SERVICE LEVEL AGREEMENT
DATED NOVEMBER 3, 2023
WITH PARAMETRIX, INC
TASK ORDER NO. 113
Subject title: Project Development and Plan Review Support
Task Order Amount: $30,000
THIS TASK ORDER is entered into on 04/16/2024 between the City of San Rafael,
a municipal corporation ("City"), and PARAMETRIX, INC, ("Contractor").
RECITALS
A. Whereas Master Consultant Services Agreement is hereby renamed Service Level Agreement;
and
B. The City and Contractor (as may be identified as "Consultant" in the original Agreement) have
entered into a Service Level Agreement ("Agreement") dated November 3, 2023 under which
Contractor has agreed to perform certain contract services for the City; and
C. Pursuant to the terms of the Agreement, the City wishes Contractor to perform certain tasks as set
forth in this Task Order, which constitute the Work;
NOW, THEREFORE, City and Contractor agree as follows:
AGREEMENT
1. Scope of services. Contractor shall provide any and all of the services set forth in Exhibit A of
this Task Order, for an amount not to exceed the Task Order Amount, identified above, as directed by the
City.
Jimmy Jessup shall be the Project Manager for Contractor for this Task Order. Additional contract
services may be performed by other Contractor staff with prior notice and approval by City.
a. City's duties. The City will:
(1) Determine the scope of services, as set forth in Exhibit A.
(2) Make available work plans and specifications and other City data related to the project,
including full information as to the City's requirements.
(3) Designate April Miller, or their designee as the person at the City responsible for
monitoring performance under this Task Order.
b. Contractor duties. The Contractor will:
(1) Provide and perform tasks identified in Exhibit A, Scope of Services.
(2) Provide miscellaneous services related to the Work and not stipulated elsewhere in this
Task Order, when requested by the City in writing. A Task Order Amendment is
Rev. March 2024
City of San Rafael Service Level Agreement
Task Order
required if these additional services cannot be performed within the Task Order budget.
2. Date of completion; Work hours estimate, Cost estimate and budget, Fee schedule: Costs are not -
to -exceed stated Task Order Amount in this Task Order. See Exhibit A for Work and fee schedule details.
Authorization to proceed.
The City will give Contractor authorization to proceed with the work specified in this Task Order only after
Contractor submits updated insurance certificates and endorsements, in accordance with the Agreement.
Service Level Agreement terms: Conflicts.
Except as expressly otherwise provided herein, all terms of the Agreement shall apply to Contractor in the
performance of work pursuant to this Task Order. If there is a conflict between this Task Order and the
Agreement, this Task Order shall control.
5. Amendment of Task Order: Conflicts.
Except as provided in Section 1(b)(2) above, this Task Order may not be modified except by an Amended
Task Order executed and approved in the same manner as the Task Order.
6. Signatures. The parties have executed this Task Order, as of the date first written above.
Rev March 2024
City of San Rafael Service Level Agreement
Task Order
CITY OF SAN RAFAEL CONTRACTOR
By: 7151ineni( i_-='cr By: A CC
Cristine Alilovich, City Manager
Name: Nathan Johnson
Title: Senior Vice President
Reviewed By
By: ?�-- '�A (if Contractor is a corporation, add signature
Genevieve Coyle, Assistant City Attorney of second corporate officer)
Exhibits:
A
Rev March 2024
Scope of work
LIZA
Name: David Pennington
Title: Vice President
Exhibit A
April Miller
From: Jimmy Jessup <JJessup@parametrix.com>
Sent: Monday, April 1, 2024 10:30 AM
To: April Miller
Cc: David Parisi
Subject: Project Development and Plan Review Support task order
Hi April,
Pursuant to your request, Parametrix proposes creating a Project Development and Plan Review Support task order
under our on -call agreement to provide near -term services as identified by the City of San Rafael. Our services under this
task order may include review and comment on transportation impact studies, transportation operation studies, or
other reports submitted as part of project development applications, civil, striping, and signal engineering design plan
set review of transportation projects, providing input to City staff on transportation engineering matters, and
responding to other requests.
The term for this task order will be the same as that for the master consultant services agreement, and the budget for
these services will not exceed $30,000 without prior written approval by the City. Services will be charged at applicable
hourly rates, and invoices will be sent on a monthly basis.
Please do advise on your agreement with this proposal, and we look forward to serving the City on these important
matters!
Best regards,
Paramotri
Jimmy Jessup
he/him
Engineer III
510.343.6512 1 direct
U E ® d
Parametrix
800 BANCROFT WAY, SUITE 203 1 BERKELEY, CA 94710 I P 510.343.6400
HOURLY SERVICE RATES FOR PROFESSIONAL SERVICES
January 1, 2024 — December 31, 2024
Principal Consultant $300.00 - $360.00
Sr Consultant
$205.00
— $255.00
Engineer IV
$165.00
- $205.00
Engineer III
$130.00
- $165.00
Planner III
$130.00
- $165.00
Sr Graphic Designer
$130.00
- $165.00
Sr Project Accountant
$130.00
- $165.00
Sr Project Controls Specialist
$130.00
- $165.00
Engineer 1
$105.00
- $135.00
Planner II
$105.00
- $135.00
Notes:
Hourly service rates are effective through December 31, 2024
Reimbursable charges include, but are not limited to, transportation charges, reproduction
services, shipping expenses and subconsultant fees. Mileage charges will be charged at
the prevailing IRS rate per mile.
