HomeMy WebLinkAboutPW Third Street Rehabilitation____________________________________________________________________________________
FOR CITY CLERK ONLY
Council Meeting: 06/03/2019
Disposition: Accepted Report
Agenda Item No: 6.b
Meeting Date: June 3, 2019
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works
Prepared by: Bill Guerin,
Director of Public Works
City Manager Approval: ________
File No.: 16.01.283
TOPIC: THIRD STREET REHABILITATION
SUBJECT: ACCEPT INFORMATIONAL REPORT REGARDING THE THIRD STREET
REHABILITATION FEASIBILITY STUDY
RECOMMENDATION: Accept the informational report.
BACKGROUND: Third Street is a major one-way westbound arterial between US 101 and West
Marin carrying approximately 30,000 vehicles per day. The study corridor is 1.3 miles in length
from Miracle Mile to Grand Avenue. On this corridor, there are 14 traffic signals, a portion of
Safe Routes to School for Davidson Middle and Laurel Dell Elementary School students, and a
variety of land uses, from downtown businesses to commercial to residential.
In 2004, the Transportation Authority of Marin (TAM) established a Measure A Expenditure
Plan, a voter-approved sales tax that provides funds for major road and infrastructure projects in
Marin County. The associated projects were prioritized based on the following: roadway
condition, traffic volumes, transit frequency, and existing bicycle and pedestrian access. In San
Rafael, the West End Revitalization Project, for example, was completed in 2009.
In a later round of project funding in 2016, San Rafael received $11 million from Measure A and
an additional $1.5 million from the State Local Partnership Program for the Third Street
Feasibility Study. After a competitive bidding process, BKF Engineers was awarded the contract
on April 17, 2017 to complete the feasibility study. The feasibility study is now completed
(Attachment 1). The appendices can be found online at https://www.cityofsanrafael.org/third-st-
rehabilitation-project/.
ANALYSIS: The consulting team held a series of outreach events, including two Community
meetings and two Technical Advisory Meetings in 2017 and 2018, which comprised
representatives from the following community groups: Bicycle and Pedestrian Advisory
Committee, Marin Transit, Safe Routes to School, and San Rafael Fire and Police Departments.
The main recommendations that came from these stakeholder meetings were: alleviate
congestion near U.S. 101, slow vehicular speeding towards the West End, improve sidewalk
and crossing facilities for pedestrians, and find a solution for the sliding hillside between East
Street and Miramar Avenue as it is an important section of Safe Routes to School.
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
With a finite amount of money and certain funding requirements, including repaving the roadway
and bringing all the curb ramps into compliance with the Americans with Disabilities Act (ADA),
the consulting team came up with a plan to meet the grant requirements, as well as include
many of the stakeholder requests. The proposed project includes: resurfacing the roadway,
repairing uneven sidewalks, reconstructing curb ramps, updating traffic signal infrastructure,
adding bulb-outs for improved pedestrian visibility, and shortened crossing distances at key
locations, narrowing travel lanes, adding trees, and reconfiguring the roadway between East
Street and Miramar Avenue to allow room for an eight to ten-foot-wide path on the south side of
Third Street. For the section between West Street and East Street, the consulting team came up
with two alternatives to include a bicycle facility: maintain on-street parking and narrow the
median and shift the lanes, or remove on-street parking while maintaining the median and travel
lanes.
Some of the desired project elements fall above the funding threshold, including bioswales,
bulb-outs at every intersection, a retaining wall for the hillside between East Street and Miramar
Avenue, reconfiguring the intersection of Fourth Street-Miracle Mile-Marquard Avenue. Possible
funding sources for these additional features are the Traffic Mitigation Fund or competitive
grants.
FISCAL IMPACT: This project with the proposed improvements in the feasibility study is funded
by Measure A. Additional features would have to be paid for using Traffic Mitigation Funds or
competitive grant funds.
