HomeMy WebLinkAboutPW Third Street Safety Improvements ProjectAGREEMENT FOR PROFESSIONAL SERVICES WITH PARK ENGINEERING, INC.
FOR CONSTRUCTION MANAGEMENT & MATERIAL TESTING SERVICES
FOR THE THIRD STREET SAFETY IMPROVEMENTS PROJECT
ARTICLE I INTRODUCTION
A. This AGREEMENT is entered into as of the day of Aug 29, 2023 2023 by and between the
following named, hereinafter referred to as CONSULTANT, and the following named, hereinafter
referred to as LOCAL AGENCY:
The name of the "CONSULTANT" is as follows: Park Enqineering, Inc., incorporated in or
authorized to do business in the State of California.
The Project Manager for the "CONSULTANT" will be Steve Patterson
The name of the "LOCAL AGENCY" is as follows: City of San Rafael
The Contract Administrator for LOCAL AGENCY will be April Miller, Public Works Director
B. The work to be performed under this AGREEMENT is described in Article III Statement of Work and
the approved CONSULTANT's Cost Proposal ("Cost Proposal") dated March 7, 2022. The approved
CONSULTANT's Cost Proposal is included in Exhibit A and incorporated by reference. If there is any
conflict between the approved Cost Proposal and this AGREEMENT, this AGREEMENT shall take
precedence.
C. CONSULTANT agrees to the fullest extent permitted by law, to indemnify, protect, defend, and hold
harmless LOCAL AGENCY, its officers, agents, and employees and volunteers from and against any
and all claims, damages, demands, liability, costs, losses and expenses, including without limitation,
court costs and reasonable attorney's and expert witness fees, arising out of any failure to comply
with applicable law, any injury to or death of any person(s), damage to property, loss of use of
property, economic loss or otherwise arising out of the performance of the work described herein, to
the extent caused by a negligent act or negligent failure to act, errors, omissions, recklessness or
willful misconduct incident to the performance of this AGREEMENT on the part of CONSULTANT,
except CONSULTANT will not reimburse LOCAL AGENCY for any such loss or damage which was
caused by the sole negligence, or willful misconduct of LOCAL AGENCY, as determined by a Court
of competent jurisdiction. The provisions of this section shall survive termination or suspension of this
AGREEMENT.
D. CONSULTANT in the performance of this AGREEMENT shall act in an independent capacity. It is
understood and agreed that CONSULTANT (including CONSULTANT'S employees) is an
independent contractor and that no relationship of employer -employee exists between the Parties
hereto. CONSULTANT'S assigned personnel shall not be entitled to any benefits payable to
employees of LOCAL AGENCY.
E. LOCAL AGENCY is not required to make deductions or withholdings from the compensation payable
to CONSULTANT under the provisions of the AGREEMENT and is not required to issue W-2 Forms
for income and employment tax purposes for any of CONSULTANT's assigned personnel.
CONSULTANT in the performance of its obligation hereunder, is only subject to the control of
direction of the LOCAL AGENCY as to the designation of tasks to be performed and the results to be
accomplished,
F. Any third -party person(s) employed by CONSULTANT shall be entirely and exclusively under the
direction, supervision, and control of CONSULTANT. CONSULTANT hereby indemnifies and holds
LOCAL AGENCY harmless from any and all claims that may be made against LOCAL AGENCY
based upon any contention by any third party that an employer -employee relationship exists by
reason of this AGREEMENT.
Page 1 of 22
G. Except as expressly authorized herein, CONSULTANT's obligations under this AGREEMENT are not
assignable or transferable, and CONSULTANT shall not subcontract any work, without the prior
written approval of the LOCAL AGENCY. However, claims for money due or which become due to
CONSULTANT from LOCAL AGENCY under this AGREEMENT may be assigned to a financial
institution or to a trustee in bankruptcy, without such approval. Notice of any assignment or transfer
whether voluntary or involuntary shall be furnished promptly to the LOCAL AGENCY.
H. CONSULTANT shall be as fully responsible to the LOCAL AGENCY for the negligent acts and
omissions of its contractors and subcontractors or subconsultants, and of persons either directly or
indirectly employed by them, in the same manner as persons directly employed by CONSULTANT.
I. No alteration or variation of the terms of this AGREEMENT shall be valid, unless made in writing and
signed by the parties authorized to bind the parties; and no oral understanding or agreement not
incorporated herein, shall be binding on any of the parties hereto.
J. The consideration to be paid to CONSULTANT as provided herein, shall be in compensation for all of
CONSULTANT's expenses incurred in the performance hereof, including travel and per diem, unless
otherwise expressly so provided.
ARTICLE II CONSULTANT'S REPORTS OR MEETINGS
A. CONSULTANT shall submit progress reports at least once a month. The report should be sufficiently
detailed for the LOCAL AGENCY's Contract Administrator to determine if CONSULTANT is
performing to expectations, or is on schedule; to provide communication of interim findings, and to
sufficiently address any difficulties or special problems encountered, so remedies can be developed.
B. CONSULTANT's Project Manager shall meet with LOCAL AGENCY's Contract Administrator, as
needed, to discuss progress on the AGREEMENT.
ARTICLE III STATEMENT OF WORK
The CONSULTANT shall perform the services specified in the Scope of Work, dated March 7, 2022,
attached hereto as Exhibit A and incorporated herein by reference. If there is any conflict between
the terms of the Cost Proposal, included in Exhibit A, and the terms of this AGREEMENT, the terms
of this AGREEMENT shall take precedence.
ARTICLE IV PERFORMANCE PERIOD
A. This AGREEMENT shall go into effect on July 1, 2022, contingent upon approval by LOCAL
AGENCY, and CONSULTANT shall commence work after notification to proceed by LOCAL
AGENCY'S Contract Administrator. The AGREEMENT shall end upon completion of the work to the
satisfaction of the LOCAL AGENCY'S Contract Administrator.
B. CONSULTANT is advised that any recommendation for AGREEMENT award is not binding on
LOCAL AGENCY until the AGREEMENT is fully executed and approved by LOCAL AGENCY.
ARTICLE V ALLOWABLE COSTS AND PAYMENTS
A. CONSULTANT will be reimbursed for hours worked at the hourly rates specified in the
CONSULTANT's approved Cost Proposal. The specified hourly rates shall include direct salary
costs, employee benefits, prevailing wages, employer payments, overhead, and fee. These rates
are not adjustable for the performance period set forth in this AGREEMENT. CONSULTANT will
Page 2 of 22
be reimbursed within thirty (30) days upon receipt by LOCAL AGENCY'S Contract Administrator of
itemized invoices in duplicate.
B. In addition, CONSULTANT will be reimbursed for incurred (actual) direct costs other than salary
costs that are in the approved Cost Proposal and identified in the approved Cost Proposal.
C. Reserved.
D. Reserved.
E. Reserved.
F. Reimbursement for transportation and subsistence costs shall not exceed the rates as specified in
the approved Cost Proposal. CONSULTANT will be responsible for transportation and subsistence
costs in excess of State rates.
G. When milestone cost estimates are included in the approved Cost Proposal, CONSULTANT shall
obtain prior written approval in the form of an AGREEMENT amendment for a revised milestone
cost estimate from the Contract Administrator before exceeding such estimate.
H. Progress payments will be made monthly in arrears based on services provided and actual costs
incurred.
CONSULTANT shall not commence performance of work or services until this AGREEMENT has
been approved by LOCAL AGENCY and notification to proceed has been issued by LOCAL
AGENCY'S Contract Administrator. No payment will be made prior to approval or for any work
performed prior to approval of this AGREEMENT.
Reserved.
K. CONSULTANT will be reimbursed within thirty (30) days upon receipt by LOCAL AGENCY'S
Contract Administrator of itemized invoices in duplicate. Invoices shall be submitted no later than
thirty (30) calendar days after the performance of work for which CONSULTANT is billing. Invoices
shall detail the work performed on each milestone, on each project as applicable. Invoices shall
follow the format stipulated for the approved Cost Proposal and shall reference this AGREEMENT
number and project title. Credits due LOCAL AGENCY that include any equipment purchased
under the provisions of Article XI Equipment Purchase, must be reimbursed by CONSULTANT
prior to the expiration or termination of this AGREEMENT. Invoices shall be mailed to LOCAL
AGENCY's Contract Administrator at the following address:
City of San Rafael Department of Public Works
April Miller
111 Morphew Street
San Rafael, CA 94901
L. Reserved.
M. The total amount payable by LOCAL AGENCY shall not exceed the amount agreed to in this
AGREEMENT, unless authorized by amendment.
N. Reserved.
Page 3 of 22
O. Reserved.
P. The total amount payable by LOCAL AGENCY for all work resulting from this AGREEMENT shall
not exceed $ 258,498.65. It is understood and agreed that there is no guarantee, either expressed
or implied that this dollar amount will be authorized under this AGREEMENT.
ARTICLE VI TERMINATION
A. This AGREEMENT may be terminated by LOCAL AGENCY, provided that LOCAL AGENCY gives
not less than thirty (30) calendar days' written notice (delivered by certified mail, return receipt
requested) of intent to terminate. Upon termination, LOCAL AGENCY shall be entitled to all work,
including but not limited to, reports, investigations, appraisals, inventories, studies, analyses,
drawings and data estimates performed to that date, whether completed or not, and in accordance
with Article XXVI, Ownership of Data.
B. LOCAL AGENCY may temporarily suspend this AGREEMENT, at no additional cost to LOCAL
AGENCY, provided that CONSULTANT is given written notice (delivered by certified mail, return
receipt requested) of temporary suspension. If LOCAL AGENCY gives such notice of temporary
suspension, CONSULTANT shall immediately suspend its activities under this AGREEMENT. A
temporary suspension may be issued concurrent with the notice of termination provided for in
subsection A of this section.
C. Notwithstanding any provisions of this AGREEMENT, CONSULTANT shall not be relieved of liability
to LOCAL AGENCY for damages sustained by LOCAL AGENCY by virtue of any breach of this
AGREEMENT by CONSULTANT, and LOCAL AGENCY may withhold any payments due to
CONSULTANT until such time as the exact amount of damages, if any, due LOCAL AGENCY from
CONSULTANT is determined.
D. In the event of termination, CONSULTANT shall be compensated as provided for in this
AGREEMENT, except as provided in Article XI, section C. Upon termination, LOCAL AGENCY shall
be entitled to all work, including but not limited to, reports, investigations, appraisals, inventories,
studies, analyses, drawings and data estimates performed to that date, whether completed or not,
and in accordance with Article XXVI, Ownership of Data.
ARTICLE VII COST PRINCIPLES AND ADMINISTRATIVE REQUIREMENTS
A. The CONSULTANT agrees that 48 CFR Part 31, Contract Cost Principles and Procedures, shall be
used to determine the allowability of individual items of cost.
B. The CONSULTANT also agrees to comply with Federal procedures in accordance with 2 CFR Part
200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal
Awards.
C. Any costs for which payment has been made to the CONSULTANT that are determined by
subsequent audit to be unallowable under 48 CFR Part 31 or 2 CFR Part 200, are subject to
repayment by the CONSULTANT to LOCAL AGENCY.
D. When a CONSULTANT or Subconsultant is a Non -Profit Organization or an Institution of Higher
Education, the Cost Principles for Title 2 CFR Part 200, Uniform Administrative Requirements, Cost
Principles, and Audit Requirements for Federal Awards shall apply.
ARTICLE VIII RETENTION OF RECORDS/AUDIT
For the purpose of determining compliance with Gov. Code §8546.7, the CONSULTANT,
Subconsultants, and LOCAL AGENCY shall maintain all books, documents, papers, accounting records,
Page 4 of 22
Independent CPA Audited Indirect Cost Rate workpapers, and other evidence pertaining to the
performance of the AGREEMENT including, but not limited to, the costs of administering the
AGREEMENT. All parties, including the CONSULTANT's Independent CPA, shall make such workpapers
and materials available at their respective offices at all reasonable times during the AGREEMENT period
and for three (3) years from the date of final payment under the AGREEMENT. LOCAL AGENCY,
Caltrans Auditor, FHWA, or any duly authorized representative of the Federal government having
jurisdiction under Federal laws or regulations (including the basis of Federal funding in whole or in part)
shall have access to any books, records, and documents of the CONSULTANT, Subconsultants, and the
CONSULTANT's Independent CPA, that are pertinent to the AGREEMENT for audits, examinations,
workpaper review, excerpts, and transactions, and copies thereof shall be furnished if requested without
limitation.
ARTICLE IX AUDIT REVIEW PROCEDURES
A. Any dispute concerning a question of fact arising under an interim or post audit of this AGREEMENT
that is not disposed of by agreement, shall be reviewed by LOCAL AGENCY'S Finance Director.
B. Not later than thirty (30) days after issuance of the final audit report, CONSULTANT may request a
review by LOCAL AGENCY'S Finance Director of unresolved audit issues. The request for review
will be submitted in writing.
C. Neither the pendency of a dispute nor its consideration by LOCAL AGENCY will excuse
CONSULTANT from full and timely performance, in accordance with the terms of this AGREEMENT.
D. CONSULTANT and subconsultant AGREEMENTs, including cost proposals and Indirect Cost Rates
(ICR), may be subject to audits or reviews such as, but not limited to, an AGREEMENT audit, an
incurred cost audit, an ICR Audit, or a CPA ICR audit work paper review. If selected for audit or
review, the AGREEMENT, cost proposal and ICR and related work papers, if applicable, will be
reviewed to verify compliance with 48 CFR, Part 31 and other related laws and regulations. In the
instances of a CPA ICR audit work paper review it is CONSULTANT's responsibility to ensure federal,
LOCAL AGENCY, or local government officials are allowed full access to the CPA's work papers
including making copies as necessary. The AGREEMENT, cost proposal, and ICR shall be adjusted
by CONSULTANT and approved by LOCAL AGENCY Contract Administrator to conform to the audit
or review recommendations. CONSULTANT agrees that individual terms of costs identified in the
audit report shall be incorporated into the AGREEMENT by this reference if directed by LOCAL
AGENCY at its sole discretion. Refusal by CONSULTANT to incorporate audit or review
recommendations, or to ensure that the federal, LOCAL AGENCY or local governments have access
to CPA work papers, will be considered a breach of AGREEMENT terms and cause for termination
of the AGREEMENT and disallowance of prior reimbursed costs.
E. CONSULTANT's Cost Proposal may be subject to a CPA ICR Audit Work Paper Review and/or audit
by Caltrans Audits and Investigation (A&I). Caltrans A&I, at its sole discretion, may review and/or
audit and approve the CPA ICR documentation. The Cost Proposal shall be adjusted by the
CONSULTANT and approved by the LOCAL AGENCY Contract Administrator to conform to the Work
Paper Review recommendations included in the management letter or audit recommendations
included in the audit report. Refusal by the CONSULTANT to incorporate the Work Paper Review
recommendations included in the management letter or audit recommendations included in the audit
report will be considered a breach of the AGREEMENT terms and cause for termination of the
AGREEMENT and disallowance of prior reimbursed costs.
1. During Caltrans A&I's review of the ICR audit work papers created by the CONSULTANT's
independent CPA, Caltrans A&I will work with the CPA and/or CONSULTANT toward a resolution
of issues that arise during the review. Each party agrees to use its best efforts to resolve any audit
disputes in a timely manner. If Caltrans A&I identifies significant issues during the review and is
unable to issue a cognizant approval letter, LOCAL AGENCY will reimburse the CONSULTANT
Page 5 of 22
at an accepted ICR until a FAR (Federal Acquisition Regulation) compliant ICR {e.g. 48 CFR Part
31; GAAS (Generally Accepted Auditing Standards); CAS (Cost Accounting Standards), if
applicable; in accordance with procedures and guidelines of the American Association of State
Highways and Transportation Officials (AASHTO) Audit Guide; and other applicable procedures
and guidelines}is received and approved by A&I.
Accepted rates will be as follows:
a. If the proposed rate is less than one hundred fifty percent (150%) - the accepted rate
reimbursed will be ninety percent (90%) of the proposed rate.
b. If the proposed rate is between one hundred fifty percent (150%) and two hundred percent
(200%) - the accepted rate will be eighty-five percent (85%) of the proposed rate.
c. If the proposed rate is greater than two hundred percent (200%) - the accepted rate will be
seventy-five percent (75%) of the proposed rate.
2. If Caltrans A&I is unable to issue a cognizant letter per paragraph E.1. above, Caltrans A&I may
require CONSULTANT to submit a revised independent CPA -audited ICR and audit report within
three (3) months of the effective date of the management letter. Caltrans A&I will then have up to
six (6) months to review the CONSULTANT's and/or the independent CPA's revisions.
3. If the CONSULTANT fails to comply with the provisions of this paragraph E, or if Caltrans A&I is
still unable to issue a cognizant approval letter after the revised independent CPA audited ICR is
submitted, overhead cost reimbursement will be limited to the accepted ICR that was established
upon initial rejection of the ICR and set forth in paragraph E.1. above for all rendered services. In
this event, this accepted ICR will become the actual and final ICR for reimbursement purposes
under this AGREEMENT.
4. CONSULTANT may submit to LOCAL AGENCY final invoice only when all of the following items
have occurred: (1) Caltrans A&I accepts or adjusts the original or revised independent CPA
audited ICR; (2) all work under this AGREEMENT has been completed to the satisfaction of
LOCAL AGENCY; and, (3) Caltrans A&I has issued its final ICR review letter. The CONSULTANT
MUST SUBMIT ITS FINAL INVOICE TO LOCAL AGENCY no later than sixty (60) calendar days
after occurrence of the last of these items. The accepted ICR will apply to this AGREEMENT and
all other agreements executed between LOCAL AGENCY and the CONSULTANT, either as a
prime or subconsultant, with the same fiscal period ICR.
ARTICLE X SUBCONTRACTING
A. Nothing contained in this AGREEMENT or otherwise, shall create any contractual relation between
LOCAL AGENCY and any Subconsultants, and no sub -agreement shall relieve the CONSULTANT
of its responsibilities and obligations hereunder. The CONSULTANT agrees to be as fully responsible
to LOCAL AGENCY for the acts and omissions of its Subconsultants and of persons either directly or
indirectly employed by any of them as it is for the acts and omissions of persons directly employed
by the CONSULTANT. The CONSULTANT's obligation to pay its Subconsultants is an independent
obligation from LOCAL AGENCY'S obligation to make payments to the CONSULTANT.
B. The CONSULTANT shall perform the work contemplated with resources available within its own
organization and no portion of the work shall be subcontracted without written authorization by the
LOCAL AGENCY Contract Administrator, except that which is expressly identified in the
CONSULTANT's approved Cost Proposal.
C. Any sub -agreement entered into as a result of this AGREEMENT, shall contain all the provisions
stipulated in this entire AGREEMENT to be applicable to Subconsultants unless otherwise noted.
Page 6 of 22
D. CONSULTANT shall pay its Subconsultants within Fifteen (15) calendar days from receipt of each
payment made to the CONSULTANT by the LOCAL AGENCY.
E. Any substitution of Subconsultants must be approved in writing by LOCAL AGENCY Contract
Administrator in advance of assigning work to a substitute Subconsultant.
ARTICLE XI EQUIPMENT PURCHASE AND OTHER CAPITAL EXPENDITURES
A. Prior authorization in writing, by LOCAL AGENCY's Contract Administrator shall be required before
CONSULTANT enters into any unbudgeted purchase order, or subcontract exceeding five thousand
dollars ($5,000) for supplies, equipment, or CONSULTANT services. CONSULTANT shall provide
an evaluation of the necessity or desirability of incurring such costs.
B. For purchase of any item, service, or consulting work not covered in CONSULTANT's approved Cost
Proposal and exceeding five thousand dollars ($5,000), with prior authorization by LOCAL AGENCY's
Contract Administrator, three competitive quotations must be submitted with the request, or the
absence of bidding must be adequately justified.
C. Any equipment purchased as a result of this contract is subject to the following:
1. CONSULTANT shall maintain an inventory of all nonexpendable property. Nonexpendable
property is defined as having a useful life of at least two years and an acquisition cost of five
thousand dollars ($5,000) or more. If the purchased equipment needs replacement and is sold
or traded in, LOCAL AGENCY shall receive a proper refund or credit at the conclusion of the
AGREEMENT, or if the AGREEMENT is terminated, CONSULTANT may either keep the
equipment and credit LOCAL AGENCY in an amount equal to its fair market value, or sell such
equipment at the best price obtainable at a public or private sale, in accordance with established
LOCAL AGENCY procedures; and credit LOCAL AGENCY in an amount equal to the sales price.
If CONSULTANT elects to keep the equipment, fair market value shall be determined at
CONSULTANT's expense, on the basis of a competent independent appraisal of such equipment.
Appraisals shall be obtained from an appraiser mutually agreeable to by LOCAL AGENCY and
CONSULTANT, if it is determined to sell the equipment, the terms and conditions of such sale
must be approved in advance by LOCAL AGENCY.
