HomeMy WebLinkAboutPW First Amendment to the Professional Services Agreement with Kimley-Horn and Associates, Inc. for Final Design of the Grand Avenue Cycle Track Project____________________________________________________________________________________
FOR CITY CLERK ONLY
Council Meeting: April 15, 2024
Disposition: Authorized the City Manager to Negotiate and Enter into a First Amendment to the
Professional Services Agreement with Kimley-Horn & Associates, Inc. for Engineering Design
Services in an Additional Amount of $86,150, Increasing the Total Not to Exceed Amount of the
Agreement to $161,040
Agenda Item No: 4.f
Meeting Date: April 15, 2024
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works
Prepared by: Eugelyn Lopez, Junior Engineer
April Miller, Public Works Director
City Manager Approval: __________
TOPIC: FIRST AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT
WITH KIMLEY-HORN AND ASSOCIATES, INC. FOR FINAL DESIGN OF THE
GRAND AVENUE CYCLE TRACK PROJECT
SUBJECT: AUTHORIZE THE CITY MANAGER TO NEGOTIATE AND ENTER INTO A
FIRST AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT
WITH KIMLEY-HORN & ASSOCIATES, INC. FOR ENGINEERING DESIGN
SERVICES ASSOCIATED WITH THE GRAND AVENUE CYCLE TRACK
PROJECT, IN AN ADDITIONAL AMOUNT OF $86,150, INCREASING THE
TOTAL NOT TO EXCEED AMOUNT OF THE AGREEMENT TO $161,040.
RECOMMENDATION:
Authorize the City Manager to negotiate and enter into a first amendment to the Professional
Services Agreement with Kimley-Horn & Associates, Inc. for engineering design services in an
additional amount of $86,150, increasing the total not-to-exceed amount of the agreement to
$161,040.
BACKGROUND:
The Grand Avenue cycle track project will install a two-way, protected Class IV, path for cyclists
and pedestrians along the east side of Grand Ave, between 2nd and 4th Street. On September
21, 2022, the City Manager awarded a professional services agreement to Kimley-Horn &
Associates, Inc. in the amount of $74,890 to prepare final design and construction ready
documents for a new two-way cycle track along the east side of Grand Ave between 2nd and 4th
Street.
ANALYSIS:
Kimley-Horn is the civil design consultant for the Grand Avenue Cycle Track Project and has
prepared a plan for the two-way cycle track between 2nd and 4th Streets along Grand Avenue.
This project requires additional consulting services for two additional scopes of work by the
consultant: (1) additional design work including pedestrian streetlighting design and (2) additional
final construction document services.
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
FISCAL IMPACT: The additional consultant fee of $86,150 will be paid from the Gas Tax Fund
(Fund #206). Funding to support this contract amendment is available within existing FY 2023-
24 budget appropriations under account 206-44-21001-9270.
OPTIONS: The City Council has the following options to consider relating to this matter:
1.Approve the staff recommendation.
2.Do not approve the staff recommendation and provide further direction to staff.
ATTACHMENT:
1.Amendment and corresponding Exhibit A & B
FIRST AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT WITH
KIMLEY-HORN AND ASSOCIATES, INC. FOR FINAL DESIGN OF THE GRAND
AVENUE CYCLE TRACK BETWEEN 2ND AND 4TH STREET
THIS FIRST AMENDMENT to the Professional Services Agreement by and between
the CITY OF SAN RAFAEL (hereinafter "CITY"), and KIMLEY-HORN AND
ASSOCIATES, INC. (hereinafter "CONSULTANT"), is made and entered into as of the
04/22/2024
RECITALS
WHEREAS, the CITY and CONSULTANT entered into a Professional Services
Agreement dated September 21, 2022 to perform professional services in connection with
CITY'S Final Design of the Grand Avenue Cycle Track Project, for an amount not to exceed
$74,890 (the "Agreement"); and
WHEREAS, CITY requires additional professional services from the CONSULTANT,
and the CONSULTANT is willing to provide such services.
AMENDMENT TO AGREEMENT
NOW, THEREFORE, the parties hereby agree to amend the Agreement as follows:
1. Article II of the Agreement, entitled "DUTIES OF CONSULTANT" is hereby
amended to include the additional services set forth in CONSULTANT's
proposals dated August 23, 2023, and August 22, 2023, attached to this First
Amendment as Exhibit A and Exhibit B, and incorporated herein by reference.