OPTIONS:
The City Council has the following options to consider relating to this matter:
1. Accept the Informational report.
2. Do not accept the informational report.
RECOMMENDED ACTION:
1. Accept the informational report.
ATTACHMENT:
1. Third Street Rehabilitation Study
2. Third Street Rehabilitation Study Attachments
THIRD STREET REHABILITATION PROJECT
Fourth Street to Grand Avenue
Project Study Report
May 2019
CITY OF SAN RAFAEL
DEPARTMENT OF PUBLIC WORKS
The following participants developed this project study report:
City of San Rafael Public Works
BKF Engineers
Wallace Roberts and Todd
Parisi Transportation Consulting
Precision Concrete Cutting
TABLE OF CONTENTS
I. EXECUTIVE SUMMARY.....................................................................................................6
Figure 1: Project Timeline 7
Figure 2: Project Cost Breakdown 8
II. PROJECT BACKGROUND .................................................................................................9
Figure 3: Project Area 10
III. PUBLIC OUTREACH........................................................................................................11
IV. PROPOSED PROJECT .....................................................................................................15
IV.A. Corridor Wide Improvements..........................................................................................15
IV.B. Commercial Downtown Zone..........................................................................................16
Figure 4: Lindaro Street Existing Condition 17
Figure 5: Lindaro Street Proposed Project 17
Figure 6: Brooks Street Existing Condition 18
Figure 7: Brooks Street Proposed Project 18
Figure 8: A Street Existing Condition 19
Figure 9: A Street Proposed Project 19
Figure 10: B Street Existing Condition 20
Figure 11: B Street Proposed Project 20
Figure 12: E Street Existing Condition 21
Figure 13: E Street Proposed Project 21
IV.C. Residential Zone.............................................................................................................22
Figure 14: Shaver Street to Miramar Avenue Existing Condition 22
Figure 15: Shaver Street to Miramar Avenue Proposed Project 22
Figure 16: Miramar Avenue to G Street Existing Condition 23
Figure 17: Miramar Avenue to East Street Proposed Project 24
Figure 18: G Street Existing Rendering 25
Figure 19: G Street Proposed Rendering 25
Figure 20: East Street to Miracle Mile/ West End Avenue Existing Condition 26
Figure 21: East Street to Miracle Mile/ West End Avenue Proposed Project- Option A27
Figure 22: East Street to Miracle Mile/ West End Avenue Proposed Project- Option B27
V. FUNDING .........................................................................................................................28
APPENDICES
Appendix A- Plans and Sections
Appendix A-1 Existing Conditions Plans
Appendix A-2 Proposed Plan
Appendix A-3 Cross Sections
Appendix B- Existing Conditions
Appendix C- Traffic Analysis
Appendix D- Future Projects Considered
Appendix E- Roadway Crown Analysis
Appendix F- Preferred Tree Species List
Appendix G- Sidewalk Evaluation by Precision Concrete
THIRD STREET REHABILITATION PAGE 4 OF 26 MAY 2019
I. EXECUTIVE SUMMARY
The City of San Rafael has secured approximately $12 million in Measure A and State Local Partnership Program
(SLPP) funds from the Transportation Authority of Marin (TAM) to rehabilitate Third Street between Fourth Street
and Grand Avenue. The City Council authorized the allocation of $300,000 of said funds to study the feasibility of
the Third Street project. The scope of the feasibility study was to consider corridor enhancements with an emphasis
on improving infrastructure, public safety, and traffic conditions.
A key component in development of the study was extensive communication with the public and key stakeholders.
Public Works staff and a team of consultants completed a series of public meetings throughout the development of
this Project Study Report (PSR). Meetings were initially held with working groups comprised of business owners,
utility companies, transit agencies, Bicycle and Pedestrian Advisory Committee (BPAC) representatives and other
community leaders. An open public meeting was also held to receive input on project goals from members of the
community.
