HomeMy WebLinkAboutPW Master Services Agreement; Task Order No. 87 HSIP & SS4A Grant Application AssistanceCity of San Rafael
MASTER CONSULTANT SERVICES AGREEMENT
DATED MAY 20, 2022
WITH ADVANCED MOBILITY GROUP (AMG)
TASK ORDER NO. 87
Transportation Discipline
Project title: HSIP and SS4A Grant Application Assistance
Contract Amount: $15,800
THIS TASK ORDER is entered into on Odo %►fir , 202g- between the City of San
Rafael, a municipal corporation ("City"), and Advanced Mobility Group (AMG), ("Consultant").
RECITALS
A. The City and Consultant have entered into a Master Consultant Services Agreement
("Agreement") dated May 20, 2022 under which Consultant has agreed to perform certain professional
consulting services for the City; and
B. Pursuant to the terms of the Agreement, the City wishes Consultant to perform certain
tasks as set forth in this Task Order, which constitute the Project;
NOW, THEREFORE, City and Consultant agree as follows:
AGREEMENT
1. Scope of services. Consultant shall provide any and all of the services set forth in Exhibit A of
this Task Order, dated July 25, 2022, as directed by the City.
Joy Bhattacharya shall be the Project Manager for Consultant for this Task Order. Additional
professional services may be performed by other Consultant staff with prior notice and approval by City.
a. City's duties. The City will:
(1) Determine the scope of services, as set forth in Exhibit A.
(2) Make available the project plans and specifications and other City data related to the
project, including full information as to the City's requirements.
(3) Designate Rafat Raie as the person at the City responsible for monitoring performance
under this Task Order.
b. Consultant duties. The Consultant will:
(1) Provide and perform tasks identified in Exhibit A, Scope of Services.
(2) Provide miscellaneous consulting and other services related to the Project and not
stipulated elsewhere in this Task Order, when requested by the City in writing. A Task
Order Amendment is required if these additional services cannot be performed within the
Task Order budget.
Rev. May 2021
City of San Rafael Master Consultant Services Agreement
Task Order
2. Date of completion; Work hours estimate; Cost estimate and budget, Fee schedule.
With regard to each project given to Consultant that is subject to this Task Order, the time of completion,
work hours estimate, cost estimate and budget and fee schedule are set forth in Exhibit A to this Task Order.
Authorization to proceed.
The City will give Consultant authorization to proceed with the work specified in this Task Order only after
Consultant submits updated insurance certificates and endorsements, in accordance with Section 10 of the
Agreement.
4. Master Agreement terms, Conflicts.
Except as expressly otherwise provided herein, all terms of the Agreement shall apply to Consultant in the
performance of work pursuant to this Task Order. If there is a conflict between this Task Order and the
Agreement, this Task Order shall control.
4. Amendment of Task Order; Conflicts.
Except as provided in Section 1(b)(2) above, this Task Order may not be modified except by an Amended
Task Order executed and approved in the same manner as the Task Order.
Signatures. The parties have executed this Task Order, as of the date first written above.
2
Rev. May 2021
City of San Rafael Master Consultant Services Agreement
Task Order
CITY OF N L
By:
J m Sch z, City anag r
Contents approved:
:
April Miller, Public Works Director
Reviewed B
By:
q& -
Rob . Epstein, Ci ttorney
CONSULTANT
By: Jf
r
f
Name: Joy Bhattacharya
Title: Vice President
(if Consultant is a corporation, add signature
of second corporate officer)
Name: Beth Clement
Title: Corporate Board Secretary
Exhibits:
A Scope of work dated July 25, 2022, time of completion, work hours estimate, cost
estimate and budget, and fee schedule (Consultant's current hourly rate)
3
Rev. May 2021
fT
Exhibit AADVANCED
AMG MOBILITY
MOBILITY
GROUP
Date: July 25, 2022
Rafat Raie
Rafat.raie@cityofsanrafael.org
Subject: Proposal for developing Grant Application Packages for Second Street Safety and
Technology Improvements Project
Dear Rafat
This letter summarizes the professional services that Advanced Mobility Group (AMG) will
provide in a timely and efficient manner to assist the City of San Rafael with the grant proposals
for the Second Street Safety and Technology Improvements Project.
