HomeMy WebLinkAboutPW Master Services Agreement; Task Order No. 27 B Street Culvert RepairCity of San Rafael
MASTER CONSULTANT SERVICES AGREEMENT
DATED DECEMBER 12, 2019
WITH BKF ENGINEERS
TASK ORDER NO. 27
Surveying & Utilities Discipline
B Street Culvert Repair: Additional Survey
THIS TASK ORDER is entered into on l 1 11 , 20JA between the City of San
Rafael, a municipal corporation ("City"), and BKF Eng►�neers, ("Consultant").
RECITALS
A. The City and Consultant have entered into a Master Consultant Services Agreement
("Agreement") dated December 12, 2019 under which Consultant has agreed to perfonn certain
professional consulting services for the City; and
B. Pursuant to the terms of the Agreement, the City wishes Consultant to perform certain
tasks as set forth in this Task Order, which constitute the Project;
NOW, THEREFORE, City and Consultant agree as follows:
AGREEMENT
1. Scope of services. Consultant shall provide any and all of the services set forth in Attachment A
of this Task Order, dated November 10, 2020, as directed by the City.
Jonathan Shattuck shall be the Project Manager for Consultant for this Task Order. Additional
professional services may be performed by other Consultant staff with prior notice and approval by City.
a. City's duties. The City will:
(1) Determine the scope of services, as set forth in Attachment A.
(2) Make available the project plans and specifications and other City data related to the
project, including full information as to the City's requirements.
(3) Designate Theo Sanchez as the person at the City responsible for monitoring performance
under this Task Order.
b.Consultant duties. The Consultant will:
(1) Provide and perform tasks identified in Attachment A, Scope of Services.
(2) Provide miscellaneous consulting and other services related to the Project and not
stipulated elsewhere in this Task Order. when requested by the City in writing. A Task
Order Amendment is required if these additional services cannot be performed within the
Task Order budget.
Rev May 2013
City of San Rafael Master Consultant Services.-tgreenrent
Task Order
2. Date of completion; Work hours estimate; Cost estimate and budget: Fee schedule
The work hours estimate, cost estimate and budget and fee schedule are set forth in the attachments to this
Task Order, as follows:
Date of completion: Exhibit A
Work hours estimate: Exhibit A
Cost estimate and budget: Exhibit A
Fee schedule (Consultant's current hourly rate): Exhibit B
With regard to each project given to Consultant that is subject to this Task Order, the time of completion,
work hours estimate, cost estimate and budget and fee schedule are set forth in Attachment A to this Task
Order.
3. Authorization to proceed.
The City will give Consultant authorization to proceed with the work specified in this Task Order only after
Consultant submits updated insurance certificates and endorsements, in accordance with Section 10 of the
Agreement.
4. Master Agreement terms; Conflicts.
Except as expressly otherwise provided herein, all terms of the Agreement shall apply to Consultant in the
performance of work pursuant to this Task Order. If there is a conflict between this Task Order and the
Agreement, this Task Order shall control.
5. Amendment of Task Order; Conflicts.
Except as provided in Section 1(b)(2) above, this Task Order may not be modified except by an Amended
Task Order executed and approved in the same manner as the Task Order.
6. Signatures. The parties have executed this Task Order, as of the date first written above.
CITY OF SAN RAFAEL CONSULTANT
,1
f
By: By: a -
I 1 uerin, Public Works Director
Contents approved:
Rev, Jan 2019r
Name: Jason Kirchmann
Title: Vice President
City of San Rafael Master Consultant Services Agreement
Task Order
By: vt,-4� �
Hunter Young, Assistant Public Works Director
Reviewed By
By. _ 94,�A . &U L
Wobert F. Epstein, City Att rney
(if Consultant is a corporation, add signature
of second corporate officer)
Name: Jean Chen
Title: CFO
Attachments:
A Scope of work, time of completion, work hours estimate, cost estimate and budget
B Fee schedule (Consultant's current hourly rate)
3
Rev. Jan 2019
o D+
RFIYOEAROS
+
ENGINEERS. SURVEYORS. PLANNERS
Task Order #02A
San Rafael On -Call Surveying — Woodland & B Street Culvert Repair
BKF Job No. 20191984-12 — Amendment 1
Date: November 10, 2020
Client: City of San Rafael Dept. of Public Works Consultant: BKF Engineers
111 Morphew Street 4040 Civic Center Dr, Suite 530
San Rafael, CA 94901 San Rafael, CA 94903
Contact: Theo Sanchez Contact: Jonathan Shattuck
This is a Task Order request associated with the Master Services Agreement between BKF Engineers and the City
of San Rafael dated December12, 2019 and is governed by the terms and conditions therein.
PROJECT MANAGER: Jonathan Shattuck
__ --1—'--- DATE:
(Signature) —Jason Kirchmann, Vice President
DATE:
(Signature)
91/10%2020
BKF Engineers 14040 Civic Center Drive, Suite 530 1 San Rafael, CA 1949011415.930.7960
De lfi.efitig fnsjsired Ini-astriiattwe
DESCRIPTION:
• BKF will supplement the topographic survey previously prepared, dated
April 1, 2020 to include items requested by the City via email on October
TASK(S):
22, 2020 and as shown on the attached exhibit A. Supplemental
information will include underground box culvert alignment, pothole data
(City to remove temporary trench plates) and topographic data in the creek
• Boundary Surveying is not included.