After an initial round of public outreach and consultation with technical and community working groups, the design
team developed a list of improvements to enhance the corridor’s many uses. The list included typical improvements
(nicknamed the “tool box” during the public outreach) such as curb bulb-outs, street trees and signal upgrades as
well as some site specific improvements such as the improved crossing and path widening from East Street to
Miramar Avenue. The combination of typical and site specific improvement strategies was used to create a
preliminary project plan. The preliminary plan was utilized to develop an order-of-magnitude cost estimate.
Given the initial feedback from the public outreach and cost estimating process, it was determined that to achieve
all of the goals and wishes for the project would exceed the currently available funding. See Figure 2 for cost
breakdown of entire project with alternatives. The City currently has several active projects around the Downtown
SMART station and Bettini Transit Center. In order to avoid overlap with other projects already funded or under
construction, the team and staff determined that the funding would be primarily allocated to the areas west of
Tamalpais Avenue. Much of the corridor study area between Grand Avenue and Tamalpais Avenue has separately
funded improvement projects already being studied, designed or constructed.
Through several additional meetings with City staff, workgroups and the community, the team prioritized the
corridors needs, presented alternatives to the initial concept plan and prioritized project elements. Through the
outreach process, alternatives were studied and refined to present a “preferred alternative” that met the primary
objectives of the City and would be anticipated to fit within the available funding.
The final preferred alternative was presented to the community in an open public meeting. While some members
of the community expressed the desire to be able to include more of the project elements which were outside the
available funding, the reception of the project by the public was positive. No significant negative comment or
feedback was provided at the meeting.
THIRD STREET REHABILITATION PAGE 5 OF 26 MAY 2019
Figure 1: Project Timeline
THIRD STREET REHABILITATION PAGE 6 OF 26 MAY 2019
Figure 2: Project Cost Breakdown
THIRD STREET REHABILITATION PAGE 7 OF 26 MAY 2019
II. PROJECT BACKGROUND
The Transportation Authority of Marin (TAM) has established a Measure A Expenditure Plan which provides funds
for major roads and related infrastructure projects within Marin County. The Measure A Strategic Plan allocated
approximately $15 million for projects in the County’s five central planning areas. The Central Planning Area was
also programmed with approximately $1.5 million in State Local Partnership Program (SLPP) funds. The first priority
project in the Central Marin planning area, the Fourth Street West End project, was completed in 2010 and utilized
$4 million of Measure A funds, leaving $11 million from Measure A and $1.5 million from SLPP funds for remaining
projects.
In September 2016, the City Council authorized the allocation of $300,000 in Measure A funding to study the Third
Street project area and develop a preliminary plan for roadway rehabilitation. The San Rafael Department of Public
Works hired a consultant team to work with staff and the community to study feasibility options for the Third Street
Corridor between Fourth Street and Grand Avenue as shown in Figure 3. The options investigated to improve the
corridor included pavement resurfacing, traffic improvements, street lighting, retaining walls for road widening and
improved capacity, examination of bicycle and pedestrian improvements, and landscaping. Traffic improvements
were also considered, including traffic signal modifications, signal/coordination timing improvements, signage and
striping, and a potential fiber optic communication trunk line. The project segment from Tamalpais Avenue to Grand
Avenue currently has several other projects that are either in design, under construction, recently constructed or
identified as separate projects in the City’s Capital Improvement Program. These projects include the SMART
extension to Larkspur, the Transit Center relocation, and funded improvements at Hetherton Street, therefore due
to projects occurring on the eastern end of the corridor, the project area was modified to be from Fourth Street to
Tamalpais Avenue.
An outreach process integrating community members, local agencies, and utility companies occurred from Winter
to Spring of 2018. It included two community meeting workshops, three focus group meetings with Community and
Technical Working Groups. The feedback from the public outreach process was compiled and presented to Staff.
The consultant team worked with Staff to develop a preliminary plan of the proposed project which balanced
infrastructure requirements, requested improvements from the community and available funding.
