HomeMy WebLinkAboutPW Landscape Architectural and Engineering Design Services; Second AmendmentSECOND AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT WITH
DAVID L. GATES & ASSOCIATES, INC. FOR LANDSCAPE ARCHITECTURAL AND
ENGINEERING DESIGN SERVICES
THIS SECOND AMENDMENT to the Professional Services Agreement by and
between the CITY OF SAN RAFAEL (hereinafter "CITY"), and DAVID L. GATES &
ASSOCIATES, INC. (hereinafter "CONSULTANT"), is made and entered into as of
Jul 17, 2024
RECITALS
WHEREAS, the CITY and CONSULTANT entered into a Professional Services
Agreement dated December 1, 2022 to perform professional services in connection with CITY'S
Landscape Architectural and Engineering Design Services, for an amount not to exceed
$498,734 (the "Agreement"); and
WHEREAS, the CITY and CONSULTANT entered into a First Amendment to the
Professional Services Agreement dated April 23, 2024, to perform additional professional
services in connection with CITY's Landscape Architectural and Engineering Design Services,
for an amount not to exceed $47,600 and increasing the total not to exceed amount under the
Agreement to $546,334; and
WHEREAS, under the terms of the Agreement, the Term of the Agreement was
to expire on December 1, 2023; however CITY and CONSULTANT agreed informally that the
Term of the Agreement would be extended, and now wish to ratify and memorialize that
extension; and
WHEREAS, CITY requires additional professional services from the CONSULTANT,
and the CONSULTANT is willing to provide such services.
AMENDMENT TO AGREEMENT
NOW, THEREFORE, the parties hereby agree to amend the Agreement as follows:
1. Article I of the Agreement, entitled "SERVICES TO BE PROVIDED" is hereby
amended to include the additional services set forth in CONSULTANT's proposal
dated June 19, 2024, attached to this Second Amendment as Exhibit A and
incorporated herein by reference.
2. Article II of the Agreement, entitled "COMPENSATION" is hereby amended to
include additional compensation payable to CONSULTANT for the services
described in Exhibit A to this Second Amendment, on a fixed fee basis in
accordance with the Exhibit A, in a not -to -exceed amount of $19,450 and to change
the total not -to -exceed amount under the Agreement to $565,784.
3. Article III of the Agreement, entitled "TERM OF AGREEMENT" is hereby
amended, effective as of December 1, 2023, to extend the Agreement term through
March 31, 2026.
4. Except as specifically amended herein, all of the other provisions, terms and
obligations of the Agreement between the parties shall remain valid and shall be in
full force.
IN WITNESS WHEREOF, the parties have executed this Second Amendment on the
day, month, and year first above written.
CITY OF SAN RAFAEL
6�� A"4VIao,(
Cristine Alitovich (Jul 17, 202412:46 PDT)
CRISTINE ALILOVICH, City Manager
ATTEST:
Brenna Nurmi (for) (Jul 17, 2024 12:58 PDT)
CONSULTANT
BY: CaSeV CaS±Jul 11. 202-111 30 PDT
Name: Casey Case
President
[If Contractor is a corporation, add signature of
second corporate officer]
LINDSAY LARA, City Clerk
fig
APPROVED AS TO FORM: Name:
Title:
RirGerF �. EbsFeuL
Robot F EPSIMn (Jul :6. 202A 21:46PDT
ROBERT F. EPSTEIN, City Attorney
0)
Exhibit A
GATES
+ASSOCIATES
Project Number
Date:
Project Title
To:
Company:
SCOPE OF WORK:
LANDSCAPE ARCHITECTURE LAND PLANNING URBAN DESIGN
ADDITIONAL WORK AUTHORIZATION #02
P6114
June 19, 2024
Pickleweed Park Enhancements
Theo Sanchez
City of San Rafael
Associate Civil Engineer
Department of Public Works
The purpose of this Additional Work Authorization (AWA) is authorizing the following additional services
for BKF and Miller Pacific related to construction Administration Services:
BKF: $16,450
Construction Administration:
Support the Design Team and Contractor during the construction phase of the project. Anticipated
services include:
- Reviewing submittal information for conformance with the Civil drawings.
- Responding to questions which arise during construction (RFIs).
- Periodically attending construction meetings.
- Periodically performing site observation and evaluating construction for conformance with the Civil
drawings.
- Preparing As -Built drawings.
- Assisting with the development of a punch list at closeout.
If the amount of time we're recommending is depleted while providing professional services requested
of us, then GATES will notify the City of San Rafael and recommend the monetary allocation be increased
proportional to the services we are being asked to provide. At this time, we anticipate this will be
sufficient to provide the services being requested of BKF, but if needed and requested, BKF can provide
additional services on a Time and Materials Basis.
