HomeMy WebLinkAboutPW Third Street Improvements PPTMay 3, 2021 THIRD STREET REHABILITATION CITY COUNCIL MEETING Third Street Projects May 3, 2021 Project Limits E STREETA STREETLINDAROC STREETB STREETD STREETLINCOLNSHAVERG STREETWEST STREETEAST STREETMeasure A, State, and Local Funds HSIP: “Highway Safety Improvement Program” 3rd Street from just east of Union St to 2nd St 2nd Street from West St to Shaver St Third Street Projects May 3, 2021 1.Technical Working Group Meeting –July 2017 2.Community Working Group Meeting –October 2017 3.Community Meeting #1 –November 2017 4.Working Group Meeting -February 2018 5.Community Meeting #2 –March 2018 6.City Council Approves Master Plan Update –July 2018 7.Feasibility Report Presentation to City Council –June 2019 8.Bicycle and Pedestrian Committee –August 5,2020 9.Community Meeting #3 September 23,2020 10.Presentation to City Council November 3,2020 11.BPAC–December 2,2020 &February 3,2021 12.Community Meeting #4 March 24,2021 Project Outreach Third Street Projects May 3, 2021 1.Improve safety for all bicyclists and pedestrians 2.Repair pavement and drainage 3.Improve pedestrian crossings and repair sidewalks 4.Upgrade traffic signals and provide safety lighting 5.Improve traffic flow for cars,transit,and emergency service 6.Add street trees 7.Enhance access for designated Safe Routes to Schools 8.Develop an economically viable project Project Goals Third Street Projects May 3, 2021 Traffic Signals New Traffic Signals: Brooks Street East Street YELLOW BAND NIGHTIME VISIBILITY COUNTDOWN SIGNALS EMERGENCY VEHICLE PREEMPTION SAFETY LIGHTING Third Street Projects May 3, 2021 Lindaro /Lootens Intersection Third Street Projects May 3, 2021 Lindaro /Lootens Intersection THIRD STREET WALGREENS Third Street Projects May 3, 2021 Raised Intersections A Street B Street C Street D Street Third Street Projects May 3, 2021 STEEP AVG Downtown Intersections Third Street Projects May 3, 2021 Second Street Bicycle Facility West StreetEast StreetIda StreetG StreetMiramar StreetHayes StreetShaver StreetMarquardAve Third Street Projects May 3, 2021 Second Street Bicycle Facility Third Street Projects May 3, 2021 Median Trees 1 2 3 4 5 Third Street Projects May 3, 2021 2 nd & East St Bicycle Facility Third Street Projects May 3, 2021 2 nd & G Street Bicycle Facility Third Street Projects May 3, 2021 2 nd & G Street Bicycle Facility Third Street Projects May 3, 2021 Second Street Wall Options Third Street Projects May 3, 2021 Form Liner Geometric pattern Variable color Texture Mural Smooth face Comply with City’s process Anti graffiti Shotcrete Natural look Variable color Texture Second Street Wall Options Third Street Projects May 3, 2021 Asphalt Berm Vertical barrier separates vehicles and bicyclists. Low cost. Bollard and Marker Visual separation between vehicles and bicyclist. Least cost. Concrete Curb Vertical barrier separates vehicles and bicyclists. Resilient Higher cost.Base Bid Deductive Alternative Bid Class IV Bikeway Barriers Third Street Projects May 3, 2021 Third Street Trees Third Street Projects May 3, 2021 Third Street Trees Adaptive to warmer climates Drought tolerant Third Street Projects May 3, 2021 Construction Process 1.About 1 year of construction 2.General sequence of work •Utilities –MMWD,sewer district,and PG&E •Sidewalk and curb ramps •Traffic signals •Paving and striping •Street trees 3.Lane closures during off peak periods •East bound (Second Street):9 am to 6 pm •West bound :6 am to 3 pm 4.Night work for paving and specific operations 5.Driveways will be closed for periods of up to 4 hours Both the City and contractor will outreach to residents and businesses during construction to provide advance notice of construction activities. Third Street Projects May 3, 2021 Project Next Steps Feasibility Study April 2017 to June 2019 Concept Design January to August 2020 Council Review 11.02.20 CEQA Review and Final Design Winter/ Spring 2020 Council Review 05.03.21 Secure TAM funding 05.10.21 & 05.27.21 Contract with CM Firm June 2022 Plans out to Bid July/Aug 2022 Construct Sept/Oct 2021 to Fall 2022 Third Street Projects May 3, 2021 Additional Information April Miller, P.E. Senior Civil Engineer April.Miller@cityofsanrafael.org 415-485-3409 www.cityofsanrafael.org/third-st-rehab/ Third Street Projects May 3, 2021 Thank youQuestions & Comments Tonight’s Objective: Staff is asking the City Council to accept the Third Street Rehabilitation project report and direct Staff to request construction funding from the Transportation Authority of Marin.