Electrifying Marin’s Buildings: A Countywide Approach –August 1, 2022
Overview
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
Tonight’s Presentation:
1.What we’re required to do for the Grand Jury
2.What Green Building Reach Codes are all about
3.What’s been taking place to date
4.Timeline for what is next
5.Grand Jury Response
What is required by the Grand Jury now
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
This is about responding to the
Grand Jury
This is not about determining
what to do with our Green
Building Reach Codes
What Green Building Reach Codes are all about
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
•Three year “Green Building”
code cycle
•Intention to reduce GHG’s,
energy, water in built
environment
•State provides optional
“reach” codes
What Green Building Reach Codes are all about
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
•Consideration of reach codes
in our Climate Change Action
Plan
•County typically leads a
countywide effort
•This year w/San Rafael, San
Anselmo, MCE Clean Energy
What Green Building Reach Codes are all about
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
1. New Construction
All-Electric Requirement
•Considers prohibiting the use of
natural gas for new construction
•Detached ADU’s
•Potential exceptions
2. Remodels
Energy Efficiency Requirements
•Flex Measures Scoring Tool
•Tier 1 and Tier 2
•Other options
What has been happening to date
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
Countywide project to develop model reach codes
Goals:
What has been happening to date
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
Reach code project
engagements
•Key stakeholder convenings
•Public engagements
•City Subcommittee
•City analysis
•Presentations (MMA, etc.)
What has been happening to date
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
City Analysis
1.GREENHOUSE GAS REDUCTIONS
2.COST EFFECTIVENESS
3.RESILIENCY
Next steps and timeline for reach code process
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
August Complete analysis
Council Subcommittee Review
Draft codes
September Council study session
October Recommendations to Council
Grand Jury Response
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
Findings
F1 –GHG’s in Buildings
F2 –Reducing gas is necessary
F3 –Gas causes health risks
F4 –Will require coordination
F5 –Equity
F6 –Requires mandatory +
AGREE
Grand Jury Response
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
Recommendations
R1 –Electrification for New
Construction
R2 –Flex measures tool for
Renovations
R3 –Countywide
electrification plan
REQUIRES FURTHER ANALYSIS
Questions and Council Action
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
OPTIONS:
The City Council has the following options to consider relating to this item:
1.Adopt the resolution as presented.
2.Adopt the resolution as amended.
3.Direct staff to return with additional information
RECOMMENDED ACTION:
Adopt a resolution approving the City of San Rafael’s response to the Marin County Civil
Grand Jury’s report entitled, “Electrifying Marin’s Buildings: A Countywide Approach”
Recommendation 3 Response Revision
Grand Jury Response: Electrifying Marin’s Buildings
August 1, 2022
OPTION: Replace 2nd paragraph with the following:
“More analysis will be required to determine the most effective and
efficient route to take. However, should other jurisdictions decide to
participate, the City would be willing to help convene and coordinate
the development of Countywide Building Electrification or
implementation action plan.”