HomeMy WebLinkAboutPW Architectural, Engineering & Interior Design Services; First AmendmentFIRST AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT WITH
NOLL & TAM ARCHITECTS FOR ARCHITECTURAL, ENGINEERING AND
INTERIOR DESIGN SERVICES
THIS FIRST AMENDMENT to the Professional Services Agreement by and between
the CITY OF SAN RAFAEL (hereinafter "CITY"), and NOLL & TAM ARCHITECTS,
(hereinafter "CONSULTANT"), is made and entered into as of the day of
Nov 1, 2023 , 2023.
RECITALS
WHEREAS, the CITY and CONSULTANT entered into a Professional Services
Agreement dated January 17, 2023 to perform professional services in connection with CITY'S
Downtown Library Improvement Project, City Project No. 11413-01, for an amount not to
exceed $67,905 (the "Agreement"); and
WHEREAS, CITY requires additional professional services from the CONSULTANT,
and the CONSULTANT is willing to provide such services.
AMENDMENT TO AGREEMENT
NOW, THEREFORE, the parties hereby agree to amend the Agreement as follows:
1. Article I of the Agreement, entitled "SERVICES TO BE PROVIDED" is hereby
amended to include the additional services set forth in CONSULTANT's
proposal dated August 30, 2023, attached to this First Amendment as Exhibit A
and incorporated herein by reference.
2. Article II of the Agreement, entitled "COMPENSATION" is hereby amended to
include additional compensation payable to CONSULTANT for the services
described in Exhibit A to this First Amendment, on a fixed fee basis in
accordance with the Exhibit A, in a not -to -exceed amount of $323,826, and to
change the total not -to -exceed amount under the Agreement to $391,731.
3. Article III of the Agreement, entitled "TERM OF AGREEMENT" is hereby
amended to extend the Agreement term by 12 months through January 17, 2025.
3. Except as specifically amended herein, all of the other provisions, terms and
obligations of the Agreement between the parties shall remain valid and shall be
in full force.
IN WITNESS WHEREOF, the parties have executed this First Amendment on the day,
month, and year first above written.
CITY OF SAN RAFAEL CONSULTANT
� -�-�=�- .A"Ola ChrisioDher Noll
Cristine Alilovich (Nov 1, 2023 21:57 PDT) By: Chnstopher Noll ,0ct 26, 2023 19:08 PDT)
CRISTINE ALILOVICH, City Manager Christopher Noll
Name:
Title: Principal
ATTEST:
[If Contractor is a corporation, add signature
`I`I NGdY` i i DY) of second corporate officer]
Brenna Nurmi (for) (Nov 2, 2023 0753 PO )
LINDSAY LARA, City Clerk
By:
APPROVED AS TO FORM: Name: Janet Tam
Title: Principal, CEO
ROBERT F. EPSTEIN, City Attorney
Exhibit A
San Rafael Downtown Library Modernization
ADDITIONAL SERVICE REOUEST NO 2
August 30, 2023
Attn: Fabiola Guillen
Fabiola Guillen
Project Manager
Department of Public Works
City of San Rafael
Re: Downtown Public Library Modernization Project
1100 E Street, San Rafael, CA 94901
NOLL
"', TA M
ARCHITECTS
Dear Ms. Guillen,
Noll & Tam Architects has amended our proposal for architectural consulting services, dated March 14, 2023, to
include conclusion of the concept phase of work as well as Construction Documents and Construction
Administration and Close-out Services as outlined in the attached Exhibit A and consultant proposals.
Project Description:
Downtown Public Library Modernization Project
Building Size: Approx.15,000 SF
Client Construction Budget: $2.21M
Design Schedule: Construction Documents (Sept 2023 — Dec 2023), Permit (Jan — March 2024), Bidding/Negotiation
(March — April 2024), Construction Administration (May — October 2024)
729 Heinz Avenue #7 1 Berkeley CA 94710 1 510-542-2200 1 www.nollandtam.com Page 1 of 3
Downtown Public Library Modernization Project
San Rafael, CA
August 30, 2023
Basic Service Consultant
Architectural Services Noll & Tam
MP Engineering Capital
Cost Estimating TBD Consultants
Electrical/Data/Lighting Capital
Subtotal Basic Services
Supplemental Services Consultant
Retro-Commissioning Capital
Interiors / FF&E Noll & Tam
Concept Phase Schedule Extension Noll & Tam
Signage Allowance
Subtotal Supplemental Services
Subtotal Basic and Supplemental Services
Reimbursable Expense Allowance
Z
O
Q
P:
� �
Z O
O_LL
O H
W
Ui
Z
O H of
O
u z
D W
l7
u
CC
Ou O
O
Ou Q a
=
O
TOTALS
in
$55,180
$4,080
$54,975
$0
$114,235
$22,440
$2,420
$6,380
$0
$31,240
$30,938
$0
$0
$0
$30,938
$31,845
$2,123
$8,492
$0
$42,460
$140,403 $8,623 $69,847 $0 $218,873
$11,253
$0
$0
$0
$11,253
$24,000
$12,000
$8,000
$0
$44,000
$0
$0
$0
$36,000
$36,000
$9,900
$550
$2,750
$0
$13,200
$45,153
$12,550
$10,750
$36,000
$104,453
$185,556
$21,173
$80,597
$36,000
$323,326
$0
$0
$0
$0
$500
Total Proposed Fee $323,826
Our basic fee for this scope shall be lump sum fixed fee as listed above of Three Hundred Twenty-three
Thousand Eight Hundred Twenty-six dollars $323,826, billed monthly on a percent complete basis.
Services rendered beyond the agreed scope of work will be billed at our hourly rates.
Noll & Tam Architects I August 30, 2023 1 San Rafael Downtown Library Modernization I SA No. 2 Page 2 of 3
Sincerely.