2. Article IV of the Agreement, entitled "COMPENSATION" is hereby amended to
include additional compensation payable to CONSULTANT for the services
described in Exhibit A and Exhibit B to this First Amendment, on a time and
materials basis in accordance with the Exhibit A and Exhibit B, in a not -to -exceed
amount of $40,850 and $45,300 respectively, and to change the total not -to -
exceed amount under the Agreement to $161,040.
3. Except as specifically amended herein, all of the other provisions, terms and
obligations of the Agreement between the parties shall remain valid and shall be
in full force.
1
IN WITNESS WHEREOF, the parties have executed this First Amendment on the day,
month, and year first above written.
CITY OF SAN RAFAEL
Q�
Cristine Alilovich (Apr 22. 2024 12:32 EDT)
CRISTINE ALILOVICH, City Manager
ATTEST:
donna Na ni (for)
Brenna Nurmi (for) (Apr 22, 202410:13 PDT)
LINDSAY LARA, City Clerk
APPROVED AS TO FORM:
N Z' 11 M
GENEVIEVE COYLE, Assistant City Attorney
2
CONSULTANT
!�
By I, iApi S, 2024 06:01 PDT)
Name: KWasi AkWabi
T,,I ,: Vice President
[If Contractor is a corporation, add signature
of second corporate officer]
41L
By: �evrfAgulpi IApr 5. 202408:48 PDT)
Name: Kevin Ag U i g U i
Title: Vice President
Exhibit A
Kimley>>> Horn
August 23, 2023 (via email)
Ms. Joanna Kwok
Senior Civil Engineer
Department of Public Works, City of San Rafael
111 Morphew Street
San Rafael, CA 94901
Re: Grand Avenue Cycle Track Project — Request for Change Order for Additional Services
Dear Joanna:
As previously discussed via phone and email, Kimley-Horn and Associates, Inc. (Kimley-Horn) is
requesting a change order related to effort expended for the additional design changes after the 95%
Package and effort to support the City prior to the construction advertisement period. The following is
a brief summary of design services that were requested by the City and completed by Kimley-Horn that
were not part of the original contract dated September 21", 2022.
- Design of pedestrian street lighting system along Grand Avenue (2"d St to Wh St), technical
specifications preparation, and bid alternate estimate preparation
- Design of landscaping planter strip between 3rd St and 4th St, technical specifications
preparation, and estimate preparation
- Design of curb ramps (field fit) at Grand Avenue and 41h St.
- Design and details for the modifications of an existing retaining wall between 912 Grand
Avenue and 450 3'd St parcels
- Design of storm drain modifications for existing 920 Grand Avenue outflow infrastructure
- Preparation of custom bicycle route wayfinding signage
- Conduct additional design and coordination meetings with City project team
We also request additional budget to prepare design revisions for the driveway entrance on the east
side of Grand Avenue between Second St. and Third St. Kimley-Horn will revise the driveway width and
add signage and striping at the driveway to facilitate a right -out only movement from the Valero parcel.
Kimley-Horn also understands additional design revisions may be requested by the City prior to
construction commencing. We request an additional budget of $7,010 to perform these design
revisions, as needed. The services will be performed only with City authorization and be billed on a
time -and -materials basis.
The total fee is $40,850 for the work described above and a breakdown of the effort is as follows:
Staff
Hours
Rate
Tota I
Analyst II
96
$165
$15,840
Analyst III
68
$190
$12,920
Professional 1
32
$215
56,899 $6,880
Sr Professional 1
6
$295
$1,770
Project Manager (Prof 1)
16
$215
$3,440
Total
1 $40,850
Kimley>>> Horn
If you have any questions, please do not hesitate to call me at (510) 250-2110.
Sincerely,
Kimley-Horn
Brendan Pittman, P.E., T.E.
Project Manager
Kimley>>> Horn
Exhibit B
August 22, 2023 (via email)
Ms. Joanna Kwok
Senior Civil Engineer
Department of Public Works, City of San Rafael
111 Morphew Street
San Rafael, CA 94901
Re: Proposal to Provide Design Services During Construction for the Grand Avenue Cycle Track
Project
DearJoanna:
We are excited to provide a Scope of Services and Fee to provide engineering services during
construction to support the City of San Rafael (City) as it works to deliver roadway modifications as
part of the Grand Avenue City Track Project. Our Scope of Services follows our understanding of the
work that is involved to support the City as it administers the construction phase of a new two-way
cycle track along the east side of Grand Avenue between 2"d Street and 4th Street.