2. Regulation 2 CFR Part 200 requires a credit to Federal funds when participating equipment with
a fair market value greater than five thousand dollars ($5,000) is credited to the project.
ARTICLE XII STATE PREVAILING WAGE RATES
A. No CONSULTANT or Subconsultant may be awarded an AGREEMENT containing public work
elements unless registered with the Department of Industrial Relations (DIR) pursuant to Labor Code
§1725.5. Registration with DIR must be maintained throughout the entire term of this AGREEMENT,
including any subsequent amendments.
B. The CONSULTANT shall comply with all of the applicable provisions of the California Labor Code
requiring the payment of prevailing wages. The General Prevailing Wage Rate Determinations
applicable to work under this AGREEMENT are available and on file with the Department of
Transportation's Regional/District Labor Compliance Officer
(http //www.dot.ca.gov/hq/construc/LaborCompliance/documents/District-
Region Map Construction 7-8-15.pd_o.
These wage rates are made a specific part of this AGREEMENT by reference pursuant to Labor Code
§1773.2 and will be applicable to work performed at a construction project site. Prevailing wages will
be applicable to all inspection work performed at LOCAL AGENCY construction sites, at LOCAL
AGENCY facilities and at off -site locations that are set up by the construction contractor or one of its
Page 7 of 22
subcontractors solely and specifically to serve LOCAL AGENCY projects. Prevailing wage
requirements do not apply to inspection work performed at the facilities of vendors and commercial
materials suppliers that provide goods and services to the general public.
C. General Prevailing Wage Rate Determinations applicable to this project may also be obtained from
the Department of Industrial Relations Internet site at http //www.dir.ca.gov.
D. Payroll Records
1. Each CONSULTANT and Subconsultant shall keep accurate certified payroll records and
supporting documents as mandated by Labor Code §1776 and as defined in 8 CCR §16000
showing the name, address, social security number, work classification, straight time and
overtime hours worked each day and week, and the actual per diem wages paid to each
journeyman, apprentice, worker, or other employee employed by the CONSULTANT or
Subconsultant in connection with the public work. Each payroll record shall contain or be verified
by a written declaration that it is made under penalty of perjury, stating both of the following:
a. The information contained in the payroll record is true and correct.
b. The employer has complied with the requirements of Labor Code §1771, §1811, and §1815
for any work performed by his or her employees on the public works project.
2. The payroll records enumerated under paragraph (1) above shall be certified as correct by the
CONSULTANT under penalty of perjury. The payroll records and all supporting documents shall
be made available for inspection and copying by LOCAL AGENCY representatives at all
reasonable hours at the principal office of the CONSULTANT. The CONSULTANT shall provide
copies of certified payrolls or permit inspection of its records as follows:
a. A certified copy of an employee's payroll record shall be made available for inspection or
furnished to the employee or the employee's authorized representative on request.
b. A certified copy of all payroll records enumerated in paragraph (1) above, shall be made
available for inspection or furnished upon request to a representative of LOCAL AGENCY, the
Division of Labor Standards Enforcement and the Division of Apprenticeship Standards of the
Department of Industrial Relations. Certified payrolls submitted to LOCAL AGENCY, the Division
of Labor Standards Enforcement and the Division of Apprenticeship Standards shall not be altered
or obliterated by the CONSULTANT.
c. The public shall not be given access to certified payroll records by the CONSULTANT. The
CONSULTANT is required to forward any requests for certified payrolls to the LOCAL
AGENCY Contract Administrator by both email and regular mail on the business day following
receipt of the request.
3. Each CONSULTANT shall submit a certified copy of the records enumerated in paragraph (1)
above, to the entity that requested the records within ten (10) calendar days after receipt of a
written request.
4. Any copy of records made available for inspection as copies and furnished upon request to the
public or any public agency by LOCAL AGENCY shall be marked or obliterated in such a manner
as to prevent disclosure of each individual's name, address, and social security number. The
name and address of the CONSULTANT or Subconsultant performing the work shall not be
marked or obliterated.
5. The CONSULTANT shall inform LOCAL AGENCY of the location of the records enumerated
under paragraph (1) above, including the street address, city and county, and shall, within five (5)
working days, provide a notice of a change of location and address.
6. The CONSULTANT or Subconsultant shall have ten (10) calendar days in which to comply
subsequent to receipt of written notice requesting the records enumerated in paragraph (1) above.
Page 8 of 22
In the event the CONSULTANT or Subconsultant fails to comply within the ten (10) day period,
he or she shall, as a penalty to LOCAL AGENCY, forfeit one hundred dollars ($100) for each
calendar day, or portion thereof, for each worker, until strict compliance is effectuated. Such
penalties shall be withheld by LOCAL AGENCY from payments then due. CONSULTANT is not
subject to a penalty assessment pursuant to this section due to the failure of a Subconsultant to
comply with this section.
E. When prevailing wage rates apply, the CONSULTANT is responsible for verifying compliance with
certified payroll requirements. Invoice payment will not be made until the invoice is approved by the
LOCAL AGENCY Contract Administrator.
F. Penalty
1. The CONSULTANT and any of its Subconsultants shall comply with Labor Code §1774 and
§1775. Pursuant to Labor Code §1775, the CONSULTANT and any Subconsultant shall forfeit to
the LOCAL AGENCY a penalty of not more than two hundred dollars ($200) for each calendar
day, or portion thereof, for each worker paid less than the prevailing rates as determined by the
Director of DIR for the work or craft in which the worker is employed for any public work done
under the AGREEMENT by the CONSULTANT or by its Subconsultant in violation of the
requirements of the Labor Code and in particular, Labor Code §§1770 to 1780, inclusive.
2. The amount of this forfeiture shall be determined by the Labor Commissioner and shall be based
on consideration of mistake, inadvertence, or neglect of the CONSULTANT or Subconsultant in
failing to pay the correct rate of prevailing wages, or the previous record of the CONSULTANT or
Subconsultant in meeting their respective prevailing wage obligations, or the willful failure by the
CONSULTANT or Subconsultant to pay the correct rates of prevailing wages. A mistake,
inadvertence, or neglect in failing to pay the correct rates of prevailing wages is not excusable if
the CONSULTANT or Subconsultant had knowledge of the obligations under the Labor Code.
The CONSULTANT is responsible for paying the appropriate rate, including any escalations that
take place during the term of the AGREEMENT.
3. In addition to the penalty and pursuant to Labor Code §1775, the difference between the prevailing
wage rates and the amount paid to each worker for each calendar day or portion thereof for which
each worker was paid less than the prevailing wage rate shall be paid to each worker by the
CONSULTANT or Subconsultant.
4. If a worker employed by a Subconsultant on a public works project is not paid the general
prevailing per diem wages by the Subconsultant, the prime CONSULTANT of the project is not
liable for the penalties described above unless the prime CONSULTANT had knowledge of that
failure of the Subconsultant to pay the specified prevailing rate of wages to those workers or
unless the prime CONSULTANT fails to comply with all of the following requirements:
a. The AGREEMENT executed between the CONSULTANT and the Subconsultant for the
performance of work on public works projects shall include a copy of the requirements in Labor
Code §§1771, 1775, 1776, 1777.5, 1813, and 1815.
b. The CONSULTANT shall monitor the payment of the specified general prevailing rate of per
diem wages by the Subconsultant to the employees by periodic review of the certified payroll
records of the Subconsultant.
c. Upon becoming aware of the Subconsultant's failure to pay the specified prevailing rate of
wages to the Subconsultant's workers, the CONSULTANT shall diligently take corrective action
to halt or rectify the failure, including but not limited to, retaining sufficient funds due the
Subconsultant for work performed on the public works project.
d. Prior to making final payment to the Subconsultant for work performed on the public works
project, the CONSULTANT shall obtain an affidavit signed under penalty of perjury from the
Subconsultant that the Subconsultant had paid the specified general prevailing rate of per diem
Page 9 of 22
wages to the Subconsultant's employees on the public works project and any amounts due
pursuant to Labor Code §1813.
5. Pursuant to Labor Code §1775, LOCAL AGENCY shall notify the CONSULTANT on a public
works project within fifteen (15) calendar days of receipt of a complaint that a Subconsultant has
failed to pay workers the general prevailing rate of per diem wages.
6. If LOCAL AGENCY determines that employees of a Subconsultant were not paid the general
prevailing rate of per diem wages and if LOCAL AGENCY did not retain sufficient money under
the AGREEMENT to pay those employees the balance of wages owed under the general
prevailing rate of per diem wages, the CONSULTANT shall withhold an amount of moneys due
the Subconsultant sufficient to pay those employees the general prevailing rate of per diem wages
if requested by LOCAL AGENCY.
G. Hours of Labor
Eight (8) hours labor constitutes a legal day's work. The CONSULTANT shall forfeit, as a penalty to
the LOCAL AGENCY, twenty-five dollars ($25) for each worker employed in the execution of the
AGREEMENT by the CONSULTANT or any of its Subconsultants for each calendar day during which
such worker is required or permitted to work more than eight (8) hours in any one calendar day and
forty (40) hours in any one calendar week in violation of the provisions of the Labor Code, and in
particular §§1810 to 1815 thereof, inclusive, except that work performed by employees in excess of
eight (8) hours per day, and forty (40) hours during any one week, shall be permitted upon
compensation for all hours worked in excess of eight (8) hours per day and forty (40) hours in any
week, at not less than one and one-half (1.5) times the basic rate of pay, as provided in §1815.
H. Employment of Apprentices
1. Where either the prime AGREEMENT or the sub -agreement exceeds thirty thousand dollars
($30,000), the CONSULTANT and any subconsultants under him or her shall comply with all
applicable requirements of Labor Code §§1777.5, 1777.6 and 1777.7 in the employment of
apprentices.
2. CONSULTANTs and subconsultants are required to comply with all Labor Code requirements
regarding the employment of apprentices, including mandatory ratios of journey level to
apprentice workers. Prior to commencement of work, CONSULTANT and subconsultants are
advised to contact the DIR Division of Apprenticeship Standards website at
https://www.dir.ca.gov/das/, for additional information regarding the employment of apprentices
and for the specific journey -to- apprentice ratios for the AGREEMENT work. The CONSULTANT
is responsible for all subconsultants' compliance with these requirements. Penalties are specified
in Labor Code §1777.7.
ARTICLE XIII CONFLICT OF INTEREST (Verbatim)
A. During the term of this AGREEMENT, the CONSULTANT shall disclose any financial, business, or
other relationship with LOCAL AGENCY that may have an impact upon the outcome of this
AGREEMENT or any ensuing LOCAL AGENCY construction project. The CONSULTANT shall also
list current clients who may have a financial interest in the outcome of this AGREEMENT, or any
ensuing LOCAL AGENCY construction project, which will follow.
B. CONSULTANT certifies that it has disclosed to LOCAL AGENCY any actual, apparent, or potential
conflicts of interest that may exist relative to the services to be provided pursuant to this
AGREEMENT. CONSULTANT agrees to advise LOCAL AGENCY of any actual, apparent or
potential conflicts of interest that may develop subsequent to the date of execution of this
Page 10 of 22
AGREEMENT. CONSULTANT further agrees to complete any statements of economic interest if
required by either LOCAL AGENCY ordinance or State law.
C. The CONSULTANT hereby certifies that it does not now have nor shall it acquire any financial or
business interest that would conflict with the performance of services under this AGREEMENT.
D. The CONSULTANT hereby certifies that the CONSULTANT or subconsultant and any firm affiliated
with the CONSULTANT or subconsultant that bids on any construction contract or on any Agreement
to provide construction inspection for any construction project resulting from this AGREEMENT, has
established necessary controls to ensure a conflict of interest does not exist. An affiliated firm is one,
which is subject to the control of the same persons, through joint ownership or otherwise.
ARTICLE XIV REBATES, KICKBACKS OR OTHER UNLAWFUL CONSIDERATION
The CONSULTANT warrants that this AGREEMENT was not obtained or secured through rebates,
kickbacks or other unlawful consideration either promised or paid to any LOCAL AGENCY employee.
For breach or violation of this warranty, LOCAL AGENCY shall have the right, in its discretion, to
terminate this AGREEMENT without liability, to pay only for the value of the work actually performed, or
to deduct from the AGREEMENT price or otherwise recover the full amount of such rebate, kickback or
other unlawful consideration.
ARTICLE XV PROHIBITION OF EXPENDING LOCAL AGENCY, STATE, OR FEDERAL FUNDS FOR
LOBBYING
A. CONSULTANT certifies to the best of his or her knowledge and belief that:
No state, federal or local agency appropriated funds have been paid or will be paid, by or on
behalf of the CONSULTANT, to any person for influencing or attempting to influence an officer or
employee of any local, State, or Federal agency, a Member of the State Legislature or United
States Congress, an officer or employee of the Legislature or Congress, or any employee of a
Member of the Legislature or Congress in connection with the awarding or making of this
AGREEMENT, or with the extension, continuation, renewal, amendment, or modification of this
AGREEMENT.
2. If any funds other than Federal appropriated funds have been paid, or will be paid to any person
for influencing or attempting to influence an officer or employee of any agency, a Member of
Congress, an officer or employee of Congress, or an employee of a Member of Congress in
connection with this AGREEMENT, the CONSULTANT shall complete and submit Standard
Form-LLL, "Disclosure Form to Report Lobbying", in accordance with its instructions.
B. This certification is a material representation of fact upon which reliance was placed when this
transaction was made or entered into. Submission of this certification is a prerequisite for making or
entering into this transaction imposed by 31 U.S.C. §1352. Any person who fails to file the required
certification shall be subject to a civil penalty of not less than ten thousand dollars ($10,000) and not
more than one hundred thousand dollars ($100,000) for each such failure.
C. The CONSULTANT also agrees by signing this document that he or she shall require that the
language of this certification be included in all lower tier sub -agreements, which exceed one hundred
thousand dollars ($100,000) and that all such subrecipients shall certify and disclose accordingly.
Page 11 of 22
ARTICLE XVI NON-DISCRIMINATION AND STATEMENT OF COMPLIANCE
A. The CONSULTANT's signature affixed herein and dated shall constitute a certification under penalty
of perjury under the laws of the State of California that CONSULTANT has, unless exempt, complied
with the nondiscrimination program requirements of Gov. Code §12990 and 2 CCR §8103.
B. During the performance of this AGREEMENT, CONSULTANT and its subconsultants shall not deny
the AGREEMENT's benefits to any person on the basis of race, religious creed, color, national origin,
ancestry, physical disability, mental disability, medical condition, genetic information, marital status,
sex, gender, gender identity, gender expression, age, sexual orientation, or military and veteran
status, nor shall they unlawfully discriminate, harass, or allow harassment against any employee or
applicant for employment because of race, religious creed, color, national origin, ancestry, physical
disability, mental disability, medical condition, genetic information, marital status, sex, gender, gender
identity, gender expression, age, sexual orientation, or military and veteran status. CONSULTANT
and subconsultants shall insure that the evaluation and treatment of their employees and applicants
for employment are free from such discrimination and harassment.
C. CONSULTANT and subconsultants shall comply with the provisions of the Fair Employment and
Housing Act (Gov. Code §12990 et seq.), the applicable regulations promulgated there under (2 CCR
§11000 et seq.), the provisions of Gov. Code §§11135-11139.5, and the regulations or standards
adopted by LOCAL AGENCY to implement such article. The applicable regulations of the Fair
Employment and Housing Commission implementing Gov. Code §12990 (a-f), set forth 2 CCR
§§8100-8504, are incorporated into this AGREEMENT by reference and made a part hereof as if set
forth in full.
D. CONSULTANT shall permit access by representatives of the Department of Fair Employment and
Housing and the LOCAL AGENCY upon reasonable notice at any time during the normal business
hours, but in no case less than twenty-four (24) hours' notice, to such of its books, records, accounts,
and all other sources of information and its facilities as said Department or LOCAL AGENCY shall
require to ascertain compliance with this clause.
E. CONSULTANT and its subconsultants shall give written notice of their obligations under this clause
to labor organizations with which they have a collective bargaining or other Agreement.
F. CONSULTANT shall include the nondiscrimination and compliance provisions of this clause in all
subcontracts to perform work under this AGREEMENT.
G. The CONSULTANT, with regard to the work performed under this AGREEMENT, shall act in
accordance with Title VI of the Civil Rights Act of 1964 (42 U.S.C. §2000d et seq.). Title VI provides
that the recipients of federal assistance will implement and maintain a policy of nondiscrimination in
which no person in the United States shall, on the basis of race, color, national origin, religion, sex,
age, disability, be excluded from participation in, denied the benefits of or subject to discrimination
under any program or activity by the recipients of federal assistance or their assignees and
successors in interest.
H. The CONSULTANT shall comply with regulations relative to non-discrimination in federally -assisted
programs of the U.S. Department of Transportation (49 CFR Part 21 - Effectuation of Title VI of the
Civil Rights Act of 1964). Specifically, the CONSULTANT shall not participate either directly or
indirectly in the discrimination prohibited by 49 CFR §21.5, including employment practices and the
selection and retention of Subconsultants.
Page 12 of 22
ARTICLE XVII DEBARMENT AND SUSPENSION CERTIFICATION
A. CONSULTANT's signature affixed herein, shall constitute a certification under penalty of perjury
under the laws of the State of California, that the CONSULTANT or any person associated therewith
in the capacity of owner, partner, director, officer, or manager:
1. Is not currently under suspension, debarment, voluntary exclusion, or determination of ineligibility
by any federal agency;
2. Has not been suspended, debarred, voluntarily excluded, or determined ineligible by any federal
agency within the past three (3) years;
3. Does not have a proposed debarment pending; and
4. Has not been indicted, convicted, or had a civil judgment rendered against it by a court of
competent jurisdiction in any matter involving fraud or official misconduct within the past three (3)
years.
B. Any exceptions to this certification must be disclosed to LOCAL AGENCY. Exceptions will not
necessarily result in denial of recommendation for award but will be considered in determining
responsibility. Disclosures must indicate to whom exceptions apply, the initiating agency, and the
dates of agency action.
C. Exceptions to the Federal Government Excluded Parties List System maintained by the U.S. General
Services Administration are to be determined by FHWA.
ARTICLE XVIII DISADVANTAGED BUSINESS ENTERPRISES (DBE) PARTICIPATION
A. This AGREEMENT is subject to 49 CFR Part 26 entitled "Participation by Disadvantaged Business
Enterprises in Department of Transportation Financial Assistance Programs". CONSULTANTs who
enter into a federally -funded agreement will assist the LOCAL AGENCY in a good faith effort to
achieve California's statewide overall DBE goal.
B. The goal for DBE participation for this AGREEMENT is 6_0%. Participation by DBE CONSULTANT
or subconsultants shall be in accordance with information contained in Exhibit 10-01: Consultant
Proposal DBE Commitment , or in Exhibit 10-02: Consultant Contract DBE Commitment attached
hereto and incorporated as part of the AGREEMENT. If a DBE subconsultant is unable to perform,
CONSULTANT must make a good faith effort to replace him/her with another DBE subconsultant, if
the goal is not otherwise met.
C. CONSULTANT can meet the DBE participation goal by either documenting commitments to DBEs to
meet the AGREEMENT goal, or by documenting adequate good faith efforts to meet the
AGREEMENT goal. An adequate good faith effort means that the CONSULTANT must show that it
took all necessary and reasonable steps to achieve a DBE goal that, by their scope, intensity, and
appropriateness to the objective, could reasonably be expected to meet the DBE goal. If
CONSULTANT has not met the DBE goal, complete and submit Exhibit 15-H: DBE Information —
Good Faith Efforts to document efforts to meet the goal. Refer to 49 CFR Part 26 for guidance
regarding evaluation of good faith efforts to meet the DBE goal.
D. DBEs and other small businesses, as defined in 49 CFR Part 26 are encouraged to participate in the
performance of AGREEMENTS financed in whole or in part with federal funds. The LOCAL AGENCY,
CONSULTANT or subconsultant shall not discriminate on the basis of race, color, national origin, or
sex in the performance of this contract. The CONSULTANT shall carry out applicable requirements
of 49 CFR part 26 in the award and administration of DOT -assisted contracts. Failure by the
CONSULTANT to carry out these requirements is a material breach of this AGREEMENT, which may
result in the termination of this AGREEMENT or such other remedy as the LOCAL AGENCY deems
appropriate, which may include, but is not limited to:
Page 13 of 22
1. Withholding monthly progress payments;
2. Assessing sanctions;
3. Liquidated damages; and/or
4. Disqualifying the contractor from future bidding as non -responsible
E. A DBE firm may be terminated only with prior written approval from LOCAL AGENCY and only for
the reasons specified in 49 CFR §26.53(f . Prior to requesting LOCAL AGENCY consent for the
termination, CONSULTANT must meet the procedural requirements specified in 49 CFR §26.53(f). If
a DBE subconsultant is unable to perform, CONSULTANT must make a good faith effort to replace
him/her with another DBE subconsultant, if the goal is not otherwise met.