Chris Noll
Principal
Approved:
Fabiola Guillen date
Project Manager, Public Works
Noll & Tam Architects I August 30, 2023 1 San Rafael Downtown Library Modernization I SA No. 2 Page 3 of 3
NOLL
L "
EXHIBIT A TAM
SCOPE OF WORK ARCHITECTS
For A/E Services for the
SAN RAFAEL DOWNTOWN LIBRARY MODERNIZAT]O
VERSION: August 17, 2023
I. CONCEPT PHASE EXTENSION
This scope includes the additional time spent aligning the concept scope and the project budget from
May - July 2023 as well as the following:
• Electrical Site Visit - 7/18/2023
II. CONSTRUCTION DOCUMENT PHASE
1. Architectural
a. Site Plan showing location of building and proposed changes to streets, curb, gutters, sidewalks,
and the location of exterior utilities and service lines
b. Floor Plans / Roof Plans / Reflected Ceiling Plans
c. Selected Interior Elevations
d. Technical Specifications documenting all building systems and materials required for the
construction of the project. Consultant shall review and provide comments regarding City front
end documents (Division 00 and 01) including, but not necessarily limited to: Invitation to Bid,
Instructions to Bidders, Proposal Format, Contract Agreement, General Conditions, and
Construction Administration Procedures. Consultant is responsible to incorporate City front end
documents with the Consultant's Project Manual that includes the Contract Specifications as part
of the Bid Set.
2. Mechanical / Plumbing
a. See attached Capital Engineering Proposal
3. Electrical/Telecommunications / Data / Security / AV / Paging / Acoustics
a. See attached Capital Engineering Proposal
4. Interior Design and Finishes
a. Consultant shall refine and develop all design items and finalize the selection of colors, materials,
fabrics, and furniture. Consultant shall refine, develop, and detail any custom millwork and update
the interiors' budget and schedule. Consultant shall prepare presentation boards showing final
furniture and fabric selections/designs for City written approval.
b. Consultant shall prepare the following deliverables: plans of standard furniture items and office
systems furniture reflecting the concept plan scope, working drawings and specifications for any
other special millwork items, written technical specifications for standard furniture items and
Noll & Tam Architects I August 17, 2023 1 San Rafael Downtown Library Modernization Page 1 of 7
office system furniture, duplicate record binders of fabrics, furniture cuts and finishes. The
furniture selected by this contract is for furniture only and does not include procurement of
computers, copiers or other technology equipment. Nor do the services include the selection of
incidental items such as trash cans, pencil sharpeners, etc. The professional services for the office
furniture include assistance with the selection of a furniture manufacture's system, finishes,
electrical needs and space plan. They do not include a parts and pieces order which will be
provided by the vendor, as is standard in the industry.
c. Furniture shall be specified from negotiated contracts to preclude a bidding process. Furniture
bidding services can be provided as an additional service.
5. Signage
a. See attached Matthew Williams proposal.
6. Retro Commissioning
a. See attached Capital Engineering Proposal
7. Cost Estimate
a. Cost Estimate of 65% Construction Documents
b. Consultant shall meet with City as necessary to reconcile any cost differences between the project
budget and the statement of probable construction cost. Based on the final review comments by
City and its other consultants, the Consultant shall provide a Final Statement of Probable
construction cost prior to the start of the Bidding Phase of the 95% Construction Documents Set.
8. Client Direction:
a. Consultant shall review and provide a written response to all comments generated by City, which
are generated from the review of the deliverables provided by the Consultant at 65% and 95%
Construction Documents. City shall prepare and present all comments for this phase to the
Consultant in a single response within the designated time period defined by the Project Schedule.
b. Consultant's response to out -of -sequence City comments shall be compensated as an additional
service.
9. Constructability Review:
a. When the 95% Construction Documents are complete, City shall have the option to engage a third
party to perform a constructability review and provide their comments to City for the Consultant's
review. The third party review shall be completed within 14 calendar days and would include a
written report to City. The Consultant shall meet with City and the third party to review the
comments and the Consultant shall provide a response prior to the start of the Bidding Phase to
all comments indicating what action, if any, was taken by the Consultant. Any review by City or a
third party does not relieve the Consultant of its design responsibility and the design is and
remains the sole responsibility of the Consultant.
Noll & Tam Architects I August 17, 2023 1 San Rafael Downtown Library Modernization Page 2 of 7
10. Meetings:
Consultant shall prepare and attend the following meetings at locations specified by City:
a. "Client Staff" 3
b. 'Public Presentations" 1
Additional meetings, if required, will be considered Additional Services
11. Plan Check Process and Permitting: [Authority Having Jurisdiction]
a. Consultant shall coordinate with Authorities as required to develop documents meeting
regulatory requirements for the State / County and City. The Consultant shall submit the
construction documents to the Building Department for a Building Permit and shall make revisions
to the plans as necessary in order for the Authority to issue required building permits.
b. Consultant shall provide number of sets of the Construction Documents required by the AHJ for
Building Department Plan Check. Following Building Department Back Check, Consultant shall
provide four (4) sets of the Bid Set of the Construction Documents to City and an additional set to
an outside printing agency for distribution by City as needed for Permitting.
12. Deferred Design Build Portions of the Work
Portions of the Work will be described as design build, or deferred approval elements, of the design,
including, but not limited to, the following:
a. Fire Alarm
II. BIDDING / NEGOTIATION PHASE
A. Assistance with Bidding:
Consultant shall assist City in identifying and evaluating potential bidders, including rendering
interpretations and clarifications of the Drawings and Specifications in appropriate written form.
B. Addenda:
Prepare any required Addenda to the Bid Package.
C. Pre -Bid Conference:
The Consultant and its key sub -consultants shall attend the Pre -bid Conference and provide a technical
overview of the design intent and answer questions from prospective bidders. The Pre -bid Conference will
be held at the project site. Consultant shall attend up to two (2) additional meetings as necessary during
this phase.
