This AGREEMENT is made this 01-7 day of �j40" _ , 202_L by and between
the Transportation Authority of Marin, hereinafter referred to as "TAM", a local public agency, and the
City of San Rafael, hereinafter referred to as "RECIPIENT", a local public agency.
SECTION 1. RECITALS
1. The One Bay Area Grant (OBAG) Program is the Metropolitan Transportation Commission's
(MTC's) funding approach that attempts to integrate the region's federal transportation program with
California's climate law (Senate Bill 375, Steinberg, 2008) and the Sustainable Communities Strategy.
2. In November 2015, MTC adopted guidelines for funding distribution from OBAG Cycle 2 that
covers a five-year period from FY 17/18 to FY 21/22.
TAM's share of OBAG 2 funds amounted to $10,870,000.
4. MTC also set aside a minimum amount for each county for CMA planning and administrative
activities, referred as "CMA Planning Funds."
5. The MTC set aside for CMA planning and administrative activities (referred as "CMA Planning
Funds") for the five-year period is $3,822,000, leaving $7,048,000 for projects and programs.
6. On July 1, 2017, TAM and MTC entered into agreement to establish the terms on the CMA
Planning Funds and allow projects with CMA Planning Funds to proceed.
7. On July 1, 2018, TAM and MTC entered into a supplement agreement to augment the $3,822,000
in CMA Planning Funds with an additional $75,000 for work associated with the Community Based
Transportation Plan in San Rafael.
8. In discussions with the City of Rafael, TAM is providing $66,230 in local funds to the City of
Rafael for work on the San Rafael Community Based Transportation Plan.
SECTION 2. PURPOSE OF FUNDING AGREEMENT
This AGREEMENT is entered into by and between TAM and RECIPIENT to document the funding
conditions necessary for the RECIPIENT to comply with applicable law and TAM policies. This
AGREEMENT consists of additional documents stated in these sections as being attached hereto and
incorporated in the AGREEMENT by reference.
SECTION 3. PROJECT DEFINITION AND SCOPE
This AGREEMENT, is made for the following purposes identified in the RECIPIENT's Project
Information Sheet (EXHIBIT A):
T%15 CMA Funding Programti15 02 Federal ProgramMOSAG 21Funding Agreement San Rafae CBTMAM Funding Agreement A-FY19-08 Revised for Funding swap
FINAL dcc Page I of 7
Community Based Transportation Plan
Additional information on project scope is included in the Project Information Sheet.
SECTION 4. GRANT
As approved by the TAM Board on March 28, 2019, TAM hereby grants to the RECIPIENT the sum of
$66,230 in local funding.
SECTION 5. COST ELIGIBILITY
All costs incurred by RECIPIENT prior to the date of execution of this AGREEMENT shall be ineligible
for reimbursement by TAM. While the costs of the Project shall be eligible for reimbursement in
accordance with the terms of this AGREEMENT, the timing and amount of reimbursement will be
subject to TAM's discretion, based on available revenues and other anticipated project requests.
SECTION 6. BUDGET AND SCOPE
RECIPIENT shall maintain a project or program budget. RECIPIENT shall carry out the project and
shall incur obligations against and make disbursements of the grant in conformity with TAM's
requirements and the budget.
SECTION 7. PROJECT MANAGEMENT
RECIPIENT shall be responsible for the project and provide management of consultant and contractor
activities for which RECIPIENT contracts, including responsibility for schedule, scope, and budget,
consistent with TAM's resolution allocating the grant unless otherwise agreed upon in writing.
SECTION 8. PROJECT OVERSIGHT
RECIPIENT shall cooperate with TAM's project management team and shall provide any requested
project information.