THIRD STREET REHABILITATION PAGE 8 OF 26 MAY 2019
Figure 3: Project Area
THIRD STREET REHABILITATION PAGE 9 OF 26 MAY 2019
III. PUBLIC OUTREACH
City of San Rafael staff and the consultant team hosted various community outreach efforts to spread awareness of
this project to residents and business owners. This includes two community meetings on November 13, 2017 and
March 15, 2018. The team worked with the City of San Rafael, the Technical Working Group, and the Community
Working Group to create a comprehensive list of issues and potential solutions along the corridor. In addition, there
was a project specific webpage on the City of San Rafael’s website with current project information and a project
specific email address for the community to provide comments.
The Technical and Community Working Groups met during the first stages of the outreach process to present the
scope of the feasibility study and to receive initial concerns that the groups would like analyzed. San Rafael Public
Works, Police, Fire, Transit, utility companies, TAM, Parking Services, and the Community Development department
were invited to attend the Technical Working Group Meetings. The initial meeting was held on July 26, 2017. The
Community Working group invitees included BPAC, ADA Advisory Committee, Design Review Board, Downtown
Business Improvements District, Safe Rotes to Schools, Chamber of Commerce, Kaiser, BioMarin, Eden Housing,
Whistlestop, and Caltrans Bicycle Advisory Committee. The initial meeting for the Community group to discuss the
upcoming community meetings approach was held on October 24, 2017. After meeting with the Working Groups,
a public community meeting was held on November 13, 2017, to allow the public to offer their input on the project.
The City and Design Team put pencil to paper to incorporate the input they received into a proposed project. Once
a preliminary plan was created, the Team met with the Technical and Community Working Groups at a joint meeting
held on February 27, 2018. After this meeting, another public community meeting was held on March 15, 2018.
Throughout the outreach process, some of the critical areas of concern were highlighted as items that needed to be
further considered. Some of the key issues we heard are as follows:
Pedestrian and bicycle safety is a top priority
o Critical areas of concern:
Crossing the street at the SMART train station
Long crossing distance between A Street and Lindaro Street
Brooks Street (Future Senior Home near intersection)
Safe Routes to School
Provide visible location for children to cross and be seen
Enhance route from G Street to Miramar
Overall funding strategies
Varying vehicle speeds along corridor
o Congestion near Highway 101
o Speeding west of Lincoln Avenue
Street markings
o Crosswalk striping (yellow in school zones)
o Parking indication
o Alert striping (Crosswalk Ahead, School Zone, etc)
Better signage along corridor
o Wayfinding + identity signage
Traffic Signals
o Outdated signal infrastructure
THIRD STREET REHABILITATION PAGE 10 OF 26 MAY 2019
o Changes to signal timing could help improve overall traffic flow along the corridor, might help
reduce sudden speeding
Lack of tree canopy
o Harsh environment walking along Third Street
Fourth Street
o Difficulty navigating through several crossings along bicycle route from Fourth Street to West
Avenue
Bike path between West Street to First Street on south side
o Fairfax to San Rafael Cross Marin Bikeway Feasibility Study
Through several additional meetings with City staff, workgroups and the community, the team prioritized the
corridors needs, presented alternatives to the initial concept plan and prioritized project elements. Through the
outreach process, the project was refined to present a preferred alternative that met the primary objectives of the
City and would be anticipated to fit within the available funding. The elements of the project’s preferred alternative
presentation included:
Pavement repair
Americans with Disabilities Act (ADA) Accessibility improvements
Re-striping and space allocation to control traffic flow and speed fluctuations
Traffic signal improvements such as larger signal heads, back plates, pedestrian countdown heads,
pedestrian push buttons, cabinets and video detection
Improved crossings along routes to schools
Curb “bulb-outs” to improve pedestrian visibility and regulate vehicular speeds at select intersections
Signalization/crossing improvements at Brooks Street
Improve sidewalk between Miramar Avenue and East Street
Landscape enhancements
Conduits for future adaptive signals and future street lighting
Safety Lighting
Project Design and Construction Management
Other key projects for the corridor which were considered, but were anticipated to be outside of available funds.