D. Respond to Bidder Questions:
Prepare written answers to questions, addenda, interpretations and clarifications in a timely manner; and
obtain written approval from City
E. Deliverables: Consultant shall provide digital pdfs of Conformed Construction Documents containing any
and all changes issued by addenda during the bidding period. These documents shall be prepared and
delivered two weeks after the bid date.
Noll & Tam Architects I August 17, 2023 1 San Rafael Downtown Library Modernization Page 3 of 7
III. CONSTRUCTION ADMINISTRATION PHASE
A. CONSTRUCTION ADMINISTRATION PHASE
The scope of services provided by the Consultant in this phase shall be coordinated with such construction
management services as City may elect to obtain, and the scope of Consultant's services for this phase
shall be separately negotiated, including compensation.
B. Observation:
Consultant shall visit the site at intervals appropriate to the stage of construction to become generally
familiar with the progress and quality of the Work and to determine and to advise City in general if the
Work is proceeding in accordance with the Contract Documents. This includes special site visits by
Consultant on a timely basis appropriate for approvals required of Consultant as specified in the
Construction Documents. However, Consultant shall not be required to make exhaustive or continuous on -
site inspections to check the quality or quantity of the work.
C. Other Meetings:
The Consultant shall attend bi-weekly virtual job construction progress meetings during the course of
construction with minimum monthly in -person site visits, additional on an as -needed basis. The
Consultant's structural, mechanical and electrical sub -consultants shall visit the site as appropriate when
work related to their engineering discipline is in progress. The estimated length of the construction phase
is 6 months, and this proposal includes 18 construction progress meetings noted above. If the construction
schedule extends beyond this time frame, and additional construction progress meetings are needed, or if
additional meetings are required within the estimated time frame, they will be provided as an additional
service.
D. Construction Responsibility:
Consultant shall not be responsible for construction means, methods, techniques, sequences or
procedures, or for safety precautions and programs in connection with the Project, and shall not be
responsible for the Contractor's failure to carry out work in accordance with the Contract Documents.
Consultant shall be available on site to the Contractor as reasonably required to provide timely
interpretations of the Drawings and Specifications to avoid critical project delay.
E. Requests for Information:
The Consultant shall be required to respond to Contractor generated RFI's in a timely manner to avoid
critical project delay.
F. Access:
Consultant shall at all times have access to the work wherever it is in preparation or progress.
G. Extent of Assistance by Consultant:
Consultant shall assist City in ascertaining that, to the best of their knowledge, information and belief, the
quality of the work is in accordance with the Contract Documents (subject to an evaluation of the work) for
conformance with the Contract Documents upon substantial completion, to the results of any subsequent
tests required by or performed under the Contract Documents, to minor deviations from the Contract
Noll & Tam Architects I August 17, 2023 1 San Rafael Downtown Library Modernization Page 4 of 7
Documents correctable prior to completion; and that the Contractor is entitled to payment in the amount
certified upon delivery of the appropriate lien waivers.
H. Rejection of Work:
Consultant may recommend that City reject work of the Contractor, which does not conform to the
Contract Documents. Whenever, in Consultant's reasonable opinion, it is necessary or advisable for the
implementation of the intent of the Contract Documents, Consultant may recommend special inspection or
testing of the work in accordance with the provisions of the Contract Documents, whether or not such
work is then fabricated, installed or completed.
I. Inspection and Tests:
The Consultant shall review special inspection and test reports and make written recommendations to the
City.
J. Submittals and Shop Drawings:
Consultant shall receive submittals, including shop drawings, product data and samples from the
Contractor and shall review and a take appropriate action, but only for conformance with the design
concept of the Project and with the provisions and intent of the Contract Documents. Consultant's review
and approval shall not relieve the Contractor of its obligation to comply with the Contract Documents.
Consultant shall be entitled to additional services for the third and subsequent reviews of any submittal
(typically back -charged to Contractor, at client's option).
K. Substitutions:
Consultant shall review substitution requests as an additional service (typically back -charged to
Contractor, at client's option).
L. Change Order Entitlement and Cost Estimate Review:
The Consultant shall review entitlement and the scope of work included in Contractor -generated Request
for Changes and provide written recommendations to City. City shall be responsible for preparing the cost
estimate and negotiating the change with the Contractor. Extensive review and negotiation over specific
change requests will be considered an additional service.
M. Certificates of Payment
The Consultant shall review and approve Certificates of Payment submitted by the Contractor for payment
by City.
N. Interior Contract Administration/Installation:
Consultant shall provide the following services: review delivery/installation schedules, answer dealer's
questions, review dealer's submittals, and prepare a final punch list on furniture items. Consultant shall also
be available to solve problems that might arise during the installation period and assist City with close out
of all vendors and work performed by contractors. Evaluating substitutions can be provided as an
additional service.
O. Project Close -Out
When the Contractor indicates in writing that work or a portion thereof, has reached Substantial
Completion, the Consultant shall visit the site and review and edit the punch list prepared by the
Noll & Tam Architects I August 17, 2023 1 San Rafael Downtown Library Modernization Page 5 of 7
Contractor. Once the Contractor indicates all items on the punch list have been completed, the Consultant
shall return to the site as needed to review and confirm the work has been completed to the Consultant's
satisfaction. Additional site visits to review incomplete work shall be an extra service (typically back -
charged to Contractor, at client's option).
P. Final Completion:
After instruction from City, Consultant shall visit the Site to determine the Dates of Substantial Completion
and Final Completion and shall issue appropriate certificates as set forth in the General Conditions.
Q. Warranties and Manuals:
Consultant shall review the operation and maintenance manual on all systems to be provided by the
Contractor for completeness.
