HomeMy WebLinkAboutCC Resolution 14668 (Climate Change GP2040 Addendum) 1
RESOLUTION NO. 14668
RESOLUTION OF THE SAN RAFAEL CITY COUNCIL ADOPTING ADDENDUM
NO. 4 TO THE CERTIFIED SAN RAFAEL GENERAL PLAN 2020 FINAL
ENVIRONMENTAL IMPACT REPORT (FEIR) (SCH# 2003052031), PREPARED FOR
THE SAN RAFAEL CLIMATE CHANGE ACTION PLAN 2030 (CITY FILE #P19-003)
The City Council of the City of San Rafael finds and determines that:
WHEREAS, on November 15, 2004, the San Rafael City Council adopted
Resolution No. 11664, certifying the San Rafael General Plan 2020 Final Environmental
Impact Report (General Plan 2020 FEIR). The General Plan 2020 FEIR is comprised of
the following:
Draft EIR prepared by Nichols-Berman Environmental Consultants, February
2004;
San Rafael General Plan 2020 Background Report prepared by the City of San
Rafael, April 2001 and updated August 2003;
Response to Comments to Draft EIR prepared by Nichols-Berman Environmental
Consultants, August 2004; and
WHEREAS, the FEIR assessed the physical environmental impacts caused by
implementation of the San Rafael General Plan 2020. The General Plan 2020 FEIR
concludes that many of the significant environmental effects can be substantially
lessened through adoption of feasible mitigation measures and that some of these
effects would remain significant and unavoidable despite the adoption of all feasible
mitigation measures. The certification of the General Plan 2020 FEIR was supported by
the following findings:
1. The FEIR for the General Plan 2020 has been completed in compliance with
CEQA;
2. The FEIR is legally sufficient, not only for approval of General Plan 2020, but for
all subsequent actions such as Rezonings, Pre-zonings, Annexations and
revisions to the San Rafael Municipal Code and regulations as necessary to
implement the provisions of the General Plan 2020;
3. The FEIR reflects the independent judgment of the City of San Rafael and the
City Council of the City of San Rafael; and
WHEREAS, subsequent to certifying the General Plan 2020 FEIR, on November
15, 2004, the San Rafael City Council adopted Resolution No. 11665 adopting the San
Rafael General Plan 2020. The adoption of the San Rafael General Plan 2020 was
supported by CEQA Findings of Fact and a Statement of Overriding Consideration
(Appendix C to Resolution 11665) and approval of a Mitigation Monitoring and Reporting
Program (MMRP, Appendix B to Resolution 11665); and
WHEREAS, since 2004, the San Rafael General Plan 2020 has been amended
numerous times. In processing and adopting subsequent amendments, the City has
relied on use of the General Plan 2020 FEIR for environmental review and clearance
and has adopted three addenda to that FEIR. In 2009, the City prepared and adopted
an Addendum to the General Plan 2020 FEIR (Addendum No. 1), which assessed a
2
General Plan Amendment to change the Plan-adopted traffic level of service (LOS)
standard at the intersection of 3rd and Union Streets; and
WHEREAS, in 2011, the City of San Rafael initiated a General Plan Amendment
(GPA11-001) which consisted of 1) amending the Housing Element for 2009-2014, 2)
incorporating a new Sustainability Element, 3) amending Conservation Element Policy
CON-3, and 4) eliminating the Project Selection Process (PSP). An Addendum to the
General Plan 2020 FEIR (Addendum No. 2) encompassed these policies and actions;
and
WHEREAS, in 2014, the City of San Rafael initiated a General Plan Amendment
(GPA14-001) to update the Housing Element for the 2015-2023 planning period,
requiring Addendum No. 3 to the General Plan 2020 FEIR; and
WHEREAS, in 2019, the City of San Rafael initiated an update of the San Rafael
Climate Change Action Plan, adopted in 2009, and the Greenhouse Gas Reduction
Strategy, adopted in 2011; and
WHEREAS, as required by the California Environmental Quality Act (CEQA)
Guidelines, the San Rafael Climate Change Action Plan 2030 (CCAP 2030) is defined
as a ‘project’ and is therefore subject to environmental review. Given the components
and scope of this project, it was determined that “tiering” from the General Plan 2020
FEIR is appropriate and consistent with the CEQA Guidelines Section 15152 in that:
1. The project and its environmental topic areas are broadly covered and analyzed
in the General Plan 2020 FEIR.
2. The project proposes a Climate Change Action Plan update that is not site-
specific or project-specific; it addresses amendments to current policies that are
applicable to the entire San Rafael Planning Area. The level of detailed
contained in this tier need not be greater than the program, plan or policy being
analyzed.
WHEREAS, to further support “tiering” from the General Plan 2020 FEIR, the
Initial Study has been prepared utilizing the most current CEQA Guidelines
environmental checklist and considered the following factors that constitute the
“baseline” for review:
1. None of the components of the project result in any changes to land use
assumptions or projections currently presented in the San Rafael General Plan
2020 and analyzed in the General Plan EIR.
2. No changes are proposed to land use designations or their respective density
and intensity parameters, nor are any changes proposed to adopted land use
designations for individual sites/properties.
3. The project proposes no changes to circulation (transportation/traffic) projections,
policies or implementing programs that would result in changes to level of service
conditions at intersections or along arterials.
4. The Climate Change Action Plan 2030 is intended to address climate change
and presents policies and implementing measures to reduce, among others,
3
GHG emissions, reliance on non-renewable fossil fuels, vehicle miles traveled,
energy consumption, water use and solid waste generation and disposal. While
the ultimate, physical implementation of proposed policies, programs and
measures on a site-specific or project-specific basis may result in individual
impacts on the environment, the current project is at a policy level that is
applicable citywide.