F. Consultant shall not be entitled to any payment for such work or material unless it is performed or
supplied by the listed DBE or by other forces (including those of Consultant) pursuant to prior written
authorization of the LOCAL AGENCY's Contract Administrator.
G. A DBE is only eligible to be counted toward the AGREEMENT goal if it performs a commercially
useful function (CUF) on the AGREEMENT. CUF must be evaluated on an agreement by agreement
basis. A DBE performs a Commercially Useful Function (CUF) when it is responsible for execution of
the work of the AGREEMENT and is carrying out its responsibilities by actually performing, managing,
and supervising the work involved. To perform a CUF, the DBE must also be responsible, with
respect to materials and supplies used on the AGREEMENT, for negotiating price, determining quality
and quantity, ordering the material and installing (where applicable), and paying for the material itself.
To determine whether a DBE is performing a CUF, evaluate the amount of work subcontracted,
industry practices, whether the amount the firm is to be paid under the AGREEMENT is
commensurate with the work it is actually performing, and other relevant factors.
H. A DBE does not perform a CUF if its role is limited to that of an extra participant in a transaction,
AGREEMENT, or project through which funds are passed in order to obtain the appearance of DBE
participation. In determining whether a DBE is such an extra participant, examine similar
transactions, particularly those in which DBEs do not participate.
I. If a DBE does not perform or exercise responsibility for at least thirty percent (30%) of the total cost
of its AGREEMENT with its own work force, or the DBE subcontracts a greater portion of the work of
the AGREEMENT than would be expected on the basis of normal industry practice for the type of
work involved, it will be presumed that it is not performing a CUF.
J. CONSULTANT shall maintain records of materials purchased or supplied from all subcontracts
entered into with certified DBEs. The records shall show the name and business address of each
DBE or vendor and the total dollar amount actually paid each DBE or vendor, regardless of tier. The
records shall show the date of payment and the total dollar figure paid to all firms. DBE prime
CONSULTANT's shall also show the date of work performed by their own forces along with the
corresponding dollar value of the work.
K. Upon completion of the AGREEMENT, a summary of these records shall be prepared and submitted
on the form entitled, Exhibit 17-F. Final Report -Utilization of Disadvantaged Business Enterprise
(DBE) First -Tier Subconsultants, certified correct by CONSULTANT or CONSULTANT's authorized
representative and shall be furnished to the Contract Administrator with the final invoice. Failure to
provide the summary of DBE payments with the final invoice will result in twenty-five percent (25%)
of the dollar value of the invoice being withheld from payment until the form is submitted. The amount
will be returned to CONSULTANT when a satisfactory "Final Report -Utilization of Disadvantaged
Business Enterprises (DBE), First -Tier Subconsultants" is submitted to the Contract Administrator.
L. If a DBE subconsultant is decertified during the life of the AGREEMENT, the decertified subconsultant
shall notify CONSULTANT in writing with the date of decertification. If a subconsultant becomes a
certified DBE during the life of the AGREEMENT, the subconsultant shall notify CONSULTANT in
Page 14 of 22
writing with the date of certification. Any changes should be reported to LOCAL AGENCY's Contract
Administrator within thirty (30) calendar days.
M. Any subcontract entered into as a result of this AGREEMENT shall contain all of the provisions of this
section.
ARTICLE XIX INSURANCE
A. Scope of Coverage. During the term of this Agreement, CONSULTANT shall maintain, at no expense
to LOCAL AGENCY, the following insurance policies:
1. A commercial general liability insurance policy in the minimum amount of one million dollars
($1,000,000) per occurrence/two million dollars ($2,000,000) aggregate, for death, bodily injury,
personal injury, or property damage.
2. An automobile liability (owned, non -owned, and hired vehicles) insurance policy in the minimum
amount of one million dollars ($1,000,000) dollars per occurrence.
3. If any licensed professional performs any of the services required to be performed under this
Agreement, a professional liability insurance policy in the minimum amount of one million dollars
($1,000,000) per occurrence/two million dollars ($2,000,000) aggregate, to cover any claims arising
out of the CONSULTANT's performance of services under this Agreement. Where CONSULTANT
is a professional not required to have a professional license, LOCAL AGENCY reserves the right to
require CONSULTANT to provide professional liability insurance pursuant to this section.
4. If it employs any person, CONSULTANT shall maintain worker's compensation insurance, as
required by the State of California, with statutory limits, and employer's liability insurance with
limits of no less than one million dollars ($1,000,000) per accident for bodily injury or disease.
CONSULTANT's worker's compensation insurance shall be specifically endorsed to waive any
right of subrogation against LOCAL AGENCY.
B. Other Insurance Requirements. The insurance coverage required of the CONSULTANT in
subparagraph A of this section above shall also meet the following requirements:
1. Except for professional liability insurance or worker's compensation insurance, the insurance policies
shall be specifically endorsed to include the LOCAL AGENCY, its officers, agents, employees, and
volunteers, as additional insureds (for both ongoing and completed operations) under the policies.
2. The additional insured coverage under CONSULTANT'S insurance policies shall be "primary and
noncontributory" with respect to any insurance or coverage maintained by LOCAL AGENCY and
shall not call upon LOCAL AGENCY's insurance or self-insurance coverage for any contribution.
The "primary and noncontributory" coverage in CONSULTANT'S policies shall be at least as broad
as ISO form CG20 01 04 13.
3. Except for professional liability insurance or worker's compensation insurance, the insurance policies
shall include, in their text or by endorsement, coverage for contractual liability and personal injury.
4. By execution of this Agreement, CONSULTANT hereby grants to LOCAL AGENCY a waiver of
any right to subrogation which any insurer of CONSULTANT may acquire against LOCAL
AGENCY by virtue of the payment of any loss under such insurance. CONSULTANT agrees to
obtain any endorsement that may be necessary to affect this waiver of subrogation, but this
provision applies regardless of whether or not LOCAL AGENCY has received a waiver of
subrogation endorsement from the insurer.
5. If the insurance is written on a Claims Made Form, then, following termination of this Agreement,
said insurance coverage shall survive for a period of not less than five years.
Page 15 of 22
6. The insurance policies shall provide for a retroactive date of placement coinciding with the effective
date of this Agreement.
7. The limits of insurance required in this Agreement may be satisfied by a combination of primary and
umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to
contain a provision that such coverage shall also apply on a primary and noncontributory basis for
the benefit of LOCAL AGENCY (if agreed to in a written contract or agreement) before LOCAL
AGENCY'S own insurance or self-insurance shall be called upon to protect it as a named insured.
8. It shall be a requirement under this Agreement that any available insurance proceeds broader than
or in excess of the specified minimum insurance coverage requirements and/or limits shall be
available to LOCAL AGENCY or any other additional insured party. Furthermore, the requirements
for coverage and limits shall be: (1) the minimum coverage and limits specified in this Agreement; or
(2) the broader coverage and maximum limits of coverage of any insurance policy or proceeds
available to the named insured; whichever is greater. No representation is made that the minimum
Insurance requirements of this agreement are sufficient to cover the obligations of the
CONSULTANT under this agreement.
C. Deductibles and SIR's. Any deductibles or self -insured retentions in CONSULTANT's insurance
policies must be declared to and approved by the PROJECT MANAGER and City Attorney and shall not
reduce the limits of liability. Policies containing any self -insured retention (SIR) provision shall provide
or be endorsed to provide that the SIR may be satisfied by either the named insured or LOCAL AGENCY
or other additional insured party. At LOCAL AGENCY's option, the deductibles or self -insured retentions
with respect to LOCAL AGENCY shall be reduced or eliminated to LOCAL AGENCY's satisfaction, or
CONSULTANT shall procure a bond guaranteeing payment of losses and related investigations, claims
administration, attorney's fees and defense expenses.
D. Proof of Insurance. CONSULTANT shall provide to the PROJECT MANAGER or LOCAL AGENCY'S
City Attorney all of the following: (1) Certificates of Insurance evidencing the insurance coverage required
in this Agreement; (2) a copy of the policy declaration page and/or endorsement page listing all policy
endorsements for the commercial general liability policy, and (3) excerpts of policy language or specific
endorsements evidencing the other insurance requirements set forth in this Agreement. LOCAL
AGENCY reserves the right to obtain a full certified copy of any insurance policy and endorsements from
CONSULTANT. Failure to exercise this right shall not constitute a waiver of the right to exercise it later.
The insurance shall be approved as to form and sufficiency by PROJECT MANAGER and the City
Attorney.
ARTICLE XX FUNDING REQUIREMENTS
A. It is mutually understood between the parties that this AGREEMENT may have been written before
ascertaining the availability of funds or appropriation of funds, for the mutual benefit of both parties,
in order to avoid program and fiscal delays that would occur if the AGREEMENT were executed after
that determination was made.
B. This AGREEMENT is valid and enforceable only, if sufficient funds are made available to LOCAL
AGENCY for the purpose of this AGREEMENT. In addition, this AGREEMENT is subject to any
additional restrictions, limitations, conditions, or any statute enacted by the Congress, State
Legislature, or LOCAL AGENCY governing board that may affect the provisions, terms, or funding
of this AGREEMENT in any manner.
C. It is mutually agreed that if sufficient funds are not appropriated, this AGREEMENT may be amended
to reflect any reduction in funds.
D. LOCAL AGENCY has the option to terminate the AGREEMENT pursuant to Article VI Termination,
or by mutual agreement to amend the AGREEMENT to reflect any reduction of funds.
Page 16 of 22
ARTICLE XXI CHANGE IN TERMS
A. This AGREEMENT may be amended or modified only by mutual written agreement of the parties.
B. CONSULTANT shall only commence work covered by an amendment after the amendment is
executed and notification to proceed has been provided by LOCAL AGENCY's Contract
Administrator.
C. There shall be no change in CONSULTANT's Project Manager or members of the project team, as
listed in the approved Cost Proposal, which is a part of this AGREEMENT without prior written
approval by LOCAL AGENCY's Contract Administrator.
ARTICLE XXII CONTINGENT FEE
CONSULTANT warrants, by execution of this AGREEMENT that no person or selling agency has
been employed, or retained, to solicit or secure this AGREEMENT upon an agreement or
understanding, for a commission, percentage, brokerage, or contingent fee, excepting bona fide
employees, or bona fide established commercial or selling agencies maintained by CONSULTANT
for the purpose of securing business. For breach or violation of this warranty, LOCAL AGENCY has
the right to annul this AGREEMENT without liability; pay only for the value of the work actually
performed, or in its discretion to deduct from the AGREEMENT price or consideration, or otherwise
recover the full amount of such commission, percentage, brokerage, or contingent fee.
ARTICLE XXIII DISPUTES
Prior to either party commencing any legal action under this AGREEMENT, the parties agree to try in
good faith, to settle any dispute amicably between them. If a dispute has not been settled after forty-five
(45) days of good -faith negotiations and as may be otherwise provided herein, then either party may
commence legal action against the other.
A. Any dispute, other than audit, concerning a question of fact arising under this AGREEMENT that is
not disposed of by agreement shall be decided by a committee consisting of LOCAL AGENCY's
Contract Administrator and other LOCAL AGENCY representatives who may consider written or
verbal information submitted by CONSULTANT.
B. Not later than thirty (30) days after completion of all work under the AGREEMENT, CONSULTANT
may request review by LOCAL AGENCY Governing Board of unresolved claims or disputes, other
than audit. The request for review will be submitted in writing.
C. Neither the pendency of a dispute, nor its consideration by the committee will excuse CONSULTANT
from full and timely performance in accordance with the terms of this AGREEMENT.
ARTICLE XXIV INSPECTION OF WORK
CONSULTANT and any subconsultant shall permit LOCAL AGENCY, the State, and the FHWA if federal
participating funds are used in this AGREEMENT; to review and inspect the project activities and files at
all reasonable times during the performance period of this AGREEMENT.
ARTICLE XXV SAFETY
Page 17 of 22
A. CONSULTANT shall comply with OSHA regulations applicable to CONSULTANT regarding
necessary safety equipment or procedures. CONSULTANT shall comply with safety instructions
issued by LOCAL AGENCY Safety Officer and other LOCAL AGENCY representatives.
CONSULTANT personnel shall wear hard hats and safety vests at all times while working on the
construction project site.
B. Pursuant to the authority contained in Vehicle Code §591, LOCAL AGENCY has determined that
such areas are within the limits of the project and are open to public traffic. CONSULTANT shall
comply with all of the requirements set forth in Divisions 11, 12, 13, 14, and 15 of the Vehicle Code.
CONSULTANT shall take all reasonably necessary precautions for safe operation of its vehicles and
the protection of the traveling public from injury and damage from such vehicles.
C. CONSULTANT must have a Division of Occupational Safety and Health (CAL -OSHA) permit(s), as
outlined in California Labor Code §6500 and §6705, prior to the initiation of any practices, work,
method, operation, or process related to the construction or excavation of trenches which are five (5)
feet or deeper.
ARTICLE XXVI OWNERSHIP OF DATA
A. It is mutually agreed that all materials prepared by CONSULTANT under this AGREEMENT shall
become the property of LOCAL AGENCY, and CONSULTANT shall have no property right therein
whatsoever. Immediately upon termination, LOCAL AGENCY shall be entitled to, and
CONSULTANT shall deliver to LOCAL AGENCY, reports, investigations, appraisals, inventories,
studies, analyses, drawings and data estimates performed to that date, whether completed or not,
and other such materials as may have been prepared or accumulated to date by CONSULTANT in
performing this AGREEMENT which is not CONSULTANT's privileged information, as defined by
law, or CONSULTANT's personnel information, along with all other property belonging exclusively
to LOCAL AGENCY which is in CONSULTANT's possession. Publication of the information derived
from work performed or data obtained in connection with services rendered under this AGREEMENT
must be approved in writing by LOCAL AGENCY.
B. Additionally, it is agreed that the Parties intend this to be an AGREEMENT for services and each
considers the products and results of the services to be rendered by CONSULTANT hereunder to
be work made for hire. CONSULTANT acknowledges and agrees that the work (and all rights
therein, including, without limitation, copyright) belongs to and shall be the sole and exclusive
property of LOCAL AGENCY without restriction or limitation upon its use or dissemination by LOCAL
AGENCY.
C. Nothing herein shall constitute or be construed to be any representation by CONSULTANT that the
work product is suitable in any way for any other project except the one detailed in this
AGREEMENT. Any reuse by LOCAL AGENCY for another project or project location shall be at
LOCAL AGENCY's sole risk.
D. Applicable patent rights provisions regarding rights to inventions shall be included in the contracts
as appropriate (48 CFR 27 Subpart 27.3 - Patent Rights under Government Contracts for federal -
aid contracts).
E. LOCAL AGENCY may permit copyrighting reports or other agreement products. If copyrights are
permitted; the AGREEMENT shall provide that the FHWA shall have the royalty -free nonexclusive
and irrevocable right to reproduce, publish, or otherwise use; and to authorize others to use, the
work for government purposes.
ARTICLE XXVII CLAIMS FILED BY LOCAL AGENCY's CONSTRUCTION CONTRACTOR
Page 18 of 22
A. If claims are filed by LOCAL AGENCY's construction contractor relating to work performed by
CONSULTANT's personnel, and additional information or assistance from CONSULTANT's
personnel is required in order to evaluate or defend against such claims; CONSULTANT agrees to
make its personnel available for consultation with LOCAL AGENCY'S construction contract
administration and legal staff and for testimony, if necessary, at depositions and at trial or arbitration
proceedings.
B. CONSULTANT's personnel that LOCAL AGENCY considers essential to assist in defending against
construction contractor claims will be made available on reasonable notice from LOCAL AGENCY.
Consultation or testimony will be reimbursed at the same rates, including travel costs that are being
paid for CONSULTANT's personnel services under this AGREEMENT.
C. Services of CONSULTANT's personnel in connection with LOCAL AGENCY's construction contractor
claims will be performed pursuant to a written contract amendment, if necessary, extending the
termination date of this AGREEMENT in order to resolve the construction claims.
ARTICLE XXVIII CONFIDENTIALITY OF DATA
A. All financial, statistical, personal, technical, or other data and information relative to LOCAL
AGENCY's operations, which are designated confidential by LOCAL AGENCY and made available
to CONSULTANT in order to carry out this AGREEMENT, shall be protected by CONSULTANT from
unauthorized use and disclosure.
B. Permission to disclose information on one occasion, or public hearing held by LOCAL AGENCY
relating to the AGREEMENT, shall not authorize CONSULTANT to further disclose such information,
or disseminate the same on any other occasion.
C. CONSULTANT shall not comment publicly to the press or any other media regarding the
AGREEMENT or LOCAL AGENCY's actions on the same, except to LOCAL AGENCY's staff,
CONSULTANT's own personnel involved in the performance of this AGREEMENT, at public
hearings, or in response to questions from a Legislative committee.
D. CONSULTANT shall not issue any news release or public relations item of any nature, whatsoever,
regarding work performed or to be performed under this AGREEMENT without prior review of the
contents thereof by LOCAL AGENCY, and receipt of LOCAL AGENCY'S written permission.
E. All information related to the construction estimate is confidential and shall not be disclosed by
CONSULTANT to any entity, other than LOCAL AGENCY, Caltrans, and/or FHWA. All of the
materials prepared or assembled by CONSULTANT pursuant to performance of this AGREEMENT
are confidential and CONSULTANT agrees that they shall not be made available to any individual or
organization without the prior written approval of LOCAL AGENCY or except by court order. If
CONSULTANT or any of its officers, employees, or subcontractors does voluntarily provide
information in violation of this AGREEMENT, LOCAL AGENCY has the right to reimbursement and
indemnity from CONSULTANT for any damages caused by CONSULTANT releasing the information,
including, but not limited to, LOCAL AGENCY's attorney's fees and disbursements, including without
limitation experts' fees and disbursements.
ARTICLE XXIX NATIONAL LABOR RELATIONS BOARD CERTIFICATION
In accordance with Public Contract Code §10296, CONSULTANT hereby states under penalty of perjury
that no more than one final unappealable finding of contempt of court by a federal court has been issued
against CONSULTANT within the immediately preceding two-year period, because of CONSULTANT's
failure to comply with an order of a federal court that orders CONSULTANT to comply with an order of
the National Labor Relations Board.
Page 19 of 22
ARTICLE XXX EVALUATION OF CONSULTANT
CONSULTANT's performance will be evaluated by LOCAL AGENCY. A copy of the evaluation will be
sent to CONSULTANT for comments. The evaluation together with the comments shall be retained as
part of the AGREEMENT record.
ARTICLE XXXI RETENTION OF FUNDS
No retainage will be held by the LOCAL AGENCY from progress payments due the CONSULTANT. Any
retainage held by the CONSULTANT or subconsultants from progress payments due subconsultants
shall be promptly paid in full to subconsultants within thirty (30) days after the subconsultant's work is
satisfactorily completed. Federal law (49 CFR §26.29) requires that any delay or postponement of
payment over thirty (30) calendar days may take place only for good cause and with the LOCAL
AGENCY's prior written approval. Any violation of this provision shall subject the violating CONSULTANT
or subconsultant to the penalties, sanctions and other remedies specified in Business and Professions
Code §7108.5. These requirements shall not be construed to limit or impair any contractual,
administrative, or judicial remedies, otherwise available to the CONSULTANT or subconsultant in the
event of a dispute involving late payment or nonpayment by the CONSULTANT, deficient subconsultant
performance, or noncompliance by a subconsultant. This provision applies to both DBE and non -DBE
CONSULTANT and subconsultants.
ARTICLE XXXII NOTIFICATION
All notices hereunder and communications regarding interpretation of the terms of this AGREEMENT
and changes thereto, shall be effected by the mailing thereof by registered or certified mail, return receipt
requested, postage prepaid, and addressed as follows:
CONSULTANT. Park Engineering, Inc.
Steve Patterson, Vice President
372 Village Square
Orinda, CA 94563
LOCAL AGENCY City of San Rafael
April Miller, Contract Administrator
111 Morphew Street
San Rafael, CA 94901
ARTICLE XXXIII CONTRACT
The two parties to this AGREEMENT, who are the before named CONSULTANT and the before named
LOCAL AGENCY, hereby agree that this AGREEMENT constitutes the entire AGREEMENT which is
made and concluded in duplicate between the two parties. Both of these parties for and in consideration
of the payments to be made, conditions mentioned, and work to be performed; each agree to diligently
perform in accordance with the terms and conditions of this AGREEMENT as evidenced by the signatures
below.
Page 20 of 22
ARTICLE XXXIV NO THIRD PARTY BENEFICIARIES
LOCAL AGENCY and CONSULTANT do not intend, by any provision of this contract, to create in any third
party, any benefit or right owed by one party, under the terms and conditions of this AGREEMENT, to the
other party.
ARTICLE XXXV COSTS AND ATTORNEY'S FEES
The prevailing party in any action brought to enforce the terms and conditions of this AGREEMENT, or
arising out of the performance of this AGREEMENT, may recover its reasonable costs (including claims
administration) and attorney's fees expended in connection with such action.
