SERVICE LEVEL AGREEMENT
DATED JUNE 20, 2023
WITH MARK THOMAS & COMPANY, INC.
TASK ORDER NO. 94.1
(Amendment to Task Order No. 94)
Lincoln Ave Bridge HBP Submittal
Amendment Amount: $3,500
THIS AMENDMENT TO TASK ORDER No. 94 is entered into on J U [ 22, 2024
between the City of San Rafael, a municipal corporation ("City"), and Mark Thomas & Company, Inc,
("Contractor").
RECITALS
A. Whereas Master Consultant Services Agreement is hereby renamed Service Level
Agreement; and
B. The City and Contractor (as may be identified as "Consultant" in the original Agreement)
have entered into a Service Level Agreement ("Agreement") dated June 20, 2023, under which Contractor
has agreed to perform certain contract services for the City; and
C. Pursuant to the Agreement, on July 13, 2023, the City and Contractor entered into "Task
Order No. 94" under which Contractor agreed to perform contract services in connection with City's
Lincoln Ave Bridge HBP Submittal (the "Project"), for a total not to exceed $6,634; and
D. City now requires additional services for the Project, and the Contractor is willing to
provide such services.
NOW, THEREFORE, City and Contractor agree to amend Task Order No. 94 as follows:
AGREEMENT TO AMEND TASK ORDER
1. Section 1 entitled "Scope of Services," is hereby amended to include the additional services set
forth in Exhibit A of this Task Order Amendment.
2. Section 2 entitled "Date of completion; Work hours estimate; Cost estimate and budget; Fee
schedule" is hereby amended to include the additional services, work hours estimate, cost estimate and
budget set forth in Exhibit A, for an amount not to exceed $3,500, changing the total not to exceed to
$10,134.
3. Except as specifically amended herein, all of the other provisions, terms and obligations of Task
Order No. 94 shall remain valid and shall be in full force.
Rev. May 2013
City of San Rafael Service Level Agreement
Amendment to Task Order
4. Signatures. The parties have executed this Amendment as of the date first written above.
CITY OF SAN RAFAEL CONTRACTOR
1111 .A"11--e
By: Cristine Alilovich (Jul 22, 202415:50 PDT)
Cristine Alilovich, City Manager
Reviewed By
Rabe�t -. C-Aaft�f'
By: Robert F. Epstein (Jul 16, 202413:31 PDT)
Robert F. Epstein, City Attorney
Exhibits:
A — Scope of Work
2
Rev Jan 2019
By:
Name: Sasha Dansky
Title:
Principal+Vice President
(if Contractor is a corporation, add
signature of second corporate officer)
Aet
By: Matt Brogan (Jul 15, 2024 08:40 PDT)
Name. Matt Brogan
Title: Secretary
Exhibit A ►/
MARK THOMAS
June 12, 2024
Mr. Theo Sanchez
Public Works Department
City of San Rafael
111 Morphew Street
San Rafael, CA 94901 US
RE: LINCOLN AVE BRIDGE HBP SUBMITTAL (TASK ORDER 94), REQUEST FOR
AMENDMENT
Dear Mr. Sanchez:
23-00182
Mark Thomas would like to submit an amendment request for the Lincoln Ave Bridge project. The
scope is as follows:
• Update HBP application and provide cost comparisons between rehabilitation and replacement.
The fee for this work will be charged on a lump sum basis, with a total cost for our services of
$3,500.
Please let me know if this amendment is acceptable to you. In the meantime, if you have any
questions, please feel free to give me a call (916) 595-7025.
Sincerely,
MARK THOMAS
Jason Hickey
Division Manager
MARKTHOMAS COM
hp,xA RAF,q�I
i 2
yo
C/ry WITH p
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Shannon Mackle (for Theo Sanchez) Extension: 3353
Contractor Name: Mark Thomas & Company, Inc.
Contractor's Contact: Jason Hickey Contact's Email: jhickey@markthomas.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor
Click here to
❑
enter a date.
b. Email contract (in Word) and attachments to City
6/14/2024
Attorney c/o Laraine.Gittens@cityofsanrafael.org
®SM
2
City Attorney
a. Review, revise, and comment on draft agreement
6/17/2024
and return to Project Manager
6/17/2024
® NT
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
© NT
3
Department Director
Approval of final agreement form to send to
6/18/2024
❑X AM
contractor
4
Project Manager
Forward three (3) originals of final agreement to
6/20/24
® SM
contractor for their signature
5
Project Manager
When necessary, contractor -signed agreement
® N/A
agendized for City Council approval *
*City Council approval required for Professional Services
❑
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
Click here to
Date of City Council approval
enter a date.
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
agreement
8
City Attorney
Review and approve insurance in PINS , and bonds
(for Public Works Contracts)
9
City Manager / Mayor Agreement executed by City Council authorized
official
10
City Clerk
Attest signatures, retains original agreement and
forwards copies to Project Manager
Task Order
Interim Agreement Report
Amendment 94.1
Created:
2024-06-20
By:
Shannon Mackie (shannon.maclde@cityofsanrafael.org)
Status:
Out for Approval
Transaction ID:
CBJCHBCAABAA2INJAInFknx v-IfFPsLsoels7JVK3c
Agreement History
P401ZQIYQil.7
Agreement history is the list of the events that have impacted the status of the agreement prior to the final signature. A final audit report will
be generated when the agreement is complete.
