HomeMy WebLinkAboutPW Master Services Agreement; Task Order No. 63 55 Brookdale AvenueCity of San Rafael
MASTER CONSULTANT SERVICES AGREEMENT
DATED MARCH 8, 2021
WITH SNG & ASSOCIATES, INC.
TASK ORDER NO. 63
Land Development Discipline
Project title: 55 Brookdale Ave (SNG-SR014)
Contract Amount: $6,608.00
THIS TASK ORDER is entered into on A 202gbetween the City of San
Rafael, a municipal corporation ("City"), and SNG & ASSOCIATES, INC., ("Consultant").
RECITALS
A. The City and Consultant have entered into a Master Consultant Services Agreement
("Agreement") dated March 8, 2021 under which Consultant has agreed to perform certain professional
consulting services for the City; and
B. Pursuant to the terms of the Agreement, the City wishes Consultant to perform certain
tasks as set forth in this Task Order, which constitute the Project;
NOW, THEREFORE, City and Consultant agree as follows:
AGREEMENT
1. Scope of services. Consultant shall provide any and all of the services set forth in Exhibit A of
this Task Order, titled 55 BROOKDALE AVENUE — 10 UNIT APARTMENT BUILDING (ED21-071),
as directed by the City.
Nanda Gottiparthy shall be the Project Manager for Consultant for this Task Order. Additional
professional services may be performed by other Consultant staff with prior notice and approval by City.
a. City's duties. The City will:
(1) Determine the scope of services, as set forth in Exhibit A.
(2) Make available the project plans and specifications and other City data related to the
project, including full information as to the City's requirements.
(3) Designate Matthew Pepin as the person at the City responsible for monitoring
performance under this Task Order.
b.Consultant duties. The Consultant will:
(1) Provide and perform tasks identified in Exhibit A, Scope of Services.
(2) Provide miscellaneous consulting and other services related to the Project and not
stipulated elsewhere in this Task Order, when requested by the City in writing. A Task
Order Amendment is required if these additional services cannot be performed within the
Rev. May 2021
City of San Rafael Master Consultant Services Agreement
Task Order
Task Order budget.
2. Date of completion, Work hours estimate,• Cost estimate and budget, Fee schedule.
With regard to each project given to Consultant that is subject to this Task Order, the time of completion,
work hours estimate, cost estimate and budget and fee schedule are set forth in Exhibit A to this Task Order.
3. Authorization to roceed.
The City will give Consultant authorization to proceed with the work specified in this Task Order only after
Consultant submits updated insurance certificates and endorsements, in accordance with Section 10 of the
Agreement.
4. Master Agreement terms; Conflicts.
Except as expressly otherwise provided herein, all terms of the Agreement shall apply to Consultant in the
performance of work pursuant to this Task Order. If there is a conflict between this Task Order and the
Agreement, this Task Order shall control.
4. Amendment of Task Order; Conflicts.
Except as provided in Section 1(b)(2) above, this Task Order may not be modified except by an Amended
Task Order executed and approved in the same manner as the Task Order.
Signatures. The parties have executed this Task Order, as of the date first written above.
2
Rev. May 2021
City of San Rafael Master Consultant Services Agreement
Task Order
CITY OF SAN RAFAEL
By:
Public Works Director
Contents approved:
By:
April Iiller, Assistant Public Works Director/City
Engineer
Reviewed By
By:
&-Aobert F. Epstein, City Attorney
CONSULTANT
By:
Name: Nanda Gottiparthy
Title: President
(if Consultant is a corporation, add signature
of second corporate officer)
By:
Name: Nanda Gottiparthy
Title: Secretary
Exhibits:
A Scope of work titled 55 BROOKDALE AVENUE — 10 UNIT APARTMENT
BUILDING (ED21-071), time of completion, work hours estimate, cost estimate and
budget, and fee schedule (Consultant's current hourly rate)
3
Rev. May 2021
1 � '
TASK ORDER
55 BROOKDALE AVENUE —10 UNIT APARTMENT BUILDING (ED21-071)
(Task Order Reference Number: SNG SR 014)
SNG & Associates, Inc. (SNG) presents the following Task Order (TO) Scope of Services as requested
by the City of San Rafael Department of Public Works (DPW) for providing staff support and review of
the development application for the 55 Brookdale Avenue - 10 unit apartment Building Project (ED21-
071). Services under this Task Order will be provided pursuant to the Master Consultant Services
Agreement dated March 8, 2021.