Monthly invoices are due withing 30 days from the date of the invoice.
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Shannon Mackie (for April Miller) Extension: 3353
Contractor Name: Parametrix, Inc
Contractor's Contact: Jimmy Jessup Contact's Email: jjessup@parametrix.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
Project Manager
DATE
Check/Initial
1
a. Email PINS Introductory Notice to Contractor
Click here to
❑
enter a date.
b. Email contract (in Word) and attachments to City
4/8/2024
Attorney c/o Laraine.Gittens@cityofsanrafael.org
®SM
2
City Attorney
a. Review, revise, and comment on draft agreement
4/9/2024
and return to Project Manager
4/9/2024
® NT
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
© NT
3
Department Director
Approval of final agreement form to send to
4/9/2024
❑X AM
contractor
Forward three (3) originals of final agreement to
4
Project Manager
Click here to
❑
contractor for their signature
enter a date.
5
Project Manager
When necessary, contractor -signed agreement
❑ N/A
agendized for City Council approval *
*City Council approval required for Professional Services
❑
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
Click here to
PRINT
Date of City Council approval
CONTINUE ROUTING PROCESS WITH HARD COPY
enter a date.
6
Project Manager
Forward signed original agreements to City
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
agreement
8
City Attorney
Review and approve insurance in PINS , and bonds
City Manager / Mayor
(for Public Works Contracts)
Agreement executed by City Council authorized
9
10
City Clerk
_official
Attest signatures, retains original agreement and
forwards copies to Project Manager
TO 113 - Project Development and Plan Review
Final Audit Report
Created: 2024-04-09
By: Shannon Mackle (shannon.mackle@cityofsanrafael.org)
Status: Signed
Transaction ID: CBJCHBCAABAAC_OYCDzhaXRsWjURkJB-gukFzRN-Isg3
2024-04-16
"TO 113 - Project Development and Plan Review" History
Document created by Shannon Mackie (shannon.mackle@cityofsanrafael.org)
2024-04-09 - 7:17:05 PM GMT
E-4' Document emailed to Nathan Johnson (njohnson@parametrix.com) for signature
2024-04-09 - 7:17:14 PM GMT
ZL Document shared with Jonathan Schellin (jonathans@cityofsanrafael.org) by Shannon Mackie
(shannon.mackle@cityofsanrafael.org)
2024-04-09 - 7:18:05 PM GMT
Email viewed by Nathan Johnson (njohnson@parametrix.com)
2024-04-11-12:05:36 PM GMT
iSo Document e-signed by Nathan Johnson (njohnson@parametrix.com)
Signature Date: 2024-04-11-12:07:24 PM GMT - Time Source: server
2+ Document emailed to David Pennington (dpennington@parametrix.com) for signature
2024-04-11 - 12:07:25 PM GMT
Email viewed by David Pennington (dpennington@parametrix.com)
2024-04-11 - 2:11:34 PM GMT
A) Document e-signed by David Pennington (dpennington@parametrix.com)
Signature Date: 2024-04-11 - 2:11:58 PM GMT - Time Source: server
E-► Document emailed to Laraine Gittens (laraine.gittens@cityofsanrafael.org) for approval
2024-04-11 - 2:11:59 PM GMT
Email viewed by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2024-04-11 - 4:03:59 PM GMT
6© Document approved by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
Approval Date: 2024-04-11 - 4:06:34 PM GMT - Time Source: server
Q Adobe Acrobat Sign
El' Document emailed to Genevieve Coyle (genevieve.coyle@cityofsanrafael.org) for signature
2024-04-11 - 4:06:36 PM GMT
Email viewed by Genevieve Coyle (genevieve.coyle@cityofsanrafael.org)
2024-04-15 - 5:39:29 PM GMT
6© Document e-signed by Genevieve Coyle (genevieve.coyle@cityofsanrafael.org)
Signature Date: 2024-04-15 - 5:40:07 PM GMT - Time Source: server
17"'* Document emailed to city.clerk@cityofsanrafael.org for approval
2024-04-15 - 5:40:09 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2024-04-15 - 5:46:31 PM GMT
6© Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi
2024-04-15 - 5:46:41 PM GMT
&0 Document approved by Brenna Nurmi(city.clerk@cityofsanrafael.org)
Approval Date: 2024-04-15 - 5:46:43 PM GMT - Time Source: server
C'y Document emailed to Cristine Alilovich (cristine.alilovich@cityofsanrafael.org) for signature
2024-04-15 - 5:46:45 PM GMT
'n Email viewed by Cristine Alilovich (cristine.alilovich@cityofsanrafael.org)
2024-04-16 - 6:26:23 PM GMT
6© Document e-signed by Cristine Alilovich (cristine.alilovich@cityofsanrafael.org)
Signature Date: 2024-04-16 - 6:27:19 PM GMT - Time Source: server
0 Agreement completed.
2024-04-16 - 6:27:19 PM GMT
Q Adobe Acrobat Sign