HomeMy WebLinkAboutPW San Quentin Pump Station Reconstruction Project; AlphaCM; First AmendmentFIRST AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT WITH
ALPHACM INC. FOR THE SAN QUENTIN PUMP STATION RECONSTRUCTION
PROJECT
THIS FIRST AMENDMENT to the Professional Services Agreement by and between
the CITY OF SAN RAFAEL (hereinafter "CITY"), and AlphaCM Inc. (hereinafter
"CONSULTANT"), is made and entered into as of
RECITALS
Feb 1, 2024
WHEREAS, the CITY and CONSULTANT entered into a Professional Services
Agreement dated December 8, 2022 to perform professional services in connection with CITY'S
San Quentin Pump Station Reconstruction project, for an amount not to exceed $515,715.88 (the
"Agreement"); and
WHEREAS, CITY requires additional professional services from the CONSULTANT,
and the CONSULTANT is willing to provide such services.
AMENDMENT TO AGREEMENT
NOW, THEREFORE, the parties hereby agree to amend the Agreement as follows:
Article II of the Agreement, entitled "DUTIES OF CONSULTANT" is hereby
amended to include the additional services set forth in CONSULTANT's proposal
dated December 18th, 2023, attached to this First Amendment as Exhibit A and
incorporated herein by reference.
2. Article IV of the Agreement, entitled "COMPENSATION" is hereby amended to
include additional compensation payable to CONSULTANT for the services
described in Exhibit A to this First Amendment, on a time and materials basis in
accordance with the Exhibit A, in a not -to -exceed amount of $267,212, and to
change the total not -to -exceed amount under the Agreement to $782,927.88.
3. Except as specifically amended herein, all of the other provisions, terms and
obligations of the Agreement between the parties shall remain valid and shall be in
full force.
IN WITNESS WHEREOF, the parties have executed this First Amendment on the day,
month, and year first above written.
CITY OF SAN RAFAEL
G'istine Ali ic-h (Feb 1, 2024 11:46 PST)
CRISTINE ALILOVICH, City Manager
ATTEST:
Srenna AW,-Mi (ford
Brenna Nui mi (For) (Feb 1, 2024 11:54 PST)
LINDSAY LARA, City Clerk
APPROVED AS TO FORM:
ROBERT F. EPSTEIN, City Attorney
2
CONSULTANT
EVIa4 A. Zaille �
By: Brian A. Dan(ey (Jan 28, 2024 11 PST)
Name: Brian A. Danley
Title: Vice President
[If Contractor is a corporation, second
corporate officer signature required]
By:
Name: David Latona
Title: President
Exhibit A
Alpha
CM
December 18th, 2023
City of San Rafael
San Quentin Pump Station Reconstruction Project
Project No. 11334, File No. 08.06.69
Request for Amendment No. 001
Staffing
I Billing Rate
Total Hours
Total Price
Project Manager
IRE/Inspector
$ 210
20
1088
$
-
$ 204
$
221,952
Scheduler
$ 196
80I
$
15,680
Subtotal
1188
$
237,632
Other Direct Costs (ODCs)
Billing Rate
Total Months
Total Price
Vehicle
RE/Inspector
1 $ 1,800
1 6
$
10,800
Cell/Data/Computer
RE/Inspector
1 $ 130T
6
$
780
Subsistence
RE/Inspector
1 $ 3,000
6
$
18,000
Subtotal
18
$
29,580
Grand Total
=
267,212
Assumptions
1. Suspension of work between January 21, 2024 thru June 23,2024.
2. Contract completion date of October 12, 2024 (based on TBC's latest unapproved
schedule).
3. 98 working days at half time through the suspension period at half time (392 hours).
4. 77 working days at full time June 24,2024 thru October 12, 2024 (616 hours).
5. 80 hours for close out.
6. Level of effort is an estimate only.
7. Each individual cost item is a guide only; total CM cost shall take precedent.
8. With the exception of vehicle/ cell/ data/computer, hourly rates include all direct and
indirect overhead normally associated with this type of work.
9. Level of Effort based on current project information as of 12/18/2023.
10. Alpha CM reserves the right to move budget between tasks and staff.
First Amendment - AlphaCM - San Quentin
Pump Station Reconstruction Project
Final Audit Report 2024-01-29
Created: 2024-01-26
By: Jonathan Schellin Qonathans@cityofsanrafael.org)
Status: Signed
Transaction ID: CBJCHBCAABAAx51AQegkdOywoRhTh4z1tJ6_k4imOgSh
"First Amendment - AlphaCM - San Quentin Pump Station Reco
nstruction Project" History
Document created by Jonathan Schellin Qonathans@cityofsanrafael.org)
2024-01-26 - 8:53:58 PM GMT
L--"y Document emailed to bdanley@alphacminc.com for signature
2024-01-26 - 8:55:25 PM GMT
Email viewed by bdanley@alphacminc.com
2024-01-28 - 7:51:51 PM GMT
4Q Signer bdanley@alphacminc.com entered name at signing as Brian A. Danley
2024-01-28 - 7:52:38 PM GMT
do Document e-signed by Brian A. Danley (bdanley@alphacminc.com)
Signature Date: 2024-01-28 - 7:52:40 PM GMT - Time Source: server
7-4 Document emailed to David Latona (dlatona@alphacminc.com) for signature
2024-01-28 - 7:52:41 PM GMT
Email viewed by David Latona (dlatona@alphacminc.com)
2024-01-29 - 5:18:42 PM GMT
60 Document e-signed by David Latona (dlatona@alphacminc.com)
Signature Date: 2024-01-29 - 5:19:29 PM GMT - Time Source: server
Agreement completed.