Throughout the public outreach process, all of the project’s elements were presented and at the first community
meeting these elements were ranked through a dot exercise shown in Image 1. Due to budget constraints not all
project elements along the corridor would be able to be funded, so after consultation with City staff and input from
the community, some elements were removed from the preferred project. These project elements would not be
precluded with the preferred project and could be further studied as separate projects as funding became available.
These include:
Road repair and modifications between Grand Avenue and Hetherton Street
Additional 2-foot to 4-foot width for multi-use path segment from West to First Street
Bio-retention facilities
Redesign of Fourth Street/Second Street intersection
THIRD STREET REHABILITATION PAGE 11 OF 26 MAY 2019
The final preferred alternative was presented to the community in an open public meeting on March 15, 2018. While
some members of the community expressed the desire to be able to include more of the project elements that were
identified to be outside the available funding, the reception of the project by the public was positive. No significant
negative comment or feedback was provided at the meeting.
Image 1: Community Meeting #1- Comment board and ranking project elements
Image 2: Community Meeting #1- Comment board
THIRD STREET REHABILITATION PAGE 12 OF 26 MAY 2019
Image 3: Community Meeting #2- Presentation
Image 4: Community Meeting #2- Workshop
THIRD STREET REHABILITATION PAGE 13 OF 26 MAY 2019
IV. PROPOSED PROJECT
Based on community input, previous studies, analysis of existing conditions, and available funding, the consultant
team has compiled the following proposed improvements along the remainder of the corridor. Refer to Appendix
A for plans and cross sections.
IV.A. Corridor Wide Improvements
Proposed improvements to be implemented throughout the Third Street project from Tamalpais Avenue to east of
Fourth Street-Second Street intersection include pavement rehabilitation, striping uniform lanes and high visibility
crosswalks in key locations, increased tree canopy, accessibility improvements to curb ramps and sidewalks, and
traffic signal upgrades. These Corridor Wide improvements are part of the Base Project cost shown in Figure 2.
The proposed project would explore reducing the cross section in the segments with the largest crown. During the
construction document design phase the team would explore the depths of existing utilities to determine any
conflicts that could occur from lowering the crown of the corridor.
Pavement. The project would fix damaged pavement, mill the surface, and place an asphalt overlay on the roadway
between Tamalpais Avenue and west of Fourth Street. The road would be striped to include high visibility crosswalks
in key locations, uniform lane line striping, and a parking buffer on the north side of Third Street between E Street
and G Street. In conjunction with the asphalt repair, the project would update curb ramps at intersections to comply
with ADA requirements and incorporate bulb-outs at key intersections to improve pedestrian safety and visibility.
Sidewalk. As part of the ADA Title II regulation, when performing pavement rehabilitation, all curb ramps adjacent
to the new pavement need to meet the ADA requirements. In addition, based on the Precision Concrete Cutting
Report in Appendix D, the team has included a recommendation to shave uneven sidewalks in the preferred project
limits.
Traffic Signals. There are 10 signalized intersections along Third Street from Lincoln Avenue to Fourth Street. The
traffic signals run with coordinated timing plans throughout the day, with three timing plans operating during the
weekdays and two plans on the weekends. The signals operate with various Econolite brand controllers.
Several of the signalized intersections on Third Street are equipped with 8-inch traffic signal heads without visors. It
is recommended that all of these be upgraded to provide 12-inch heads with visors (Lincoln Avenue, Lindaro Street,
B Street, C Street, D Street, Shaver Street, and G Street). In addition, all of the mast arm poles along the corridor
should be inspected to determine if they have the capability to accommodate more than one signal head assembly
to increase the visibility of signal heads.
All signal heads should be converted to more energy efficient LEDs, and pedestrian countdown heads should be used
for all signalized pedestrian crossings. All pedestrian push buttons and adding pedestrian countdown heads will be
considered for each intersection to meet current ADA requirements. All the signalized intersections will include the
addition of video detection.
Provision of a fiber optic traffic signal interconnect should also be considered along the Third Street corridor.
