Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutDRB 2013-10-08 #7CITY OF
Meeting Date: October 8, 2013
Case Numbers: ED10-072
Project Planner: Raffi Boloyan (415) 485-3095
Community Development Department — Planning Division
REPORT TO DESIGN REVIEW BOARD
SUBJECT: 31 Gold Hill Grade — Environmental and Design Review Permit for a new 6,468 gross sq. ft.
single family residence in a two level structure, over a basement, on a vacant 1.07 -acre hillside
parcel with a 28% slope; APN: 015-091-04; R1a-H Zone; Stephen Charlip, Applicant; George
Mann and Stephanie Morgan, owners; Dominican/Black Canyon Neighborhood. (Continued
from July 17, 2012 DRB meeting)
Note: A separate memo has been provided with instructions for accessing the site.
BACKGROUND
This is an application for an Environmental and Design Review Permit for the construction of a new
single family hillside residence on a 1.07 -acre upsloping flag lot in the Dominican/Black Canyon
neighborhood. This application was previously reviewed on three occasions by the Design Review
Board (DRB). First, on March 22, 2011 the DRB reviewed and continued the application to a future date
to allow the applicant to address their recommendations and comments. The applicant revised their
project and returned to the DRB on November 8th, 2011. At the conclusion of the November 8th meeting,
the Board found that the project was moving in the right direction, but again continued the project with
additional recommended modifications. There are no written meeting minutes, however, the video
recording of the November meeting can be viewed at www.citvofsanrafael.orq/meetings and clicking on
the video link for the 11/8/11 DRB meeting date.
The applicant then returned to the Board on July 17, 2012, for review of revisions made since the
November 8, 2011 meeting. In summary, the changes proposed to the design at that time were as
follows: 1) two chimneys were eliminated, 2) a small shed roof was added between the Vt and 2 I
floors, and 3) a dormer was reintroduced on the roof of the front elevation. At the conclusion of the July
17th meeting, the Board found that some minor improvements had been made, but that the project
design still did not address the prior comments about reducing mass of structure by stepping back the
upper floor or pushing the entire structure back on the site. There are no written meeting minutes from
this meeting, however, the video recording can be viewed at www.cityofsanrafael.org/meetings and
clicking on the video link for the 07/17/12 DRB meeting date. Staff has summarized the Board's
consensus recommendations and those are included in the Analysis section below.
The applicant has resubmitted plans with very minor modifications made in response to the Board
comments. The Board is asked to review and provide a final recommendation on the project to the
Zoning Administrator or Planning Commission. The Zoning Administrator of Planning Commission will
take appropriate action based on referral recommendations of the Board and analysis of the project's
compliance with City policies and criteria.
PROJECT DESCRIPTION
Project Revisions:
The following revisions have been made to the project since the July 17, 2012 DRB meeting:
0 Revisions to the design of the structure, including
o Adding a standing seam metal roof shed over the wrap-around deck at the main floor level.
This new roof would integrate with the proposed gable roof that was previously added just
over the main entry. The proposed new metal roof would be a "brownstone" color (Sheet A-5
- Front Elevation)
o Adding a standing seam metal shed roof between the main floor and upper floor level along
the rear elevation (Sheet A-6 Rear Elevation)
o Increasing the size of two upper story windows on the rear elevation (Sheet A-6 — Rear
elevation)
o Changing two small windows on side elevation of the main level to one large window. (Sheet
A-5 Right Elevation)
o Raising the grade under the front entry deck by three feet to reduce the perceived height of
the front deck (Sheet A-8 Section A -A)
o Extend a 24" inch drainage pipe from under the driveway to 12 inches past the corner of the
foundation of the existing house at 27 Gold Gill Grade and provide a dissipation bed at the
outfall (Sheet SP -3)
o Addition of six new Pittasporum trees next to the existing bamboo, in the landscape and
scenic easement along the front of the site
Please note, all revisions have been shown on the plans by a cloud and the clouded area of the change
has been highlighted.
Revised Project Description:
With the proposed revisions, the project proposes a new three-level, single-family residence with three
bedrooms, den, kitchen, study, living room, dining room, loft and storage. In addition, the attached
structure would provide a 3 car garage, as follows:
Lower Level: 831 sq. ft.