R. Record Drawings:
The Contractor shall maintain an up-to-date set of drawings reflecting construction conditions of the work
by the Contractor and the subcontractors, including all changes to the documents. Consultant's review of
the as -built drawings and annotated specifications shall be based upon Consultant's observations at the
site and its knowledge of the contract documents. Upon completion of the work, the Contractor shall
forward the as -built drawings and annotated specifications to Consultant with its certificate as to their
accuracy. Consultant shall receive and review for accuracy and completeness the Contractor's submission
of as -built drawings, and annotated specifications and operation and maintenance manuals. The
Consultant will then update the electronic documents accordingly and provide CAD as -built drawings and
specifications, which will serve as the "Record Documents" for the project.
S. Fundamental Commissioning:
Consultant shall provide the following basic commissioning, see attached engineering proposals.
Noll & Tam Architects I August 17, 2023 1 San Rafael Downtown Library Modernization Page 6 of 7
IV. EXCLUSIONS
The following items are excluded from the current Scope of Work:
2. Architectural:
a. Preparation of any Environmental or CEOA Reports
b. Value Engineering Services may be provided as an additional service
c. Life cycle cost analysis
3. Civil Design
4. Structural Design
5. Electrical:
a. Emergency generator
b. Photovoltaic system design
6. Fire Protection
a. Design of Fire Sprinkler System
7. Elevators:
a. Modification of existing elevators
8. LEED Certification
9. Acoustic:
a. Environmental noise survey may be provided as an additional service
10. Telecommunications:
a. Relocation of IDF/MDF
11. Interior Design:
a. Move coordination services
b. Owner Purchasing Department to manage bid process and bid packages for furniture if
negotiated contracts not selected or otherwise required.
c. Selection and specification of library automation systems (we will provide infrastructure and
design to accommodate what the Library selects)
12. Public Art:
a. Public Art/Artist selection and coordination with artists and artwork in the building may be
provided as an additional service
13. Fundraising and Donor Recognition:
a. Assistance with fundraising or grant applications, and the preparation of any donor recognition
materials may be provided as an additional service.
Noll & Tam Architects I August 17, 2023 1 San Rafael Downtown Library Modernization Page 7 of 7
COj71TCL 7.19.2023
engineering Page 2 of 5
A. Project Description:
The project is located at 1100 E Street, San Rafael Ca. 94901.
2 The project was originally constructed in 1906 (5,000sf) and a subsequent
addition was built in 1959 (11,000sf). The building was remodeled 1995.
3. The existing building has no fire sprinklers, and we believe the current CBC will
not require them. The City of San Rafael may require at their discretion, that
Fire Sprinklers may be desired. Generally for Design -Assist Projects we see a FP
Contractor coming on board during the design process. To that end our
proposal excludes any Fire Sprinkler Design Services.
B. Scope of Services:
1. The scope of basic services shall include heating, ventilating and air
conditioning design - and plumbing design.
2. Construction Documents Phase: Prepare construction drawings and technical
specifications for tenant plumbing systems and components as outlined
under Design Development Phase above.
3. Bidding/Con tract Award Phase: Prepare plumbing addenda and clarification
documents, interpret plumbing drawings and specifications where required to
clarify the intent of construction documents
4. Construction Phase: Review shop drawings and submittal data for general
compliance with mechanical contract documents, respond to RFI's, prepare
change order documents where required to meet existing job conditions, and
provide 3 periodic site visits during the course of construction.
S. Seismic Anchorage and Restraint Systems: Pre -approved restraint systems are
assumed as the predominance of the piping and ductwork support systems.
Any deviations from the pre -approved systems or specialty restraints and
anchors for equipment or piping will require structural calculations and
associated documentation. CECI will not assume the responsibility for the
calculations but will provide the drawing documentation based on mark-ups
provided by the Structural Engineer of record.
C. Extra Services: The following services are not included in the basic proposal. The
Engineer shall be additionally compensated for work hereunder when the Architect
requests such services in writing.
1. Design services to provide alternate bid items, and descriptions of phased
construction except as identified in Paragraphs A and B above.
2. Employment of special sub consultants at the request of the Architect.
3. ' Preparation of owning or operating cost studies.
11020 Sun Center Drive, Suite 100 1 Rancho Cordova, CA 95670
Office:916.851.3500 1 Fax:916.631.4424 � office@capital-engineering.com I www.capital-engineering.com
CC1PITCIL 7.19.2023
engineering Page 3of3
4. Life cycle cost analyses, energy effectiveness studies and preparation of
maintenance or operating manuals, except as listed otherwise in this proposal.
5. Design services related to landscape sprinklers, site drainage, site sewer, or
special piping systems.
6. Work outside the five feet line of the building.
7. Detailed itemized cost estimates.
8. Fire Sprinkler Design Services.
D. Materials and Services Furnished by the Architect:
1. Base sheets of architectural floor plans and site plan with drawing files in
AutoCAD or compatible format, along with full-size PDF files of the working
drawings. Half-size prints of all of the construction drawings shall be provided
at time of first DSA submission and at time of release of bid documents to the
Bidders.
2. All reproduction, including drawings, specifications and reports.
11020 Sun Center Drive, Suite 100 1 Rancho Cordova, CA 95670
Office:916.851.3500 1 Fax:916.631.4424 I or"ficeCocapital-engineering.com I www.capital-engineering.com
SAN RAFAEL MAIN LIBRARY
O P#: 23-0240 C C'1 j71 T C1 L 04/20/2023
Commissioning ke engineering Page 2 of 10
A. Project Description: The project is located at 1100 E Street, San Rafael, CA. As we
understand the San Rafael Public Library was originally constructed in 1909. The
Library has undergone two expansions since this time, in the 1960's when an addition
was added and the most recent in 2008 with a major HVAC system renovation
project. The intent of this proposed Petro-Cx effort is to functionally test the HVAC
and related controls and recommend corrections, and enhancements to retune the
performance ofthe system as close as possible to its original design intent.