ARTICLE XXXVI LOCAL AGENCY BUSINESS LICENSE I OTHER TAXES
CONSULTANT shall obtain and maintain during the duration of this contract, a LOCAL AGENCY business
license as required by the San Rafael Municipal Code. CONSULTANT shall pay any and all state and
federal taxes and any other applicable taxes. LOCAL AGENCY shall not be required to pay for any work
performed under this contract, until CONSULTANT has provided LOCAL AGENCY with a completed Internal
Revenue Service Form W-9 (Request for Taxpayer Identification Number and Certification).
ARTICLE XXXVII WAIVERS
The waiver by either party of any breach or violation of any term, covenant or condition of this AGREEMENT,
or of any ordinance, law or regulation, shall not be deemed to be a waiver of any other term, covenant,
condition, ordinance, law or regulation, or of any subsequent breach or violation of the same or other term,
covenant, condition, ordinance, law or regulation. The subsequent acceptance by either party of any fee,
performance, or other consideration which may become due or owing under this AGREEMENT, shall not be
deemed to be a waiver of any preceding breach or violation by the other party of any term, condition,
covenant of this contract or any applicable law, ordinance or regulation.
ARTICLE XXXVIII APPLICABLE LAW
The laws of the State of California shall govern this AGREEMENT
CONSULTANT shall observe and comply with all applicable federal, state and local laws, ordinances, codes
and regulations, in the performance of its duties and obligations under this AGREEMENT. CONSULTANT
shall perform all services under this AGREEMENT in accordance with these laws, ordinances, codes and
regulations. CONSULTANT shall release, defend, indemnify and hold harmless LOCAL AGENCY, its
officers, agents and employees from any and all damages, liabilities, penalties, fines and all other
consequences from any noncompliance or violation of any laws, ordinances, codes or regulations.
Page 21 of 22
ARTICLE XXXIX SIGNATURES
CITY OF SAN RAFAEL
Cristine Alilovic (Aug29. 202311:03 PDT)
CRISTINE ALILOVICH
City Manager
I_1a1*31
a-enna Numi (fay)
Brenna Nurmi (for) (Aug 2q 311:219
LINDSAY LARA
City Clerk
APPROVED AS TO FORM
ROBERT F. EPSTEIN
City Attorney
PARK ENGINEERING, INC.
By.
Title: Vice President
and
By;JarmmP.nY f •, _07317:13PDT,
Title: President/CEO/CFO
Page 21 of 22
Exhibit A
March 7, 2022
Shawn Graf
City of San Rafael
111 Morphew Street
San Rafael, CA 94901
RE: Construction Management & Material Testing Services — Cost Proposal
3`d Street Safety Improvements Project
Dear Shawn,
Thank You again for selecting Park Engineering to provide Construction Management &
Material Testing Services for the City's 3`d Street Safety Improvements Project, we are
looking forward to continue working with the City on this project.
Attached please find our cost proposal to furnish the required services to ensure the
project's quality & compliance, as well as efforts to complete the project safely for both
the workers and the public.
If there are any questions, or if any additional information is needed, please contact me
on my mobile at 510-701-0319 or at spatterson@park-enp,.com.
Sincerely,
Steve Patterson, P.E.
Vice President
Attachments
Orinda Office
372 Village Square
Orinda, CA 94563
Tel: 925-257-2508
Fax: 925-401-7030
Emeryville Office
3960 Adeline Street, #3
Emeryville, CA 94608
Tel: 925-257-2508
Fax: 925-401-7030
Proposal to Provide
City of San Rafael
Construction Management, Inspection and Testing Services
for the Third Street Safety Improvements Project
City Project No. 11362
February 3, 2022
PARK
ENGINEERING
February 3, 2022
Shawn Graf, Assistant Engineer
City of San Rafael
111 Morphew Street
San Rafael, CA 94901
RE: Construction Management, Inspection & Material Testing Services for
Third Street Safety Improvements Project
Dear Shawn,
Park Engineering, Inc. is pleased to submit this proposal to provide construction
management, inspection & material testing services for the Third Street Safety
Improvements Project. We appreciate the opportunity to continue to work with the City
on this project that will improve signal operations and pedestrian travel for a number of
intersections along V Street near Highway 101. Improvements consist of curb ramp &
sidewalk, high -visibility crosswalks, drainage and traffic signal improvements.
Steve Patterson, with over 30 years of experience, will be the Resident Engineer for this
project. Steve brings expertise in public works and roadway construction with federal
funding and has managed multiple local agency roadway, including multiple projects for
the City. Most recently, Steve was the Construction Manager for the Francisco Blvd. East
Sidewalk Improvement Project, which required extensive public outreach and
coordination with utilities, other contractors, businesses, local residents and daily
commuters, as well as being federally funded.
Assisting Steve on this project is Construction Inspector, Andy Bodo who has 22 years of
experience providing construction management and inspection for public works
construction projects. Andy has worked on a previous signal improvement project for
the City of San Mateo and briefly helped out on the City's 2017 FEMA funded Slide Repair
Project. Mike Johnson will be available for an optional 2nd inspector for possible
extended day and night work operations.
To provide materials testing on the project, we have included Applied Materials &
Engineering, a local materials testing and special inspection firm with exceptional
experience with Caltrans and ASTM certified testing for roadway and public works
construction projects.
As principal in charge, I will provide oversight to the construction team as well as provide
any other needed support to the City. Our team can meet the challenges anticipated on
this project and will ensure that the work is successfully completed in accordance with all
local, state and federal regulations. Our team has the necessary technical expertise, as
well as soft skills required to complete this project for the City of San Rafael.
We have read and will comply with City's sample Professional Service Agreement without
changes. Should you have any questions or need additional information, please do not
Officelage
hesitate to contact me. I can be reached at 372 Village Square, Orinda, CA 94563,
72 Vil
372 Vilclalage Square
ipark@park-eng.corn and (925) 818-3756.
Orinda, CA 94563
Tel: 925-257-2508
Fax: 925-401-7030
Sincerely,
Emeryville Office
vl~H
3960 Adeline Street, #3
Emeryville, CA 94608
Jaemin Park, PE
Tel: 925-257-2508
President
Fax: 925-401-7030
EXPERIENCE & TECHNICAL COMPETENCE
FIRM PROFILE
Park Engineering, Inc. was founded in 2013 with
the vision of providing high quality construction
management, construction inspection, program/
project management, project controls, and
contract administration services to public agencies
on transportation and infrastructure projects.
Park Engineering is led by Jaemin Park and Steve
Patterson as the principals of the company. Our
company of 13 is comprised of experienced
professionals who have worked together for
numerous transportation and local agencies
throughout the San Francisco Bay Area. Our
collective project experience includes roadway
rehabilitation and repaving, streetscapes including
street lighting and signals, sanitary sewer projects,
bridge rehabilitation and replacements, rail and
grade separations, and many other local agency
projects constructed to Local, Caltrans and Federal
requirements.
Park Engineering specializes in projects with
Federal, State, bond, grant and other specialty
funding requiring coordination with and audits by,
Caltrans, FHWA and other oversight agencies.
Specialties
Construction Management
Resident Engineering
Construction Inspection
Program Management/Project
Management
Project Controls and Document Control
SWPPP Implementation and Inspection
Scheduling and Schedule Control
Cost Estimating and Cost Control
Utility Coordination
Claims Analysis, Negotiation and Resolution
Support
Value Engineering
Permit Compliance
Constructability and Bid -ability Review
Bid Advertisement and Award
Staff Augmentation
Federal and State Audit Support
Federal Fund Reimbursement and Project
Closeout
Public and Community Outreach
Training and Staff Development
Certifications
State of California CUCP DBE/UDBE (No.
41711)
State of California DGS SBE (No. 1757722)
Park Engineering, Inc.
2013
• • Corporation
Headquarters:
• • 372 Village Square
Orinda, CA 94563
Tel: (925) 257-2508
Fax: (925) 401-7030
www.park-eng.com
Additional Office:
3960 Adeline Street, #3
Emeryville, CA 94608
Jaemin Park, PE
President
Cell: (925) 818-3756
E-Mail: ipark@park-
eng.com
13
• . Jaemin Park, PE
President
Steve Patterson, PE
Vice President
Registered Professional
Civil Engineer(s), State of
California
Park Engineering, Inc. has expertise delivering
projects for local agencies that include new
roadway and street improvements, bridge
replacements, widenings and retrofits,
streetscapes, water and sewer lines, buildings,
pump stations, signals and lighting, and working
in sensitive environments. Our expertise
includes administering construction projects to
Caltrans Standards and Local Assistance
Procedures and administering projects that
receive funding from multiple sources, including
federal, State, local tax measure, special grant
and local funds. We have the skills necessary to
ensure thorough reporting and strict adherence
to federal and state guidelines.
City of San Rafael
Construction Management Services for
Third Street Safety Improvements Project
SIMILAR PROJECT EXPERIENCE
Our firm currently holds construction management
and inspection contracts with cities and counties
throughout the Bay Area. The firm's most recent
similar projects to provide Construction
Management & Inspection Services include:
As -Needed Project Management, Construction
Management and Inspection Services; City of San
Rafael, Public Works Department, San Rafael, CA
Description: Park Engineering is currently working
with the Public Works Department. Projects include
improvements to roadways and bridges, drainage
and pump stations, and facility upgrades at
community centers and parking structures. Park
Engineering has provided assistance with multiple
project studies, designs, project deliveries and the
construction management — all phases of the work.
Our staff has provided project & construction
management & inspection services for the following
projects:
Francisco Blvd East Sidewalk Improvement Project
This federally funded project constructed
improvements between Vivian Street & Grand Ave
Bridge that included demolition of existing curb
ramps, asphalt, curb, gutter, sidewalk and striping;
construction of new curb, gutter, sidewalk and
driveways to current ADA standards for an 8-foot
sidewalk; construction of curb ramps to current
ADA standards for multiple intersections along
Francisco Blvd East; installation of new and
adjustments of existing storm drain systems;
adjusting & relocating existing utilities to finish
grade; upgrades to traffic signal and street lighting;
irrigation and planting improvements; and final
roadway striping work.
2017 Storm Damage Slide Repair Project
This FEMA funded project repair storm damage
slides at three locations throughout the City. The
damage for storms in 2017 were repaired through
three separate construction projects in 2018 &
2019. The project rebuilt existing failed slopes,
added retaining walls, repaired damaged drainage
systems & roadways, and worked closely with
adjacent impacted residents. Park Engineering
provided construction inspection services for all
three projects.
2"d Street & Grand Ave Intersection Improvement
Project improved this busy intersection with new &
RELEVANT PROJECT EXPERIENCE
improved curb ramps while widening the
northbound approach on Grand Ave. The project
also upgraded and replaced all the traffic signal
components. Daily traffic control and coordination
with adjacent businesses was also a critical
component of the project work.
Regional Transportation Safety Enhancement
Project is an ongoing project to prepare the City's
busy downtown / transit area for the arrival of the
SMART train. Work includes traffic signal upgrades
and extensive sidewalk & curb ramp
improvements.
H Street Roadway Improvements which replaced
a failing drainage system and relocated the
existing sanitary sewer main down the middle of H
Street. Installation of twin 30-inch pipes required
extensive traffic control and coordination with
businesses & resident. The entire street was
resurfaced as well as curb & sidewalk
improvements.
Other projects include:
• Canal Street Storm Water Pump Station
Repair Project
■ 1309 5th Ave Demo & Parking Lot
Terra Linda Pool House Renovation
B Street Community Center Projects
City -Owned Parking Structure Study
3`d & Union Improvements
Client Contact
April Miller, PE
Assistant PW Director
111 Morphew Street
San Rafael, CA 94901
(415) 485-3409
�T�ype
On -call & project specific work
I Contract
for public works construction
and capital building projects
Dates of
2013 — Present
Service
Dollar Amount
Projects range from $30K to
of Contract
$6M
Key Personnel
Steve Patterson, PM/RE
Jaemin Park, PM/RE
Chris Kinser, Inspector
James Beauchamp, Inspector
Andy Bodo, Inspector
RELEVANT PROJECT EXPERIENCE
Marin County Public Works, On -Call Construction
Management Services
Park Engineering is providing on -call construction
management and inspection services for County
public works projects, including street
rehabilitation, bicycle lanes, pedestrian
improvements, bridges and roadway
improvements. Completed Projects:
2021 Northern Road Rehabilitation Project
This $1.9M project includes pavement
rehabilitation work on multiple roads in the Lucas
Valley Neighborhood just north of San Rafael.
Project work involved full width grinding, repairing
road base failures, road resurfacing, installing and
modifying minor drainage improvements,
concrete curb & gutter, sidewalk and accessibility
curb ramps; traffic striping and marking, and road
sealing. Project work also included traffic control,
pedestrian considerations, and water pollution
control effort.
2019 Southern Region Project
This $2M project includes pavement rehabilitation
work on 3 roads in the Strawberry Neighborhood
in southern Marin County. Beyond repaving, the
three roads will receive sidewalk improvements,
accessibility features, bicycle safety upgrades,
updated traffic striping and signage, improved
drainage infrastructure, and a radar speed
feedback sign. The improvement project will be
covered by the County's Road and Bridge
Rehabilitation Fund and the California Senate Bill 1
(SB1) funding.
Client Contact
Eric Miller, PE
Principal Civil Engineer
Marin County Public Works
3501 Civic Center Drive
San Rafael, CA 94903
(415)473-6453
Dates of Service
2019 - Current
Project Value
$2 & 1.9M (Construction Value)
Key Personnel
Jaemin Park, Project Manager
Steve Patterson, PM/RE
Andy Bodo, Const. Inspector
Danielle White, Inspector
Marin County Transit District — 2018 State of
Good Repair Bus Stop Improvement Project
Park Engineering provided construction
management and inspection services for this project
that included re -construction of 10 existing bus
stops throughout Marin County with work in
Novato, San Anselmo, Corte Madera, Tiburon,
Larkspur, Ross & San Rafael. Bus stop
improvements included concrete removal &
replacement work to meet current ADA standards
with some locations also installing new Bus Shelters
and site furnishings. Coordination with the various
cities, Caltrans, adjacent residents & businesses and
Bus Services were necessary to complete the
improvements.
Client Contact
Anna Pennoyar
Senior Capital Analyst
Marin Transit
711 Grand Ave, Suite 110, San
Rafael, CA 94901
(415) 226-0867
Dates of Service
2018 - Current
ue
$500,000 (Construction Value)
nel
FF
Steve Patterson, Res. Engineer
Andy Bodo, Const. Inspector
City of Novato, Public Works Department,
Measure A, Group 10 Pavement Rehab Project
This $1.6M project includes rehabilitation of the
pavement on Nave Drive between Alameda Del
Prado and Bel Marin Keys Blvd, Be[ Marin Keys
Blvd from Nave Drive to 200 ft. North of Digital
Drive, and Bolling Drive from Nave Drive to Marin
Valley Drive. The improvements will include
construction of ADA compliant access ramps,
removal and replacement of damaged concrete
curb, gutter and sidewalk, replacement of existing
traffic signal detection, pavement repairs
consisting of asphalt concrete dig -out and
patches, slurry seal application at some locations,
grinding of the existing pavement, placement of
reinforcing fabric, hot mix asphalt overlay,
replacement of pavement striping and markings,
and installation of new traffic signs.
Client Contact
Gosia Woodfin, PE
Project Engineer
City of Novato Public Works
922 Machin Ave
Novato, CA 94945
(415)899-8997
Dates of Service
2019 - Current
Project Value
$1M (Construction Value)
Key Personnel
Jaemin Park, Resident Engineer
City of San Rafael
Construction Management Services for
Third Street Safety Improvements Project
RELEVANT PROJECT EXPERIENCE
City of Concord Project Management,
Construction Management and Inspection
Services, Concord, California
Description: Park Engineering has provided
construction management and inspection services
for City public works projects, including street
rehabilitation, bicycle lanes, pedestrian
improvements, bridges and roadway
improvements. Projects include:
Clayton Road Traffic Operations Improvements
This $450k locally funded project involves the
installation of fiber optic communications cable in
conduit, conduits, pull boxes, fiber optic splicing
and testing, fiber optic switches, fiber optic small
form pluggable modules, fiber pig tails, and other
items required by the contract documents. Other
work includes potholing, traffic control and
construction signage, pedestrian detours, and
water pollution control.
Denkinger Road Pavement Rehabilitation
This $1.2M locally funded project rehabilitated the
existing pavement for approximately 1/2 mile
along Denkinger Road by a full depth reclamation
process. 7 curb ramps were also upgraded, spot
repairs were made at various curb location, and
final re -striping of the roadway and adjacent
intersection with Concord Blvd.
Measure Q Paving Rehabilitation, Project #8
This $1.3M project included roadway
reconstruction work on 8 local residential
roadways, including construction of 14 new curb
ramps and replacement of existing valley gutters
and curb & gutter. Roadway reconstruction
methods were varied degrees of grinding &
repaving with some pavement failure digouts and
use of RHMA as the final wearing course.
West Concord Bikeways
This $80,000 project work involved the installation
of new buffered bike lanes on Meridian Parkway
Blvd. and Galaxy Way / John Glenn Drive.
Citywide Accessibility Improvement Projects #4,
5,6and 7
These projects involved the re -construction of
pedestrian curb ramps at various intersections
throughout the City, with a number of locations
included as Alternate Bid Items to allow the City
flexibility to add or remove this specific work
based on bid results.
i' "_N "y
Central Concord Pedestrian Improvements
Project included roadway resurfacing work of both
the mill and fill method for Willow Pass Road and
a slurry seal for Broadway, as well as replacement
of non-ADA compliant curb ramps for 25
intersections in downtown Concord, new traffic
signal, and streetscape features installed near the
Concord BART Station.
Detroit Avenue Bicycle and Pedestrian
Improvements Project
This federally funded (OBAG) Project constructed
roadway and streetscape improvements on Detroit
Avenue from Monument Blvd. to Clayton Road.
Work on this $4M project involves full street
rehabilitation including, grading, AC paving, signals
and lighting, new curb, gutter and sidewalks, new
curb ramps, drainage improvements, irrigation and
lighting, and enhanced striping and pavement
markings.
Ellis Lake Restroom Building Project
This locally funded project included the site
preparation and utility installation to accept a pre-
fabricated 4-unit restroom building. New sidewalk,
re -installation of irrigation and grass and a new picket
fence were also part of the project.
City-wide Bridge Rehabilitation Program —
Package 1
Project work included construction of maintenance
repairs for six bridges throughout the City that
include: Willow Pass Road Over Mount Diablo Creek,
Kirker Pass Road Over Mount Diablo Creek, Diamond
Blvd over Walnut Creek — Left, Diamond Blvd over
Walnut Creek — Right, Cowell Road Over Galindo
Creek, and Walnut Ave Over Contra Costa Canal.
FClient Contact
Bernard Enrile, PE
Manager, CIP
City of Concord
(925)671-3031
Dates of Service
2015 - Current
Project Value
$80,000 to $4M (Construction
Value)
Key Personnel
Jaemin Park, Project Manager
Steve Patterson, Res. Engineer
Chris Kinser, Const. Inspector
Pete Martin, Constr. Inspector
James Beauchamp, Inspector
RELEVANT PROJECT EXPERIENCE
On -Call Construction Management and
Inspection Services - City of San Mateo, Public
Works Department, San Mateo, California
Client Contact
Jay Yu, Engineering Manager
City of San Mateo
(650) 522-7323
jyu@cityofsanmateo.org
Type of
Public works construction.
Project(s)
roadway and bridges
Date of
2014 to Present
Performance
Construction
$1M to $6M (Construction
Cost
Value);
Key Personnel
Jaemin Park, PM
Steve Patterson, RE
Andy Bodo, Inspector
James Beauchamp, Inspector
Description: Park Engineering staff provided
construction management and inspection services
for several bridge and roadway improvement
projects for the City of San Mateo. Services have
included full construction management including
CCO, RFI and submittal management, schedule,
constructability reviews, bidding assistance, and
federally funded project support including
contract administration, contract compliance,
audit support and fund reimbursement. Projects
included:
Downtown Parking Technology Improvements
Project This federally funded project upgraded
single & multi -space parking meter systems in the
downtown area. New level -by -level count
systems were installed in the City's five downtown
parking structures as well as installation of new
way finding signs for parking.
Citywide Crosswalk Improvement Project This
federally funded project constructed high visibility
crosswalks in 40 locations throughout San Mateo.
In addition to the crosswalk upgrades, work
consisted of new and relocated signage, a
pedestrian refuge island, installation of a retro-
reflective flashing beacon system, accessible ramp
improvements, thermoplastic pavement markings,
and green bike lane and box installation.
E. 3rd Ave Street Rehabilitation Project This
project scope included concrete improvements;
asphalt concrete pavement grinding and removal,
hot mix asphalt paving, pavement striping, storm
drain replacement and utility structure
adjustments.
Poplar Corridor Safety Improvement Project
The project constructed a median island on Poplar
Ave from Amphlett Blvd to Idaho St, as well as
traffic calming improvements along Humboldt St.