SECTION 9. ATTRIBUTION AND SIGNAGE
If any portion of grant funds is used for production of reports, acknowledgment of the TAM's role shall
be included in the documents. If any portion of grant funds is used for construction, RECIPIENT shall,
upon initiation of field work or at the earliest feasible time thereafter, install and maintain a sign at the
construction site identifying TAM (e.g., TAM and RECIPIENT's logos) as a partner. For non -
construction capital purchases funded by any portion of grant funds, RECIPIENT shall aux permanent
signage identifying TAM as a funding source. RECIPIENT shall demonstrate compliance with attribution
and signage requirements as an indispensable condition for authorization of reimbursements for project
expenses.
SECTION 10. PRESS RELEASES
RECIPIENT shall notify TAM in advance of any press releases about project and program activities,
particularly groundbreakings and ribbon cuttings, in connection to grant funds expended from this
AGREEMENT.
T 415 CMA Funding Program%15 02 Federa Programs%DBAC 21Funding Agreement San Rafae CBTP\TAM Funding Agreement A FV 19-08 Revised for Funding swap
FINAL doc Page 2 of 7
SECTION 11. COMPLIANCE WITH LAW
In the performance of its obligations pursuant to this AGREEMENT, RECIPIENT shall keep itself fully
informed of the federal, state and local laws, ordinances and regulations in any manner affecting the
performance of this Agreement, and must at all times comply with such laws, ordinances, and regulations
as they may be amended from time to time.
SECTION 12. ENVIRONMENTAL COMPLIANCE
RECIPIENT shall undertake all environmental mitigation measures that may be identified as
commitments in applicable documents (such as environmental assessments, environmental impact
statements and reports, and memoranda of agreement) and comply with any conditions imposed as a part
of a finding of no significant impact or a record of decision; all such mitigation measures are incorporated
in this AGREEMENT by reference. Recipient shall be responsible for obtaining all necessary
environmental permits for performance of work.
SECTION 13. FINANCES
All costs charged to the project shall be supported by properly prepared and documented time records,
invoices, or vouchers evidencing in detail the nature and propriety of the charges and the basis for the
percentage charged to TAM.
SECTION 14. RECORDS
All checks, payrolls, invoices, contracts, vouchers, journal entries, work orders, or other accounting
documents pertaining in whole or in part to the project shall be maintained by RECIPIENT for a period of
five (5) years after the later of project closeout or termination of grant. Such project documents shall be
clearly identified, readily accessible, and, to the extent feasible, kept separate and apart from all other
similar documents not pertaining to the project.
SECTION 15. REIMBURSEMENTS
Payment shall be made by TAM for costs reimbursable under the terms of this AGREEMENT. Payment
to RECIPIENT of the grant shall be upon written approval by TAM, upon submittal by RECIPIENT of
appropriate support documentation and identification of expenses incurred.
RECIPIENT may make a request for exceptions in writing. Exceptions may be made at the sole
discretion of TAM. Reimbursement requests, with appropriate documentation, may be submitted on a
regular basis but no more frequently than monthly.
Each reimbursement request shall include RECIPIENT's certification that the amounts sought are only
for project elements included in the Project Information Sheet, and that RECIPIENT is in compliance
with TAM's requirements mentioned in this AGREEMENT.
SECTION 16. ELIGIBLE EXPENSES
RECIPIENT shall expend funds only on eligible expenses as follows: operating costs, direct staff time
(salary and benefits), consultants; right of way engineering and acquisition costs (including permitting),
and competitively bid constriction contracts. Indirect costs (as defined by OMB Circular A-87) will not
be considered an eligible expense.
T 115 CN1A Funding Program115 02 Federal PrcgramMOBAG 21Funding Agreement San Rafael CBTPITAM Funding Agreement A-FY19-08 Revised for Funding swap
FINAL doc Page 3 of 7
TAM shall provide notice to RECIPIENT of any and all expenditures made by RECIPIENT which are
not in compliance with this AGREEMENT promptly after TAM becomes aware of any such expenditure.
SECTION 17. AUDITS
TAM reserves the right at any time to conduct or require a financial or performance audit of the
RECIPIENT'S compliance with this AGREEMENT. TAM will give advance notice of the requirement.