SERVICES TO BEGIN:
Upon receipt of written authorization
TO BE COMPLETED:
Within two weeks of notice to proceed
DELIVERABLES:
Signed Topographic Map
ORIGINAL T.O. VALUE:
$ 6,000
CURRENT ADDENDUM VALUE:
$ 4,600
TOTAL TASK ORDER VALUE:
$ 10,600 (Time and Materials, Not -To -Exceed)
PROJECT MANAGER: Jonathan Shattuck
__ --1—'--- DATE:
(Signature) —Jason Kirchmann, Vice President
DATE:
(Signature)
91/10%2020
BKF Engineers 14040 Civic Center Drive, Suite 530 1 San Rafael, CA 1949011415.930.7960
De lfi.efitig fnsjsired Ini-astriiattwe
WOMB
I IJ
VICINITY HAP
Lu
>
WB k f loo-
YE ..
ENGINEERS. SURVEYORS PLANNERS
BKF ENGINEERS
PROFESSIONAL SERVICES RATE SCHEDULE
JANUARY 1, 2020 - DECEMBER 31, 2020
CLASSIFICATION
HOURLY RATE
PROJECT MANAGEMENT
Principal/Vice President
$251.00
Senior Associate/Vice President
$225.00
Associate
$219.00
Senior Project Manager I Senior Technical Manager
$214.00
Project Manager I Technical Manager
$209.00
Engineering Manager I Surveying Manager I Planning Manager
$193.00
TECHNICAL STAFF
Senior Project Engineer I Senior Project Surveyor I Senior Project Planner
$179.00
Project Engineer I Project Surveyor I Project Planner
$157.00
Design Engineer I Staff Surveyor I Staff Planner
$137.00
BIM Specialist I, II, III
$137.00 - $157.00 - $179.00
Technician I, II, III, IV
$130.00- $139.00 - $152.00 - $164.00
Drafter I, II, III, IV
$102.00 - $112.00 - $121.00 - $135.00
FIELD SURVEYING
Survey Party Chief
$179.00
Instrumentman
$154.00
Survey Chainman
$116.00
Utility Locator I, II, III, IV
$93.00 - $132.00 - $158.00 - $180.00
Apprentice I, II, III, IV
$71.00 - $95.00 - $105.00 - $111.00
CONSTRUCTION ADMINISTRATION
Senior Consultant
$234.00
Senior Construction Administrator
$203.00
Resident Engineer
$151.00
Field Engineer I, II, III
$137.00 - $157.00 - $179.00
ASSISTANTS
Project Assistant
$84.00
Engineering Assistant I Surveying Assistant 'Planning Assistant
$82.00
Clerical I Administrative Assistant
$70.00
Expert witness rates are available upon request.
Subject to the terms of a services agreement:
• Charges for outside services, equipment, materials, and facilities not furnished directly by BKF Engineers will
be billed as reimbursable expenses at cost plus 10%. Such charges may include, but shall not be limited to:
printing and reproduction services; shipping, delivery, and courier charges; subconsultant fees and
expenses; agency fees; insurance; transportation on public carriers;
meals and lodging; and consumable
materials.
• Allowable mileage will be charged at the prevailing IRS rate per mile.
• Monthly invoices are due within 30 days from invoice date. Interest
will be charged at 1.5% per month on
past due accounts.
i\
Z
r�vITH P�
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Iman Kayani for Theo S Extension: 3352
Contractor Name: BKF Engineers
Contractor's Contact: Jason Kirchmann Contact's Email: jkirchmann@bkf.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION ... . �-jItVVER
DEPARTMENT
DATE Check/Initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor
C Clea,. here to
❑
enter a dat,°
b. Email contract (in Word) and attachments to City
12/2/2020
Attorney c/o Laraine.Gittens@cityofsanrafael.org
NIKK
2
City Attorney
a. Review, revise, and comment on draft agreement
12/7/2020
❑x LG
and return to Project Manager
12/7/2020
❑x LG
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
3
Department Director
Approval of final agreement form to send to
12/11/2020
BG
contractor
4
Project Manager
Forward three (3) originals of final agreement to
12/11/2020
❑x IKK
contractor for their signature
5
Project Manager
When necessary, contractor -signed agreement
Nx N/A
agendized for City Council approval *
*City Council approval required for Professional Services
❑X IKK
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
!
Click lierc to
Date of City Council approval
enter a Crate.
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
12/21/2020
IKK
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
j �� ' 1
"1
agreement
8
City Attorney
Review and approve insurance in PINS, and bonds
(for Public Works Contracts)
tAlu2
9
C4*A4aRager1 Mayor
VW
Agreement executed by City Council authorized
1/ `L
Dir =
official
P-0
City Clerk
Attest signatures, retains original agreement and
-
forwards copies to Project Manager
b�
3 �-�
N