Traffic calming improvements included: bulbouts,
landscaping with new trees, pedestrian level
lighting, radar feedback signs, and signal upgrades
at Humboldt/Poplar.
2014 Street Rehabilitation Project
Project consisted of removal and replacement of
curb & gutter, sidewalk, driveways and
construction of new Handicap ramps, bulb outs,
islands, new drainage inlets and storm drain pipes,
relocation of street lights. Work also involved
grinding and paving city streets and parking lots,
striping and pavement markings, and installing
new tree grates.
Additional projects included:
• 2014-15 Street Rehabilitation Phase 1
2015 Community Development Block Grant
(Federally Funded)
Downtown San Mateo Creek Bridge
(Federally Funded)
East Hillsdale Bridge Seismic Retrofit
(Federally Funded)
• Norfolk Street Bridge Replacement (Federally
Funded)
Delaware Street Bike Lane and Streetscape
Improvement Project (Federally Funded)
El Camino Real Master Plan, Phase 1
Improvements (Federally Funded)
f Page 6 City of San Rafael
R'FMa Construction Management Services for
Third Street Safety improvements Project
RELEVANT PROJECT EXPERIENCE
City of Orinda Multiple Project -Specific
Construction Services & On -Call Construction and
Project Management Services
Client Contact
Jason Chen, PE
FORMER City Engineer
City of Orinda
(925) 949-9776
Dates of Service
2014 — Current
Project Value
$140,000 to $10M
Key Personnel
Steve Patterson, PM/RE
Jaemin Park, PM/RE
Linda DeBolt, PM
James Beauchamp,
Danielle White - Inspectors
Description: Park Engineering provided the City
construction & project management services for
multiple capital project. Services included project
delivery, resident engineering, construction
inspection, and materials testing. Also representing
the City during construction for interactions with
public / homeowners directly impacted. Projects
have included:
Orinda Way Pavement Rehabilitation
Construction Cost: $10M
Park Engineering provided construction
management for this $650,000 federally funded
project. The project included rehabilitation of
Orinda Way using Mill and Fill rehabilitation
method. In addition, the work includes pavement
(digout) repairs, curb ramp reconstruction,
drainage improvements, utility adjustments,
replacing detector loops, striping and curb, gutter
and sidewalk repair.
2017 Annual and Measure J & L Paving
Rehabilitation Project
Construction Cost: $10M
Park Engineering provided construction
management for this project. The project work
consisted of improvements occurring on 65
different streets within the City. Roadway
rehabilitation was primarily through Full Depth
Reclamation with an HMA overlay, extensive
drainage and concrete curb & gutter replacement
work. Other work consisted of utility adjustments,
replacement of HMA dikes & swales and roadway
delineation. The project was locally funded with
the use of both City funds and Contra Costa
County Measure funds.
Crossroads Area & BART Wayfinding Signage
Construction Cost: $140,000
Park Engineering managed the planning and
design and will manage the construction of this
project that will furnish and install new custom
fabricated wayfinding signs, wall graphics and
fabricated light cabinet, concrete foundation,
replacement of existing sidewalk where needed,
extension of electrical conduits and conductor as
needed.
BART-Downtown Access Ramp & Lighting
Construction Cost: $900,000
Park Engineering provided construction
management for this project. The project work
consisted of removing an existing concrete
stairway and replacing with a new stairway and
ADA compliant ramp to link the City's busy
Theater District with the adjacent Orinda BART
Station. A series of seven retaining walls were
constructed to achieve the ADA ramp in small
work area, located on Caltrans right-of-way.
Other work included improved lighting and new
landscaping with an improved irrigation system.
2014 Annual and Measure J Paving Rehab Project
Construction Cost: $1.40M
Park Engineering provided construction
management for this project. The project work
consisted of a combination of pavement
rehabilitation, both slurry seal and mill of existing
pavement with Hot Mix Asphalt paving; base
failure repairs, both digout repairs and Full Depth
Reclamation; minor drainage improvements and
repairs; and re -installation of striping and
pavement markings. The project was locally
funded with the use of both City and Contra Costa
County Measure L funds.
City of Son Rofoel
Construction Management Services for
a.-opci.. l Third Street Safety Improvements Project
RELEVANT PROJECT EXPERIENCE
On -Call Construction Management and
Inspection Services
Contra Costa County Public Works Department,
Contra Costa County, California
Client Contact
Adelina Huerta, PE
Division Manager
Contra Costa County
Design and Construction
(925)313-2305
Dates of Service
2014 — Current
Project Value
$2M to $25M (Construction
Value)
Key Personnel
Jaemin Park, PM & RE
Steve Patterson, RE
James Beauchamp, RE & ARE
Mike Johnson, ARE/Inspector
Andy Bodo, ARE/Inspector
Danielle White, ARE/Inspector
Description: Park Engineering's personnel
provided construction management and
inspection for County public works projects
through an on -call Construction Management and
Inspection contract. The team worked on several
federally funded public works as well as privately
funded developer projects, such as new
subdivision construction and the expansion of
local roadways and arterial improvements.
Projects include:
Kirker Pass Road Northbound Truck Climbing
Lane Project —The project improves safety
and reduces congestion along Kirker Pass
Road by constructing a truck climbing lane in
the northbound direction. The project is
approximately 1 mile in length, beginning at
the Concord Pavilion and ending at the
northern Hess Road intersection. Road
widening requires significant retaining walls
due to the existing slopes and drainage
adjacent to the roadway. The project also
includes pavement rehabilitation on the north
and south bound lanes between the City of
Concord/County limits to approximately 4,200
feet north of North Hess Road for a total of
about 1.6 miles. The total project length is
about 2 miles. The project is funded by
Federal grants, State SB1 funds, and local
County funds.
San Pablo and Wildcat Creeks Levee
Remediation — FEMA mandated levee
remediation to raise freeboard to 100 year
flood requirements. Work involved
installation of sheetpile walls, levee fill,
concrete walls, and HMA pavement to raise
levee roads. The project required close
environmental monitoring and coordination
with various entities including East Bay
Regional Park District and County Flood
Control District. The project was funded by
local County funds and State funds.
2015 Asphalt Rubber Cape Seal; 0672-61.12149
The work consisted of applying an asphalt
rubber chip seal covered with a type II slurry
seal to approximately 259,020 square yards of
roadway located at East Richmond Heights area
of west Contra Costa County and Shadow Creek
area of Blackhawk in the East Contra Costa.
Work also included installation of 40 survey
monuments, surface preparation, striping
removal, and placement of thermoplastic
striping and pavement markings.
Bollinger Canyon Bridge over Japonica Creek
(Federally Funded)
= South Dougherty Road Bridge and North
Dougherty Road Bridge
Vasco Road Safety Improvements, Phase I
(Federal and CCTA Funded)
Countywide Microsurfacing Project
Giaramita Street Rehabilitation (federal Block
Grant Funds)
Services Provided: Park Engineering staff managed
several overall construction projects, including
performing field reviews; preparing daily Resident
Engineer reports and project status reports for the
County; managing correspondence; and
maintaining communication with the general
public and other, numerous related public
agencies.
r7 T` Page S City of Son Rafael
Construction Management Services for
* Third Street Safety Improvements Project
TEAM ORGANIZATION & KEY PERSONNEL
KEY PERSONNEL
Park Engineering is a DBE firm that brings an
experienced construction team to represent the
City for this improvement project. We specialize in
providing construction management and
inspection services to public agencies for projects
just like this. Our team is knowledgeable of
Caltrans, Federal and Greenbook requirements,
and has experience completing comparable
projects and will meet all the City's Quality
Assurance Plan requirements.
Steve Patterson, PE, Project Manager/Resident
Engineer will be primary contact managing all
aspects of the project for the City and
management of Park Engineering team.
Steve has over 30 years of experience providing
project management, construction management,
and construction administration for local agency,
highway, bridge, building and public works
infrastructure projects throughout the Bay Area.
He has worked with state, regional and local
agencies in the capacity of project principal,
project manager, resident engineer, construction
inspector, project engineer, and office engineer.
He has worked on numerous projects for the City
for the past 8 years, with both federal & local
funding involved. Steve is also currently the RE
for a signal interconnect project for the City of
Concord.
Andy Bodo, Construction Inspector
Andy Bodo has 22 years of experience providing
construction management and inspection for
roadway, bridge and public works construction
projects. His experience has included roadway
rehabilitations, underground utilities, and
streetscapes. Andy is proficient in Caltrans
construction manuals and specifications and has
experience with federal and bond funded
projects.
Mike Johnson, Construction Inspector (if needed)
Mike has over 35 years of experience as an
inspector for transportation and public works
construction projects that have included bridges
and other structures roadways and highways,
drainage, signal & lighting, and multiple utility
installation / relocations. Mikes has extensive
experience working with local agencies on
federal and local funded projects most recently
completing San Pablo Avenue Complete Streets
Project.
Applied Materials & Engineering
Park Engineering Team Member Applied
Materials & Engineering, Inc. (AME) will provide
quality assurance testing as required. Testing
will be performed in the frequencies required by
the City's Quality Assurance Program and the
Caltrans Local Assistance Procedures Manual.
AME will provide summary of tests performed
and results of tests performed to support quality
of the work. They will provide sufficient
information so that the resident engineer can
satisfy the requirements of certifying that all
materials used on the project meet the contract
requirements.
Jaemin Park, PE, Principle In Charge will be
providing technical support, oversight and
management of the project.
Jaemin has 30 years of experience providing
project management, construction management,
construction administration, and design of
highway, bridge, building and public works
infrastructure projects throughout California.
Availability
All members of the team are available within the
duration of the contract and will not be
substituted without the City's permission.
Please see resumes at back of this proposal
Pages City of San Rafael
Construction Management Services for
Third Street Safety Improvements Project
i
PROJECT UNDERSTANDING & APPROACH
PROJECT UNDERSTANDING
There are many challenges that come with the
responsibility of providing quality service on
public works construction projects. At Park
Engineering, we understand that a public agency
has to answer to elected officials, oversight and
permitting agencies, and third -party funding
sources. We also understand the public relations
pressures on visible community improvements
projects and that public perception can make the
difference to the success of a project. Our
resident engineers and construction inspectors
take ownership of our projects and act in the
City's best interest to manage, coordinate and
inspect the project to successful completion.
Park Engineering specializes in providing
construction management and inspection
services to public agencies for projects just like
this and our proposed team of professionals has
the experience and expertise to ensure that this
project is completed successfully. For this
contract, we will provide a part-time Project
Manager/Resident Engineer and a full-time
inspector for the duration of the project. A
possible second inspector will be available for
combined day & night work that may occur. All
will report directly to the City's project manager
For this project, the work occurs at specific
intersections along 3rd Street from Grand Ave to
Lootens Place. Improvements consist of curb
ramp & sidewalk improvements, high -visibility
crosswalks, drainage work and traffic signal
improvements related to improved pedestrian
safety.
The engineer's estimate is approximately $2.5
million and is federally funded. Project duration
is estimated at 120 working days with an
anticipated start time of late April.
KEY ISSUES
Having performed construction inspection for
similar projects, we have identified elements of
the work that are key to the success of this
project. They include, but are not limited to:
• Public Outreach & Safety —The planned curb
ramp, sidewalk and signal improvements will
impact the normal patterns of the daily foot
traffic — both school / business routes and daily
routines of exercise & dog walks. Advance
notice for any closures of the traveled lanes,
sidewalks and driveways for the improvement
work to limit impacts to businesses, residents,
the traveling public, delivery, emergency and
transit customers will be essential. Additionally,
strict adherence to approved traffic handling
plans, work schedules related to business access,
no parking postings, and closely monitoring
pedestrian access will help keep the public
informed on what to expect and when, will
improve the project's safety during construction
and minimize issues with the public.
• Coordination — Multiple stakeholders are
directly involved with this project. Accurate
construction details will need to be provided
to Caltrans, SMART, and local transit along
with the adjacent businesses already
mentioned. Improvements will be
performed adjacent to the City's bus transit
center and the SMART station. Additional
impacts may occur to local deliveries and
services, along with postal, garbage and
emergency services. Lastly, the City will have
a concurrent larger improvement project
along 3rd Street that will require coordination
to avoid conflicting activities and/or traffic
control. Weekly progress meetings will be a
beneficial tool to help identify work
activities, and their related schedule, that
have a need for coordination with any of the
multiple involved project partners.
F4�509m`
Page 10 City ofSon Rafael
Construction Management Servicesfor
v Third Street Safety Improvements Project
PROJECT UNDERSTANDING & APPROACH
Tracking of Costs & Schedule — Constant
monitoring and reporting of project
quantities constructed to control bid
quantity overruns that can occur and for any
change order work to prevent escalated
contract costs are critical to keep the project
on budget. Daily Inspection Reports and
progress pictures will be kept current and
provided to the City in a timely manner to
benefit the monitoring of the project's
schedule.
Project Documentation and Administration
With federal funding, making sure that the
project is administered in accordance with
the Caltrans Local Assistance Procedures
Manual, will ensure swift and easy audits. It
is critical that the project is administered
using standard, recognized administration
systems that meet the needs and established
system of the City. Project documents, such
as our inspection reports, supporting
calculations for progress payments and
employee interviews, will be developed for
the project files and provided to the City in a
timely manner. Our experience in
documenting the important aspects of
similar projects will provide key information
of the work performed, compliance with the
contract requirements and well -organized
project documents for federal funding
audits.
Quality of Work —Acceptance of only the
best quality work ensures the funds utilized
are well invested and the improvements will
last. Strict adherence to the City's quality
assurance program (QAP), City, County &
Caltrans standards, performing the required
acceptance testing to verify quality of the
completed work and documenting results for
compliance with local, state and federal
requirements.
Project Appearance / Environmental
Concerns / Permits/ Water Pollution
Control — A clean project will promote a
positive public perception, increase the
project safety and aid the effort to
compliance with Permits, Environmental and
Water Pollution Control requirements.
Installing water pollution control measures
and maintaining it regularly is very important
to prevent violations to permits from
Regional Water Quality Control Board.
Additionally, weekly project cleanup will
provide a safer environment for the public
and the project personnel.
WORK PLAN
Park Engineering will support the City by
providing construction management, inspection,
and materials testing & survey services for this
project. We will perform all the duties required
in the RFP, including, but not limited to the
following:.
TASK ONE — Resident Engineer & Construction
Inspection Services
Pre -Construction Services
• Park Engineering's Project Manager/Resident
Engineer, Steve Patterson, will conduct
and/or attend coordination meetings with
permitting agencies, utility companies and
the public— residents & businesses.
City of Son Rafael
Construction Management Services for
Third Street Safety Improvements Project
PROJECT UNDERSTANDING & APPROACH
Prior to bidding the project, a
constructability review can be performed
with identified issues detailed and discussed
with the project Design Team.
If requested, we can assist the City with
Project Advertisement & Award.
We will lead the pre -construction meeting
with all involved parties. Meeting minutes
will be prepared and distributed to ensure
that all discussions, agreements and
understandings are documented.
Project Administration
• Act as the single point of contact for all
communications and coordination between
the contractor, utility companies, regulatory
agencies, local businesses and residents, the
designer, and the City.
• Coordinate, conduct and summarize weekly
progress meetings with the Contractor
during construction.
• Maintain close contact with City Project
Manager for project status to ensure that
the City is kept up to date on all project
matters.
• Review contractor's planned schedule for
conformance with the specifications and for
reasonableness of the sequence and
duration of the activities.
• Review work progress as compared to the
planned schedule and notify contractor of
schedule slippage.
• Photo documentation of project work and the
project site before, during & after
construction.
• Monitor and report on project budget and
construction status and provide any necessary
info needed for update reports.
• Maintain all project records specific to
Contractor's activities including schedule,
costs, correspondence, submittals and
documenting all daily activities.
• Prepare, monitor & distribute Weekly
Statements of Working Days to monitor
project schedule.
• Manage and coordinate with project
stakeholders, schools, residents, and any
necessary utility coordination for conflicts or
relocation work required.
• Assist with the review and approval of
contractor submittals required by the
construction contract plans and
specifications including traffic control plans,
Storm Water Pollution Control Plans, sewer
by-pass systems/plans and various mix
designs.
• Support the management of submittals from
the contractor, tracking date submitted,
duration for review and making sure that
submittals are reviewed and returned within
the allotted time to prevent any delays.
• Coordinate, manage and respond to
Requests for Information (RFI's) submitted
by the contractor, including tracking RFI's
sent to the designers and/or other agencies
for timely replies.
• Review contract documents to determine
validity of change orders and provide
support to the City.
• Evaluate contractor's change order requests
and claims and make recommendations to
the City based on the merit and
circumstances.
• Review and approve change orders with the
City's concurrence.
• Review cost estimates and back up
documentation for any contract change
order work.
City of San Rafael
IRE
Construction Management Servicesfor
Third Street Safety Improvements Project
PROJECT UNDERSTANDING & APPROACH
• Prepare independent cost estimates to verify
contractor's cost proposals for change
orders.
• Negotiate and prepare any contract change
orders with justification memorandums for
the City's approval.
• If change order prices cannot be agreed
upon with the contractor, perform work at
force account and track all labor equipment
and materials.
• Identify actual and potential problems
associated with the construction project and
recommend sound engineering solutions to
the City Project Manager.
• We will analyze, negotiate, provide
recommendation and supporting
information to resolve any outstanding
potential claims.
• We will support the City to fight and resolve
any outstanding issues, looking out for the
best interests of the City.
• Prepare supporting quantity calculations for
work performed, including any contract
change orders, and progress pay estimates on
a monthly basis.
• Review contractor's invoices to verify accuracy
and "sign -off' on construction progress pay
estimates for City's payment approval.
• Review and approve extra work bills
verifying hours of labor, equipment and
materials and rates for labor, equipment as
well as costs for material.
• Include change order payments in monthly
progress payments and review. contractor's
invoices to ensure accuracy.
• Assist with the review of contractor's weekly
certified payroll for compliance with prevailing
wage requirements and conduct any necessary
labor compliance interviews of Contractor's
field staff.
• Monitor contractor's construction activities
for conformance with the approved Water
Pollution Control Plan, SWPPP and NPDES
General Permit requirements.
• Work with the contractor's staff to prepare
and transition, official and accurate
construction record drawings.
Conduct, review, and follow up on inspection
work to assure completion of the contract
including any punch list items of work.
Perform final inspection of all work for
acceptance.
Field Inspection Services
• Review all contract documents to become
familiar with all project details — plans, specs,
schedule & sequence, traffic control and any
permit requirements / restrictions.
• Attend the project's Pre -Construction
Meeting and pro -actively discuss potential
project issues.
• Perform all field inspection activities to
monitor compliance with the contract plans
and specifications. Record all items of work,
labor, equipment, materials incorporated,
materials tested, traffic control utilized and
any other pertinent information in a daily
diary for permanent record.
• Monitor all field work for contract compliance
and document with daily reports and pictures.
Notify the City's RE about any non-compliance
items / issues.
• Project photographs and video
documentation of project progress and
major work components will be done on a
weekly basis and kept for permanent records
to support disputes and verify quality for
acceptance.
n Y� Page 13 City of San Rafael
1� Construction Management Services for
Third Street Safety Improvements Project
PROJECT UNDERSTANDING & APPROACH
• Work closely with City staff on project
schedule, field progress and issues to monitor
overall project completion.
• Prepare supporting quantity calculations for
work performed, including any contract
change orders, and progress pay estimates on
a monthly basis.
• Review, evaluate & discuss proposed change
orders and estimates for accurate scope,
cost and time impacts.
• Maintain and enforce safety awareness for
the protection of workers and public
• Review all necessary sampling and testing of
materials for the project — performed by
both the Contractor and AME —to meet the
specifications and City's QAP to ensure all
materials meet the contract requirements.
Failing results will be detailed to the RE.
• Attend any progress or public meetings as
requested.
• Conduct interviews of field personnel for EEO /
Labor Compliance monitoring.
• Work closely with City Staff on final punchlist
and acceptance of the contract work.
• Assist City Staff as needed on various project
administration tasks, such as review of
certified payrolls, submittals and/or RFIs.
Public & Community Relations
• Ensure all public notifications are accurate
and posted in a timely manner
• Coordinate and communicate with adjacent
businesses and residents to minimize impact
and maintain a neighborly reputation for the
project.
• Coordinate with any businesses and property
owners, City Staff, transit agencies and
delivery services to inform them of the
project's upcoming work.
• Coordinate any necessary utility agency
coordination for conflicts and/or relocation
needed.
• Assist in organization and execution of any
public outreach meetings and events.
• Assist with questions from the public
concerning the project work and schedule.
• Address public concerns on a daily, weekly,
and monthly basis.
Post Construction
• Review/assist with the preparation of all
required close-out documents, as required,
as submitted by the Contractor.
• Coordinate efforts with the Designer for the
conversion of the As -Built Drawings to the
Record Drawings for the project work.
• Finalize all bid item and change order totals for
the project's Final Progress Payment.