Main Level: 2,862 sq. ft.
Upper level: 1,763 sq. ft
TOTAL 5,456 sq. ft.
The basement area of the main structure is included in the gross building square footage calculations
given that it is habitable and has a ceiling height in excess of 7 feet. Other covered areas around the
structure such as the covered rear patio and area of the new wrapped veranda and under elevated
decks would total an additional 972 sq. ft. and are also included as gross building square footage (as
defined by the hillside guidelines). The proposed structure would therefore, have a total of 6,428 sq. ft of
gross building floor area.
The main structure would be setback approximately 39 ft. from the front property line, 47 ft. from the
west (side) property line, 23 ft. from the east (side) property line, and 188 ft. from the rear. An elevated
porch is proposed along the eastern two third of the front elevation and wraps around the side (east)
elevation. A majority of the proposed understory area of the porch would be enclosed by hog wire
fencing, planted with vines for screening.
A new 12 -ft to 20 ft wide concrete driveway would be constructed from the street to the main parking
area and garage. The driveway would have a slope of 15.9% at its steepest point. A driveway profile is
provided on Sheet SP -5. Two off-street parking spaces are provided to the side of the driveway,
composed of decomposed granite. Another space is proposed off the street adjacent to the driveway to
replace an existing space.
The finish floor elevation of the lower floor is 112.5 ft. with overall building height of 25.16 ft above
natural grade at the highest point. Retaining walls are proposed around the upper portions of the
driveway and parking area ranging from 2 ft to 6 ft in height. A geotechnical investigation has been
prepared for this property. The project would qualify for an environmental exemption under California
Environmental Quality Act (CEQA), Section 15303a (New Construction of a Single -Family Residence),
provided that it does not impact an environmental resource of hazardous or critical concern designated
on an official map pursuant to the Section 15300.2 (Exceptions). Proposed architecture, landscaping,
grading and tree removal are further described below.
Architecture
The building is a contemporary craftsman design with three -levels facing the downhill elevation. The
building steps up to two levels at the rear with a three -car garage attached to the main structure at an
angle. The garage includes vaulted ceiling. An uncovered porch wraps around the eastern two thirds of
the front elevation and a portion of the side (right) elevation. A standing seam metal roof covers the
entire front wrap around porch, with a gable feature over the main entry and a shed roof over the
remaining. An elevated deck is also proposed at the west side of the building, off the master bedroom
on the upper level. This deck would connect to the backyard area via a staircase. The understory of the
deck would be enclosed with hog wire lattice. The hog wire lattice is also proposed too enclose the
understory around the front deck. The roof form consists of off -setting gable roofs, with the gable ends
on the side (east and west) elevations. A former is proposed on the western part of the front elevation,
would incorporate with the second story windows from the master bedroom on the upper level. Story
poles have been installed on-site and the story pole plan is provided on Sheet SP -6.
The colors and materials consist of painted hardiplank siding and trim, painted wood trim around
windows, doors and railings, brown composite decking, wood pilasters and railings, cultured stone
veneer and asphalt shingle roofing. Most of the building's exterior colors mimic the natural wood and
earth tones, with cream/khaki used for trim and detailing. Flat hardscape includes a brushed finish
concrete driveway and parking area, concrete retaining walls and decomposed granite for guest parking
and entry paths at the front of the site. The colors and materials board will be presented at the hearing.
The building lighting would be wall mounted sconces. Site lighting is also proposed, composed of
landscape walkway lights and stair lights. Landscape up -lights are proposed to illuminate a few of the
larger native trees. Cut sheets of the fixtures are attached (Exhibit 3) and locations of the proposed
lights are shown on the plans (Sheet SP -2).
Landscaping
The landscape plan proposes to generally maintain natural conditions around the rear of the site in the
hillside portions of the site to the north, with ornamental landscaping in pockets around the house and
the parking area. There are numerous large Eucalyptus trees and Oaks and Bay trees on-site, primarily
around the upper rear portion of the site. Nearly all of these existing trees would be would be retained,
however, there are 6 trees that have already been removed, including 3 Eucalyptus at the upper portion
of the site and 3 dead trees (one 18" Eucalyptus, one 12" Pine and one 16" Oak.) around the
development area (See Sheet SP -1.1)
A new cluster of 12, 15 -gallon Redwood trees would be planted at the rear of the site in the hillside
area. In addition, the area around the structure and the lower portion of the site would be heavily
planted with fruit trees and ornamental landscaping. In addition, six new Pittasporum trees are proposed
to be added next to the existing bamboo, in the landscape and scenic easement along the front of the
site. The remainder of the palette proposes palms in these areas, including Canary Island Date Palms.