2024-01-29 - 5:19:29 PM GMT
Q Adobe Acrobat Sign
SAN RAFAEL
THE CITY WITH A MISSION
Agenda Item No: 4.f
Meeting Date: January 16, 2024
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works
April Miller, Public Works Director +fi
I�
Prepared by: Theo Sanchez, Associate Civil Engineer City Manager Approval:
TOPIC: SAN QUENTIN PUMP STATION RECONSTRUCTION
SUBJECT: AMENDMENTS TO PROFESSIONAL SERVICE AGREEMENTS WITH ALPHACM,
INC., CSW/ST-STROEH ENGINEERING GROUP, AND AUTHORIZATION OF SUPPLEMENTAL
BUDGET APPROPRIATION
RECOMMENDATION:
Staff recommends that the City Council authorize the three actions described below
AUTHORIZE THE CITY MANAGER TO EXECUTE A FIRST AMENDMENT TO THE
PROFESSIONAL SERVICES AGREEMENT WITH ALPHACM, INC. FOR ADDITIONAL
CONSTRUCTION MANAGEMENT, INSPECTION, AND TESTING SERVICES, IN THE
AMOUNT NOT TO EXCEED $267,212, FOR A TOTAL NOT -TO -EXCEED CONTRACT
AMOUNT OF $782,928.
• AUTHORIZE THE CITY MANAGER TO EXECUTE A FIRST AMENDMENT TO THE
PROFESSIONAL SERVICES AGREEMENT WITH CSW/STUBER-STROEH ENGINEERING
GROUP FOR ADDITIONAL CONSTRUCTION SUPPORT SERVICES IN THE AMOUNT NOT
TO EXCEED $19,313 FOR A TOTAL NOT -TO -EXCEED CONTRACT AMOUNT OF $523,880.
• AUTHORIZE SUPPLEMENTAL BUDGET APPROPRIATION OF $286,525 TO AUGMENT THE
EXISTING BUDGET FOR THE SAN QUENTIN PUMP STATION PROJECT WITHIN THE
STORMWATER FUND (FUND 205) VIA A TRANSFER FROM AVAILABLE GENERAL FUND
FUND BALANCE SET -ASIDE FOR PRIORITY CAPITAL PROJECTS.
BACKGROUND:
On October 17th, 2022, the City Council awarded a construction contract to Thompson Builders
Corporation, a professional services agreement to AlphaCM, Inc. for construction management,
inspections, and testing services, and a second amendment to the professional services agreement with
FOR CITY CLERK ONLY
Council Meeting: January 16, 2024
Disposition: Authorized the City Manager to Execute Amendments to Professional Service
Agreements with AlphaCM, Inc., CSW/St-Stroeh Engineering Group, and Authorized Supplemental
Budget Appropriation
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
CSW/Stuber-Stroeh Engineering Group, Inc. for the San Quentin Pump Station Reconstruction Project.
Construction began on April 3rd, 2023, and had a projected completion date around April 2024.
ANALYSIS:
Several delays have pushed the project end date back significantly, including supply chain issues that
currently anticipate the arrival of electrical components arriving in Summer 2024. Given this, project
completion is currently estimated for Fall 2024.
Due to the extended length of this project and unforeseen conditions that took more time to resolve, staff
recommend amendments to both the AlphaCM, Inc. and CSW/Stuber-Stroeh Engineering Group, Inc. to
ensure sufficient budget to work through the entirety of the construction duration.
FISCAL IMPACT:
The current FY 2023-24 budget includes appropriations totaling $8.0 million within the Stormwater Fund
(205) for the San Quentin Pump Station Project.
AlphaCM, Inc. has estimated that an additional $267,212 would be needed to ensure construction
management services are provided through Fall 2024. This would increase their total contract amount to
$782,928.
CSW/Stuber-Stroeh Engineering Group, Inc. has estimated that $19,313 would be needed to continue to
provide construction support services through Fall 2024. This would increase their total contract amount
to $523,880.
While funding to support the original contracts has been provided through existing appropriations, a
supplemental budget appropriation in the amount of $286,525 is required to cover both contract
amendments, as described. Funding to support this budget augmentation is available through General
Fund resources (fund balance) set -aside for high priority capital projects.
OPTIONS:
The City Council has the following options to consider on this matter:
1. Authorize the City Manager to enter into the agreement and allow supplemental budget
appropriations as recommended.