• Maintain the construction contract
accounting, filing and administration in
accordance with City requirements and
provide files (electronically and/or paper
files) to the City upon project completion &
acceptance.
• Provide a list and details of any lessons
learned during construction specific to the
work performed for use on future City
projects.
• If requested, and necessary, provide
supporting information to dispute
construction claims and/or perform an as -
built schedule analysis.
:��,�,,:�„r � a-'4��+ter*■_:..- ,�
1' Page 14 City of San Rafael
Construction Monagement Services for
{ Third Street Safety Improvements Project
PROJECT UNDERSTANDING & APPROACH
TASK TWO — Materials Testing / Sampling Services
• Review all necessary sampling and testing of
materials for the project, performed by the
Contractor, in accordance with the
specifications and ensure that all materials
meet the contract requirements.
• Make sure that the Contractor performs
necessary quality control sampling & testing
required.
• Review test data and materials certifications
submitted by the contractor and suppliers for
compliance with the contract requirements.
• Schedule and coordinate acceptance and
quality assurance sampling and testing to be
performed by Applied Materials & Engineering.
• Applied Materials & Engineering will provide
materials testing and sampling services to
ensure the installation of materials is in
accordance with contract requirements and
the City's QAP. Materials include:
- Native Soils / Subgrade Compaction
- Trench Backfill & Base Rock
- Hot Mix Asphalt (minor)
- Concrete placed
• All tester certifications will be provided
• We will review quality assurance testing as
required. Testing will be performed in the
frequencies required by the City's Quality
Assurance Program (QAP) and any other
required State and Federal guidelines like the
Caltrans Local Assistance Procedures Manual
and Construction Manual.
• Observe and document final testing &
acceptance of the utility work performed.
• Maintain and enforce safety awareness for
the protection of workers and public.
• Analyze records of materials used in the
project in accordance with ASTM and
California Standard Test Methods.
Page 15 City of San Rafael
�'ni iy�:y7 Construction Management Services for
Third Street Safety Improvements Project
APPENDIX - KEY PERSONNEL
STEVE PATTERSON, P.E., RESIDENT ENGINEER / PROJECT MANAGER
Years of Experience
30
Education
B.S. Civil Engineering, Michigan State University, East Lansing, 1991
Professional Registrations
Professional Engineer: California, #C54481, 1995
QSD / QSP: Certificate #22073
Key Qualifications
Steve Patterson's experience includes roadway widening and rehabilitation, highways and interchanges,
emergency slide and flood repairs, sound walls, MSE walls, retaining walls, storm box culverts, utility
installations and relocations. He has worked in the capacity of Project Manager, Resident Engineer,
Construction Inspector, and Office Engineer. Steve is familiar with the Caltrans Standard Specifications,
Standard Plans, Construction Manual, Local Assistance Procedures Manual, and the "Greenbook" Standard
Specifications for Public Works Construction.
Steve is experienced with supervising inspection staff, CPM schedules, project controls and costs, quality
control/quality assurance, analyzing claims, preparing reports, planning personnel resources, negotiating
contract change orders. Steve coordinated project work with utility companies, cities, counties, Caltrans,
California Department of Fish and Game, Regional Water Quality Control Board, Union Pacific Railroad,
private businesses, and the public.
Representative Project Experience
City of San Rafael Public Works, Francisco Blvd East Sidewalk Improvement Project
Steve is the construction manager on this $5M federally funded project that widens the existing
sidewalk to 8-feet for almost a mile along the busy Francisco Blvd East, Vivian to Grand. Other work
includes replacing existing storm drain systems & street lighting, installing new irrigation & trees, and
pedestrian improvements to the signal at Medway.
Contra Cost County Public Work, Kirker Pass Road Northbound Truck Climbing Lane Project, Concord
Steve is the construction manager on this $14.1M federally funded project that constructs an
additional lane for improved truck climbing safety. The project constructs six retaining walls to
complete the widening lane, as well as grind & pave of all lanes (4) for approximately 2 miles, related
drainage improvements and restriping work. Coordination is needed with the Cities of Concord *&
Pittsburg, Union 76 for their close proximity gas line and the Concord Pavilion.
City of San Rafael, Public Works & Engineering Department, San Rafael, CA
City Owned Property Improvements, Roadway and Drainage Improvements
Steve was Project Manager and Resident Engineer for numerous City Projects ranging in construction
costs from $30,000 to $2 million and including street rehabilitation, curb ramp improvements, drainage
improvements, bridge resurfacing, City -owned facility improvements and sanitary sewer replacements.
Assisted City Staff to develop and/or assist delivery of project documents for construction, advertise
projects for bidding, answer pre -bid questions and evaluate bids, and monitor contract progress.
• City of Concord, Multiple Projects
Steve was the Resident Engineer/Project Manager on the following projects:
✓ Denkinger Road Pavement Rehabilitation Project, $1.2M
Rehabilitated the existing pavement for approximately 1 mile along Denkinger Road by full depth
reclamation process. 7 curb ramps were also upgraded, spot repairs made at various locations.
City of San Rafael
Construction Management Services for
��i Third Street Safety Improvements Project
APPENDIX - KEY PERSONNEL
✓ Citywide Accessibility Improvement Project #6, $300,000
Federally funded project that upgraded 30 curb ramps with signal & striping improvements.
✓ Measure Q Pavement Repair Project #8, $1.3M
Rehabilitated the existing pavement on 8 local streets along with the construction of ADA curb
ramps and valley gutters.
✓ West Concord Bikeways, $80k
Revised the existing striping to create a buffered Class II bike lane in both directions.
✓ Citywide Accessibility Improvements #4, $365k
Federally funded project that upgraded 45 curb ramps with signal & striping improvements.
✓ Central Concord Pedestrian Improvements Streetscape Project, $3M — Roadway resurfacing
project that included work of both the mill and fill method and slurry seal, curb ramps for 25
intersections in downtown Concord, a new traffic signal, and streetscape features.
✓ Ellis Lake Restroom Project, $120k—This locally funded project included the site preparation,
utility connections and installation of a prefabricated 4-unit restroom building.
City of Orinda, 2017 Paving Rehabilitation Project & BART-Downtown Access Ramp & Lighting Project
Construction Cost: $10M & $900,000 (respectively)
Construction Manager for this project that required work to occur on 65 different streets within the
City. Roadway rehabilitation is primarily through Full Depth Reclamation with extensive drainage and
concrete curb & gutter replacement work. Other work consists of utility adjustments, replacement AC
dikes and roadway delineation. BART-Downtown Access Ramp consisted of removing an existing
concrete stairway and replacing with a new stairway and ADA compliant ramp to link the City's busy
Theater District with the adjacent Orinda BART Station. A series of seven retaining walls were
constructed to achieve the ADA ramp in small work area, located on Caltrans right-of-way. Other work
includes improved lighting and new landscaping with an improved irrigation system.
• Moraga Road Utility Undergrounding, Sidewalks & Pavement Resurfacing Projects, Town of Moraga,
CA - $2.7M
Steve was the Resident Engineer/Project Manager on these three projects for the Town of Moraga
that were construction simultaneously.
✓ Utility Undergrounding, $1.7M — A Rule 20A project with PG&E for the Town to convert
existing overhead utilities to new underground facilities along one of the main roadways for the
Town. Work consisted of extensive daily traffic control for vehicles and pedestrians to perform
the installation of new joint trench and utility vault systems.
✓ Bicycle & Pedestrian Improvements, $160k — A federally funded project to construct about 300
LF of sidewalk to connect two critical side streets along Moraga Road.
✓ Resurfacing Project, $800k — A federally funded project that removed and replaced the top 3-
inches of existing Moraga Road. Pone of the Town's busiest roadways and only a 2-lane road,
daily one-way traffic control was required. Advance notice and monitoring of traffic control
was critical to the community outreach on the project.
• City of Orinda 2014 Street Rehabilitation Project, Orinda, CA
Resident Engineer for this $1.4 million pavement rehabilitation project. Steve was responsible for
managing all aspects of this project including contract administration, contract compliance and
acceptance, project costs and schedule, and public relations.
• City of Emeryville, Safe Routes to School Project, Emeryville, CA
Resident Engineer for this federally funded $650K project that upgraded multiple cross -walk
intersections, installed rectangular rapid flash beacon systems and speed feedback assemblies, and
upgraded an existing traffic signal. Work was coordinated with Caltrans, as it was performed on State
Route 123 (San Pablo Ave).
City of San Rafael
•..
Construction Management Services for
Third Street Safety Improvements Project
APPENDIX - KEY PERSONNEL
ANDREW BODO, EIT, SENIOR CONSTRUCTION INSPECTOR
Years of Experience
22
Education
B.S. Construction Engineering & Construction Management, Western Michigan University, 1999
Registration
Engineer -in -Training, No. 115429, CA
Key Qualifications
Mr. Bodo has more than 22 years of construction management experience in bridge and highway
construction to Caltrans specifications. He has provided field inspection, office engineering, and contract
administration to Caltrans highway and bridge and local assistance projects built to Caltrans specifications.
His technical knowledge encompasses bridge construction and demolition, active utilities crossing the
bridge, CISS piles, construction over water, stage construction, slope protection, AC paving, striping,
pavement markings, and signage, streetlights, safety, SWPPPP, and traffic control, bridges, bridge
falsework, masonry soundwalls, retaining walls and MSE walls, and electrical and low -voltage system
construction, including temporary and permanent intersections, traffic signal loop detectors, ramp
metering, and fiber optic cable.
Representative Project Experience
Highway 101 Multi -Use Path Overcrossing Project (Federally funded), City of Palo Alto
Andy is the Structures Inspector for this $13 million project that consists of construction of a new
bridge over Highway 101. Specific items of work include construction of the east and west concrete
approach ramps; construction and installation of the prefabricated steel truss principal span;
prefabricated steel truss at Adobe and Barron Creeks confluence; abutments and cast -in -drilled hole
(CIDH) pile foundations; overlook, railing and fencing, crosswalks, driveways, and sidewalks
improvements, pavement, traffic control, stormwater pollution control, street and bridge lighting,
signs, potholing, surveying, striping, landscaping and irrigation, art elements installation coordination,
and Adobe Creek Reach Trail. The project funded by federally HBP program and on State Right of Way
requiring contract administration in accordance with Caltrans Local Assistance Procedures Manual and
subject to Caltrans audits, and oversight from Caltrans.
1-880 Express Lane Conversion Project, MTC - BAIFA
Structures Inspector for the project that converted the existing 1-880 HOV lanes from Hegenberger
Road to Dixon Landing Road. The conversion involved lane striping and installing sign gantries, signs,
FasTrak° toll tag readers, traffic monitoring video cameras, a data communications network and CHP
observation areas. Project work resulted in 51 express lane miles from Oakland to Milpitas. This
project was coordinated with Caltrans' project to replace the median barrier on 1-880 with an
approximate construction cost of $45M, funded by BAIFA using local funds.
Poplar Corridor Safety Improvement Project, City of San Mateo
The project constructs a median island on Poplar Ave from Amphlett Blvd to Idaho St, as well as traffic
calming improvements along Humboldt St. from Peninsula Ave to E. Poplar Ave as a result of the traffic
diversion. Traffic calming improvements include: bulbouts at College/ Humboldt intersection and mid -
block in front of the court house, landscaping with new trees, pedestrian level lighting, radar feedback
signs, and signal upgrades at Humboldt/Poplar. Andy performed construction inspection and daily
documentation of contractor's activities; assisted RE with submittal reviews and RFI correspondence; plan
review and compliance of project plans and specifications; monitoring traffic control, pedestrian safety,
and residential noise regulations; monitoring permitting compliance; and SWPPP inspection.
City of Son Rafael
� Construction Management Services for
��J i Third Street Safety Improvements Project
APPENDIX - KEY PERSONNEL
San Pablo and Wildcat Creeks Levee Remediation, Contra Costa County
Construction Inspector for this FEMA mandated levee remediation to raise freeboard to 100-year flood
requirements. Work involved installation of sheetpile walls, levee fill, concrete walls, and HMA pavement
to raise levee roads. The project required close environmental monitoring and coordination with various
entities including East Bay Regional Park District and County Flood Control District. The project was funded
by local County funds and State funds.
Hercules Intermodal Transit Center San Francisco Bay Trail Project Phase 1, City of Hercules
This $6 million dollar project included the construction of four large soil nail retaining walls with
architectural finishes, new sewer and storm drains, a 48" culvert for a brackish stream, and an asphalt
pedestrian trail. The two biggest challenges of this project were working in close proximity to UPRR/
Amtrak, and two active fuel lines. Andy's responsibilities included, construction inspection, daily
documentation of the contractor's activities, scheduling materials testing at on and off site locations,
ensuring contractor adherence to all involved agency regulations, contract designs and specifications.
1-680 Contra Costa South Express Lane Project
Structures Inspector for the project that converts existing HOV lanes to express lanes on 1-680 from
Alcosta Rd. and Livorna Rd. (NB) and from Rudgear Rd. to Alcosta Blvd. (SB). The conversion includes
striping lanes and installing overhead and roadside signage, FasTrak® toll tag readers, and traffic
monitoring equipment. Concrete barrier modifications are required for the lane reconfiguration. The
estimated construction cost is $19.2 million is fully funded by BAIFA using local funds. As Structures
Inspector, Andy is providing field inspection for all structural work items.
Roberts Road Bridge Reconstruction, Town of Los Gatos
Construction Inspector for $2.5 million project that included replacing an existing two -span bridge on
Roberts Road with a single span structure; constructing cast -in -drilled -hole pile foundations, soldier
pile, and tieback walls; constructing retaining walls, curb, gutter, sidewalks, and road resurfacing; and
water and gas utility relocation. The residential area required outreach to keep the public informed
and adherence to project noise restrictions. Andy performed construction inspection and daily
documentation of contractor's activities; assisted RE with submittal reviews and RFI correspondence;
plan review and compliance of project plans and specifications; monitoring traffic control, pedestrian
safety, and residential noise regulations; monitoring permitting compliance; and SWPPP inspection.
Charles Hill/ Honey Hill/ Miner Road Pavement Rehabilitation, City of Orinda
Construction Inspector for reconstructing failing pavement by grinding and placing overlay;
constructing roadway improvements; installing new striping and pavement markings; and providing
traffic control and public outreach for nearby businesses. Andy provided inspection and field
observation and documentation for the entire project.
San Bruno Grade Separation Program, Peninsula Corridor Joint Powers Board
Assistant Structures Representative for this project that raised the railroad in a retained embankment
and lower roadways crossing the Caltrain right-of-way from just south of the
1-380 flyover. The at -grade vehicular crossings were eliminated at San Bruno Avenue, San Mateo
Avenue, and Angus Avenues and the existing San Bruno Caltrain station was relocated onto an
elevated structure at San Bruno and San Mateo Avenues. Mr. Bodo's responsibilities included:
construction inspection and daily documentation of contractor's activities; assisting the Resident
Engineer with submittal reviews and RFI correspondence; plan review and compliance of project plans
and specifications; monitoring traffic control, pedestrian safety, and residential noise regulations;
monitoring permit compliance with regulatory agencies; and Stormwater Pollution Prevention
Program (SWPPP) inspection.
• " City of San Rofoel
{- 7 `• (� Construction Management Services for
cY--..,t•.J Third Street Safety Improvements Project
APPENDIX - KEY PERSONNEL
MIKE JOHNSON, SENIOR CONSTRUCTION INSPECTOR
Years of Experience
35+
Certifications and Training
California Standard Test Methods: 201, 202, 216, 217, 226, 227, 231, 375, 518, 533, 539-541
Nuclear Gauge Certified, ACI Level 1, Concrete Technician
40-Hour HazMat Certified
Key Qualifications
Mike's experience in the construction industry includes construction inspection and materials testing on
highway, bridge, and underground utility projects. He has intimate knowledge of Caltrans standards and
has performed construction inspection and material testing in accordance with Caltrans requirements. He
is skilled in construction inspection, materials testing, concrete sampling, asphalt pavement inspection,
pile driving and concrete placement, excellent communication skills, submittal review, progress pay
estimates, and effective teaming with contractors, designers, oversight agencies, and the general public.
Representative Project Experience
San Pablo Avenue Complete Streets Project (Federally Funded), City of San Pablo
Mike was Construction Inspector for this $6M, multiple grant funded, roadway improvement project
including streetscape and pavement rehabilitation. The Project is located along San Pablo Avenue
between Rivers Street and Hilltop Drive. The project will improve San Pablo Avenue for all roadway
users by adding Class 2 bike lanes in both directions of travel, constructing sidewalk along the western
side of San Pablo. Existing traffic signals at all intersections will be replaced or modified and a new
signalized intersection at La Puerta will be constructed. Two new retaining walls will be constructed
along with a new soil nail wall to allow the roadway to be widened sufficiently to accommodate the
new facilities for non -motorized roadway use.
San Pablo and Wildcat Creeks Levee Remediation, Contra Costa County
Construction Inspector for this FEMA mandated levee remediation to raise freeboard to 100-year flood
requirements. Work involved installation of sheetpile walls, levee fill, concrete walls, and HMA pavement
to raise levee roads. The project required close environmental monitoring and coordination with various
entities including East Bay Regional Park District and County Flood Control District. The project was funded
by local County funds and State funds.
Kirker Pass Northbound Truck Climbing Lane, Contra Costa County, CA
Construction inspector for a $14 million, mile -long truck safety lane on Kirker Pass Road, one of Contra
Costa County's most traveled and most dangerous commute routes. Pavement widening on the east side
of the roadway provides a 12-foot truck lane and an 8-foot paved shoulder. Project construction of six
retaining walls adjacent to the road and paving of both north and southbound lanes. Funding sources
include Measure J, the state Transportation Improvement Program, a state match, a local Streets and
Road Program and gas tax revenues.
East Contra Costa Bay Area Rapid Transit (BART) Extension Project Transfer Platform and Guideway
Improvements, Pittsburg, CA.
Construction Inspector. Site work constructed approximately 3.5 miles of rail transit facilities within
the median of SR-4, West of BART's existing Pittsburg/Bay Point Station. Work included the
construction of a platform for BART riders to switch trains, (from existing electrical to new diesel
trains), electrical facilities, including an ancillary train control building, median traffic barriers and
City of San Rafael
Construction MonagementServicesfor
Third Street Safety Improvements Project
APPENDIX - KEY PERSONNEL
subgrade construction. Additional work encased an EBMUD 96" underground aqueduct with
reinforced concrete (staging, excavation, placement).
San Francisco International Airport (SFIA) Indicator Pile Program, City and County of San Francisco,
San Francisco, CA.
Field Inspector. Mike was the field inspector for all piles exceeding 120 LF, for the SFIA Master Plan
Expansion Project. In this capacity, Mike inspected fabrication and storage of pre-tensioned/pre-cast
concrete piles, inspected and monitored pile driving operations to determine bearing capacity and
embedment needed, as well as the inspection and monitoring of load testing.
1-80/ Central Avenue Operational Improvements Project — Phase I, Contra Costa Transportation
Authority (CCTA), Richmond, CA
Construction Inspector. This project improves the traffic operations at the 1-80/Central Avenue
interchange and along Central Avenue between Rydin Road and San Pablo Avenue. The project will be
completed in two phases. This phase redirects left turns from westbound Central Avenue onto 1-80
WB to the adjacent 1-580 eastbound on -ramp at Rydin Road during weekend peak hours; and installs
traffic signals at the 1-580 ramps.
Safe Routes to School - Cycle 1 Improvements, Federal -Aid Project No. SRTS-5137(038), City of
Richmond, Engineering Services Department; Richmond, CA.
Construction Inspector. The Safe Routes to School Cycle 1 Improvements Project enhanced pedestrian
safety near Ford, Grant, King, and Lincoln elementary schools in Richmond, by making improvements
to asphalt and concrete infrastructure, including installing in -roadway lights, constructing ADA-
compliant curb ramps, installing pavement striping and markings, and erecting safety signs.
East Hillsdale Bridge Seismic Retrofit, (federally funded) City of San Mateo, CA
Assistant Resident Engineer and primary bridge inspector for this federally -funded project, which installed
48" cast -in -steel -shell (CISS) out -board piles and post -tensioned bent -cap strengthening. Mike provided
the extensive traffic handling and coordination required to create the work area necessary to perform the
retrofit work. He provided field inspection of the project's construction activities, verified work
conformance to requirements of the project plans and specs, inspected large diameter CISS pile extension
incorporated into enlarged post -tensioned bent -caps, and documented the construction contractor's
activities in a daily report. Additionally, Mike was accountable for pay quantities calculation, documented
work performed, and provided quality assurance for materials used.
Hammer Lane Grade Separation, City of Stockton/Union Pacific Railroad (UPRR), Stockton, CA.