Therefore, the project would install conduits and pull boxes for future adaptive signals and signal interconnects.
With the anticipated amount of upgrades to the signalized intersection, it would be prudent to install new signal
controllers and cabinets. The project cost estimate includes the anticipated cost of cabinet upgrades in the budget
for signalized intersections. At this time, the Department of Public Works anticipates installing the new controllers
as a separate project prior to the commencement of construction with this Third Street project. The current project
budget does not include costs associated with signal controller upgrades.
THIRD STREET REHABILITATION PAGE 14 OF 26 MAY 2019
Safety Lighting. In an effort to increase pedestrian safety along the corridor, the project will include pedestrian
lighting at all of the signalized intersections. The lighting will meet current standards at a minimum of 1-foot candle.
Trees. In an effort to make Third Street more enjoyable for its residents and visitors, the proposed project includes
additional trees to line the street. Trees do much more than add green vegetation to the street; they help maintain
certain levels of comfort both for separation from vehicles and providing shade that are needed to enjoy a stroll
down the sidewalk. Trees also help reduce the heat island effect, because the tree crown tends to cover a significant
portion of surrounding paving such as the sidewalk and adjacent roadway. Not only are trees beneficial to people
walking down the sidewalk, but trees help aid in visual cueing for drivers. Studies show that motorists tend to drive
slower when there is a significant tree canopy present. This tunnel effect creates the illusion of a more narrow street.
The project proposes to fill in the existing scattered trees for a more consistent pattern. An overall goal dealing with
the sidewalk conditions would be to allow enough space for pedestrians and planting. The planting could act as a
buffer between vehicles along Third Street and pedestrians walking down the sidewalk.
In addition the design team should evaluate the existing tree species along the corridor to assess whether to
recommend replacement for either invasive species or existing species that commonly push up sidewalk. See
Appendix C for the City Preferred tree species list.
IV.B. Commercial Downtown Zone
For the proposed project limits the Commercial Downtown zone is from Tamalpais Avenue to E Street. Community
comments and issues are traffic congestion to speeding, long distance between crosswalks, inconsistent tree
canopies, pedestrian visibility at intersections, on-street versus off-street parking and visibility issues on a vertical
curve. Below is a more detailed description of the proposed project per intersection from east to west.
Image 5: Symbols and Legend for Proposed Project Figures
Lindaro Street Intersection
As shown in Figure 4, the existing intersection is a four-legged intersection with the north leg serving as a driveway
to the Walgreens shopping center.
The proposed project, as shown in Figure 5, will extend out the curb on southeast corner to widen the sidewalk along
the left turn pocket. On the north side the City and design team will work with the shopping center to reconfigure
the driveway to increase visibility and pedestrian safety along the sidewalk.
THIRD STREET REHABILITATION PAGE 15 OF 26 MAY 2019
Figure 4: Lindaro Street Existing Condition
Figure 5: Lindaro Street Proposed Project
A Street Intersection
THIRD STREET REHABILITATION PAGE 16 OF 26 MAY 2019
Brooks Street intersection
The proposed development at the former PG&E site on Third Street between Lindaro and Brooks Street includes a
senior housing element. The community raised concerns about the long distance between signalized crossings for
seniors. Currently the closest crossings are at A Street, approximately 200 feet to the west and Lindaro Street,
approximately 450 feet to the east. The existing Brooks intersection is shown in Figure 6.
The applicant for future development of the parcel west of Brooks Street and south of Third Street is analyzing traffic
and pedestrian movements along this stretch of Third Street. Mitigations identified in conjunction with this private
development are anticipated to be placed as project conditions of approval and will be the responsibility of the
private applicant. The applicant is currently conducting a traffic impact analysis and recommended mitigations.
Below is a proposed condition consistent with the corridor wide improvements. The concept is shown hereon for
reference, but will ultimately be determined by the final traffic analysis and mitigations appropriate for the private
project. The anticipated costs associated with the improvements shown below are not included in the project
budget.