B. Assumptions:
1. General:
a. The scope of work will be documented in no more than one phase of
construction.
b. The project delivery method is xxx.
C. Scope of Services:
Commissioned Systems
a. HVAC and Related Controls
2. Sampling strategy during the functional tests per the list below:
a. 100% HVAC and Related Controls
3. Retro-Commissioning Scope of . ,.)r.�_
a. Assessment Phase
1) Review any available As -built drawings, Test and Balance
reports, Control documents/sequences and O&Ms.
b. Investigation Phase
1) Interview with the facility operator to discuss any known
ongoing, operational or comfort issues.
2) If trends are available, then we will perform a 2 weeks trend data
review analysis prior to the functional testing.
3) Functional Testing:
(1) Development: Write functional tests for commissioned
systems and distribute them to the owner for review and
comments. Revise and finalize the test procedures
accordingly.
(2) Witnessing: Attend functional testing of commissioned
systems executed by the owner or the owner's
contractor.
11020 Sun Center Drive, Suite 100 1 Rancho Cordova, CA 95670
Office:916.851.3500 1 Fax:916.631.4424 I office@capital-engineering.com I www.capital-engineering.com
SAN RAFAEL MAIN LIBRARY 4ke
111^11110� COP'T�L
O P : 23-0240 04/20/2023
Commissioning engineering Page 3 of10
4)
(3) Recording: Commissioning Agent to complete the
functional test forms and maintain a commissioning
issues log indicating any test failures.
Commissioning Corrective Action Matrix (CCAM) — Document
and track Cx issues found during this and previous phases.
5) Add Alt#2: Issues Back -check: When the Commissioning Agent
is notified that noted corrections have been made, CxA will
back -check the corrections and update the CCAM log. Test and
issues log will be provided to the owner.
C. Hand Off Phase
1) Commissioning Report: CxA will assemble content provided by
self and others and provide a Cx Report summarizing the Cx
Activites and Results including the as -built Sequence of
operations.
4. Summary of major activities provided in this fee proposal:
a.
b.
C.
d.
e.
D. Clarifications:
Three Virtual Team meetings during the Assessment and Investigation
phase.
One Trend review analysis of 2 weeks data is included.
No TAB Sample verification / Startup Witnessing / Duct leakage Testing
/ Piping Pressure testing site visits.
Up to Two days of Functional Testing site visits. (Limited to Two person -
days)
Add Alt#2: Up to One day of Issues Back -check site visits. (Limited to
One person -day)
This proposal is assuming only one round of functional testing on existing
equipment
E. Extra Services: The following services are not included in this proposal.
1. Energy Audit
2. Implementation of recommendations or Back -check of issues found during
the functional tests. (See Add Alt#2)
3. Employment of special sub -consultants at the request of the Client.
4. Life cycle cost analyses, owning or operating cost studies, and energy
effectiveness studies.
11020 Sun Center Drive, Suite 100 I Rancho Cordova, CA 95670
Office: 916.851.3500 I Fax:916.631,4424 1 office@capital-engineering.com I www.capital-engineering.com
CCIPITICIL 08.08.2023
Page 1 o`5
DATE: 8.8.2023
Ms. Amy B. Watson, AIA
Senior Associate
Noll & Tam Architects
729 Heinz Avenue #7
Berkeley CA. 94710
PROJECT: SAN RAFAEL LIBRARY RENOVATION
CITY OF SAN RAFAEL
SAN RAFAEL, CA
SUBJECT: PROPOSAL FOR MECHANICALAND PLUMBING SERVICES -
CONSTRUCTION DOCUMENTS THROUGH CONSTRUCTION ADMINISTRATION
Dear Amy,
We are pleased to offer this fee proposal for engineering services for the subject project.
Please reach out if you have any questions, comments, or concerns.
A. Project Description:
The project is located at 1100 E Street, San Rafael Ca. 94901.
2. The project was originally constructed in 1906 (S,000sf) and a subsequent
addition was built in 1959 (11,000sf). The building was remodeled 1995.
B. Scope of Services:
The scope of basic services shall include electrical, fire alarm, low voltage
design as described in the Project Description.
a. Provide LED lighting and controls in Carnegie Building.
b. Provide emergency lighting and illuminated exit signage.
C. Relocate existing main building panels. Reconnect existing circuits.
d. Relocate existing panel in Circulation. Reconnect existing circuits.
e. Provide receptacles through building.
f. Provide new power panels for connection of receptacles and
equipment. Extend power from existing switchboard on exterior of
building.
g. Provide data outlets. Connect to existing MDF with CAT 6 cables.
h. Provide intrusion detectors or relocate as necessary.
i. Provide manual fire alarm system.
11020 Sun Center Drive, Suite 100 1 Rancho Cordova, CA 95670
Office:916.851.3500 1 Fax:916.631.4424 1 office@capital-engineering.com I www.capital-engineering.com
ke
ke
CCIPITC1L 08.08.2023
engineering Page 2 of 5
2. Construction Documents Phase: Prepare construction drawings and technical
specifications for electrical systems and components as outlined under Design
Development Phase above.
3. Bidding/Contract Award Phase: Prepare electrical, fire alarm, and low voltage
addenda and clarification documents, interpret electrical, and low voltage
drawings and specifications where required to clarifythe intent of
construction documents
4. Construction Phase: Review shop drawings and submittal data for general
compliance with electrical contract documents, respond to RFI's, prepare
change order documents where required to meet existing job conditions, and
provide 3 periodic site visits during the course of construction.
S. Seismic Anchorage and Restraint Systems: Pre -approved restraint systems are
assumed as the predominance of the piping and ductwork support systems.
Any deviations from the pre -approved systems or specialty restraints and
anchors for equipment or piping will require structural calculations and
associated documentation. CECI will not assume the responsibility for the
calculations but will provide the drawing documentation based on mark-ups
provided bythe Structural Engineer of record.