Scope of Services:
The scope of services shall include review and staff support as needed for submittal review, preparation of
draft comment memo, coordination of traffic and geotech comments, and prepare final comment
memo. We will also conduct a site visit and review GIS for utilities/easements. The services shall include
attendance at meetings with developers, staff, engineers and others as requested by the City.
Estimated Fees:
SNG will provide services included in the above Scope of Work to meet mutually agreed upon deadlines
for every submittal. The Estimated Fee to perform the Scope of Work is $6,608.00, which will be billed
on a time -and -expense basis in accordance with our 2021 Billing Rate Schedule (Attachment A).
The estimated fees are based on the preliminary documents submitted by the applicant and information
available. The estimate reflects a reasonable level of effort that can be expected for projects similar in
nature and scope to this application, and assumes 2-3 submittals for review. Requests for additional
fees may be submitted if additional reviews are required or the project extends beyond normal
approval timelines.
NMWO
Tasks
Associate
Project
Manager
Principal
Estimated Fee
S150410ur
S18811011r
S2151hour
1. Review Plans Associated Documents
4
5
$1,540.00
and Research Project
2. Project- Specific Meeting
Attendance, Preparation, Project Plan
4
10
2
$2,910.00
Filing and DPW Communication.
3. Prepare Comment Memo
4
6
2
$2,158.00
TOTAL
$1,800.00
$3,948.00
$860.00
$6,608.00
5776 Stoneridge Mall Road, Suite 365, Pleasanton, CA 94588
Phone: 925-251-0100 Fax: 925-242-5894
ATTACHMENT A
BILLING RATES SCHEDULE
Position Hourly Rate
Principal Engineer
215.00
Project Manager
188.00
Senior Engineer
178.00
Construction Manager
150.00
Associate Engineer II
150.00
Associate Engineer 1
135.00
Assistant Engineer
131.00
Senior Engineering Inspector
128.00
Engineering Technician/CAD Drafting
103.00
Engineering Inspector
113.00
Clerical/ Admin Support
81.00
Licensed Land Surveyor
170.00
Note: Sub -consultants and outside services billed at 110% of actual cost. Rates valid through
December 31, 2021. Rates will be adjusted annually every January 15twith maximum annual
increase in rates of 3%.
SNG & Associates, Inc.
5776 Stoneridge Mall Road, Suite 365, Pleasanton, CA 94588
Phone: 925-251-0100 Fax: 925-242-5894
Page 2
7
RAP
s �
0
1
frI WITH p`rl'S
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Ashley Dohrmann for MP
Contractor Name: SNG & Associates, Inc.
Contractor's Contact: Nanda Gottiparthy
❑ FPPC: Check if Contractor/Consultant must file Form 700
Extension: 3352
Contact's Email: nanda.gottiparthy@sngassociates.com
Step
RESPONSIBLE
DESCRIPTION
I
COMPLETED
REVIEWER
DEPARTMENT
a. Email PINS Introductory Notice to Contractor
DATE
Check/Initial
1
Project Manager
Click here to
❑
enter a clate.
b. Email contract (in Word) and attachments to City
Click here to
Attorney c/o Laraine.Gittens@cityofsanrafael.org
enter a date.
NAD
2
City Attorney
a. Review, revise, and comment on draft agreement
12/19/2021
❑X LG
and return to Project Manager
12/19/2021
❑X LG
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
12/20/2021
3
Department Director
Approval of final agreement form to send to
❑x BG
Project Manager
contractor
Forward three (3) originals of final agreement to
4
12/20/2021
jx]
contractor for their signature
5
Project Manager
When necessary, contractor -signed agreement
❑X N/A
agendized for City Council approval *
*City Council approval required for Professional Services
0
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
Click here to
4 PRINT
Project Manager
Date of City Council approval
enter a date.
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Forward signed original agreements to City
1/5/22
AD
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
agreement
G
8
City Attorney
_
Review and approve insurance in PINS , and bonds
0
_
(for Public Works Contracts)
9
City Manager/ Mayor
Agreement executed by City Council authorized
official
10
City Clerk
Attest signatures, retains original agreement and
��
All
forwards copies to Project Manager