RECIPIENT shall permit TAM, or any of its duly authorized representatives, to inspect all work,
materials, payrolls, and other data and records with regard to the project, and to audit the books, records,
and accounts of the RECIPIENT and its contractors with regard to the project.
SECTION 18. THIRD PARTY CONTRACT AUDITS
TAM reserves the right to request an audit of other third party contracts for any reason. If RECIPIENT is
subject to third party financial audit requirements imposed by another funding source, copies of audits
performed in fulfillment of such requirements shall be provided to the TAM.
SECTION 19. CLOSEOUT PROCEDURES AND PROJECT CLOSEOUT REPORT
Project closeout occurs either when TAM notifies RECIPIENT of the project closeout or forwards to
RECIPIENT the final grant payment. RECIPIENT shall provide to TAM a copy of the final CBTP report
with the final reimbursement request. RECIPIENT shall provide supporting documentation for
expenditures and revenues from its accounting and financial management system. RECIPIENT shall
certify that the amounts sought are only for project elements included in the Project Information Sheet.
Upon request by TAM or discovery by RECIPIENT, after the project completion date or termination by
TAM, RECIPIENT shall submit a certified financial statement identifying all ineligible expenditures,
which the RECIPIENT shall be required to refund, as well as third party audit reports, in the event that
ineligible expenditures were reimbursed with funds from this AGREEMENT. Project closeout shall
not terminate any continuing obligations imposed on the RECIPIENT by this AGREEMENT.
SECTION 20. RESCISSION OF AUTHORIZATION OF FUNDS
TAM reserves the right to rescind its authorization of unneeded grant funds prior to, or at the time of,
project closeout. Funds are determined to be unneeded if they are uncommitted at time of project
closeout.
SECTION 21. TERMINATION FOR CAUSE
RECIPIENT agrees that, upon ten (10) working days written notice, TAM may suspend or terminate all
or part of the financial assistance provided herein for failure to correct a breach of this AGREEMENT.
Any failure to make reasonable progress, inconsistency with the Project Information Sheet, unauthorized
use of grant funds as specified in this AGREEMENT, or other violation of the AGREEMENT that
significantly endangers substantial performance of the project shall be deemed to be a breach of this
AGREEMENT and cause for termination. Upon mutual consent, RECIPIENT will repay TAM any
unexpended funds originally provided under this Agreement.
SECTION 22. CORRECTION OF BREACH
With respect to any breach, which is reasonably capable of being cured, RECIPIENT shall have thirty
(30) days from the date of notice of breach to initiate steps to cure. If RECIPIENT diligently pursues
T%15 CMA Funding Program\15 02 Federal ProgramslOBAG 2\Funding Agreement San Rafael CBTP\TAM Funding Agreement A-FY19-0B Revised for Funding swap
FINAL doe Page 4 of 7
cure, such RECIPIENT shall be allowed a reasonable time to cure or by a time established in writing by
TAM.
SECTION 23. LIABILITY
Neither TAM nor any officer or employee thereof, shall be responsible for any damage or liability
occurring by reason of anything done or omitted to be done by RECIPIENT under or in connection with
any work, authority, or jurisdiction delegated to RECIPIENT under this AGREEMENT. It is also
understood and agreed that pursuant to Government Code Section 895.4, RECIPIENT shall filly defend,
indemnify and hold TAM harmless from any liability imposed for injury (as defined by Government
Code Section 810.8) occurring by reason of anything done or omitted to be done by RECIPIENT under or
in connection with any work, or jurisdiction delegated to RECIPIENT under this AGREEMENT.
Neither RECIPIENT nor any officer or employee thereof, shall be responsible for any damage or liability
occurring by reason of anything done or omitted to be done by TAM under or in connection with any
work, authority, or jurisdiction delegated to TAM under this AGREEMENT. It is also understood and
agreed that pursuant to Government Code Section 895.4, TAM shall fully defend, indemnify and hold
RECIPIENT harmless from any liability imposed for injury (as defined by Government Code Section
810.8) occurring in by reason of anything done or omitted to be done by TAM under or in connection
with any work, authority, or jurisdiction delegated to TAM under this AGREEMENT.