C. Extra Services: The following services are not included in the basic proposal. The
Engineer shall be additionally compensated for work hereunder when the Architect
requests such services in writing.
1. Design services to provide alternate bid items, and descriptions of phased
construction except as identified in Paragraphs A and B above.
2. Employment of special sub consultants at the request of the Architect.
3. Preparation of owning or operating cost studies.
4. Life cycle cost analyses, energy effectiveness studies and preparation of
maintenance or operating manuals, except as listed otherwise in this proposal.
5. Design services related to landscape architectural fountains, water features or
water displays, landscape sprinklers, site drainage, site utilities, or special
piping systems not specifically noted in proposal.
6. Work outside the five feet line of the building unless noted otherwise.
7. Detailed itemized cost estimates.
8. The modification of electrical drawings (AutoCAD files) to show final
mechanical and electrical ceiling devices that will be used directly by Architect
to show locations of ceiling devices on Architectural drawings by the means of
directly referencing or linking the mechanical and electrical files or model.
11020 Sun Center Drive, Suite 100 1 Rancho Cordova, CA 95670
Office:916.851.3500 1 Fax:916.631.4424 1 office@capital-engineering.com I www.capital-engineering.com
C I CCIPITOL 08.08,2023
engineering Page 3 or 5
9. Partnering sessions, value engineering sessions or review of Contractor or
Construction Manager proposed cost cutting recommendations.
10. Work involved in securing utility company rebates.
11. Additional time over and above the normal and customary to clarify, negotiate,
or otherwise respond to unreasonable or inaccurate interpretations of the
code by the code officials including circumstances where we become "caught
in the middle" between code interpretations of office reviewers and field
reviewers.
12. Non -Title 24 commissioning of building systems, services related to the
development of commissioning plans and services related to support third
party commissioning of the building, other than as described above.
13. Title-24 required Division 01 specifications, functional testing, development of
the systems manual, operational training, and the commissioning report.
14. Design services related to LEED certification or other sustainability (WELL,
Green Guide for Health Care, etc.) of building, studies necessaryto determine
feasibility of certification and the preparation or coordination of the
documentation necessary for certification.
15. Design services related to CHPS certification of building, studies necessary to
determine feasibility of CHPS certification and the preparation or coordination
of the documentation necessaryfor CHPS certification.
16. Changes to Basis of Design if the Owners Project Requirements are changed
following completion of the Schematic Design phase or significant changes in
physical configuration after Design Development, significant changes in Revit
or AutoCAD project setup such as but not limited to, change in coordinates,
changes in or additional phasing.
17. Redesign required due to a construction cost guarantee bythe prime design
professional or for other reasons that are not the responsibility of the
Consulting Engineer is not included.
18. Review of submittals beyond described above.
19. Engineering work caused from construction that is installed differentlyfrom
the permitted drawings if work could be installed as shown and permitted.
20. Engineering rework resulting from other trades not coordinating or installing
work different from approved coordination drawings.
D. Materials and Services Furnished by the Architect:
Base sheets of architectural floor plans and site plan with drawing files in
AutoCAD or compatible format, along with full-size PDF files of the working
drawings. Half-size prints of all of the construction drawings shall be provided
at time of first DSA submission and at time of release of bid documents to the
Bidders.
11020 Sun Center Drive, Suite 100 1 Rancho Cordova. CA 95670
Office:916.851.3500 I Fax:916.631.4424 1 office@capital-engineering.com I www.capital-engineering.com
• • consultants
August 3, 2023 rev2
Amy Watson
Noll & Tam Architects
729 Heinz Ave. #7
Berkeley, CA 94710
Re: San Rafael Carnegie Library Renovation — CD Phase
Fee Proposal for Cost Consulting Services
Dear Amy,
93 Moraga Way
Suite 206
Orinda, CA
94563
Phone 415 981 9430
Direct 415 872 0999
Mobile 415 205 6460
abeyer@tbdconsultants.com
www.tbdconsultanfs.com
We are pleased to offer Cost Consulting services for the above project.
We understand the project occurs at the existing Carnegie Library at 1100 E Street, San
Rafael, CA. The project includes a renovation focused on upgrades for accessibility,
building MEPFS systems, life safety, operations, reconfiguration, and interior finishes
The project occurs in both the 5,000 gsf original 2 story wing, as well as the 6,000 gsf 2
story addition wing.
Scope of Services
Our fee proposal is based on providing the following:
i. 65% CD: 1 Estimate draft + 1 revision per estimate review comments.
ii. 95% CD: 1 Estimate draft (limited to an update of the 65% estimate) + 1 revision
per estimate review comments.
iii. Allowance for mtgs for design coordination (4 hrs) and estimate reviews (4 hrs).
The estimates will identify the total cost of construction based on the quantities or allowances
with composite unit rates where applicable reflecting the scope of work and the current market
conditions. The estimate will utilize TBD's standard format, Uniformat II (a systems format), and
not via the shopping list style provided in the prior project phase. We will not obtain any bids or
opinions of cost from subcontractors unless the work is of such a unique nature that no other cost
information is available. Noll & Tam and their design consultants shall provide design docs for
our use. Should additional work be required, our standard hourly billing rate of $225 in 2023 /
$235 in 2024 will apply, in the absence of an Add Service Proposal.
Notable Exclusions:
The following items are excluded from the scope in this fee proposal:
- Reconciliation with estimates by others.
- Attending in -person meetings.
- Site visits.
- Estimating soft costs.
- Estimating design options.
- Estimating design changes when providing the estimate revision of each estimate draft.
- Estimating complex alternates, or estimating lots of alternates.
- Value analysis / value engineering, or other cost studies.
- Design & estimate 'churning' to reach a budget.
