for two parking garages and three office buildings. The office buildings at 770 and 790
Lindaro Street and the western parking garage are under construction. Completion and occupancy of the
"shell" (i.e., no interior improvements) for the 770 and 790 Lindaro Street office buildings is expected to
occur in late summer (September 2009). To date, no lease agreements have been signed for these
buildings. Office surveys indicate that with completion of these buildings, San Rafael will be facing a
30% office vacancy rate. Considering the projections of this survey, it is expected that tenant occupancy
of the 770 and 790 Lindaro Sheet office buildings will occur very slowly.
ANALYSIS: The OPDDA, rather than the Development Agreement, governs the timing of construction
on this project. Under the OPDDA, upon completion of the exterior shells of the 770 and 790 Lindaro
Street office buildings and the western parking garage, construction must start immediately on final office
building (791 Lincoln Avenue) and the eastern parking garage (788 Lincoln Avenue).
FOR AGENCY SECRETARY ONLY
File No.:
Agency Meeting:
Disposition:
Page 2
Seagate believes that commencement of construction on the 791 Lincoln Avenue office building and the
788 Lincoln Avenue parking garage according to this schedule is economically unfeasible in light of the
adverse effects of the current deep economic recession on the City's office vacancy rate, and the limited
availability of commercial real estate construction financing for the project. For these reasons, Seagate is
seeking to postpone the commencement of construction of the final two buildings in the project. (See
attached Seagate letter dated June 22, 2009)
Section 9.04 of the OPDDA permits the Agency and the property owner to agree in writing to extensions
of the times of performance under the agreement. Pursuant to this section, Seagate is requesting that the
Agency Board agree to an extension of 30 months to commence construction of the 791 Lincoln Avenue
office building and the 788 Lincoln Avenue parking garage, with the possibility of a second 30 -month
extension upon reasonable request by Seagate and agreement by the Agency Board. The requested
extension will allow Seagate time to investigate financing options for completing the construction.
Seagate's letter also notes that an extension will allow further exploration of the possibility of enlarging
the 788 Lincoln Avenue parking garage structure for joint use by SMART passengers, an idea that has
been under discussion by SMART and Seagate for several months.
Seagate proposes that during the extension period, it will promptly complete the final, approved
landscaping up to the building pad for the 791 Lincoln Avenue office building and install a perimeter
fence with screening around the building pad. Additionally, Seagate will provide interim parking
meeting City standards until the 788 Lincoln Avenue parking garage is completed. Staff concurs with
these proposals.
Staff has prepared the attached Resolution approving Seagate's June 22, 2009 request. The Agency
Board's adoption of the Resolution will satisfy Section 9.04's requirement that the extension agreement be
in writing.
FISCAL IMPACT: None.
OPTIONS: Staff recommendation is to adopt the attached resolution. Alternative actions include:
• Do not agree to a time extension. This is not recommended as construction of this final office
building will add to the City's office supply at a time of 30% office vacancies.
• Direct staff regarding a different time extension.
ACTION REQUIRED: Adopt Resolution
ATTACHMENTS
A: June 22, 2009 letter request from Seagate
B: Resolution
MOVED BY:
SAN RAFAEL REDEVELOPMENT AGENCY
RESOLUTION NO.
SECONDED BY:
A RESOLUTION OF THE BOARD OF THE SAN RAFAEL REDEVELOPMENT
AGENCY APPROVING A REQUEST FOR A POSTPONEMENT OF THE
CONSTRUCTION SCHEDULE TO COMPLETE THE PHASE II BUILDINGS FOR
THE SAN RAFAEL CORPORATE CENTER PROJECT
WHEREAS, on February 17, 1998 the San Rafael City Council approved a Development
Agreement with Fair, Isaac and Company, Inc. ("Fair, Isaac") for the development of a phased
office park on property located at Second and Lindaro Streets now known and hereafter referred
to as the San Rafael Corporate Center; and
WHEREAS, on May 18, 1998, in connection with the City Council's approval of the
Development Agreement, the San Rafael Redevelopment Agency entered into an Owner
Participation, Disposition and Development Agreement (the "OPDDA") providing for the sale to
and development by Fair, Isaac of certain Agency real property as part of the San Rafael
Corporate Center; and
WHEREAS, the San Rafael Corporate Center project, including title to the properties
subject to the Development Agreement and the OPDDA and all the rights and obligations of