The proposed project shown in Figure 7 to install a new traffic signal or pedestrian beacon with a crosswalk on the
east side at the Brooks Street intersection to improve pedestrian circulation and safety. If a new signal is installed, it
would be timed with the existing signals on Third Street to minimize traffic delays for this additional crossing.
Figure 6: Brooks Street Existing Condition
Figure 7: Brooks Street Proposed Project
A Street Intersection
THIRD STREET REHABILITATION PAGE 17 OF 26 MAY 2019
A Street intersection
According to data collected in October 2017 for a re-timing project in Central San Rafael, this intersection was
identified as one of the higher volume pedestrian crossing locations with Kaiser Permanente at the southeast corner.
The existing intersection is shown in Figure 8.
The proposed project shown in Figure 9 will add bulb-outs at the corners, to increase pedestrian visibility and reduce
the crossing distance. Along the east and west crossing of Third Street, high visibility ladder crosswalk striping will be
installed.
Figure 8: A Street Existing Condition
See Figure 5
Figure 9: A Street Proposed Project
B Street Intersection
THIRD STREET REHABILITATION PAGE 18 OF 26 MAY 2019
B Street Intersection
The existing B Street intersection is shown in Figure 10.
The project shown in Figure 11 proposes to bulb-out the southern corners to provide enhanced pedestrian visibility,
reduce crossing distance, and stabilize vehicular speeds.
Figure 10: B Street Existing Condition
Figure 11: B Street Proposed Project
E Street Intersection
THIRD STREET REHABILITATION PAGE 19 OF 26 MAY 2019
E Street Intersection
This existing intersection as shown in Figure 12 is located on the top of a hill at a sweeping turn. Clear sight lines and
pedestrian safety are a big concern.
In Figure 13, the proposed improvements show the west side of the intersection with bulb-outs to reduce the
crossing distance for pedestrians and improve visibility between vehicles and pedestrians. In addition, at the bulb-
outs on the west side of the intersection will install larger trees west of the crosswalk to attempt to block the setting
sun in the evening. Also, the bulb-outs on the south side are proposed to have a tighter radius to slow cars making a
left onto E Street.
Figure 12: E Street Existing Condition
Figure 13: E Street Proposed Project
North Side Shaver Street to Miramar Avenue
THIRD STREET REHABILITATION PAGE 20 OF 26 MAY 2019
IV.C. Residential Zone
The Residential zone is from E Street to Fourth Street. Community comments and issues include speeding, pedestrian
crossings, wide travel lanes, visibility on the vertical curve, and narrow sidewalk on south side along hill long. Below
is a more detailed description of the proposed project from east to west.
North Side Shaver Street to Miramar Avenue.
Figure 14 shows the existing roadway configuration in this section of road. Third Street west of E Street slopes down
a hill on a curve as vehicles move towards Hayes Street. The existing travel lanes are very wide and the sidewalks are
narrow. Residents along this zone have expressed concerns over the vehicle speeds and about the challenges of
exiting their driveways.
In Figure 15, the proposed improvements include narrowing the travel lanes to 11-12 feet wide, adding trees,
extending the curb and sidewalk to narrow the road, providing a buffered parking area, widening the sidewalk, and
bulbing out the corners at the intersections. On the south side of the street between Miramar Avenue and East
Avenue, the project proposes to widen the sidewalk. A rendering cross section of the road at G Street as shown in
Figure 19 shows the widened sidewalk on the south side.
Figure 14: Shaver Street to Miramar Avenue Existing Condition
Figure 15: Shaver Street to Miramar Avenue Proposed Project
South Side Miramar Avenue to East Street
THIRD STREET REHABILITATION PAGE 21 OF 26 MAY 2019
South Side Miramar Avenue to East Street
The existing sidewalk along the south side of Third Street between Miramar Avenue and East Street is narrow and
the existing hillside is eroding onto the pedestrian walkway. Miramar Avenue across to the north side of G Street has
been identified as a Safe Route to School. The existing layout of Third Street between Miramar Avenue and East
Street is shown in Figure 16.