Structures Construction Inspector. Site work constructed two (2) new cast -in -place concrete railroad
bridges, retaining walls, new roadway, a pump station, coordination with extensive roadway and track
detours, utility, lighting and electrical work, as well as curb, gutter and sidewalks. Mike inspected for
excavation shoring, inspected and monitored false -work erection and removal, pile driving and
foundation construction, rebar placement and concrete placement, verified elevations for sub-
structure and super -structure, as well as inspected and monitored post -tensioning. He also inspected
roadway construction.
East Contra Costa Bay Area Rapid Transit (BART) Extension Project Transfer Platform and Guideway
Improvements, Pittsburg, CA.
Construction Inspector. Site work constructed approximately 3.5 miles of rail transit facilities within
the median of SR-4, West of BART's existing Pittsburg/Bay Point Station. Work included the
construction of a platform for BART riders to switch trains, (from existing electrical to new diesel
trains), electrical facilities, including an ancillary train control building, median traffic barriers and
subgrade construction. Additional work encased an EBMUD 96" underground aqueduct with
reinforced concrete (staging, excavation, placement).
�. City of San Rafael
.`m
Construction MonogementServicesfor
Third Street Safety Improvements Project
APPENDIX - KEY PERSONNEL
JAEMIN PARK, P.E., PRINCIPAL IN CHARGE
Years of Experience
29
Education
B.S. Civil Engineering, Cal Poly Pomona 1992
Licenses and Registrations
Professional Engineer: California, #C54476, 1995
Licensed General Contractor #770073, California 1999
Key Qualifications
Jaemin has over 28 years of experience providing project management, construction management,
construction administration, and design of highway, bridge, building and public works infrastructure
projects throughout California. He has worked with state, regional and local agencies in all capacities, as
well as contributed to numerous constructability/bid-ability reviews and value engineering studies. He
has provided claims analysis, mitigation and resolution support to state, regional and local agencies.
Jaemin is an expert in federally funded projects including HBP, HBRR, ARRA, SRTS, NTPP, and TIGER funds.
Representative Project Experience
• On -Call Construction Management, Inspection and Materials Testing Services - Contra Costa County
Jaemin was the Project Manager for this on -call contract constructing numerous public works projects,
federally funded, tax measure funded, locally funded and developer projects throughout the County,
including new roads, bridges and bridge widenings, concrete curb, gutter and sidewalks, storm drains,
traffic signals, culverts, parks and playgrounds, and utilities.
• On -Call Construction Management and Inspection Services — City of San Mateo
Jaemin was the Project Manager for this on -call contract constructing numerous public works projects
throughout the City for over 13 years. Projects were funded from various sources including federal grant
funds, state grant funds, local funds and developer funds.
• John Daly Boulevard Streetscape Improvements Project (federally funded), City of Daly City
Resident Engineer/Project Manager for this $3.3 million federally funded streetscape improvements
project that includes roadway modifications, installation of a concrete walkway, ADA compliant ramps,
landscaping, irrigation using recycled water, bioswales, Class II bicycle lanes, and pedestrian amenities
such as benches and trash/recycling receptacles
• Contra Costa Boulevard Improvements and Pavement Rehabilitation Project (Federally Funded), City
of Pleasant Hill, CA
Project Manager and Resident Engineer for this $4 million project funded through three federal HSIP and
STP grant funds and CCTA measure J grant fund. Project included traffic safety, roadway and other
improvements, including full depth pavement restoration, grind and overlay, intersection and traffic
signal upgrades, bike lanes, enhanced sidewalks and crosswalks, new irrigation and landscaping, and
decorative street median and pedestrian lighting on the main arterial through a busy commercial district.
John Daly Boulevard OC Widening (Federally Funded), City of Daly City, CA
Jaemin was the Project Manager and Resident Engineer for this $4 million project that consisted of
widening the structure to add one additional traffic lane and a wider pedestrian walkway. Jaemin
provided construction management and administration for this bridge -widening and interchange
modification project that crossed over both 1-280 and Highway 1 and was adjacent to the Daly City
BART station, requiring traffic control for heavy vehicular and pedestrian traffic. The project was also
federally funded requiring cooperation with Caltrans Local Assistance.
"}� City of Son Rafael
il.+� Construction MonogementServicesfor
?_ Third Street Safety Improvements Project
Local Assistance Procedures Manual EXHBIT 10-Q
Disclosure of Lobbying Activities
No Lobbying activities to report.
EXHIBIT 10-Q DISCLOSURE OF LOBBYING ACTIVITIES
COMPLETE THIS FORM TO DISCLOSE LOBBYING ACTIVITIES PURSUANT TO 31 U.S.C. 1352
1. Type of Federal Action: 2. Status of Federal Action: 3. Report Type:
❑ a. contract ❑ a. bid/offer/application ❑ a. initial
❑ b. grant ❑ b. initial award ❑ b. material change
❑ c. cooperative agreement ❑ c. post -award
❑ d. loan For Material Change Only:
❑ e. loan guarantee year quarter
❑ f. loan insurance date of last report
4. Name and Address of Reporting Entity 5. If Reporting Entity in No. 4 is Subawardee,
Enter Name and Address of Prime:
❑ Prime ❑ Subawardee
Tier , if known
Congressional District, if known
6. Federal Department/Agency:
8. Federal Action Number, if known:
Congressional District, if known
7. Federal Program Name/Description:
CFDA Number, if applicable
9. Award Amount, if known:
10. Name and Address of Lobby Entity 11. Individuals Performing Services
(If individual, last name, first name, MI) (including address if different from No. 10)
(last name, first name, MI)
(attach Continuation Sheet(s) if necessary)
12. Amount of Payment (check all that apply) 14. Type of Payment (check all that apply)
$ ❑ actual ❑ planned ❑a. retainer
El b. one-time fee
13. Form of Payment (check all that apply): El c. commission
❑ a. cash ❑d. contingent fee
❑ b. in -kind; specify: nature ❑e. deferred
Value ❑f. other, specify
15. Brief Description of Services Performed or to be performed and Date(s) of Service, including
officer(s), employee(s), or member(s) contacted, for Payment Indicated in Item 12:
(attach Continuation Sheet(s) if necessary)
16. Continuation Sheet(s) attached: ❑ Yes ❑No
17. Information requested through this form is authorized by Title r�T�
31 U.S.C. Section 1352. This disclosure of lobbying reliance Signature:
was placed by the tier above when his transaction was made or
entered into. This disclosure is required pursuant to 31 U.S.C. Print Name: Steve Patterson, PE
1352. This information will be reported to Congress
semiannually and will be available for public inspection. Any
person who fails to file the required disclosure shall be subject Title: Vice President
to a civil penalty of not less than $10,000 and not more than
$100,000 for each such failure. Telephone No.: 510,701.0319 Date:
Federal Use Only:
Form LLL Rev. 04-28-06
Distribution: Orig- Local Agency Project Files
014MR.
Authorized for Local Reproduction
Standard Form - LLL
Page 1
LPP 13-01 May 8, 2013
Local Assistance Procedures Manual Exhibit 10-01
Consultant Proposal DBE Commitment
1. Local Agency:
EXHIBIT 10-01 CONSULTANT PROPOSAL DBE COMMITMENT
City of San Rafael 2. Contract DBE Goal: 13%
3. Project Description: Third Street Safety Improvements
4. Project Location: San Rafael, CA
5. Consultant's Name: Park Engineering, Inc. 6. Prime Certified DBE:
7. Description of Work, Service, or Materials
8. DBE
Certification 9. DBE Contact Information
10. DBE %
Supplied
Number
Construction management and inspection services
41711 Park Engineering, Inc., 925.257.2508
Steve Patterson, Vice President
88
Local Agency to Complete this Section
17. Local Agency Contract Number:
11. TOTAL CLAIMED DBE PARTICIPATION 88
18. Federal -Aid Project Number:
19. Proposed Contract Execution Date:
20. Consultant's Ranking after Evaluation:
IMPORTANT: Identify all DBE firms being claimed for credit,
Local Agency certifies that all DBE certifications are valid and information on
regardless of tier. Written confirmation of each listed DBE is
this form is complete and accurate.
required.
^�
2/1/22
21. Local Agency Representative's Signature 22. Date
12. Preparer's Signature 13. Date
Steve Patterson, PE 510.701.0319
23. Local Agency Representative's Name 24. Phone
14. Preparer's Name 15. Phone
Vice President
25. Local Agency Representative's Title
16. Preparer's Title
DISTRIBUTION: Original — Included with consultant's proposal to local agency.
ADA Notice: For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or TDD (916) 654-
3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.
LPP 18-01 Page 1 of 2
January 2019
Local Assistance Procedures Manual Exhibit 10-01
Consultant Proposal DBE Commitment
INSTRUCTIONS — CONSULTANT PROPOSAL DBE COMMITMENT
CONSULTANT SECTION
1. Local Agency - Enter the name of the local or regional agency that is funding the contract.
2. Contract DBE Goal - Enter the contract DBE goal percentage as it appears on the project advertisement.
3. Project Location - Enter the project location as it appears on the project advertisement.
4. Project Description - Enter the project description as it appears on the project advertisement (Bridge Rehab,
Seismic Rehab, Overlay, Widening, etc.).
5. Consultant's Name - Enter the consultant's firm name.
6. Prime Certified DBE - Check box if prime contractor is a certified DBE.
7. Description of Work, Services, or Materials Supplied - Enter description of work, services, or materials to be
provided. Indicate all work to be performed by DBEs including work performed by the prime consultant's own
forces, if the prime is a DBE. If 100% of the item is not to be performed or furnished by the DBE, describe the
exact portion to be performed or furnished by the DBE. See LAPM Chapter 9 to determine how to count the
participation of DBE firms.
8. DBE Certification Number - Enter the DBE's Certification Identification Number. All DBEs must be certified
on the date bids are opened.
9. DBE Contact Information - Enter the name, address, and phone number of all DBE subcontracted consultants.
Also, enter the prime consultant's name and phone number, if the prime is a DBE.
10. DBE % - Percent participation of work to be performed or service provided by a DBE. Include the prime
consultant if the prime is a DBE. See LAPM Chapter 9 for how to count full/partial participation.
11. Total Claimed DBE Participation % - Enter the total DBE participation claimed. If the total % claimed is
less than item "Contract DBE Goal," an adequately documented Good Faith Effort (GFE) is required (see Exhibit
15-H DBE Information - Good Faith Efforts of the LAPM).
12. Preparer's Signature - The person completing the DBE commitment form on behalf of the consultant's firm
must sign their name.
13. Date - Enter the date the DBE commitment form is signed by the consultant's preparer.
14. Preparer's Name - Enter the name of the person preparing and signing the consultant's DBE commitment
form.
15. Phone - Enter the area code and phone number of the person signing the consultant's DBE commitment form.
16. Preparer's Title - Enter the position/title of the person signing the consultant's DBE commitment form.
LOCAL AGENCY SECTION
17. Local Agency Contract Number - Enter the Local Agency contract number or identifier.
18. Federal -Aid Project Number - Enter the Federal -Aid Project Number.
19. Proposed Contract Execution Date - Enter the proposed contract execution date.
20. Consultant's Ranking after Evaluation — Enter consultant's ranking after all submittals/consultants are
evaluated. Use this as a quick comparison for evaluating most qualified consultant.
21. Local Agency Representative's Signature - The person completing this section of the form for the Local
Agency must sign their name to certify that the information in this and the Consultant Section of this form is
complete and accurate.
22. Date - Enter the date the DBE commitment form is signed by the Local Agency Representative.
23. Local Agency Representative's Name - Enter the name of the Local Agency Representative certifying the
consultant's DBE commitment form.
24. Phone - Enter the area code and phone number of the person signing the consultant's DBE commitment form.
25. Local Agency Representative Title - Enter the position/title of the Local Agency Representative certifying the
consultant's DBE commitment form.
LPP 18-01 Page 2 of 2
January 2019
r
�s�----•cam -
� �•� ���-�"`� �w►�"F���i cam- • ...' � V`
a
=i'G< Y� _ ~✓�_u•�LJ!`�.%wL'i(•srv'a .<3� �. . __ - - -- • _a r..YY'_•uv.'
372 Village Square
Orinda, CA 94563
(925) 257.2508
EXHIBIT 10-A
A&E CONSULTANT FINANCIAL DOCUMENT REVIEW REQUEST
Caltrans Division of Local Assistance
(Completed by Local Agencies, One per Contract)
(For New Proposed A&E Consultant Local Agency Contracts of $150,000 or Greater)
(For Amendments, use only when there are additional subconsultants or changes in ICR)
EMAIL TO:
California State Department of Transportation
Independent Office of Audits and Investigations Federal/State Project No.: HSIPL-5043 (043)
conl'ormmiice.review @doi.ca.aov
Attention: Audit Manager, External Contracts -Local Agencies
Please check one:✓ New Contract []Amendment ❑Other
A&E Contract No.: City Project No. 11362
Total Contract or Amended amount of $ 258,498.65
Prime Consultant Full Legal Name: Park Engineering, Inc.
Date: 3/7/2022
The Project Description is: Providing Construction Management & Materials Testing Services for the 3rd Street
Safety Improvement Project
Complete below for Prime and all Sub -consultants on this contract.
Consultant's Name
Participation
Amount
Category 1, 2, 3, 4, 5
Caltrans ICR Acceptance
ID # (if available)
Park Engineering
$228,498 65
2
D2021-0896 (11/18121)
Applied Materials & Engineering, Inc
$30,000.00
2
L2021-1481 (12/06/21)
Note: Add pages if necessary.
I verify we received financial documents from the prime and sub -consultants based on the requirements
specified in the Exhibit 10-A Checklist.
Name
Title
Name of Local Agency and Department:
Address:
Phone No.:
Signature
February 2019
P.0i biI III- \ ( hecWW
CALTRANS A&I FINANCIAL DOCUMENT REVIEW REQUIREMENTS
FOR ARCHITECTURAL AND ENGINEERING (A&E) CONSULTANTS
ON LOCAL GOVERNMENT AGENCY CONTRACTS
Requirements For total contract amount equal to or greater than S150,000.
Local Government Agency must provide the following:
1 ) A&E Consultant Financial Document Review Request Letter (Exhibit 10-A) (a)
2) Local Agency and Prime Consultant's Points of Contact
APPLICABLE ONLY IF NOI
Prime and all sub -consultants ninst provide the following documents based on their applicable category. CATEGORY 1, 2, or 3
CATEGORY I
CATEGORY 2:
CATEGORV 3:
CATEGORY 4:
CATEGORY 5:
Firms with
Firms with
Firms Requesting
Consultant
Consultant
Cognizant
Caltrans
Safe Harbor Rate
Participation
Participation
Type of Financial Documents and Information
Approval Letter
Acceptance ID
(SHR)
Amount Leas
Amount Equal to
for ICR FYE proposed +
for ICR FYE
Number for ICR
than $150K
or Greater than
Proposed
FYE Proposed
S150K
Cost Proposals (Examples at Exhibit 10-H1 through 10-H4)
✓
✓
✓
✓
✓
Consultant Annual Certification of Indirect Costs and Financial Management
✓
✓
System (Exhibit 10-K)
Indirect Cost Rate (ICR) Schedule with FAR References For Disallowed Costs (b)
Note: Prime Consultant must have a CPA Audited ICR Schedule for contracts
✓
✓
✓
equal to or greater than SIM.
Cognizant Approval Letter for the TCR FYE proposed
i
Caltrans' ICR Acceptance ID its For ICR FYE proposed **
✓
AASHTO Internal Control Questionnaire (TCQ) Appendix B (c)
i
Post Closing Trial Balance (d)
Prevailing Wage (PW) Policy for PW work (e)
✓
✓
✓ ...
✓
✓
Safe Harbor Rate Documents:
Consultant Certification of Eligibility of Contract Costs and Financial Management
System (Attachment IR)
✓
When applicable, additional documents may be requested:
Prior Year ICR Schedule
Supplemental Reconciliation Schedule (to tie the proposed ICR Schedule to the
Trial Balance) (d)
Chart of Accounts
Income Statement (d)
Uncompensated Overtime Adjustments (f)
Vacation/Sick Policy
Bonus Policy
Executive Compensation Analysis (ECA) (d)
Related Party Rent Analysis (d)
Vehicle, Equipment, and Other Direct Costs Schedules (d)
n 2m.
Local Assistance Proc d— Menuel Exhibit 10-.A Ch,d M
* ICR FYE = Indirect Cost Rate Fiscal Year End. Items on this checklist may not be all inclusive. A&I reserves the right to
request additional documentats as deemed necessary.
** Caltrans ICR Acceptance ID # is an identification number issued by Caltrans upon review and acceptance of consultant's
indirect cost rate(s) schedule for a specific fiscal year. This ID # can be referenced for use on fitture contracts using the same FYE
ICR.
***Firms using SHR can be reimbursed.for the prevailing wage deltas either as an Other Direct Cost or as an Overhead/Indirect
Cost - refer to A&I's PW Interpretive Guidance on Mute//ire.dot.ca.jeov/resourcesleeruraironod.html
(a) Local Agencies are required to complete Exhibit 10-A and include all applicable required documents upon .submission.
(b) See Table 8-1 of the AASHTO Audit Guide, fora listing of common unallowable costs.
For financial document packages received between January 1, 2019 to June 30, 2019, the 2017 FYE ICR could be submitted if the
FYE 2018 ICR is not available. Foy -financial document packages received between
July 1, 2019 to December 31, 2019, the 20181CR must be submitted.
(c) Go to AASHTO website @ audit. transportation.org, for Appendix B-Internal Control Questionnaire
(d) Accounts and balances must match costs proposed on the ICR schedule.
(e) Consultants performing Prevailing Wage (PW) work are required to provide written PW Policy. The policy must specify their
accounting method for treatment of delta base and delta fringe. Refer to A&1's PW Interpretive Guidance on
htW.-11.e.dot, ca.gov/resources/,eentrainmod. html
Fbra 2019
Local Assistance Procedures Manual
EXHIBIT 10-HI COST PROPOSAL Page I oF3
EXHIBIT 10-H1
Cost Proposal
COST -PLUS -FIXED FEE OR LUMP SUM OR FIRM FIXED PRICE CONTRACTS
(DESIGN, ENGINEERING AND ENVIRONMENTAL STUDIES)
Note: Mark-ups are Not Allowed ❑� Prime Consultant ❑ Subconsultant ❑ 2"1 Tier Subconsultant
Consultant Park Engineering, Inc.
Project No. 11349 Contract No. HSIPL-5043 (043) Date 03/04/2022
DIRECT LABOR
Classification/Title
Name
Hours
Actual Hourly Rate
Total
Constr. Inspector
Andy Bodo - Regular Rate
980.00
$ 65.73
$ 98.60
$ 88.64
$ 68.55
$ 64,415.40
$ 1,972.00
$ 29,251.20
$ 5,484.00
Constr. Inspector"
Andy Bodo - Overtime Rate
20.00
Resident Engineer
Steve Patterson
330.00
80.00
Constr. Inspector "
Chris Kinser
LABOR COSTS
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see page 2 for calculation)
$ 101,122.60
c) TOTAL DIRECT LABOR COSTS [(a) + (b)] $ 101,122.60
INDIRECT COSTS
d) Fringe Benefits (Rate: 42.17°i) e) Total Fringe Benefits [(c) x (d)] $ 42,643.40
0 Overhead (Rate: 63.25% ) g) Overhead [(c) x (f)] $ 63,960.04
h) General and Administrative (Rate: 0.00% ) i) Gen & Admin [(c) x (h)] $ 0.00
j) TOTAL INDIRECT COSTS [(e) + (g) + (i)] $ 106,603.44
FIXED FEE k) TOTAL FIXED FEE [(c) + O)] x fixed fee10.00% ] $ 20,772.60
1) CONSULTANT'S OTHER DIRECT COSTS (ODCI — ITEMIZE (Add additional napes if necessarvl
Description of Item
Quantitv
Unit I Unit Cost
Total
Mileage Costs
$ 0.00
Eouioment Rental and StloDlies
$ 0.0
Permit Fees
$ 0.0
Plan Sheets
$ 0.0
Test
$ 0.00
I) TOTAL OTHER D1REC"P COSTS g n on
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary)
Subconsultant 1: Applied Materials & Engineering. Inc-
Subconsultant 2:
Subconsultant 3:
Subconsultant 4:
$ 30,000.00
m) TOTAL SUBCONSULTANTS' COSTS $ 30.000.00
n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(I)+(m)] $ 9n ant) nn
TOTAL COST [(c) + 0) + (k) + (n)] $ 258.498.65
NOTES:
1. Key personnel must be marked with an asterisk(*) and employees that are subject to prevailing wage requirements must be marked
with two asterisks (**). All costs must comply with the Federal cost principles. Subconsultants will provide their own cost proposals.
2. The cost proposal format shall not be amended. Indirect cost rates shall be updated on an annual basis in accordance with the
consultant's annual accounting period and established by a cognizant agency or accepted by Caltrans.