In the event of concurrent negligence of RECIPIENT and TAM, the liability for any and all claims for
injuries or damages to persons and/or property shall be apportioned under the California theory of
comparative negligence as presently established or as may hereafter be modified.
SECTION 24. OBLIGATIONS
In general, termination of financial assistance under this AGREEMENT will not invalidate obligations
properly incurred by RECIPIENT before the termination date; to the extent those obligations cannot be
canceled.
SECTION 25. INTEGRATION
This AGREEMENT represents the entire AGREEMENT of the parties with respect to the subject matter
thereof. No representations, warranties, inducements or oral agreements have been made by any of the
parties except as expressly set forth herein, or in other contemporaneous written agreements.
SECTION 26. AMENDMENT
Except as otherwise provided herein, this AGREEMENT may not be changed, modified or rescinded
except in writing, signed by all parties hereto, and any attempt at oral modification of this AGREEMENT
shall be void and of no effect.
SECTION 27. INDEPENDENT AGENCY
RECIPIENT performs the terms and conditions of this AGREEMENT as an entity independent of TAM.
None of RECIPIENT'S agents or employees shall be agents or employees of TAM.
SECTION 28. ASSIGNMENT
T 115 CMA Funding Prcgram115 02 Federal Programs108AG 21Funding Agreement San Rafael CBM -TAM Funding Agreement A-FY191CO Revised for Funding swap
FINAL doc Page 5 of 7
The AGREEMENT may not be assigned, transferred, hypothecated, or pledged by any party without the
express written consent of the other party.
SECTION 29. BINDING ON SUCCESSORS, ASSIGNEES OR TRANSFEREES
This AGREEMENT shall be binding upon the successor(s), assignee(s) or transferee(s) of TAM or
RECIPIENT as may be the case. This provision shall not be construed as an authorization to assign,
transfer, hypothecate or pledge this AGREEMENT other than as provided above.
SECTION 30. EXPENSES
Each party shall be solely responsible for and shall bear all of its own respective legal expenses in
connection with any dispute arising out of this AGREEMENT and the transactions hereby contemplated.
RECIPIENT may not use GRANT funds, or other TAM programmed funds, for the aforementioned
purpose.
SECTION 31. SEVERABILITY
Should any part of this AGREEMENT be declared unconstitutional, invalid, or beyond the authority of
either party to enter into or carry out, such decisions shall not affect the validity of the remainder of this
AGREEMENT, which shall continue in full force and effect; provided that the remainder of this
AGREEMENT can, absent the excised portion, be reasonably interpreted to give effect to the intentions
of the parties.
SECTION 32. EXHIBITS
The following Exhibits are hereby made part of this AGREEMENT:
EXHIBIT A: Project Information Sheet
SECTION 33. ACCEPTANCE OF GRANT
RECIPIENT does hereby declare that all written statements, representations, covenants, and materials
submitted as a condition of this AGREEMENT are true and correct and does hereby accept TAM's grant
and agrees to all of the terms and conditions of this AGREEMENT. The parties have executed this
AGREEMENT as of the date first written above.
City of San Rafael:
By:
Jim Schutz
Print Name
City Manager
Print Title
Transportation Authority of Marin (TAM):
By:ic (�----.
