HomeMy WebLinkAboutDS Managed Technology Services Provider; First AmendmentFIRST AMENDMENT TO AGREEMENT FOR
MANAGED TECHNOLOGY SERVICES PROVIDER SELECTION
THIS FIRST AMENDMENT is made and entered into this 13 day of September, 2019, by and
between the CITY OF SAN RAFAEL (hereinafter "CITY"), and Pivotal LLC (hereinafter "CONTRACTOR").
WHEREAS, the CITY and the CONTRACTOR entered into an original Agreement for assistance
to manage the selection of a Managed Service Provider (MSP) for its technology support operations dated
March 25, 2019 (the "Agreement"), with the initial term beginning on March 25, 2019, and ending on
September 24, 2019; and
WHEREAS, the parties wish to extend the term of the Agreement for an additional thirty-seven (37)
days, through October 31, 2019 so that CONTRACTOR can continue to provide the services as described
in Exhibit 1 of the Agreement;
NOW, THEREFORE, the parties hereby agree to amend the Agreement as follows:
1. Section 4 of the Agreement, entitled "COMPENSATION" is hereby amended to include additional
compensation payable to CONTRACTOR in the amount of $4,000 for an additional thirty-seven (37)
days of services described in Exhibit "A" to the Agreement, for a total compensation amount under the
Agreement not to exceed $22,000.
2. Section 5 of the Agreement, entitled "TERM OF AGREEMENT" is hereby amended to extend the term of
the Agreement to end on October 31, 2019.
3. Except as amended herein, all terms of the Agreement as executed on March 25, 2019 shall remain in full
effect.
IN WITNESS WHEREOF, the parties have executed this First Amendment as of the day, month
and year first above written.
CITY OF SAN RAFAEL
JIMCHU Z, City Manag
ATTEST:
LINDSAY LARA, City Clerk
1A-.-�-St-7
CONTRACTOR
AD ENNE DALE, Managing Member
APPROVED AS TO FORM:
RFS
ROBERT F. EPSTEIN, City ttomet
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Digital Service and Open Government
Project Manager: Gus Bush Extension: (415) 485-3061
Contractor Name: Pivotal LLC
Contractor's Contact: Adrienne Dale Contact's Email: Adrienne.dale@pivotal-Ilc.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor
3/6/2019
❑x GB
b. Email contract (in Word) and attachments to City
8/23/2019
❑x GB
Attorney c/o Laraine.Gittens@cityofsanrafael.org
2
City Attorney
a. Review, revise, and comment on draft agreement
8/26/2019
❑x
and return to Project Manager
8/26/2019
❑x
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
3
Department Director
Approval of final agreement form to send to
8/29/2019
❑x GB for
contractor
RW
4
Project Manager
Forward three (3) originals of final agreement to
8/29/2019
0 GB
contractor for their signature
5
Project Manager
When necessary, contractor -signed agreement
® N/A
agendized for City Council approval *
*City Council approval required for Professional Services
©GB
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
Click here to
Date of City Council approval
enter a date
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
9/11/2019
GB
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
f
agreement
��/Z Q
(/l
8
City Attorney
Review and approve insurance in PINS, and bonds
n
(for Public Works Contracts)
9
City Manager/ Mayor
Agreement executed by City Council authorized
7
official
10
City Clerk
Attest signatures, retains original agreement and
forwards copies to Project Manager
q ) q