The proposed project shown in Figure 17 will re-allocate space and striping to allow for two twelve foot lanes and
widen the sidewalk on the south side to a total width of 8-10 feet including obstructions. This work will include
relocation or undergrounding of the joint utility poles. Future projects along the south side include extending the
widened sidewalk to West End Avenue and widening the trail to 12 feet wide by adding a retaining wall and removing
on street parking.
Figure 16: Miramar Avenue to East Street Existing Condition
South Side Miramar Avenue to East Street
THIRD STREET REHABILITATION PAGE 22 OF 26 MAY 2019
Figure 17: Miramar Avenue to East Street Proposed Project
THIRD STREET REHABILITATION PAGE 23 OF 26 MAY 2019
G Street Intersection
This project proposes to bulb-out the sidewalk at the corners on the north side of the intersection to provide more
refuge for pedestrians waiting to cross and increased visibility for vehicles. Figure 18 shows existing conditions and
Figure 19 illustrates the proposed conditions.
Figure 18: G Street Existing Rendering
Figure 19: G Street Proposed Rendering
THIRD STREET REHABILITATION PAGE 24 OF 26 MAY 2019
South Side East Street to Miracle Mile
The existing sidewalk along the south side of Third Street between East Street and the West End Avenue/ Miracle
Mile is narrow due to existing driveways, landscape and overhead utility poles. At East Street, an existing Rectangular
Rapid Flashing Beacon (RRFB) crosswalk connects to the north at Jack in the Box. To the west of the Miracle Mile
intersection, West End Avenue has bicycle sharrows leading bicycles to the intersection. The existing layout of Third
Street between East Street and the West End Avenue is shown in Figure 20.
There are two proposed options shown in Figure 21 and Figure 22. Option A shown in Figure 21 proposes to remove
nine existing on-street parking spaces between West End Avenue and East Street and provide a buffered Class II bike
facility that will connect to the widened sidewalk to Miramar Avenue. At East Street, Option A proposes to remove
the left turn pocket into the Jack in the Box and create a pedestrian refuge in the middle of the crossing. This directs
left turning and U-turn traffic to the G Street intersection. The RRFB would be replaced to allow pedestrians to also
activate the crosswalk at the new the median refuge. Option B shown in Figure 22, proposes to remove or create a
narrow center median between West Street and East Street. This option shifts the travel lanes to the north creating
space to provide a buffered bike lane, while maintaining seven of the nine existing parking stalls. At West Street and
East Street, the left turn pockets would be removed as part of this lane shift.
Figure 20: East Street to Miracle Mile/ West End Avenue Existing Condition
THIRD STREET REHABILITATION PAGE 25 OF 26 MAY 2019
Figure 21: East Street to Miracle Mile/ West End Avenue Proposed Project- Option A
Figure 22: East Street to Miracle Mile/ West End Avenue Proposed Project- Option B
THIRD STREET REHABILITATION PAGE 26 OF 26 MAY 2019
V. FUNDING
Funding originates from Measure A, administered by the Transportation Authority of Marin. From this grant the
project has $12.5 Million at its disposal, $9 million of which will go to street resurfacing, ADA curb ramps, design,
and traffic control. Using experience from similar projects, the consultant team developed a streetscape plan that
would fit within the allowable budget and identified as the proposed project above. Measure A requires that the
money go to repaving the corridor, so the majority of the cost of improvements comes from repaving the road.
The cost estimate takes into account final design, management, testing, escalation and construction for the items
shown on the conceptual streetscape drawings. At this time, it is anticipated that all the projects listed as the
proposed project will fit within the available funding, however this will need to be determined by the design team
and market conditions at the time of planned construction. Non-priority items were removed from the overall
project. The alternatives considered are listed in Appendix D. It is recommended that the design team and staff
study the alternatives and consider include them as add alternatives in the final project design documents. See Figure
2 for funding breakdown.