Anne Rman, Executive Director
T%15 CMA Fundmg Program115 02 Federal Programs%OBAG 21Funding Agreement San Rafael CBTPITAM Funding Agreement A-FY19-08 Revised for Funding swap
FINAL doc Page 6 of 7
Approved as to form (optional):
By: c
V
City of S6 Rafael, Attorney
Robert F. Epstein
Print Name
T%15 CMA Funding Pregram115 02 Federal ProgramslORAG 21Funding Agreement San Rafael CBTMTAM Funding Agreement A-FY19-08 Revised for Funding swap
FINAL doe Page 7 of 7
FEHRtPEERS
July 19, 2021
Rafat Raie
City of San Rafael
111 Morphew Street
San Rafael, CA 94901
Subject: Proposal to Update Canal Neighborhood CBTP
Dear Rafat:
Fehr & Peers appreciates the opportunity to submit this proposal to prepare an update to the Canal
Neighborhood Community -Based Transportation Plan (CBTP) completed in 2006. This proposal
builds on direction provided by City Public Works and Community Development staff on our recent
June 28 call as well as scopes for prior CBTP studies completed for TAM in 2015.
NVO11C4aI_101
Attachment A provides a detailed work plan that describes key work tasks and deliverables
including an engagement plan, an existing conditions summary, meeting agenda packets and
notes, a summary of outreach activities, and the Draft and Final version of the updated CBTP. The
scope also includes six committee meetings (three TAC meetings and three Stakeholder Committee
meetings) and attendance at one City Council Meeting.
FEE AND SCHEDULE
Fehr & Peers would complete Tasks 1 through 7 for a budget of $79,750. The budget includes a
$10,000 stipend for a community-based organization to support the CBTP engagement process.
Invoices will be submitted monthly on a time -and -materials basis. We will prepare a detailed
schedule with City staff that meets the grant deadline for completing a Final CBTP by May 2022,
assuming receipt of notice to proceed by September 1, 2021. We appreciate the opportunity to
submit this proposal. Please do not hesitate to call me at (415) 426-2520 if you have any questions.
Sincerely,
FEHR & PEERS
Bob Grandy, TE
Principal
P27 -2200 -SF
345 California Street I Suite 450 1 San Francisco, CA 94104 1 (415) 348-0300
wwiv fehrandpeers.com
ATTACHMENT A
WORK PLAN
Fehr & Peers' Scope of Services outlines our approach and project deliverables. The scope builds on
previous planning and engagement efforts completed in the Canal District as part of the recent San Rafael
General Plan 2040 Update effort and documented in the March 20, 2020 document titled History, Safety,
Parking, and Quality of life for Latinos in San Rafael: Community Engagement and Urban Planning for the
Next 20 Years prepared by Ricardo Huerta Nino and Communities in Collaboration, LLC (in partnership with
Voces del Canal Leadership Team and Canal Alliance). Just under half the scope and budget is devoted to
gathering additional input and direction from the Canal community including the project Stakeholder
Committee. A smaller portion (about 15 percent) of the scope and budget is dedicated to original analysis
of transportation strategies identified by the community or by our consultant team to address
transportation needs and barriers. We will use the analysis budget to focus on topics and answer questions
highlighted by the community in the first half of the project.
TASK 1: PROJECT INITIATION
Project Goals, Objectives, and Detailed Schedule
Fehr & Peers will work with City staff to review and finalize project goals, objectives, and schedule and
discuss public outreach activities. We assume one round of revisions may be made to the work plan and a
draft schedule.
Project Review Committees
The task of recruiting committee members (Technical Advisory Committee, Community Stakeholder
Committee) will be the responsibility of the City of San Rafael staff. Fehr & Peers will collaborate with City
of San Rafael staff in the development of a candidate list of committee members for consideration.
Technical Advisory Committee: Comprised of city staff and agency partners that may include staff from
Marin Transit, Golden Gate Transit, TAM, and Marin County Health & Human Services (Employment and
Training Branch).
Stakeholder Committee: Comprised of Canal community leaders and supporting organizations that may
include representatives from Canal Alliance, Voces del Canal, Bahia Vista and Laurel Dell Elementary Schools,
Davidson Middle School, San Rafael High School, Conservation Corps North Bay, Mission Evangelica Peniel,
Pickleweed Library, Marin Community Clinics (access to new planned clinics outside Canal neighborhood),
Community Action Marin, and Multicultural Center of Marin.