Fair, Isaac under the Development Agreement and the OPDDA and all amendments to those
agreements, have since been comprehensively assigned and transferred to a new property
owner/developer called Seagate SR Corporate Center LLC, a California limited liability
company (hereafter "Seagate SRCC"); and
WHEREAS, the OPDDA establishes the schedule for construction of the San Rafael
Corporate Center, and provides, in part, that once Seagate SRCC commences construction on
Phase II of the project it must diligently pursue construction of the remaining structures and
parking without interruption until completion; and
WHEREAS, Section 9.04 of the OPDDA provides that times of performance under the
OPDDA may be extended in writing by the Agency and the developer; and
WHEREAS, Seagate SRCC has commenced construction of Phase H in compliance with
the Development Agreement and the OPDDA, and expects to complete construction of the office
buildings at 770 and 790 Lindaro Street and the parking garage at 775 Lindaro Street in
September 2009;
WHEREAS, to continue to comply with the required construction schedule, Seagate
SRCC will be required to commence construction on the final Phase R office building, at 791
1
Lincoln Avenue, and parking garage, at 788 Lincoln Avenue, immediately following completion
of the structures now under construction; and
WHEREAS, by letter dated June 22, 2009, Seagate SRCC has requested that the Agency
Board agree to a postponement of the commencement of construction of the 791 Lincoln Avenue
building and the 788 Lincoln Avenue parking garage, for a period of thirty (30) months, with the
agreement that a second thirty (30) month extension may be granted by the Agency Board upon
reasonable request by Seagate SRCC; and
WHEREAS, Seagate SRCC has cited the adverse impacts of the nation's current severe
economic recession on local office vacancy rates, and the limited availability of commercial real
estate construction financing, as reasons for its request to postpone construction; and
WHEREAS, the Agency Board and Seagate SRCC agree that it would be beneficial to
both parties to postpone the time for commencement of construction as requested.
NOW, THEREFORE, IT IS HEREBY RESOLVED as follows:
1. Pursuant to Section 9.04 of the OPDDA, the Agency Board hereby approves
Seagate SRCC's June 22, 2009 written request to postpone the commencement of construction of
the 791 Lincoln Avenue office building and the 788 Lincoln Avenue parking garage by a period
of thirty (30) months. The effective date of the extension shall be the date of issuance of the last
occupancy permit for the exterior shells of the 775 Lindaro Street parking garage and the 770
and 790 Lindaro Street office buildings.
2. The Agency Board may grant a second thirty (30) month extension upon
reasonable request by Seagate SRCC made not less than thirty (30) days prior to expiration of the
initial extension.
3. As a condition of the Agency Board's approvals herein, Seagate SRCC shall take
the following actions proposed in its June 22, 2009 request for extension:
a. Until the 788 Lincoln Avenue parking garage is constructed, Seagate SRCC
shall continue to provide parking for tenants of the occupied office buildings in the San
Rafael Corporate Center, including provisions for interim, paved surface parking on the
788 Lincoln Avenue parking garage parcel. This interim, paved surface parking shall
be striped and available prior to occupancy of the first office tenant in the 770 or 790
Lindaro Street buildings. At no time during this interim period shall the ratio of
parking to occupied office space for the San Rafael Corporate Center be less than 3.3
spaces per 1,000 gross square feet.
b. Upon the start of the extension period, Seagate SRCC shall promptly complete
the final, approved landscaping up to the building pad for the 791 Lincoln Avenue
office building, and shall install a perimeter fence with screening around the building
pad. The final landscaping shall be installed as per the approved landscape plan on file
with the City's Department of Community Development.
2
I, ESTHER C. BEIRNE, Agency Secretary of the San Rafael Redevelopment Agency,
hereby certify that the foregoing was duly and regularly introduced and adopted at a regular
meeting of the Redevelopment Agency of the City of San Rafael held on the 20`s day of July
2009, by the following vote:
AYES: MEMBERS:
NOES: MEMBERS:
ABSENT: MEMBERS:
ESTHER C. BEIRNE, Agency Secretary
3
June 22, 2009
Ms. Lisa A. Goldfien, Esq.
Deputy City Attorney 11
City of San Rafael
1400 Fifth Avenue
San Rafael, CA 94901
Re: San Rafael Corporate Center
Building Entitlements
Dear Lisa:
This letter is being written as a follow up to our recent conversations regarding the above`
referenced project.