Two new Arbutus Marina trees are proposed to be planted along the driveway/turnaround area along
the eastern side of the property. Low level wall and path lighting is indicated. The landscape plan is
illustrated on Sheets SP1.1 and SP -2). Images of the proposed species are provided as Exhibit 4.
Grading and Drainage
Site grading consists primarily of cut (655 cubic yards) to prepare the site for placement of house. Some
minor fill (30 cubic yards) would be added in the lower portion of the driveway. Net off -haul of 655 cubic
yards is anticipated (equivalent to 65 truckloads).
Proposed drainage would generally follow the existing drainage patterns on the site. A new concrete v -
ditch and debris collector would be installed part way up the hill to the rear of the house to collect water
from the upper portions of the site. The drainage would then enter a closed underground system (8"
PVC pipe) that would go downhill along the eastern side of the property until it meets the exiting
drainage swale. A 6ft by 6ft dissipation bed at the top and bottom of the closed system with rip rap
would be installed. A closed drainage consisting of a 6" PVC pipe would collect water around the rear
and side of the building and would transverse along the front of the building. A new 24" detention basin
consisting of an underground pipe is proposed to be installed near the driveway to collect water and
provide controlled discharge. This water would be conveyed to the east side of the site and would enter
a 36 sq. ft. dissipation bed and then enter into an 8" PVC storm drain. This run-off would then be
conveyed to the natural drainage swale at the east side of the lower driveway. In addition, an earthen
swale would collect run off at the rear of the structure and convey it to a 6 -inch storm drain pipe that
would wrap around the west and front sides of the structure and would connect to the new 8 -inch pipe
along the eastern end. Two 36 sq ft dissipation beds would be created on both sides of the natural
culvert that bisects the driveway before the run-off is conveyed to the existing culvert system. The
drainage plan the proposes to extend the 24" pipe past the driveway and extend 12 inches onto the
adjacent property 27 Gold Hill Grade, with a dissipation bed at the outfall. (Sheet SP -3)
Geotechnical peer review has been required and conducted for this site, and a drainage plan has been
reviewed by Public Works. No unique soils constraints or drainage issues have been identified as a
result of this review.
Zoning Entitlements
As proposed, the project would require an Environmental and Design Review permit for a new hillside
home on a flag lot.
Other Approvals
The project must meet Wildland-urban interface planting requirements, green building regulations, and
landscape efficiency requirements. Fire and Building have reviewed the project for conformance with
these provisions, and the applicant has revised plans in response to their comments, including provision
of Fire Information on Sheet F-1. In addition, an encroachment permit would be required to allow the
installation of concrete and other minor site improvements in the public right of way at the base of the
driveway. The Fire Department has determined that there is no requirement to remove any live
Eucalyptus trees from the site. Removal of live Eucalyptus trees is allowed and desired, but not
required. However, any trees within 100 feet of a structure must be limbed up (or skinned up in the case
of a Eucalyptus tree) a minimum of 10 feet above the ground.
ANALYSIS
On July 17, 2012, the Board reviewed the revised project for the third time, including the changes that
were made in response to the first two reviews on March 25, 2011 and November 8, 2011. At its July
17, 2012 meeting, the majority of the Board found that the project had improved some since the initial
review with the addition of the dormer and elimination of chimeny's, but reiterated their prior comments
and concerns with the mass and need for stepping back of the upper floor of the structure or moving the
entire building back, moving the deck and hot tub on the side of the building back, and concern with the
drainage. The Board voted 5-0) to continue the matter with recommendations to date uncertain.
The applicant has only slightly revised the plans since the last meeting. The applicant contends that the
design complies with the Hillside Design Guidelines, including the massing and stepback requirements.
The apFlicant has provided the attached letter (Exhibit 2) responding to the Board's comments from the
July 17 h meeting. The applicant has revised the plans to provide a new shed roof over the entire front
wrap around porch on the front elevation as well as some other minor changes to windows and rear
elevation. A full size and 11" x 17" reduced set of the revised plans are included in the Board's packet.