Deliverable #1A Draft Goals, Objectives, and Schedule
Deliverable #1B Final Goals, Objectives, and Schedule + Committee Listserves
TASK 2: EXISTING CONDITIONS SUMMARY
A first step for this task will be a benchmarking evaluation of the 2006 Canal Neighborhood CBTP
recommendations, and other study recommendations relevant to the Canal Neighborhood, to identify what
has and has not been accomplished on previous plan wish lists.
A
ATTACHMENT A
OIRK PLAN
The Draft Existing Conditions Summary will contain four sections: Community Profile, Transportation
Context, a summary of Community Engagement input obtained from Canal Neighborhood stakeholders as
part of the recent General Plan Update, and Relevant Studies/Reports/Plans. The summary will build on
available demographic and traffic data as collection of new data is not included in the work plan. The
summary will be presented to the TAC for review and comment prior to transmittal to the Stakeholder
Committee in Task 3. At this meeting, the TAC will discuss the existing conditions summary and provide
recommendations for subsequent elements of the studies.
Deliverable #2A Draft Existing Conditions Summary for the Canal Neighborhood
Deliverable #26 Preparation and facilitation of TAC Meeting #1, summary notes
Deliverable #2C Final Existing Conditions Summary (PPT Deliverable)
TASK 3: INITIATE COLLABORATIVE PLANNING AND OUTREACH PROCESS
Fehr & Peers has experience engaging low-income and primarily Spanish-speaking communities. Using
lessons learned from these past experiences, there are three principles of engagement that we would follow
in the Canal Neighborhood:
Make it easy. Create project information materials and event notifications in Spanish and English
that are easy to understand and access.
Make it relevant. Send a clear message as to why the project matters and how public input will
help shape the community's future.
Go to where the people are. Use grassroots organization techniques to generate enthusiasm about
the project and gather feedback in a setting frequented by neighborhood residents.
The success of a community engagement program lies within the proper identification of the target
audiences, communication channels, and venues. Fehr & Peers will work with City staff to invite and include
Canal Alliance representatives on the team, to be funded through a $10,000 stipend, to help make these
identifications for inclusion in the draft Canal Neighborhood Community Outreach Plan. Preliminary ideas
are included in Task 4, below. The Consultant Team will present the draft outreach plan to the Stakeholder
Committee for review and refinement.
Deliverable #3A PowerPoint presentations on the planning process, scope of work, schedule, and
proposed outreach plan
Deliverable #3113 Preparation and facilitation of Stakeholder Committee Meeting #1, summary notes
Deliverable #3C Final Canal Neighborhood Community Outreach Plan detailing specific target
audiences, communication channels, venues, and engagement strategies.
TASK 4: IMPLEMENT COMMUNITY OUTREACH PLAN
Community engagement for the CBTP will build on recent input collected as part of outreach efforts for the
San Rafael General Plan Update, the San Rafael Bicycle and Pedestrian Master Plan, and the March 20, 2020
A2
ATTACHMENT A
WORK PLAN
document titled History, Safety, Parking, and Quality of life for Latinos in San Rafael: Community Engagement
and Urban Planning for the Next 20 Years. The input collected for each of these efforts was robust and
provides a strong foundation from which to start CBTP outreach. The following engagement strategies are
recommended to inform the CBTP. These strategies will be confirmed with Canal Alliance and the
Stakeholder Committee:
1. Spread the Word — with support from City staff, members of the Stakeholder Committee, team
member Canal Alliance, and other interested groups, Fehr & Peers will publicize the project goals,
timeline, and ways to participate. This will include social media, website notice, email distribution
and postings on transit, transit stops, and in local markets.
2. Gather Transit Input via Surveys
and Drop -In Sites — We will
develop a simple electronic and
paper survey to gather input from
transit riders and potential transit
riders. The survey will be translated
into Spanish, distributed
electronically via neighborhood
organizations, apartment
complexes and business
associations, offered as a paper
survey at local gathering spots such
as Pickleweed Library, and
administered as an intercept survey
at local bus stops. The Consultant
Team will administer the intercept
surveys and host up to three (3) drop-in hours at local gathering spots.