Scope of Services:
Project Understanding
As part of this project, Final construction documents (design plans, technical specifications, and
Engineers Opinion of Probable Construction Cost) were developed by Kimley-Horn for the Grand
Avenue Cycle Track Project. The construction documents included the following design elements:
■ Roadway modifications (new sidewalk, curb and gutter, and curb ramps)
■ Drainage modifications
■ Traffic signal modifications at three (3) locations on Grand Avenue
■ Landscaping improvements (removal and planting of trees)
■ Pedestrian scale street light improvements
■ Pavement rehabilitation
■ Pavement delineation and signage modifications
Kimley-Horn understands the City is currently in the process of obtaining a construction contractor to
build this Project and is seeking professional services support to assist during the construction phase.
For the purposes of this scope, we have assumed a construction phase to begin in September 2023
and end in Summer 2024 (approximately 9 month construction period).
Based on our previous phone conversations, our Project Understanding, Scope of Services, Schedule,
and Fee Proposal are as follows.
Scope of Services
Task 1: Project Management
Kimley»>Horn
This task includes general project administration, including management of project staff, quality
control, and project accounting. A brief monthly description of services will be prepared and
submitted with our standard invoicing. It is assumed that the project duration is nine (9) months.
Task 1 Deliverables:
• Monthly invoices and progress reports
Task 2: Design Services During Construction
Kimley-Horn team will provide design support during project construction by responding to contractor
inquiries and preparing design modifications for construction contract change orders as applicable.
Kimley-Horn assumes a total effort of 180 hours for budgeting purposes and will be performed on a
time and materials basis. Effort in excess of 180 hours will be billed at a time and materials basis at our
then current hourly rates, and only after written authorization from the City. It is assumed that support
during construction will occur over nine months. Kimley-Horn will have no responsibility for any
contractors means, methods, techniques, sequence, schedule, or safety practices, nor shall Kimley-
Horn have any authority or responsibility to stop or direct the work of any contractor.
Design Services During Construction Services may include, as budget allows:
1. Attend and prepare information for an internal handoff meeting to discuss possible
construction issues and items of special consideration for the construction management team.
2. Attend the pre -construction meeting.
3. Attend construction progress meetings as directed by the City.
4. Review and response to appropriate RFIs, which may include revisions and clarifications of
design details and specifications.
5. Review and response to material and equipment submittals.
6. Review and response to proposed substitutions, if any, for conformance to the construction
documents.
7. Review and response to proposed changes to the contract (Request for Quotations and
Contract Change Orders).
8. Participate in up to one meeting for the final punch list walk through. We will observe the
construction and provide recommendations for the City to consider for generating the final
punch list.
9. Prepare Record Drawings based upon red -lines provided by the contractor and field reviews
performed by the City construction management team. Kimley-Horn will not inspect the
contractor's work. If requested, Kimley-Horn will periodically observe and bring any possible
discrepancies with the construction documents to the City's construction management team.
10. Review and provide comment on construction Contractor's temporary traffic control plans.
11. Participate in coordination calls/meetings as they relate to the other City projects under
construction that may affect this project.
Task 2 Deliverables:
• Construction meeting attendance, if applicable
• Responses to RFIs, submittals, requests for substitutions, and change orders; and revised
details, plans, or specifications
• Record drawings prepared in AutoCAD and provided to the City in AutoCAD and PDF formats,
1300 Clay Street, Suite 325, Oakland, California 94612
Kimley>»Horn
as budget allows
Schedule
Kimley-Horn will provide our services as noted in the Scope of Services as expeditiously as practicable
to meet the mutually agreed upon schedule.
Fee and Billing
Kimley-Horn will provide the professional services outline in the Scope of Services on a labor fee plus
expense basis not to exceed $45,300. This fee includes administrative labor costs and direct expense
(travel, tolls, meals, etc.) incurred in performing these services. The table below includes the break-
down of cost per task.
Task Number Description
1.0 Project Management
$7,320
2.0 Design services During Construction
$37,580
Total Cost
$44,900
Expenses:
$400
Total:
$45,300
We note that any services other than those set forth in the Scope of Services will constitute additional
services. Additional services shall be performed only with your authorization and be billed on'a time -
and -materials basis. Thank you for the opportunity to provide our professional services to the City of
San Rafael. Please contact me at (510) 250-2110 (office) or via email at brendan.pittman@kimley-
horn.com should you have any question or need any clarifications.
Kimley-Horn and Associates, INC.
Brendan Pittman, PE, TE
Project Manager
1300 Clay Street, Suite 325, Oakland, California 94612