Project Scope
AMG's scope of work specifically includes:
1. Kick-off meeting to discuss and finalize
a. Project components
b. Countermeasures
c. Project's eligibility for HSIP Cycle 11 and Safe Streets and Roads for All (SS4A)
Grant Program
2. Concept drawings for the project
3. Planning level cost estimates and schedule
4. Collision analysis to support the grant proposal
5. Prepare Grant Proposal Forms for HSIP Cycle 11 and Safe Streets and Roads for All
(SS4A)
6. Prepare Exhibits required for grant proposal (e.g., BCR calculations for HSIP, maps, etc.)
7. Letter of Support templates
8. Weekly coordination meetings with City as necessary.
The assumptions that went into our scope of work and costs associated with the grant proposal
development are:
1. To apply for the local HSIP funds, an agency must have completed their Local Roadway
Safety Plan (LRSP) or an equivalent of the LRSP. It is assumed that the 2018 Marin
County Travel Safety Plan is qualified to fulfill that requirement.
2. SS4A Implementation Grants are available to implement strategies or projects that are
consistent with an existing Action Plan. AMG assumes that the 2018 Marin County
Travel Safety Plan is qualified as an existing action plan and that the Project's strategies
will be consistent with the Plan.
3. The city will formally request letters of support based on the templates provided by
AMG.
4. No new traffic data collection is required.
Advanced Mobility Group 1 3003 Oak Rd. Suite 100, Walnut Creek, Ca. 94597 1 P: 415.688.002
www.amobility.com
ADVANCE
ANUG G ROUP
5. AMG will not conduct a Level of Service analysis or any other technical analysis to
validate the project.
Budget
The estimated lump sum cost for the HSIP Cycle 11 Grant Proposal development is $9,800 and
SS4A for the same project is $6,000.
Qualifications and Availability
AMG has successfully helped our clients to secure more than $85 million in state and federal
funding, through various competitive grant programs including HSIP to develop and deliver
critical transportation projects. Some examples include $10M-HSIP Cycle 8, City of Oakland;
$1.6M-HSIP Cycle 9, City of Rancho Cordova, and $1.5M-HSIP Cycle 10, City of Concord. Other
successful grants include CMAQ, ATCMTD, ADS, IDEA, SRTS, Office of Traffic Safety, Section 130,
State and Community Highway Safety Grant Program (Section 402), etc. We are currently
assisting other agencies on both these Grant Proposals and are familiar with the grant
requirements and deadlines and there is no learning curve there. This will help our staff meet
the grant deadlines.
Staff — Vasavi Pannala, who has extensive experience in preparing successful grant
applications, will be the Project Manager for this project. She will be supported by me,
Christopher Thnay, and Chris Higbee.
Best Regards,
Advanced Mobility Group (AMG),
Joy Bhattacharya, Vice President
RAP
7�
S F
Ty IVITH P rr
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Ashley Dohrmann (for Rafat) Extension: 3352
Contractor Name: Advanced Mobility Group (AMG)
Contractor's Contact: Joy Bhattacharya Contact's Email: joy@amobility.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor
Click here to
❑
enter a date.
b. Email contract (in Word) and attachments to City
7/26/2022
Attorney c/o Laraine.Gittens@cityofsanrafael.org
NAD
2 City Attorney
a. Review, revise, and comment on draft agreement
8/24/2022
and return to Project Manager
8/24/2022
❑X GC
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
❑X GC
3 Department Director
8/25/2022
Approval of final agreement form to send to
❑X AM
contractor
4 Project Manager
Forward three (3) originals of final agreement to
8/30/2022
contractor for their signature
5
Project Manager
When necessary, contractor -signed agreement
❑X N/A
agendized for City Council approval *
*City Council approval required for Professional Services
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
Click here to
Date of City Council approval
enter a date.
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
9/20/2022
AD
Attorney with printed copy of this routing form
7 City Attorney
Review and approve hard copy of signed
q��'7iZ
agreement
VL
8 City Attorney
Review and approve insurance in PINS, and bonds
n
`�
(for Public Works Contracts)
��� 22
%
-007
9 City Manager/ Mayor Agreement executed by City Council authorized
s %
official
10
City Clerk
Attest signatures, retains original agreement and
l�
forwards copies to Project Manager