2. Do not authorize the City Manager to enter into the agreement nor allow supplemental budget
appropriations and provide further direction to staff.
RECOMMENDED ACTION:
Staff recommends that the City Council:
• Authorize the City Manager to execute a first amendment to the professional services agreement
with AlphaCM, inc. For additional construction management, inspection, and testing services, in
the amount not to exceed $267,212, for a total not -to -exceed contract amount of $782,928.
• Authorize the City Manager to execute a first amendment to the professional services agreement
with CSW/Stuber-Stroeh engineering group for additional construction support services in the
amount not to exceed $19,313 for a total not -to -exceed contract amount of $523,880.
• Authorize supplemental budget appropriation of $286,525 to augment the existing budget for the
San Quentin Pump Station project within the stormwater fund (fund 205) via a transfer from
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 3
available General Fund fund balance set -aside for priority capital projects to support these
increased project costs.
ATTACHMENTS:
N/A
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Jonathan Schellin (for Theo Sanchez) Extension: Teams
Contractor Name: Alpha CM
Contractor's Contact: Brian Danley Contact's Email: bdanley@alphacminc.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1
Project Manager a. Email PINS Introductory Notice to Contractor
Click here to
❑
enter a date.
b. Email contract (in Word) and attachments to City
1/25/2024
X❑JS
Attorney c/o Laraine.Gittens@cityofsanrafael.org
2
City Attorney
a. Review, revise, and comment on draft agreement
1/25/2024
and return to Project Manager
1/25/2024
❑X NT
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
® NT
3
Department Director
Approval of final agreement form to send to
1/25/2024
® AM
contractor
5
Project Manager
When necessary, contractor -signed agreement
❑ N/A
agendized for City Council approval *
*City Council approval required for Professional Services
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
1/16/2024
Date of City Council approval
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
agreement
8
City Attorney
Review and approve insurance in PINS , and bonds
(for Public Works Contracts)
9
City Manager / Mayor
Agreement executed by City Council authorized
official
Attest signatures, retains original agreement and
10
City Clerk
forwards copies to Project Manager
Alpha CM 1st Amendment San Quentin Pump
Station
Final Audit Report 2024-02-01
Created: 2024-01-29
By: Jonathan Schellin Oonathans@cityofsanrafael.org)
Status: Signed
Transaction ID: CBJCHBCAABAAwoumNbCfTb1Og5sQKweBd67ojarxiOgW
"Alpha CM 1 st Amendment San Quentin Pump Station" History
Document created by Jonathan Schellin Qonathans@cityofsanrafael.org)
2024-01-29-11:30:29 PM GMT
7-4 Document emailed to Laraine Gittens (laraine.gittens@cityofsanrafael.org) for approval
2024-01-29-11:32:20 PM GMT
Email viewed by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2024-01-30 - 5:31:43 PM GMT
GS© Document approved by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
Approval Date: 2024-01-30 - 5:32:22 PM GMT - Time Source: server
C'► Document emailed to Genevieve Coyle (genevieve.coyle@cityofsanrafael.org) for signature
2024-01-30 - 5:32:23 PM GMT
Email viewed by Genevieve Coyle (genevieve.coyle@cityofsanrafael.org)
2024-01-30 - 8:05:10 PM GMT
FSo Document e-signed by Genevieve Coyle (genevieve.coyle@cityofsanrafael.org)
Signature Date: 2024-01-30 - 8:06:34 PM GMT - Time Source: server
C'y Document emailed to city.clerk@cityofsanrafael.org for approval
2024-01-30 - 8:06:39 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2024-01-30 - 9:27:57 PM GMT
6o Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi
2024-01-30 - 9:28:08 PM GMT
J�R SAN RAFAEL Adobe
Acrobat Sign
6o Document approved by Brenna Nurmi(city.clerk@cityofsanrafael.org)
Approval Date: 2024-01-30 - 9:28:10 PM GMT - Time Source: server
'► Document emailed to cristine.alilovich@cityofsanrafael.org for signature
2024-01-30 - 9:28:11 PM GMT
Email viewed by cristine.alilovich@cityofsanrafael.org
2024-02-01 - 7:45:44 PM GMT
bo Signer cristine.alilovich@cityofsanrafael.org entered name at signing as Cristine Alilovich
2024-02-01 - 7:46:25 PM GMT
bo Document e-signed by Cristine Alilovich (cristine.alilovich@cityofsanrafael.org)
Signature Date: 2024-02-01 - 7:46:27 PM GMT - Time Source: server
17� Document emailed to city.clerk@cityofsanrafael.org for signature
2024-02-01 - 7:46:28 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2024-02-01 - 7:54:38 PM GMT
bo Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi (for)
2024-02-01 - 7:54:53 PM GMT
i bo Document e-signed by Brenna Nurmi (for)(city.clerk@cityofsanrafael.org)
Signature Date: 2024-02-01 - 7:54:55 PM GMT - Time Source: server
Agreement completed.
2024-02-01 - 7:54:55 PM GMT