The Board's consensus items from the July 17, 2012 meeting are identified below bold and followed by
staff response and analysis.
1. Upper floor level of structure still needs to be stepped back as previously recommended
No changes are proposed to push back the upper level of the front of the structure. Instead, the
applicant has added a standing seam metal roof over the entire porch that wraps around the front
and side elevation. Previously, there was only a small gable roof over the porch, located at the
entryway to the house, but the latest revision now adds a shed roof over the entire front porch. (See
Sheets A-4 & 5 upper floor plan and front and right side elevations). The applicant has submitted a
letter (Exhibit 2), explaining their rational for how they believe that the building as designed is
adequately stepped.
Anal
The applicant has not made any changes to the structure to step back the upper floor. Instead, they
have proposed to add a more significant roof form between the main floor and upper floor to provide
visual relief between the two levels. The applicant has explained their rational for this design in their
attached resubmittal letter.
Staff notes that prior to the November 8th meeting, the project had been revised to reduce overall
building height and in the understory space and provide additional stepping of the front of elevation
through the creation of the deck. At that time, staff indicated that we no longer had a concern with
the design of the front elevation of the structure and that we believed the structure complied with the
setback requirements of the hillside guidelines. This recommendation continues to hold on this
resubmittal. This is primarily based on the location of the property and its distance from the street
(over 150 feet), the setback of the structure from the front of the flat lot (nearly 40 feet, where 20
feet is required) and the dense vegetation that exists between the properties. The front downhill
elevation does comply with the stepback requirements that limit wall heights (in a single plane) on
downhill elevation to 20 feet.
Staff's recommendation is that although we were supportive of the design previously, this new roof
over the front deck is a further improvement from the prior and provides more visual relief in the
front elevation. Therefore, staff continues to support project design in terms of massing and
articulation.
2. Deck and hot tub on upper level need to be stepped back significantly as previously
recommended
No changes have been made to the upper deck or hot tub. (See Sheets A-4 and 5 Upper Floor Plan
and Front Elevation)
Analysis
The applicant has not addressed this comment and has not provided any justification or rational in
their response letter.
3. Board maintains concern with the drainage plan, and would strongly recommend that all
water be collected and conveyed to drainage across the street, rather than use the existing
drainage way in front of neighbors property
This latest revision proposes to add a 24" pipe extension to extend the closed drainage system from
under the driveway all the way onto the adjacent property (12 inches onto the adjacent property at
27 Gold Hill Grade). The closed system would terminate just past the foundation corner for of
building at 27 Gold Hill Grade and drainage would dissipate through a new dissipation bed at the
outfall. See Sheet SP -3.
Analysis
As previously reported, the drainage plan has been prepared by a licensed engineer and been
review by the city's Department of Public Works staff and found to be acceptable and in
conformance with City standards. Based on the fact that the drainage plan has been prepared by
licensed professionals, and reviewed by licensed professionals in charge of reviewing drainage, staff
recommends that this issue is addressed. Staff does not that the Department of Public Works has
not indicated that this is the only drainage solution that would be acceptable on the site, but that as
proposed and designed, meets city standards. They have indicated that if the applicant proposes an
alternative drainage plan, which takes all water off this site, across Gold Hill Grade and into the
drainage channel there, that could also be an acceptable solution, however, it would require a study
of the entire watershed, since it changes the current drainage patterns in the area.
One important note about the proposed drainage plan is that the applicant's current plan shows that
they would extend a closed drainage system onto the neighboring property and construct a rip rap
dissipation bed as well on that property (27 Gold Hill Grade). Staff had requested that the applicant
submit evidence of the permission from the adjacent property owner of permission to build these
improvements on the adjacent property. The applicant has indicated that he has been working with
adjacent property owner to get this authorization, but has not at this point. According to the
applicant, the adjacent property owner does not want to authorize the encroachment until the City
approves the project. The applicant states if we require the authorization now, he cannot get the
DRB to review his resubmittal. Therefore, staff has agreed to defer this authorization as include it as
a condition of approval if the project is approved that would have to be satisfied prior to issuance of
a building permit. Ultimately, it is the applicant's choice if he wants to proceed without that assure.
