HomeMy WebLinkAboutPW Third Street Rehabilitaion PPTDepartment of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 1 Third Street Rehabilitation Feasibility Study Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 2 Third Street •Major arterial between US 101 and West Marin •1.3 miles •14 Traffic signals •Part of Safe Routes to School •Surrounded by residential, commercial, and downtown land uses Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 3 Background •2004: TAM established Measure A Expenditure Plan –Funds for major roads/infrastructure projects in Marin –Based on: roadway condition, traffic volumes, transit frequency, bicycle and pedestrian access –West End Revitalization Project completed in 2009 •2016: Measure A ($11 million) + State Local Partnership Program ($1.5 million) for Third Street Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 4 Third Street Projected Activities Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 5 Possible Funding Sources •Local –Measure A •Regional -Measure 3 (Transit Center Relocation) •State –SB1 (Gas Tax) •Federal –Highway Safety Improvement Program (HSIP), Innovative Deployment of Enhanced Arterials (IDEA) •Private –Residential and Commercial Developments fronting Third Street Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 6 Tonight’s Objective •Staff asking for City Council input on the Feasibility Study Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 7 Third Street Project Limits: Lindaro Street to Miracle Mile Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 8 Project Timeline Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 9 Technical & Community Working Groups Who was invited? Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 10 Public Outreach Community Meeting #1: Comment Boards Community Meeting #2: Presentation & Workshop Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 11 Previous Community Prioritization 1.Street Trees 2.Widened Sidewalk 3.Curb Extension 4.Street Lights 5.Gateway/Civic Identity 6.Signalized Intersection 7.Vegetative Buffer 8.Sidewalk Paving 9.Painted Crosswalk 10.Wayfinding + Signage 11.Sidewalk Seating 12.On Street Parking Bicycle Access +Safety Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 12 What we heard Pedestrian and bike safety and access Vehicular congestion (at Highway 101) and speed Need for tree canopy and level of comfort Enhance accessibility and sidewalks Provide bicycle access from Miracle Mile to Miramar Simplified bike and pedestrian crossing at 4th Street intersection Maintain parking in residential zones Improve safety at Shaver Street intersection Safe access to schools Improve wayfinding Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 13 Conceptual Design Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 14 Available Budget Baseline Improvements$5 M $12.5M -Additional cost for 12’ Multiuse Path (Miramar to Miracle Mile) -4th Street Intersection at Miracle Mile -Crown replacement Total budgetFuture-Pavement repair, resurfacing, and striping -Accessibility enhancements -Upgrade signal infrastructure and conduits -Street trees -8 to 10 foot widened sidewalk with Miramar to East Avenue -Bike facility eastbound between East Avenue and Miracle Mile -Improvements at key intersections -Safety lighting Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 15 Corridor wide Improvements Conduits for Future Bulb-outs Traffic Signal Upgrades High Visibility Crosswalks Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 16 Corridor wide Improvements Key School Routes/Sidewalks Pavement Rehabilitation Street Trees ADA / Curb Ramps Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 17 Example Corridor wide Improvements: Proposed: A St & B St Improvements: Bulbouts Traffic Signal Upgrades High visibility crosswalks Sidewalk improvements Street Lights Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 18 Proposed: Hayes St to Shaver St Overall Improvements: Bulbouts Sidewalk widening Uniform lane widths Parking buffer At Shaver: Traffic Signal Upgrades High visibility crosswalks Street Lights Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 19 Proposed: Hayes St to Shaver St 12’ lane Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 20 Proposed: Miramar Ave to East St Overall Improvements: 8-10 ft widen sidewalk on south side (incl. obstructions) Bulbouts at G Street Sidewalk between G Street and Ida St. Uniform lane widths Parking buffer Traffic Signal Upgrades and safety lighting High visibility crosswalks Sharrows on Miramar Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 21 G Street Cross Section Proposed Improvements: 8-10 foot path with utility obstructions Future Improvement: 12 foot wide path with underground utilities and retaining wall Existing Proposed Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 22 Option A: East St to Miracle Mile Remove On-street Parking Overall Improvements: Remove 9 on-street parking stalls Provide Class II bike lane with buffer Provide pedestrian refuge by removing left turn lane into Jack in the Box Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 23 Option B: 4th St to East St Remove Center Median Overall Improvements: Shift lanes and narrow median, includes removal of both left turn into Jack in the Box and onto West St Maintains 7 of 9 existing on-street parking stalls Provide Class II bike lane with buffer Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 24 Project Goals and Objectives •Improve safety for all users •Repair Pavement and drainage •Improve pedestrian crossings and repair sidewalks •Signal upgrades •Improve traffic flow for cars, transit, and emergency response •Street Trees •Improve Multi-modal access (including Safe Routes to School) •Develop an economically viable project Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 25 4th Street Intersection-Existing Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 26 4th Street Intersection-Proposed Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 27 Next Steps •Incorporate Council feedback •Summer 2019: Issue Request for Proposals (RFP) for Environmental work and design –18 months to 2 years •Spring/Summer 2021: Issue RFP for Construction Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 28 Thank you Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 29 Questions and Comments Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 30 Closing Slide Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 31 Third Street Original Project Limits Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 32 Third Street Proposed Project Limits Department of Public Works Third Street Rehabilitation Feasibility Study June 3, 2019 www.cityofsanrafael.org/DPW Slide 33 Project Cost Breakdown