As we discussed Seagate SR Corporate Center LLC, ("SRCC") as the owner of the SR
Corporate Center Phase One LLC and SR Corporate Center Phase Two LLC properties located
at 750,775,790 and 770 Lindaro St. and 781,788 and 791 Lincoln Ave, Assessor Parcel Number
(APN's) 013-012-34 and 35 and 013-021-50,51,52,53,54, and 55 ("Property") is currently in
compliance with all material terms and conditions of the Development Agreement and Owners
Participation Disposition & Development Agreement ("OPDDA")
The rights and entitlements governing the Property remain valid, as vested, and provide for the
right to construct a total of five office buildings up to a maximum of four hundred and six
thousand (406,000) square feet of gross floor and two (2) parking structures. The 750 Lindaro
St. and 781 Lincoln St. buildings are complete and occupied. SRCC has been in the process of
completing construction the 775 Lindaro garage and the buildings located at 770 and 790
Lindaro for the past eighteen months. Construction of the 775 Lindaro garage has now been
completed and we expect to complete construction of the two new Lindaro office buildings by
September of 2009. These three new office buildings will be the first for -lease LEED Gold
certified office buildings to be constructed in Marin County.
As you are no doubt aware, Marin County has not been exempt from the effects of the current
deep nationwide economic recession. The office vacancy rate in Marin is at a level not seen in
many decades. In addition, the financing market for commercial real estate and in particular
commercial real estate construction loans, is non-existent at this time. Many of the traditional
lenders have either left the business, been taken over by the Federal government or are in a
retrenchment mode and thus not able or willing to make new loans to development projects.
Finally, prospective tenants are not looking at expanding or moving as the fear of future
economic uncertainty has placed most business plans on hold and left most businesses in a'
"retrenchment" mode.
Attachment A
960 FIFTH AVENUE • SAN RAFAEL, CALIFORNIA 94901
(415) 455-0300 • FAX (415) 453-2892 -
Ms. Lisa A. Goldflen, Esq. Page 2
June 8, 2009
Under these uncertain circumstances, we believe it is economically unfeasible to start
construction on the final two structures immediately after completion of the current
construction in September of this year.
The OPDDA provides in Section 9.04 and the Development Agreement provides in Section 7,1
and in Section 9.1 that the City may agree to a delay in completion of the project. Ve believe
that a mutual agreement between SRCC and the City to delay the start of construction of the
final two structures would be appropriate and beneficial to both parties.
An agreed upon delay would also provide an opportunity to further explore an-excitog
possibility, that is, to expand the parking capacity of the proposed Lincoln Street garage ft ai
benefit future users of the proposed Sonoma Marin Area Rail Transit ("SMART") train sLTviN
For several months now SRCC has been in active discussions with SMART conceming*s •
possible joint use, however, it is clear that given the recent distress in the bond and cOni='rciak''
mortgage markets, combined with the dismal State and Federal economies, additional time will
be needed before SMART and SRCC are able to determine if a joint utilization and expansion
of the Lincoln Street garage will be feasible.
In short, these factors have convinced us that it would be in the best interests of the City, SRCC
as well as the broader community, to delay the start of construction of the 788 Lincoln Street
garage and the proposed building at 791 Lincoln.
Therefore, SRCC requests that the City and SRCC mutually agree to a delay in start of
construction on both the Lincoln Street garage and the proposed building at 791 Lincoln while
SRCC determines the (i) feasibility of constructing the expanded garage for use by SMART
and other public agencies, and (ii) the methods of financing the garage as well as the proposed
building at 791 Lincoln. Specifically, SRCC requests that the City and SRCC agree to an
initial extension of thirty (30) months, with an agreement that a second thirty (30) month
extension may be granted upon reasonable request therefore by SRCC, which request shall be.
made at least 30 days prior to expiration of the initial extension. The effective date of the first
extension would be the date of issuance of the last occupancy permit for the shells of the 775
Lindaro garage and the buildings located at 770 and 790 Lindaro Street. SRCC intends to
complete the final, approved landscaping up to the building pad for the 791 Lincoln Street -
building and we will install a perimeter fence with screening around the building pad during
this interim period. The final landscaping will be installed per the approved landscape plan,
which is on file with the City Department of Community Development.
Until the Lincoln Street garage is constructed on the former City Corporation Yard site
("Eastern Parcel'), SRCC will continue to provide parking for tenants of the occupied office
buildings, which will include provisions for interim, paved surface parking on the:Eastern
Parcel. The interim, paved surface parking on the Eastern Parcel will be striped and available
prior to occupancy of the first office tenant in either the 770 or 790 Lindaro Street buildings.
At no time during this interim period will the ratio of parking to occupied office space be less
than 3.3 spaces per 1,000 gross square feet.
Ms. Lisa A. Goldfien, Esq.
June 8, 2009
Page 3
Please do not hesitate to call with any further questions you may have regarding the San Rafael
Corp ate Cente project or this request.
Sinc ely,
1 \ `
Dennis P. Fisco
Seagate SR Corporate Center, LLC
Cc: Rob Epstein, City Attorney
Ken Nordhoff, City Manager
Naucy Hackle, I7Ogtty City;Manager
Wick Polite, Seagate SR Corporate Center, LLC