The City just needs to ensure that the authorization is received prior to the issuance of a building
permit (if the project is approved).
As noted in the last report, staff has discussed the drainage plan and the DRB's comments on
multiple occasions with the Department of Public Works. The plan as designed is acceptable and
consistent with City standards. Public Works has indicated that a different drainage plan,
recommended by the DRB (to reroute the run off straight down the driveway then under Gold Hill
Grade and into the creek), could also be acceptable. However, the current configuration of the
drainage crosses onto a neighbor's property prior to approaching the road right of way. In this case
redirecting the water is considered a change to the neighbor's property and would require approval
from the neighbor as well as a study of the drainage patterns in the entire watershed area. Although
this is a possibility, staff does not recommend that there is any nexus to require the change to the
existing drainage patterns in the area since adequate drainage is currently shown to be possible
with the proposed plan that was designed by a licensed engineer and reviewed by the City Public
Works Department. Furthermore, the drainage plan as proposed now identifies that the net run off,
both volume and flow, would be within existing levels, therefore, it is a drainage plan that is
consistent with city requirements
The applicant has also indicated that they have discussed the drainage plan with the adjacent
neighbor, but at this point, staff has not received any confirmation of approval from the adjacent
property. Staff notes that there still does not appear to be mutual agreement between the two
parties, but that is not a City issue.
As designed, the proposed drainage plan is designed by a licensed engineer and is designed to
accommodate a 100 year storm event. The improvements proposed on the property (24" diameter
underground detention pipe to control the run-off during a storm event) would reduce any increase
volume from post development to pre -development levels. The proposed detention pipe/basin
serves this purpose and is a standard design feature used in drainage plans to detain increases in
run off. The detained water would then be discharged into the 8" storm drain pipe that then be
discharged into the existing natural drainage swale after the peak of the storm event has passed. In
addition, dissipation beds have been added around the site to reduce the velocity of the run off and
reduce it's energy. At this point, the drainage plan is consistent with City standards to be designed
to accommodate a 100 year event, with both intensity and volume of post development run-off equal
pre -development levels. The Public Works Department has reviewed the drainage plan. In general,
they have found that the preliminary drainage plan is feasible and have found the preliminary plan
adequate for the planning phase of the project. During the building permit phase of this project,
Public Works will be examining the detail calculations and requiring the applicant to address how
water will be released into the creek during peak periods as well as clarifying all aspects of the final
drainage plan.
NEIGHBORHOOD CORRESPONDENCE
Notice of this meeting as well as all previous meetings was posted on site and mailed to the surrounding
residents and property owners within 300 feet, as well as the Dominican/Black Canyon Neighborhood
101
and Gold Hill Grade Neighborhood Associations, 15 days prior to this and all prior Design Review Board
meeting. Story poles are erected to reflect the proposed design and are visible on site.
Prior to the first DRB meeting, staff had received written and oral comments from the resident/owners of
the property to the front of this site (27 Gold Hill Grade) as well as written comments from the resident
of the property to the east (51 Gold Hill Grade). These letters cited concern with drainage from the site,
location of the structure being too close, privacy, mass of the structure, and windows facing their
properties. Prior to the second DRB meeting, staff received both written and oral comments from the
resident/owners of the 27 Gold Hill grade. These letters cited concern with drainage, privacy impacts on
their studio unit from the deck and west facing windows; type of planting proposed in the landscape
easement area and the location of the proposed new 6' fence between the two properties.
Prior to the July 17, 2012 DRB meeting, written comments and oral comments were submitted from
adjacent neighbors. A letter from Mary Coman, owner of 27 Gold Hill Grade, expressing confern that the
new home is too large and close to their property, supporting the addition of a 6 ft screening fence, and
expressing concern with the drainage. In addition, she provided oral comments at the hearing. In
addition, there was a comment letter from Gary Coman, property owner of 27 Gold Hill Grade,
expressing concern with the drainage plan., Lastly, there was a letter from Christina Quinn, of 51 Gold
Hill Grade, expressing concern for water supply and consideration for the neighbors.
At the time of the preparation of this staff report, no new written or verbal correspondence has been
received for this hearing. Any correspondence received after the report is distributed on Thursday
October 3`d will be forwarded to the Board under separate cover.