- Estimating 100% CD design documents
Project !Management I Construction Cost Management
Matthew Williams Design 510.559.1830 desk mw@matthewwilliamsdesign.com Proposal
ki 1450 Fourth Street, Studio 9 415.205,0412 mobile www.matthewwilliamsdasign.com
Berkeley, CA 94710 USA
Signage Design and Consulting
9 August 2023 Chris Noll Noll & Tam Architects San Rafael Downtown Library
Amy Watson 729 Heinz Avenue #7 Revitalization
Karl Holmquist Berkeley, CA 94710
1: Overview
Project Description
The following proposal outlines the Scope of Work, sets forth estimated costs and working conditions, and defines specifications
for exterior and interior signage design and consulting services for the renovation and revitalization of the San Rafael Downtown Library
located at 1100 E Street in San Rafael, California. Matthew Williams Design (MWD) will provide design and consulting services for the
development of exterior and interior wayfinding, area identification, and code -required signage for the newly -renovated library.
MWD will work closely with Noll & Tam Architects (N&T) and designated staff to provide clearly understandable, aesthetically pleasing,
and cost-effective signage and wayfinding which will reflect the architectural character of the newly -renovated library, and be designed
in accordance with the City of San Rafael's LEED requirements where applicable. MWD will coordinate with N&T, designated San Rafael
Library staff, and designated staff from the City of San Rafael and the Marin County Planning Department as required during the course
of the project. All signage will comply with California Title 24/ADAAG, Title 19, and the CBC as applicable. The Scope of Work will be
divided into four phases as described in Section 2: Project Development.
MWD will be responsible for programming and schematic design, design development, preparation of construction documents for competitive
bid, and contract administration. The construction documents will include a sign schedule and sign location plans, annotated design intent
drawings, and performance specifications.
MWD anticipates addressing the following signage components:
Interior Signage
Self -checkout
Basement staff area
Memory Lab
Visitor, administrative, and staff -oriented signage
Room identification
ADA and Title 24 signage
Counter information/Service desks
Children's Storytime
Directional, informational, and operational signage
Directory and/or orientation display
Stack, section, and area identification
Fire/Life safety
I
kiMatthew Williams Design 510.559.1830 desk mw@matthewwilliamsdesign.com Proposal
1450 Fourth Street, Studio 9 415.205.0412 mobile www.matthewwilliamsdesign.com
Berkeley, CA 94710 USA
2. Project Development
Phase 1: Programming, Concept, and Schematic Design (SD):
• Review and establish scope of project; develop design criteria for interior and exterior signage with N&T.
• Review SO drawings, including plans from engineers and Architectural narratives.
• Review and establish operational requirements for the signage.
• Review site plan, floor plan, and circulation patterns.
• Identify all exterior and interior sign types to be utilized.
• Develop preliminary sign location plans and sign schedule.
• Develop schematic drawings for representative elements of the interior and exterior sign families, showing approximate size, shape,
and typography, with preliminary color and material recommendations.
• Review preliminary sign location plans, sign schedule, and schematic design options with N&T for comment and selection
of a design option. Incorporate comments.
• Ensure all exterior signage complies with the requirements of the City of San Rafael Sign Ordinance.
• Ensure code compliance throughout the system.
• Develop submittal with selected schematic design option, sign schedule, sign location plans, and specifications for preliminary
fabrication/installation estimate for client review.
• Review all details of the schematic design phase with N&T and designated San Rafael Library staff for comments and approval.
Consultant Deliverables
• Preliminary sign schedule and sign location plans.
• Schematic design options.
• Submittal for fabrication/installation estimate (95% Arch. CD).
Phase 2: Design Development (DD):
• Incorporate comments from schematic design phase.
• Develop and refine all sign types including graphic layout, colors, recommended materials, and finishes.
• Review and coordinate all sign types with N&T and designated San Rafael Library staff.
• Review site plan, architectural, structural, electrical, and reflected ceiling plans with respect to proposed placement of signage
to identify and resolve potential conflicts.
• Obtain 'over the counter" review and approval of exterior signage from the planning department, if necessary.
• Continue development of sign location plans and sign schedule.
• Present design development drawings to N&T and library staff for review and approval.
Consultant Deliverables
• Approved design development package: sign schedule, sign location plans, design development drawings, preliminary specifications.
2
Matthew Williams Design 510.559.1830 desk mw®matthewwilliamsdesign.com Proposal
1450 Fourth Street, Studio 9 415.205.0412 mobile www.matthewwilliamsdesign com
Berkeley. CA 94710 USA
Phase 3: Construction Documents (CD):
• Incorporate comments from design development review.
• Finalize sign schedule and sign location plans.
• Continue coordination with N&T and designated San Rafael Library staff.
• Prepare annotated design intent drawings and performance specifications, including qualified sign vendors, for all sign types.
• Specify all interior sign types from the Standards. The design intent drawings will indicate graphic layouts, materials, finishes,
colors, and relevant dimensions. Methods of fabrication will be suggested, but not shown in detail.
• Submit 90% complete package for permit, coordination, review and comments. Incorporate comments.
• Submit 100% construction documents suitable for competitive bid.
Consultant Deliverables:
• 90% Submittal for final review and permit.
• 100% Submittal forbid.
Included in Phase 3 are three meetings:
• Kickoff meeting.
• Coordination meeting with N&T.
• Coordination meeting with designated San Rafael Library staff.
Phase 4: Construction Administration (CA):
• Attend prefabrication conference with the selected sign subcontractor to confirm project conditions, specifications, submittals,
and schedule prior to start of fabrication.
• Review shop drawings, samples, and prototypes to ensure compliance with design intent.
• Provide clarification to the sign subcontractor for drawings and specifications. Respond to RAS.
• Continue coordination with N&T and designated San Rafael Library staff.
• Conduct a pre -installation walkthrough with the signage fabricator.
• Conduct a punchlist walkthrough and prepare a punchlist of all items requiring corrections. Backpunch the work.