WHEREAS, in preparing the Initial Study, the project was reviewed against
impacts identified and mitigation measures included in the certified General Plan 2020
FEIR (2004). The purpose of this review was to determine if the project would result in:
new significant impacts; an increase in the severity of impacts; or new or expanded
mitigation measures from those analyzed and determined in the General Plan EIR; and
WHEREAS, the project and the findings of the Initial Study were assessed to
determine whether an Addendum to the EIR, Supplemental EIR or Subsequent EIR
would be appropriate to address environmental review for adoption of the San Rafael
Climate Change Action Plan 2030 (City File #P19-003). Public Resources Code Section
21166 and CEQA Guidelines Section 15162 set forth limited situations in which a
Supplemental EIR or Subsequent EIR is required once an FEIR has been certified.
Further, CEQA Guidelines Section 15164 provides for preparation of an Addendum EIR
if no Supplemental EIR or Subsequent EIR is required; and
WHEREAS, as demonstrated in the preparation of an Initial Study and
comparing the project activities and actions against the impacts identified and mitigation
measures included in the General Plan 2020 FEIR, none of the conditions analyzed
under the General Plan 2020 FEIR have changed, nor does the proposed project meet
the criteria for preparing a Subsequent EIR or Supplemental EIR. Further, the project
will not result in one or more significant effects not discussed in the General Plan EIR,
nor does the project create substantially more severe significant effects than previously
examined in the General Plan EIR. Therefore, the Initial Study supports and
recommends an Addendum versus the preparation of a Subsequent EIR or
Supplemental EIR and
WHEREAS, on February 22, 2019, Addendum No. 4 to the San Rafael General
Plan 2020 FEIR was prepared for the San Rafael Climate Change Action Plan 2030
(City File #P19-003); and
WHEREAS, on May 6, 2019, the City Council reviewed and considered the
Addendum No. 4 for the San Rafael Climate Change Action Plan 2030 (City File #P19-
003), along with the previously certified General Plan FEIR and all applicable mitigation
measures therein; and
WHEREAS, the custodian of documents, which constitute the record of
proceedings upon which this decision is based, is the Community Development
Department;
NOW, THEREFORE, BE IT RESOLVED, that the City Council adopts the
Addendum No. 4 to San Rafael General Plan 2020 FEIR, dated February 22, 2019, for
the San Rafael Climate Change Action Plan 2030 (City File #P19-003) based on the
following findings, and hereby reaffirms the findings made by the City in adopting
Resolution No. 11664 (listed above) certifying the General Plan 2020 FEIR as follows:
4
1. CEQA Section 21166 and its corresponding CEQA Guidelines Sections 15162
and 15163, provide that once an EIR has been prepared, no subsequent or
supplemental EIR shall be required by the lead agency unless: (a) substantial
changes are proposed in the project, requiring major revisions in the EIR due to
the involvement of new significant environmental effects or a substantial increase
in the severity of previously identified significant effects; (b) substantial changes
arise in the circumstances of the project's undertaking, requiring major revisions
in the EIR due to the involvement of new significant environmental effects or a
substantial increase in the severity of previously identified significant effects; or
(c) new information, which was not known and could not have been known at the
time the EIR was certified, shows any of the following:
The project will have one or more significant effects not discussed in the
previous EIR;
Significant effects previously examined will be substantially more severe than
shown in the previous EIR;
Mitigation measures or alternatives previously found not to be feasible would
in fact be feasible, and would substantially reduce one or more significant
effects of the project, but the project proponents decline to adopt the
mitigation measure or alternative; or
Mitigation measures or alternatives which are considerably different from
those analyzed in the previous EIR would substantially reduce one or more
significant effects on the environment, but the project proponents decline the
mitigation measure or alternative.
2. CEQA Guidelines Section 15164(a) provides that a lead agency shall prepare an
Addendum to a previously certified FEIR if some changes or additions to the
certified EIR are necessary but none of the conditions calling for the preparation
of a supplemental EIR have occurred. Based on the analysis and documentation
in Addendum No. 4 and the supportive Initial Study environmental checklist
prepared for the proposed project, none of the situations described in CEQA
Section 21166 and CEQA Guidelines Sections 15162 and 15163 apply here.
Based on the results of the supportive Initial Study environmental checklist, the
City has concluded that the proposed project would not result in new significant
adverse impacts nor an increase in the severity of impacts identified and studied
in the certified General Plan 2020 FEIR. None of the conditions requiring a
supplemental or subsequent EIR exists and the Addendum has been prepared in
compliance with CEQA.
3. The Addendum has been prepared in accordance with CEQA, the CEQA
Guidelines, and the provisions of the City of San Rafael Environmental
Assessment Procedures Manual.
4. The Addendum has been presented to the City Council, who has reviewed and
considered the information in the Addendum and the certified General Plan 2020
FEIR prior to approving the project.
5. The Addendum No. 4 and the certified General Plan 2020 FEIR reflect the City's
independent judgment and analysis.
I, LINDSAY LARA, Clerk of the City of San Rafael, hereby certify that the foregoing
resolution was adopted at a regular meeting of the City Council on the 6th day of May
2019.
5
AYES: COUNCILMEMBERS: Bushey, Colin, Gamblin, McCullough & Mayor Phillips
NOES: COUNCILMEMBERS: None
ABSENT: COUNCILMEMBERS: None
LINDSAY LARA, City Clerk