CONCLUSION
The revised plans do not appear to address the Board's July 17, 2012 recommendations. However,
Staff finds that the project as designed for this location would substantially comply with the hillside
design criteria, zoning regulations and General Plan policies, with conditions. Staff also continues to find
that the architecture and massing are adequate for this site and it's surroundings.
This project has been before the Board for four separate occasions Therefore, staff requests that the
Board provide a final recommendation on the project revisions on the quality of the design and whether
the project design complies with the applicable review criteria. Following a recommendation by the
Board, this matter will be scheduled for a hearing for final action.
EXHIBITS
1. Vicinity Map
2. Letter from George Mann, applicant, August 15, 2013
3. DRB Meeting Minutes — Summary action, July 17, 2012
➢ Revised Project Plans (Full-sized and 11 "x17" plans have been provided to the DRB members only).
cc: Stephen Charlip
Stephen Charlip Architect
104 5th St
Petaluma, CA 94952
George Mann
78 Rafael Dr
San Rafael, CA 94901
Christa Quinn
51 Gold Hill grade
San Rafael, CA 94901
Dominican/Black Canyon NA
PO Box 151702
San Rafael, CA 94915-1702
Gold Hill Grade HOA
Jack Nixon, President
301 Locust Avenue
San Rafael, CA 94901
Mary and Gary Coman
27 Gold Hill Grade,
San Rafael, CA 94901
V I] .�/ Ll j 11 Cl � 1'� � f
y hvdl L )-/\/\(h �'b �'t 1
SCALE 1 :2,087
100 0 100 200 300
FEET
N
Thursday, November 03, 2011 10:27 AM
15 August 2013
15-C I V E 0
AUG 15 2013
Raffi Boloyan, Planning Manager PLANNING
City of San Rafael, Community Development Department Planning Division
P. O. Box 151560
San Rafael, CA 94915-151560
Dear Raffi:
You have suggested that it would be beneficial to describe in writing how our proposed house at 31
Gold Hill Grade meets each of the described Hillside Guidelines for San Rafael, as well as explaining the
most recent changes to our design made in order to respond to the concerns of the Design Review
Board. We made a point of meeting all of the listed guidelines before we submitted our first set of
plans. We have since made numerous changes to the plans based on the comments received from the
board and public comment from two neighbors. As detailed below, we meet all of the guidelines as set
forth in the Hillside guidelines.
Hillside Guideline Section A." Building Stepback": The proposed house has only the front staircase and a
portion of the front deck entering into the 15' stepback area behind the 20' setback area between the
lot at 27 Gold Hill Grade. In this area, the staircase and pertinent railing rise to approximately 8' from
grade and stepout approximately 5'. We have now added a roof over the deck to provide an additional
stepping effect. With this change, the elevation then changes to the covered entry area which varies in
height from approximately 6' above the railing to 10' above the railing. None of this area within the
stepback goes above 18', which in fact only occurs at the dormer above the front entry. All of this is well
within the 20' height limit under this guideline. This area, which is all inside of the stepback area, steps
back approximately 6' more to the second level of the house. In all this provides three distinct tiers to
the house.
On the east side of the lot the garage sits approximately 5' into the 15' stepback area behind the 15'
setback area. Here, the top of the garage roof line only reaches 7' above the existing grade as it is set
back into the hillside with a retaining wall.
Hillside Guideline Section B. "Setbacks": The proposed house is well inside of the required 20' front, 15'
side, and 25' rear setbacks.
Hillside Guidelines Section C. "Natural State": As noted on drawing SP -4, the average slope of the lot is
25.75%. Along with the minimum 25% the total requirement for being in a natural state is 50.75%. The
landscape plans call for 68% of the lot to remain in a natural state.
Hillside Guidelines Section D. "Gross Building Square Footage": As the lot is over 46,000 square feet the
allowed gross building square footage maxes out at 6,500 square feet. The proposed house has a gross
15 August 2013
Raffi Boloyan
Page 2 of 3
building area of 6,428 feet which is within the required square footage. This comes after including some
400 square feet of airspace inside the house, and almost 1,000 square feet in areas under the covered
entry, under decks, and under overhangs.