"Task Order Amendment 94.1" History
Document created by Shannon Mackle (shannon.mackle@cityofsanrafael.org)
2024-06-20-10:18:54 PM GMT- IP address: 199.88.113.8
P"-► Document emailed to Sasha Dansky (sdansky@markthomas.com) for signature
2024-06-20 - 10:21:13 PM GMT
Email viewed by Sasha Dansky (sdansky@markthomas.com)
2024-07-10-11:09:58 PM GMT- IP address: 71.6.35.186
b© Document e-signed by Sasha Dansky (sdansky@markthomas.com)
Signature Date: 2024-07-11 - 5:36:36 PM GMT - Time Source: server- IP address: 71.6.35.186
E7* Document emailed to Matt Brogan (mbrogan@markthomas.com) for signature
2024-07-11 - 5:36:38 PM GMT
Email viewed by Matt Brogan (mbrogan@markthomas.com)
2024-07-11 - 5:43:24 PM GMT- IP address: 68.233.192.146
&G Document e-signed by Matt Brogan (mbrogan@markthomas.com)
Signature Date: 2024-07-15 - 3:40:52 PM GMT - Time Source: server- IP address: 68.233.192.146
c'. Document emailed to Laraine Gittens (laraine.gittens@cityofsanrafael.org) for approval
2024-07-15 - 3:40:54 PM GMT
SAN RAFAEL I Adobe
111, -vv:rrurAISYcu Acrobat Sign
Task Order Amendment 94.1 - Mark Thomas &
Company - Lincoln Ave Bridge
Final Audit Report 2024-07-22
Created: 2024-07-16
By: Nataly Torres (nataly.torres@cityofsanrafael.org)
Status: Signed
Transaction ID: CBJCHBCAABAA3JFjLGspr ngJXeeNVWWYTGM_dgv_d6m
"Task Order Amendment 94.1 - Mark Thomas & Company - Linc
oln Ave Bridge" History
in Document created by Nataly Torres (nataly.torres@cityofsanrafael.org)
2024-07-16 - 4:39:10 PM GMT- IP address: 199.88.113.8
P+ Document emailed to Laraine Gittens (laraine.gittens@cityofsanrafael.org) for approval
2024-07-16 - 4:40:37 PM GMT
Email viewed by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2024-07-16 - 4:40:59 PM GMT- IP address: 104.47.65.254
X. Document shared with Shannon Mackie (shannon.mackle@cityofsanrafael.org) by Nataly Torres
(nataly.torres@cityofsan rafael. org)
2024-07-16 - 4:41:17 PM GMT- IP address: 199.88.113.8
&0 Document approved by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
Approval Date: 2024-07-16 - 4:44:00 PM GMT - Time Source: server- IP address: 199.88.113.8
Py Document emailed to rob.epstein@cityofsanrafael.org for signature
2024-07-16 - 4:44:02 PM GMT
ii Email viewed by rob.epstein@cityofsanrafael.org
2024-07-16 - 8:31:21 PM GMT- IP address: 104.28.123.171
b© Signer rob.epstein@cityofsanrafael.org entered name at signing as Robert F. Epstein
2024-07-16 - 8:31:41 PM GMT- IP address: 104.28.123.171
&o Document e-signed by Robert F. Epstein (rob.epstein@cityofsanrafael.org)
Signature Date: 2024-07-16 - 8:31:43 PM GMT - Time Source: server- IP address: 104.28.123.171
SAN PAFAEL Powered by
Adobe
'"` - '; ''°"S`:" Acrobat Sign
El Document emailed to city.clerk@cityofsanrafael.org for approval
2024-07-16 - 8:31:45 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2024-07-16 - 8:43:25 PM GMT- IP address: 104.47.64.254
6© Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi
2024-07-16 - 8:43:33 PM GMT- IP address: 199.88.113.8
rSm Document approved by Brenna Nurmi (city.clerk@cityofsanrafael.org)
Approval Date: 2024-07-16 - 8:43:35 PM GMT - Time Source: server- IP address: 199.88.113.8
P4 Document emailed to cristine.alilovich@cityofsanrafael.org for signature
2024-07-16 - 8:43:40 PM GMT
Email viewed by cristine.alilovich@cityofsanrafael.org
2024-07-16 - 8:56:43 PM GMT- IP address: 174.195.80.156
Email viewed by cristine.alilovich@cityofsanrafael.org
2024-07-22 - 10:49:39 PM GMT- IP address: 104.47.65.254
b© Signer cristine.alilovich@cityofsanrafael.org entered name at signing as Cristine Alilovich
2024-07-22-10:50:44 PM GMT- IP address: 199.88.113.8
d© Document e-signed by Cristine Alilovich (cristine.alilovich@cityofsanrafael.org)
Signature Date: 2024-07-22 - 10:50:46 PM GMT - Time Source: server- IP address: 199.88.113.8
® Agreement completed.
2024-07-22-10:50:46 PM GMT
SAN RAFAEL I 'by
Adobe
112 I --YON Acrobat Sign