Consultant Deliverables:
• Completed and punched work.
Included in Phase 4 are:
• One prefabrication conference.
• One pre -installation walkthrough.
• One site visit for punchlist.
• One site visit for backpunch.
3
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Nataly Torres (for Fabiola Guillen-Urfer) Extension: 3353
Contractor Name: Noll & Tam Architects
Contractor's Contact: Amy Watson Contact's Email: amy.watson@nollandtam.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor
Click here to
❑
e11te1- a date.
b. Email contract (in Word) and attachments to City
N/A
Attorney c/o Laraine.Gittens@cityofsanrafael.org
❑x
2
City Attorney
a. Review, revise, and comment on draft agreement
10/23/2023
and return to Project Manager
10/23/2023
❑X NT
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
❑X NT
3
Department Director
Approval of final agreement form to send to
10/23/2023
X AM
contractor
4
Project Manager
Forward three (3) originals of final agreement to
10/25/2023
contractor for their signature
5
Project Manager
When necessary, contractor-siened agreement
❑ N/A
agendized for City Council approval *
*City Council approval required for Professional Services
Xi
Agreements and purchases of goods and services that exceed
Or
$7S,000; and for Public Works Contracts that exceed $17S,000
9/18/2023
Date of City Council approval
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
agreement
8
City Attorney
Review and approve insurance in PINS, and bonds
(for Public Works Contracts)
9
City Manager / Mayor Agreement executed by City Council authorized
official
City Clerk Attest signatures, retains original agreement and
10
forwards copies to Project Manager
First Amendment - Noll & Tam - Downtown
Library Modernization
Final Audit Report 2023-11-02
Created: 2023-10-25
By: Nataly Torres (nataly.tares@cityofsanrafael.org)
Status: Signed
Transaction ID: CBJCHBCAABAAva—PruindkF4VFFYuZAB6rPp_urtTnb
"First Amendment - Noll & Tam - Downtown Library Modernizati
on" History
Document created by Nataly Torres (nataly.torres@cityofsanrafael.org)
2023-10-25 - 11:37:28 PM GMT
Document emailed to chris.noll@nollandtam.com for signature
2023-10-25 - 11:52:31 PM GMT
Email viewed by chris.noll@nollandtam.com
2023-10-26 - 6:43:55 AM GMT
i Signer chris.noll@nollandtam.com entered name at signing as Christopher Noll
2023-10-27 - 2:08:51 AM GMT
do Document e-signed by Christopher Noll (chris.noll@nollandtam.com)
Signature Date: 2023-10-27 - 2:08:53 AM GMT - Time Source: server
Document emailed to Janet Tam Oanet.tam@nollandtam.com) for signature
2023-10-27 - 2:08:54 AM GMT
Email viewed by Janet Tam Qanet.tam@nollandtam.com)
2023-10-27 - 2:10:00 AM GMT
b© Document e-signed by Janet Tam Oanet.tam@nollandtam.com)
Signature Date: 2023-10-27 - 2:13:11 AM GMT - Time Source: server
Document emailed to Laraine Gittens (laraine.gittens@cityofsanrafael.org) for approval
2023-10-27 - 2:13:13 AM GMT
Email viewed by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2023-10-27 - 5:09:11 AM GMT
R, SAN RAFAEL Adobe
ll���
Acrobat Sign
b© Document approved by Laraine Gittens(laraine.gittens@cityofsanrafael.org)
Approval Date: 2023-10-27 - 3:55:30 PM GMT - Time Source: server
Document emailed to Genevieve Coyle (genevieve.coyle@cityofsanrafael.org) for signature
2023-10-27 - 3:55:32 PM GMT
Email viewed by Genevieve Coyle (genevieve.coyle@cityofsanrafael.org)
2023-10-27 - 3:55:38 PM GMT
Email viewed by Genevieve Coyle (genevieve.coyle@cityofsanrafael.org)
2023-11-01 - 10:45:11 PM GMT
bo Document e-signed by Genevieve Coyle (genevieve.coyle@cityofsanrafael.org)
Signature Date: 2023-11-01 - 10:45:34 PM GMT - Time Source: server
Document emailed to city.clerk@cityofsanrafael.org for approval
2023-11-01-10:45:36 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2023-11-01-10:45:52 PM GMT
b© Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi
2023-11-01 - 10:46:06 PM GMT
b� Document approved by Brenna Nurmi (city.clerk@cityofsanrafael.org)
Approval Date: 2023-11-01 - 10:46:08 PM GMT - Time Source: server
P- 4 Document emailed to cristine.alilovich@cityofsanrafael.org for signature
2023-11-01 - 10:46:09 PM GMT
Email viewed by cristine.alilovich@cityofsanrafael.org
2023-11-01 - 11:29:17 PM GMT
b© Signer cristine.alilovich@cityofsanrafael.org entered name at signing as Cristine Alilovich
2023-11-02 - 4:57:27 AM GMT
b© Document e-signed by Cristine Alilovich (cristine.alilovich@cityofsanrafael.org)
Signature Date: 2023-11-02 - 4:57:29 AM GMT - Time Source: server
C'-. Document emailed to city. clerk@cityofsanrafael.org for signature
2023-11-02 - 4:57:30 AM GMT
Email viewed by city.clerk@cityofsanrafael.org
2023-11-02 - 2:52:44 PM GMT
b© Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi (for)
2023-11-02 - 2:53:03 PM GMT
fir• SAN RAFAEL P--dbY
Adobe
rive ury wine a r.ossor+ Acrobat Sign
do Document e-signed by Brenna Nurmi (for)(city.clerk@cityofsanrafael.org)
Signature Date: 2023-11-02 - 2:53:05 PM GMT - Time Source: server
Agreement completed.
2023-11-02 - 2:53:05 PM GMT
SAN RAFAEL I Powered
ower by
THE CRY Acrobat Sign