HomeMy WebLinkAboutPW Third Street Rehabilitation Project PPTFebruary 7, 2022
THIRD STREET REHABILITATION
CITY COUNCIL MEETING
Third Street Project
Project Limits
E STREETA STREETLINDAROC STREETB STREETD STREETLINCOLNSHAVERG STREETWEST STREETEAST STREETRehabilitation Project: TAM & local funds
Safety Project: Federal & local funds
3rd Street from just east of Union St to 2nd St
2nd Street from West St to Shaver St
Third Street Project
Staff is asking the City Council to:
1.Award the Construction Contract to the lowest responsive and responsible bidder:Ghilotti
Bros.Inc.
2.Approve and authorize an amendment to the professional services agreement with CSW to
perform construction support services.
3.Approve and authorize the execution of a reimbursement agreement with San Rafael
Sanitation District.
4.Approve and authorize the execution of a reimbursement agreement with Marin Municipal
Water District.
Tonight’s Objectives
Third Street Project
Prior TAM identifies Third Street as priority project
2017 City begins planning process
2017-2018 Community Meetings #1 
2017-2018 Community &Technical Working Group Meetings
June 2019 Feasibility Report Presented at City Council
Aug.2020 Bicycle and Pedestrian Committee Meeting
Sept.2020 Community Meeting #3
Nov.2020 Presentation to City Council for Update
Dec.2020 Bicycle and Pedestrian Committee Meeting
Feb.2021 Bicycle and Pedestrian Committee Meeting
Mar.2021 Community Meeting #4
May 2021 Presentation to City Council for TAM funding
Project History & Outreach
Third Street Project
1.Improve safety for all bicyclists and pedestrians
2.Repair pavement and drainage
3.Improve pedestrian crossings and repair
sidewalks
4.Upgrade traffic signals and provide safety lighting
5.Improve traffic flow for cars,transit,and
emergency service
6.Add street trees
7.Enhance access for designated Safe Routes to
Schools
8.Develop an economically viable project
Project Goals
Third Street Project
1.Provide bicycle and pedestrian access from Miracle mile to
Miramar:maximized public right of way to balance multiple needs
2.Complete a bicycle connection all the way to West End,even if
interim solution.
3.Maintain parking in residential zones:Revised initial Class 1 MUP
to Class IV bikeway +sidewalk to maintain parking.
4.Lindaro/Lootens Intersection:Exit Only versus closing (Part of
Third Street Safety Project)
5.Enhance accessibility and sidewalks:Raised intersections.
What we Heard
Third Street Project
Raised Intersections
A Street
B Street
C Street
D Street
Third Street Project
Second Street Bicycle Facility
West StreetEast StreetIda StreetG StreetMiramar StreetHayes StreetShaver StreetMarquardAve
Third Street Project
2 nd & East St Bicycle Facility
Third Street Project
Second Street Bicycle Facility
Third Street Project
Median Trees
Proposed Large Diameter Trees
Lane Merge if tree remains
Parking Removed
Non-standard bike path
Third Street Project
Third Street Trees
Third Street Project
B Street Conversion Project
Benefits of converting B Street
•This is the last North-South one way street downtown
•Less around the block circulation
•Better access and visibility to store fronts
•Consistency and better wayfinding
•Improved parking experience
•More outreach to follow before any implementation!
Third Street Project
Construction Process
1.About 18 months of construction
2.General sequence of work
•Utilities –MMWD,sewer district
•Retaining wall and median shift
•PG&E relocation and undergrounding on Second St
•Sidewalk and curb ramps
•Traffic signals
•Paving and striping
•Street trees
3.Driveways will be closed for periods of up to 4 hours
Both the City and contractor will
outreach to residents and
businesses during construction
to provide advance notice of
construction activities.
Third Street Project
Construction Hours
1.Lane closures during off peak periods
•East bound (Second Street):9 am to 6 pm
•West bound :6 am to 3 pm
•Miramar Sewer work:full closure 7am to 6pm
2.Night work:8pm to 6am
•Utility work east of Lincoln
•Work requiring more than one lane closure
•Paving and striping
3.Miramar Sewer work:full closure 7am to 6pm
Sign up for weekly emails on the website
www.cityofsanrafael.org/third-st-rehab/
Third Street Project
Project Funding
Funding Source Funding Amount
Transportation Authority of Marin (Measure A and AA)$10,485,806
San Rafael Sanitation District $4,779,700
Marin Municipal Water District $3,715,328
Gas Tax Fund #206-RMRA $1,524,166
Traffic Mitigation Fund #246 $290,000
Technology Fund $122,000
Total $20,917,000
Third Street Project
Additional Information
April Miller, P.E.
Assistant Director
April.Miller@cityofsanrafael.org
415-485-3409
www.cityofsanrafael.org/third-st-rehab/
Third Street Project
Thank you