HomeMy WebLinkAboutPW TAM Funding Agreement 2018-20; Measure A; Francisco Blvd West MUPFUNDING AGREEMENT NO. 2018-20
COOPERATIVE FUNDING AGREEMENT BY AND BETWEEN THE
TRANSPORTATION AUTHORITY OF MARIN
AND THE CITY OFSAN RAFAEL
This AGREEMENT is made this 2,;;' day of JUN 2018, by and between the
Transportation Authority of Marin, hereinafter referred to as "TAM," and the City of San Rafael,
hereinafter referred to as "CITY."
RECITALS:
WHEREAS, The North South Greenway is a non -motorized transportation network in Marin
County that has been, and will continue to be, implemented in phases. TAM has sponsored
several projects that are closing gaps in the Greenway network, and
WHEREAS, CITY is pursuing a project to create a multi -use path facility connecting the
northern terminus of the Cal Park Hill Pathway to Second Street near the Bettini Transportation
Center and is adjacent to the SMART railroad tracks in downtown San Rafael. Project is part of
the Greenway network, and
WHEREAS, CITY may phase the project due to limited funding resources and if necessary will
seek future funding to complete the original scope of work, and
WHEREAS, TAM and the Metropolitan Transportation Commission (MTC) support building this
facility and have allocated funds to advance the project in the past, and
WHEREAS, CITY has diligently developed the project by completing an environmental analysis,
finalized the construction documents, obtained resource agency permits and is prepared to
enter into a contract to construct the project, and
WHEREAS, CITY has worked with the Sonoma Marin Area Rail Transit (SMART) District to
allow the multi -use path to be constructed within SMART right-of-way, and CITY and SMART
will work together to allow path to be constructed concurrent with the passenger rail extension
project from San Rafael to Larkspur to the extent possible consistent with SMART's construction
schedule and the funding available to CITY, and
WHEREAS, On February 12, 2018 the TAM Board authorized the Executive Director to submit
a request to the MTC to allocate $2.95M of Regional Measure 2 funding and authorized entering
into a funding agreement with the CITY under several conditions stated below, and
WHEREAS, TAM does not own any facilities in the area and is merely providing funding for the
project.
NOW, THEREFORE, it is mutually agreed by and between the parties as follows:
AGREEMENT:
TAM agrees that it shall:
1. Reimburse CITY for direct project costs associated with the construction of the project in
an amount not -to -exceed $2,950,000 in accordance with the conditions of the Board.
TAM recognizes these funds contribute to the funding plan but do not fully fund the
project.
Page 1 of 3
LA_3.1(v0
2. Provide financial oversight of project in cooperation with CITY.
CITY agrees that it shall:
1. Submit the construction documents, estimates, resource agency permits to TAM for their
record when available.
2. Contribute funding, work with Marin County to secure funding, seek grant funding, and/or
secure private funds to close funding gap if one exists.
3. Use all other committed funding sources first before using Regional Measure 2 funds.
4. Complete project with no representation or guarantee that any additional funds will be
contributed from TAM
5. Enter into a contract with SMART to implement the scope of work if SMART is willing to
do so.
6. Submit progress invoice and a final invoice to TAM with back-up documentation to
support invoice amount.
7. Submit brief progress report to TAM for reporting requirements to MTC as necessary.
B. Post on both sides of the construction site at least two signs visible to the public stating
project is funded with Regional Measure 2 Toll Revenues.
It is Mutually Agreed:
TERM: This AGREEMENT shall terminate upon the completion of the construction
phase and acceptance by the CITY or on June 30, 2020, whichever is earlier
2. MODIFICATION: This AGREEMENT, constitutes the entire AGREEMENT, supersedes
all prior written or oral understandings, and may not be extended past the term without
written consent from both parties
3. The CITY shall indemnify and hold harmless TAM, its Commissioners, officers, agents
and employees from all claims, demands, injury, and/or liability, direct or indirect,
incurred by reason of any act or omission of CITY, its officers, agents, employees, and
sub -contractors, under or in connection with this funding agreement including but not
limited to the PS&E package. CITY agrees at its own cost, expense, and risk, to defend
any and all claims, actions, suits, or other legal proceedings brought or instituted against
TAM, its Commissioners, officers, agent, and employees, or any of them, arising out of
such act or omission, and to pay and satisfy any resulting judgments.
4. The TAM shall indemnify and hold harmless CITY, its Supervisors, officers, agents and
employees from any and all claims, demands, injury, and/or liability, direct or indirect,
incurred by reason of any act or omission of TAM, its officers, agents, employees, and
sub -contractors, under or in connection with this funding agreement including but not
limited to the PS&E package. TAM agrees at its own cost, expense, and risk, to defend
any and all claims, actions, suits, or other legal proceedings brought or instituted against
CITY, its Supervisors, officers, agent, and employees, or any of them, arising out of such
act or omission, and to pay and satisfy any resulting judgments.
5. SEVERABILITY: Should any part of this AGREEMENT be declared unconstitutional,
invalid, or beyond the authority of either party to enter into or carry out, such decisions
Page 2of3
shall not affect the validity of the remainder of this AGREEMENT, which shall continue in
full force and effect; provided that the remainder of this AGREEMENT can, absent the
excised portion, be reasonably interpreted to give effect to the intentions of the parties.
6. TERMINATION: This AGREEMENT will be subject to termination as follows: a) if path
project is not completed as part of SMART's passenger rail extension project from San
Rafael to Larkspur, or b) breach of any obligation, covenant or condition by the other
party, upon notice to the breaching party, or c) by mutual consent of both parties.
IN WITNESS WHEREOF, the parties hereto have executed this AGREEMENT on the day first
written above.
TRANSPORTATION AUTHORITY OF MARIN
C
Dianne S einhauser
Executive Director
CITY OF SAN RAFAEL
Ji Sch tz 'IQ
Ci ager
APPROVED AS TO FORM (Optional):
Oaz4eity Attorney
Page 3 of 3