3. Anticipated salary increases calculation (page 2) must accompany.
Page 1 of 9
January 2020
Local Assistance Procedures Manual EXHIBIT 10-1-11
Cost Proposal
EXHIBIT 10-H1 COST PROPOSAL Page 2 of 3
COST -PLUS -FIXED FEE OR LUMP SUM OR FIRM FIXED PRICE CONTRACTS
(CALCULATIONS FOR ANTICIPATED SALARY INCREASES)
1. Calculate Average Hourly Rate for 1st year of the contract (Direct Labor Subtotal divided by total hours)
Direct Labor
Total Hours per
Avg 5 Year
Subtotal
per Cost
Cost Proposal
Hourly Contract
Proposal
Rate Duration
$250,000.00
500
= $50.00 Year 1 Avg
Hourly Rate
2. Calculate hourly rate for all years
(Increase the Average Hourly Rate for a year by proposed escalation %)
Avg Hourly Rate
Proposed Escalation
Year 1
$50.00
+ 2% _
$51.00 Year 2 Avg Hourly Rate
Year 2
$51.00
+ 2% _
$52.02 Year 3 Avg Hourly Rate
Year 3
$52.02
+ 2% _
$53.06 Year 4 Avg Hourly Rate
Year 4
$53.06
+ 2% _
$54.12 Year 5 Avg Hourly Rate
3. Calculate estimated hours per year (Multiply estimate % each
year by total hours)
Estimated % Completed
Total Hours per Cost
Total Hours per
Each Year
Proposal
Year
Year 1
20.0%
5000 =
1000 Estimated Hours Year 1
Year 2
40.0%
5000 =
2000 Estimated Hours Year 2
Year 3
15.0%
5000 =
750 Estimated Hours Year 3
Year 4
15.0%
5000 =
750 Estimated Hours Year 4
Year 5
10.0%
5000 =
500 Estimated Hours Year 5
Total
100%
Total =
5000
4. Calculate Total Costa including Escalation (Multiply Average Hourly Rate by the number of hours)
Avg Hourly Rate
Estimated hours
Cost per
(calculated above)
(calculated above)
Year
Year 1
$50.00
1000
= $50,000.00 Estimated Hours Year 1
Year 2
$51.00
2000
= $102,000.00 Estimated Hours Year 2
Year 3
$52.02
750
= $39,015.00 Estimated Hours Year 3
Year 4
$53.06
750
= $39,795.30 Estimated Hours Year 4
Year 5
$54.12
500
= $27,060.80 Estimated Hours Year 5
Total Direct Labor Cost with Escalation
= $257,871.10
Direct Labor Subtotal before Escalation
= $250,000.00
Estimated total of Direct Labor Salary
= Transfer to Page 1
Increase
$7,871.10
NOTES:
1. This is not the onlyway to estimatesalaly increases. Other methodswill be accepted if they clearlyindicate the %
increase, the # of years of the contract, and a breakdown of the labor to be performed each year.
2. An estimation that is based on direct labor multiplied by salary increase % multiplied by the # of years is not
acceptable.
(i.e. $250,000 x 2% x 5 yrs = $25,000 is not an acceptable methodology)
3. This assumes that one year will be worked at the rate on the cost proposal before salary increases are granted.
4. Calculations for anticipated salary escalation must be provided.
Page 2 of 9
January 2020
Local Assistance Procedures Manual EXHIBIT 10-1-11
Cost Proposal
EXHIBIT 10-1-111 COST PROPOSAL Page 3 of 3
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the
cost proposal(s) in this contract are actual, reasonable, allowable, and allocable to the contract in
accordance with the contract terms and the following requirements:
1. Generally Accepted Accounting Principles (GAAP)
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Requlations Part 31 - Contract Cost Principles and Procedures
5. 23 Code of Federal Requlations Part 172 - Procurement, Management, and
Administration of Engineering and Design Related Service
6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when
applicable)
All costs must be applied consistently and fairly to all contracts. All documentation of compliance must
be retained in the projectfiles and be in compliance with applicable federal and state requirements.
Costs that are noncompliant with the federal and state requirements are not eligible for reimbursement
Local governments are responsible for applying only cognizant agency approved or Caltrans accepted
Indirect Cost Rate(s).
Prime Consultant or Subconsultant Certifying:
Name: Steve Patterson
Sigaature
Title'
Vice President
Date of Certification (mm/dd/yyyy): 03/07/2022
Email spatterson@park-eng.com Phone Number: (510) 701-0319
Address.372 Village Square. Orinda, CA 94563
*An individual executive or financial officer of the consultant's or subconsultant's organization at
a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has
authority to represent the financial information utilized to establish the cost proposal for the
contract
-Ist services the consultant is providinq under the proposed contract:
Construction Management and Materials Testing Services for the 3rd Street Safety Improvements Project.
Page 3 of 9
January 2020
Local Assistance Procedures Manual Exhibit 10-K
Consultant Annual Certification of Indirect Costs and Financial Management System
EXHIBIT I O-K CONSULTANT ANNUAL CERTIFICATION OF
INDIRECT COSTS AND FINANCIAL MANAGEMENT SYSTEM
(Note: If a Safe Harbor Indirect Cost Rate is approved, this form is not required.)
Consultant's Full Legal Name:
Important: Consultant means the individual or consultant providing engineering and design related
services as a party of a contract with a recipient or sub -recipient of Federal assistance. Therefore, the
Indirect Cost Rate(s) shall not be combined with its parent company or subsidiaries.
Indirect Cost Rate: Combined
Rate 105.43 % OR
Home Office Rate % and Field Office Rate (if applicable) %
Facilities Capital Cost of % (if applicable)
Memodyperiod * 1 /l /2020 — 12/31 /2020
* Fiscal period is annual one year applicable accounting period that the Indirect Cost Rate was developed (not
the contract period). The Indirect Cost Rate is based on the consultant's one-year applicable accounting period
for which financial statements are regularly prepared by the consultant.
I have reviewed the proposal to establish an Indirect Cost Rate(s) for the fiscal period as specified above and have
determined to the best of my knowledge and belief that:
• All costs included in the cost proposal to establish the indirect cost rate(s) are allowable in
accordance with the cost principles of the Federal Acquisition Regulation (FAR) 48, Code of
Federal Regulations (CFR), Chapter 1, Part 31 (48 CFR Part 31);
• The cost proposal does not include any costs which are expressly unallowable under the cost
principles of 48 CFR Part 31;
• The accounting treatment and billing of prevailing wage delta costs are consistent with our
prevailing wage policy as either direct labor, indirect costs, or other direct costs on all federally -
funded A&E Consultant Contracts.
• All known material transactions or events that have occurred subsequent to year-end affecting the
consultant's ownership, organization, and indirect cost rates have been disclosed as of the date of
this certification.
I am providing the required and applicable documents as instructed on Exhibit 10-A.
Financial Management System:
Our labor charging, job costing, and accounting systems meet the standards for financial reporting, accounting
records, and internal control adequate to demonstrate that costs claimed have been incurred, appropriately
accounted for, are allocable to the contract, and comply with the federal requirements as set forth in Title 23
United States Code (U.S.C.) Section 1 I2(b)(2); 48 CFR Part 31.201-2(d), 23 CFR. Chapter 1, Part 172.11(a)(2);
and all applicable state and federal rules and regulations.
Our financial management system has the following attributes:
• Account numbers identifying allowable direct, indirect, and unallowable cost accounts;
• Ability to accumulate and segregate allowable direct, indirect, and unallowable costs into separate cost
Page 1 of 2
March 2018
Local Assistance Procedures Manual Exhibit 10-K
Consultant Annual Certification of indirect Costs and Financial Management System
accounts;
• Ability to accumulate and segregate allowable direct costs by project, contract and type of cost;
• Internal controls to maintain integrity of financial management system;
• Ability to account and record costs consistently and to ensure costs billed are in compliance with FAR;
• Ability to ensure and demonstrate costs billed reconcile to general ledgers and job costing system; and
• Ability to ensure costs are in compliance with contract terms and federal and state requirement
Cost Reimbursements on Contracts:
I also understand that failure to comply with 48 CFR Part 16.301-3 or knowingly charge unallowable costs to
Federal -Aid Highway Program (FAHP) contracts may result in possible penalties and sanctions as provided by
the following:
• Sanctions and Penalties - 23 CFR Part 172.11 (c)(4)
• False Claims Act - Title 31 U.S.C. Sections 3729-3733
• Statements or entries generally - Title 18 U.S.C. Section 1001
• Major Fraud Act - Title 18 U.S.C. Section 1031
All A&E Contract Information:
• Total participation amount $ 8,036,617 on all State and FAHP contracts for Architectural &
Engineering services that the consultant received in the last three fiscal periods.
• The number of states in which the consultant does business is 1
• Years of consultant's experience with 48 CFR Part 31 is 21
• Audit history of the consultant's current and prior years (if applicable)
❑ Cognizant ICR Audit R1 Local Gov't ICR Audit ❑ Caltrans ICR Audit
El CPA ICR Audit El Federal Gov't ICR Audit
I, the undersigned, certify all of the above to the best of my knowledge and belief and that I have reviewed the
Indirect Cost Rate Schedule to determine that any costs which are expressly unallowable under the Federal cost
principles have been removed and comply with Title 23 U.S.C. Section 1 12(b)(2), 48 CFR Part 31, 23 CFR Part 172, and
all applicable state and federal rules and regulations. i also certify that i understand that all documentation of
compliance must be retained by the consultant. I hereby acknowledge that costs that are noncompliant with the
federal and state requirements are not eligible for reimbursement and must be returned to Caltrans.
Name**: Jaemin Park Title**: President/CEO/CFO
Signature: Date of Certification (mm/dd/yyyy): 3/7/2022
Email**: jparl mark-eng.com Phone Number**: 925-818-3756
**An individual executive or financial officer of the consultant's or subconsultan i's organization at a level no lower than a Vice President, a
Chief Financial Officer, or equivalent, who has authority to represent the financial information used to establish the indirect cost rate.
Note: Both prime and subconsultants as parties of a contract must complete their own Exhibit 10-Kforms.
Caltrans will not process local agency's invoices until a complete Exhibit 10-Kform is accepted and approved by
Caltrans Audits and Investigations.
Distribution: 1) Original - Local Agency Project File
2) Copy - Consultant
3) Copy -Caltrans Audits and Investigations
Page 2 of 2
March 2018
Local Assistance Procedures Manual Exhibit 10-K
Consultant Annual Certification of Indirect Costs and Financial Management System
EXHIBIT 10-K CONSULTANT ANNUAL CERTIFICATION OF
INDIRECT COSTS AND FINANCIAL MANAGEMENT SYSTEM
(Note: If a Safe Harbor Indirect Cost Rate is approved, this form is not required)
Consultant's Full Legal Name: Applied Materials & Engineering, Inc.
Important: Consultant means the individual or consultant providing engineering and design related
services as a party of a contract with a recipient or sub -recipient of Federal assistance. Therefore, the
Indirect Cost Rate(s) shall not be combined with its parent company or subsidiaries.
Combined Rate % OR
Home Office Rate 157.86 % and Field Office Rate (if applicable) %
Facilities Capital Cost of Money % (if applicable)
Fiscal period *
1 /1 /20 to 12/31 /20
* Fiscal period is annual one year applicable accounting period that the Indirect Cost Rate was developed (not
the contract period). The Indirect Cost Rate is based on the consultant's one-year applicable accounting period
for which financial statements are regularly prepared by the consultant.
I have reviewed the proposal to establish an Indirect Cost Rate(s) for the fiscal period as specified above and have
determined to the best of my knowledge and belief that:
• All costs included in the cost proposal to establish the indirect cost rate(s) are allowable in
accordance with the cost principles of the Federal Acquisition Regulation (FAR) 48, Code of
Federal Regulations (CFR), Chapter 1, Part 31 (48 CFR Part 31);
• The cost proposal does not include any costs which are expressly unallowable under the cost
principles of 48 CFR Part 31;
• The accounting treatment and billing of prevailing wage delta costs are consistent with our
prevailing wage policy as either direct labor, indirect costs, or other direct costs on all federally -
funded A&E Consultant Contracts.
• All known material transactions or events that have occurred subsequent to year-end affecting the
consultant's ownership, organization, and indirect cost rates have been disclosed as of the date of
this certification.
I am providing the required and applicable documents as instructed on Exhibit 10-A.
Financial Management System:
Our labor charging, job costing, and accounting systems meet the standards for financial reporting, accounting
records, and internal control adequate to demonstrate that costs claimed have been incurred, appropriately
accounted for, are allocable to the contract, and comply with the federal requirements as set forth in Title 23
United States Code (U.S.C.) Section 1 12(b)(2); 48 CFR Part 31.201-2(d), 23 CFR, Chanter 1. Part 172.1 1(a)(2);
and all applicable state and federal rules and regulations.
Our financial management system has the following attributes:
• Account numbers identifying allowable direct, indirect, and unallowable cost accounts;
• Ability to accumulate and segregate allowable direct, indirect, and unallowable costs into separate cost
Page 1 of 2
March 2018
Local Assistance Procedures Manual Exhibit 10-K
Consultant Annual Certification of Indirect Costs and Financial Management System
accounts;
• Ability to accumulate and segregate allowable direct costs by project, contract and type of cost;
• Internal controls to maintain integrity of financial management system;
• Ability to account and record costs consistently and to ensure costs billed are in compliance with FAR;
• Ability to ensure and demonstrate costs billed reconcile to general ledgers and job costing system; and
• Ability to ensure costs are in compliance with contract terms and federal and state requirement
Cost Reimbursements on Contracts:
I also understand that failure to comply with 48 CFR Part 16.301-3 or knowingly charge unallowable costs to
Federal -Aid Highway Program (FAHP) contracts may result in possible penalties and sanctions as provided by
the following:
• Sanctions and Penalties - 23 CFR Part 172.11(c)(4)
• False Claims Act - Title 31 U.S.C. Sections 3729-3733
• Statements or entries generally - Title 18 U.S.C. Section 1001
• Major Fraud Act - Title 18 U.S.C. Section 1031
All A&E Contract Information:
• Total participation amount $--$600,000 on all State and FAHP contracts for Architectural &
Engineering services that the consultant received in the last three fiscal periods.
• The number of states in which the consultant does business is 31.00
• Years of consultant's experience with 48 CFR Part 31 is 25.00
• Audit history of the consultant's current and prior years (if applicable)
❑ Cognizant ICR Audit ❑ Local Gov't ICR Audit ❑ Caltrans ICR Audit
I] CPA ICR Audit
❑ Federal Gov't ICR Audit
I, the undersigned, certify all of the above to the best of my knowledge and belief and that I have reviewed the
Indirect Cost Rate Schedule to determine that any costs which are expressly unallowable under the Federal cost
principles have been removed and comply with Title 23 U.S.C. Section I I2(b)(2), 48 CFR Part 31 23 CFR Part 172, and
all applicable state and federal rules and regulations. I also certify that I understand that all documentation of
compliance must be retained by the consultant. I hereby acknowledge that costs that are noncompliant with the
federal and state requirements are not eligible for reimbursement and must be returned to Caltrans.
Name": Applied Materials & Engineering, Inc. Title": President
Signature:
Email": dushyant@appmateng.com
Date of Certification (mm/dd/yyyy): 11 /16/2021
Phone Number": (510) 420-8190
**An individual executive or financial officer of the consultant's or subconsultant's organization at a level no lower than a Vice President, a
Chief Financial Officer, or equivalent, who has authority to represent the financial information used to establish die indirect cost rate.
Note: Both prime and subconsultants as parties of a contract must complete their own Exhibit 10-Kforms.
Caltrans will not process local agency's invoices until a complete Exhibit 10-Kform is accepted and approved by
Caltrans Audits and Investigations.
Distribution: l) Original - Local Agency Project File
2) Copy -Consultant
3) Copy-Caltrans Audits and Investigations
Page 2 of 2
March 2018
RAP
i 2
o
Y '^/ITH P
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Nataly Torres (For Philip Buckley) Extension: 3353
Contractor Name: Park Engineering, Inc.
Contractors Contact: Steve Patterson Contact's Email: sptterson@park-eng.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor
Click here to
C
enter a date.
b. Email contract (in Word) and attachments to City
4/13/2022
Attorney c/o Laraine.Gittens@cityofsanrafael.org
❑X IKK
2
City Attorney
a. Review, revise, and comment on draft agreement
4/13/2022
® LG
and return to Project Manager
4/13/2022
® LG
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
3
Department Director
Approval of final agreement form to send to
7/11/2023
© AM
contractor
4
Project Manager
Forward three (3) originals of final agreement to
8/7/2023
lZ
contractor for their signature
5
Project Manager
When necessary, contractor -signed agreement
❑ N/A
agendized for City Council approval *
*City Council approval required for Professional Services
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
4/18/2022
Date of City Council approval
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
agreement
8
City Attorney
Review and approve insurance in PINS, and bonds
(for Public Works Contracts)
9
City Manager / Mayor
Agreement executed by City Council authorized
official
Attest signatures, retains original agreement and
10
City Clerk
forwards copies to Project Manager
Final Federal PSA - Third St Rehab - Park
Engineering - CM and Materials testing
Final Audit Report 2023-08-29
Created: 2023-08-07
By: Nataly Torres (nataly.torres@cityofsanrafael.org)
Status: Signed
Transaction ID: CBJCHBCAABAAFsZjxXiAwh3d9dUxjE6IAY1ZdgjiY3-j
"Final Federal PSA - Third St Rehab - Park Engineering - CM an
d Materials testing" History
Document created by Nataly Torres (nataly.torres@cityofsanrafael.org)
2023-08-07 - 11:48:53 PM GMT
E-I Document emailed to Steve Patterson (spatterson@park-eng.com) for signature
2023-08-07 - 11:54:00 PM GMT
Email viewed by Steve Patterson (spatterson@park-eng.com)
2023-08-07 - 11:54:32 PM GMT
6o Document e-signed by Steve Patterson (spatterson@park-eng.com)
Signature Date: 2023-08-07 - 11:55:16 PM GMT - Time Source: server
E' Document emailed to Jaemin Park apark@park-eng.com) for signature
2023-08-07 - 11:55:20 PM GMT
Email viewed by Jaemin Park apark@park-eng.com)
2023-08-08 - 0:01:39 AM GMT
�© Document e-signed by Jaemin Park Qpark@park-eng.com)
Signature Date: 2023-08-08 - 0:13:06 AM GMT - Time Source: server
C'-► Document emailed to Laraine Gittens (laraine.gittens@cityofsanrafael.org) for approval
2023-08-08 - 0:13:10 AM GMT
Email viewed by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2023-08-08 - 7:13:52 PM GMT
Ey New document URL requested by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2023-08-16 - 4:53:49 PM GMT
Powered by
' ` SAN RAFAEL I Adobe
1%01`"`" """" SiO� Acrobat Sign
Email viewed by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2023-08-16 - 4:54:00 PM GMT
&o Document approved by Laraine Gittens(laraine.gttens@cityofsanrafael.org)
Approval Date: 2023-08-16 - 4:54:15 PM GMT - Time Source: server
�'� Document emailed to Genevieve Coyle (genevieve.coyle@cityofsanrafael.org) for signature
2023-08-16 - 4:54:21 PM GMT
Email viewed by Genevieve Coyle (genevieve.coyle@cityofsanrafael.org)
2023-08-16 - 5:01:48 PM GMT
6o Document e-signed by Genevieve Coyle (genevieve.coyle@cityofsanrafael.org)
Signature Date: 2023-08-16 - 5:12:10 PM GMT - Time Source: server
L'. Document emailed to city.clerk@cityofsanrafael.org for approval
2023-08-16 - 5:12:16 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2023-08-16 - 5:22:13 PM GMT
&a Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi
2023-08-16 - 5:22:26 PM GMT
b© Document approved by Brenna Nurmi(city.clerk@cityofsanrafael.org)
Approval Date: 2023-08-16 - 5:22:28 PM GMT - Time Source: server
C'. Document emailed to cristine.alilovich@cityofsanrafael.org for signature
2023-08-16 - 5:22:32 PM GMT
n Email viewed by cristine.alilovich@cityofsanrafael.org
2023-08-21 - 4:53:32 AM GMT
t Email viewed by cristine.alilovich@cityofsanrafael.org
2023-08-29 - 6:01:11 PM GMT
�© Signer cristine.alilovich@cityofsanrafael.org entered name at signing as Cristine Alilovich
2023-08-29 - 6:03:52 PM GMT
6o Document e-signed by Cristine Alilovich (cristine.alilovich@cityofsanrafael.org)
Signature Date: 2023-08-29 - 6:03:54 PM GMT - Time Source: server
C'� Document emailed to city.clerk@cityofsanrafael.org for signature
2023-08-29 - 6:03:59 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2023-08-29 - 6:21:17 PM GMT
& SAN RAFAEL � Powered by
i Adobe
Adobe
THE ❑rvv,mi-'mIss:o,v Acrobat Sign
Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi (for)
2023-08-29 - 6:21:42 PM GMT
6© Document e-signed by Brenna Nurmi (for)(city.clerk@cityofsanrafael.org)
Signature Date: 2023-08-29 - 6:21:44 PM GMT - Time Source: server
Agreement completed.