Hillside Guideline Section E. "Ridgeline Development": This section does not apply to this house/lot as
we are at the bottom of a much higher hillside.
Hillside Guidelines Section F. "Parking requirements": This section calls for a minimum of two additional
parking spaces. This project is designed with three covered and three uncovered parking spaces
exceeding the minimum requirement.
The remaining two guidelines, sections G and H, do not actually deal with the house itself, rather they
deal with the lot size and the need to go before the DRB, so no comment is necessary on them.
I am unclear why the DRB members believe the proposed structure is not site specific. We originally
designed the house to have a similar look and feel as the house directly to the west which is much larger
than ours and directly to the east which is smaller but one of three housing units on their site. Currently
the biggest difference in feel is that we have gone to lap siding using Hardiplank from our original plan
to use shingles. This change was made specifically based on comments from the DRB. I do understand
that one member said there is now a shingle product we could use, but we decided to not change back.
With regard to bulk and massing, we have added the roof over the deck to reduce the perception of size
and add a third step to the design as explained above. We chose a standing seem metal roof to both
complement and contrast the other materials we are using additionally, a metal seem roof is a better
long term choice for the minimally sloped areas over the deck.
Further commenting on the design being site specific, due to the nature of the lot being a flag lot in a
hillside environment, we chose to place the main structure in the area after the flag lot opens up. This
greatly reduces the visibility of the house from the street. In fact, anyone transiting the area has to go
out of their way to notice where the house is located.
The drainage issues relate to the corner lot which cuts in and makes our lot a flag lot. The owners of
that lot were the trustees of the trust which sold out lot to us. Just prior to our purchasing the lot they
put in place an easement such that they could screen the view between our lots by placing landscaping
in areas of our lot. Additionally the easement calls for them to handle drainage issues between the lots.
In the view area between their house and our proposed house they have between five and fifteen feet
of our property on an uphill grade in which they can landscape to screen the properties and handle any
drainage issues in that area if needed. On the side of the lots which will have our driveway their house
abuts the property line with no setback. Additionally, the corner of their house is on the absolute edge
of the seasonal creek which runs from the two acre lot to our east, through our lot, and through their lot
15 August 2013
Raffi Boloyan
Page 3 of 3
where it curves and then goes under the street. While one member of the DRB suggested keeping the
water in the pipe until it reaches the far side of the street, the adjoining property owner would prefer to
keep the current seasonal creek bed in place on their property. That leaves the only practical way to
solve the problems of drainage is to take the outflow past the corner of their house which puts the
landing point beyond their foundation. This change has been made to our plans.
Should you have any questions, please let me know.
Regards,
George Mann
78 Rafael Drive
San Rafael, CA 94901
415-717-3530
IN THE COUNCIL CHAMBER OF THE CITY OF SAN RAFAEL, July 17, 2012
ltias9rm liip�
Regular Meeting
San Rafael Design Review Board Minutes
For a complete video of this meeting, go to http://www.cityofsanrafael.org/meetings.
CALL TO ORDER
Present: Bob Huntsberry
Cheryl Lentini
Stewart Summers
Mohit Garg
Jeff Kent, Chair
Jack Robertson, Planning Commission Liaison
Absent: Serge Fedorov
Also Present: Kraig Tambornini, Senior Planner
Raffi Boloyan, Principal Planner
Caron Parker, Associate Planner
Sarjit Dhaliwal, Associate Planner
STAFF COMMUNICATION
Staff gave its communication
BOARD COMMUNICATION
Board gave its communication
APPROVAL OF MINUTES
1. Minutes, June 19, 2012
Stewart Summers moved and Mohit Garg seconded to approve minutes as follows:
AYES:
Bob Huntsberry, Cheryl Lentini, Stewart Summers, Mohit Garg, Jeff Kent, Chair
NOES:
None
ABSTAIN:
None
ABSENT:
Serge Fedorov
CONSENT
2. Target Store (125 Shoreline Parkway - Review of final details for outdoor dining area and
approved building materials and colors for the new Target Building. Project Planner:
Sariit Dhaliwal
Bob Huntsberry moved and Stewart Summers seconded to move item off Consent to Old Business. The
vote is as follows:
AYES:
Bob Huntsberry, Cheryl Lentini, Stewart Summers, Mohit Garg, Jeff Kent, Chair
NOES:
None
ABSTAIN:
None
ABSENT:
Serge Fedorov
Bob Huntsberry moved and Stewart Summers seconded to approve the project with the incorporation of
the following consensus items:
1) The reveals of the tower (as depicted on the perspective) continue on all four sides of the tower.