3. Gather General Input via Focus Groups — The Team will work with City staff to conduct two focus
groups. The conversations will aim to confirm transportation -related pain points identified in the
previous Canal Neighborhood engagement efforts and add any new concerns that have manifested
in the time since those plans were completed. The group will also be'asked to prioritize
improvement project types. These focus groups will be facilitated by Fehr & Peers and will be hosted
by a local community organization. The make-up of these groups will be determined at part of Task
3. If desired, the Stakeholder Committee could be one of the focus groups. Focus groups may be
conducted entirely in Spanish if invitees indicate that as their preference on the RSVP form.
4. Host Open House to Facilitate Review of Draft Plan - Key elements of the Draft Plan and
Implementation Plan described in Task 6 will be presented to the general public for feedback in
an Open House format with different stations for different components of the Plan. This event
would take place at a local community center such as a school, library or park and would include
food and activities for children.
Deliverable #4A Announcement content for survey and open house (social and traditional media)
ATTACHMENT A
WORK PLAN
Deliverable #413 Survey development, language to support distribution, in-person intercept and
drop-in surveying, and compiled results
Deliverable #4C Notice, agenda, questions, facilitation of focus groups and summaries (up to 2)
Deliverable #413 Agenda, materials, and facilitation of open house
Deliverable #4E Final report of community outreach efforts
The Consultant Team will provide one consolidated round of revisions to all outreach materials and will
provide Spanish translation of all engagement materials.
TASK 5: IDENTIFY TRANSPORTATION GAPS AND POTENTIAL SOLUTIONS
In this task, Fehr & Peers will conduct a technical analysis to assess the key gaps in the transportation
networks for the Canal neighborhood study area.
The first part of the task will be to organize the findings from the initial phase of community outreach into
distinct gap categories. We expect the gaps to generally fall into mode -based categories, such as transit,
bicycle, pedestrian, and automobile -specific categories, although some may be multi -modal in nature. Once
categorized, any similar or overlapping gaps can be assessed to determine overarching themes upon which
to focus recommendations. To facilitate this task, a spreadsheet will be developed to categorize information
on gaps, recommendations, and with a grading system for each gap category. This will provide a simple
structure that will facilitate the ranking process. Effectiveness and feasibility criteria will be developed and
included in the spreadsheet, which will be the basis of the final grading. Throughout the process, the focus
of the consultant team, when working with the TAC, will be on the feasibility of fixes for identified issues.
As part of this task, the following information will be identified for each recommendation:
Preliminary identification of order -of -magnitude costs
o Use recent capital and operational costs in Marin County and neighboring counties
Potential funding sources
o Many are provided in the 2006 Canal Neighborhood CBTP which will be
updated/supplemented by our knowledge of new Federal legislation and local/regional
grant programs
Potential for effective and/or efficient implementation
o Lessons learned from the benchmarking assessment of the Canal Neighborhood CBTP and
relevant San Rafael reports (Task 3) will be applied to the new CBTP so that potential
solutions are those that are demonstrably implementable, and that identified barriers are
at least known and preferably mitigated through our proposals.
The draft presentation will outline a prioritized list of the gaps and associated improvements. Cost effective
transit improvements will be key to addressing gaps in the Canal Neighborhood, and Fehr & Peers will draw
upon technical expertise in this field with shuttles and other bus service, to determine the best possible
transit solutions to bridge the gaps identified. We will collaborate with Marin Transit and Golden Gate
Transit to explore the feasibility, cost, and timing of potential transit solutions. Fehr & Peers will also draw
upon our wide-ranging expertise in active transportation (which includes access to the bicycle & pedestrian
technical discipline group) to propose inclusive, effective, and context -sensitive active transportation
solutions.