2) That the Board look at the building colors at a paint -out prior to the actual painting of the building.
The vote is as follows:
AYES:
Bob Huntsberry, Cheryl Lentini, Stewart Summers, Mohit Garg, Jeff Kent, Chair
NOES:
None
ABSTAIN:
None
ABSENT:
Serge Fedorov
OLD BUSINESS
3. 195 North Redwood Drive (Marin Covenant Church) - Reauest(s) for amendments to the
Previously approved Environmental and Design Review Permit (ED77-114) and Master Use
Permit (UP73-82) for the existing church use. The proposed project would add 10,381
square feet of new floor area to the existing church building. The new addition would
create a Youth Center Building and also enclose the existing patio area to create a new
indoor lobby/entrance. Interior renovations are also proposed and well as revised
landscaping. No changes to the church activities or hours of operation are proposed. The
building expansion would encroach into the common lot area and therefore requires a Lot
Line Adiustment; APN: 155-271-09,10,11; Office (0) Zoning District; Marin Covenant
Church, owners; Brad Oldenbrook, applicant; File No(s): ED12-013/UP12-007/LLA12-001.
This_prolect was continued from the June 5, 2012 meeting date). Proiect Planner: Caron
Parker
Stewart Summers moved and Cheryl Lentini seconded to approve project with the incorporation of the
following consensus items:
1) That additional finger islands be added to the parking area.
2) That the mullions and doors are revised to line up on the storefront.
The vote is as follows:
AYES:
Cheryl Lentini, Stewart Summers, Mohit Garg, Jeff Kent, Chair
NOES:
Bob Huntsberry
ABSTAIN:
None
ABSENT:
Serge Fedorov
4. 31 Gold Hill Grade -Environmental and Design Review Permit for a new 6,468 qross sa. ft.
Lingle family residence in a two level structure over a basement on a vacant 1.07 -acre
hillside parcel with a 28% slope; APN: 015-091-04• R1a-H Zone; Stephen Charlie
Applicant: George Mann and Stephanie Morgan owners; Dominican/Black Canyon
Neighborhood. Proiect Planner: Raffi Bolovan
Stewart Summers moved and Mohit Garg seconded to continue item to allow applicant to redesign
elements of the project as follows:
1) Upper floor level needs to be stepped back to integrate better into the hillside and break up massing.
2) The deck/hot tub needs to be stepped back significantly.
3) Drainage should be collected and conveyed across the street and away from the neighbor.
The vote is as follows:
AYES: Bob Huntsberry, Cheryl Lentini, Stewart Summers, Mohit Garg, Jeff Kent, Chair
NOES: None
ABSTAIN: None
ABSENT: Serge Fedorov
NEW BUSINESS
5. 207 Chula Vista Drive (Pilgrim Residence) -Requests for Environmental and Design
Review Permit to allow the construction of a 4,144 -sq. ft. new single family residence and
associated site and landscaping improvements, and a Lot Line Adjustment to consolidate
two existing lots into one vacant 23,860 -sq. ft. hillside site, with 44% slope; APN: 011-022-
10 and 11; Single Family Residential (R10) District; Craig Pilgrim, owner; Don Henderson,
applicant; File No.: ED12-031; LLA12-002. Project Planner: Sarjit Dhaliwal
Mohit Garg moved and Stewart Summers seconded to approve project with the incorporation of the
following consensus items concerning landscaping:
1) Consider adding genetic diversity into the treescape by the adding of native oaks near the
Hammerhead.
2) Break up the long row of Arbutis Marina trees with oaks to result in two smaller groves of trees.
The vote is as follows:
AYES: Bob Huntsberry, Cheryl Lentini, Stewart Summers, Mohit Garg, Jeff Kent, Chair
NOES: None
ABSTAIN: None
ABSENT: Serge Fedorov
ADJOURNMENT:
ANNE DERRICK, Administrative Assistant III
APPROVED THIS—DAY—OF '2012
JEFF KENT, Chair