A 11
ATTACHMENT A
WORK PLAN
TAC and Stakeholder Committee Meetings
At these meetings, the consultant team will present a preliminary list of prioritized recommendations. To
help facilitate the ranking discussion, the consultant will prepare a preliminary scoring system, whereby
each gap will have an associated rating on a three-point Likert scale relating to: cost-effectiveness, number
of people impacted, effectiveness of potential solutions, and most importantly the level of community
support. The consultant team will also predetermine the consistency of potential solutions with relevant
planning and policy documents.
Deliverable #5A Presentation summarizing transportation gaps and potential solutions identified
during the first phase of outreach, including initial technical analysis on range of
solutions and initial prioritization of potential solutions
Deliverable #5113 Preparation and facilitation of TAC Meeting #2, summary notes
Deliverable #5C Preparation and facilitation of Stakeholder Committee Meeting #2, summary notes
TASK 6: DRAFT COMMUNITY-BASED TRANSPORTATION PLAN
Fehr & Peers will assemble the task -level technical and outreach reports into a draft action plan. As part of
this task, we will work with the TAC to develop an Implementation Plan, which will include an initial
prioritized program of transportation improvements matched with potential funding streams. The program
will categorize projects that can be implemented in the next 6 months (quickbuild), <2 years, 2-5 years, 5-
10 years, and long-range/visionary. Key elements of the Draft Plan and Implementation Plan will be
presented to key stakeholders and the general public for feedback in an Open House format. Our budget
assumes one round of revisions to the Draft Plan and PowerPoint based on one set of consolidated
comments.
Fehr & Peers will meet with the TAC to review the feedback from the Open House and comments on the
Draft CBTP. The Stakeholder Committee will then convene to review the final direction from the TAC and
provide final comments on the CBTP.
Deliverable #6A Draft Community -Based Transportation Plan and PowerPoint presentation
Deliverable #613 Preparation, facilitation and summary from TAC Meeting #3
Deliverable #6C Preparation, facilitation and summary from Stakeholder Committee Meeting #3
TASK 7: PREPARE AND PRESENT FINAL COMMUNITY-BASED TRANSPORTATION PLAN
In this final task, Fehr & Peers will prepare the final plan for presentation to the San Rafael City Council. We
will work with members of the Stakeholder Committee and participants from the outreach process to
develop presentation materials and will attend these final meetings in a support role. We assume one round
of revisions to these materials based on a set of consolidated comments.
Deliverable #7A Final Community -Based Transportation Plan and PowerPoint presentation
Deliverable #76 Attendance and Presentation at the San Rafael City Council meeting
RAP.
1
' 2
s
/ryVVITH Pah
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Iman Kayani for LD Extension: 3352
Contractor Name: Transportation Authority of Marin (TAM)
Contractor's Contact: Dave Chan Contact's Email: DChanlcr tam.ca.gov
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor _ pick here to
❑
enter a date.
b. Email contract (in Word) and attachments to City 9/13/2021
Attorney c/o Laraine.Gittens@cityofsanrafael.org
❑x IK_K
2
City Attorney
a. Review, revise, and comment on draft agreement 9/27/2021
® LG
and return to Project Manager 9/27/2021
❑X LG
b. Confirm insurance requirements, create Job on
(N/A)
PINS, send PINS insurance notice to contractor
3
Department Director
Approval of final agreement form to send to
,Ick or tap
❑
contractor
to enter a
date.
4
Project Manager
Forward three (3) originals of final agreement to
Click here to
❑
contractor for their signature
enter a daf-
5
Project Manager
When necessary, contractor -signed agreement
❑ N/A
agendized for City Council approval *
*City Council approval required for Professional Services
❑
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
..lick here to
Date of City Council approval
enter a date
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
All
agreement
MAg2021
8
City Attorney
Review and approve insurance in PINS , and bonds
g J
(for Public Works Contracts)
7 /a-�ZOZ1
9
City Manager/ Mayor
Agreement executed by City Council authorized
qJZ41q
official
10
City Clerk
Attest signatures, retains original agreement and
11.
forwards copies to Project Manager
/v