Miller Pacific: $3,000
Phase 3 (Construction Administration Support)
- Review and respond to requires for information
- Submittal reviews
- Modifying any recommendations, as needed, based on the encountered conditions on site.
- Respond to questions during bid phase
1655 N. MAIN STREET STE 365 1 WALNUT CREEK, CALIFORNIA 94596 1 T 925.736.8176 1 WWW. DGATES.COM
GATES
+ASSOCIATES LANDSCAPE ARCHITECTURE LAND PLANNING URBAN DESIGN
FEES FOR WORK:
FixedRate: ......................... .................................................................................................... .... $19,450
Please return one signed copy of this work authorization to Gates + Associates as soon as possible. If you
have questions or comments regarding this matter, please contact us at your earliest convenience
ISSUED: AUTHORIZATION CONFIRMED.
BY: .... DATE: 2024-W19BY:.................................................. DATE:.....................
MELON REyrioLu.,, .TE PRINCIPAL
1655 N. MAIN STREET STE 365 1 WALNUT CREEK, CALIFORNIA 94596 1 T 925.736.8176 1 WWW. DGATES.COM
2nd Amendment - Gates - Pickleweed Park
Enhancements
Final Audit Report 2024-07-11
Created: 2024-07-11
By: Shannon Mackie (shannon.mackle@cityofsanrafael.org)
Status: Signed
Transaction ID: CBJCHBCAABAAsIZYw5g2LbTTtiuxWXy6PoXo5AgnipZ8
"2nd Amendment - Gates - Pickleweed Park Enhancements" His
tory
Document created by Shannon Mackie (shannon.mackle@cityofsanrafael.org)
2024-07-11 - 4:07:42 PM GMT- IP address: 199.88.89.34
E'► Document emailed to Casey Case (casey@dgates.com) for signature
2024-07-11 - 4:08:30 PM GMT
L� Email viewed by Casey Case (casey@dgates.com)
2024-07-11 - 6:30:26 PM GMT- IP address: 104.47.73.254
6a Document e-signed by Casey Case (casey@dgates.com)
Signature Date: 2024-07-11 - 6:30:37 PM GMT - Time Source: server- IP address: 64.21.203.66
® Agreement completed.
2024-07-11 - 6:30:37 PM GMT
'• SAN RAFAEL Adol e'Y
I Acrobat Sign
RAF,q�!
i
F
TYwITH P�
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Shannon Mackie (for Theo Sanchez) Extension: 3353
Contractor Name: Gates & Associates
Contractor's Contact: Melonie Reynolds Contact's Email: melonie@dgates.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor
Click here to
❑
enter a date.
b. Email contract (in Word) and attachments to City
7/2/2024
Attorney c/o Laraine.Gittens@cityofsanrafael.org
❑X SM
2
City Attorney
a. Review, revise, and comment on draft agreement
7/10/2024
and return to Project Manager
7/10/2024
© NT
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
© NT
3
Department Director
Approval of final agreement form to send to
7/11/2024
® SM
contractor
4
Project Manager
Forward three (3) originals of final agreement to
7/11/2024
❑x
contractor for their signature
5
Project Manager
When necessary, contractor -signed agreement
❑ N/A
agendized for City Council approval *
*City Council approval required for Professional Services
_x1
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
7/15/2024
Date of City Council approval
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
7/16/24
SM
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
agreement
8
City Attorney
Review and approve insurance in PINS, and bonds
(for Public Works Contracts)
9
City Manager / Mayor Agreement executed by City Council authorized
official
City Clerk Attest signatures, retains original agreement and
10
forwards copies to Project Manager
2nd Amendment - Gates & Associates -
Pickleweed Park Enhancements
Final Audit Report 2024-07-17
Created: 2024-07-16
By: Nataly Torres (nataly.torres@cityofsanrafael.org)
Status: Signed
Transaction ID: CBJCHBCAABAAZGda MT4aOPEWKGmciUf97185LJwMvGo
rr2nd Amendment - Gates & Associates - Pickleweed Park Enha
ncements" History
Document created by Nataly Torres (nataly.torres@cityofsanrafael.org)
2024-07-16 - 8:14:07 PM GMT- IP address: 199.88.113.8
L-4 Document emailed to Laraine Gittens (laraine.gittens@cityofsanrafael.org) for approval
2024-07-16 - 8:16:20 PM GMT
1L Document shared with Shannon Mackle(shannon.mackle@cityofsanrafael.org) by Nataly Torres
(n ata I y. to rres @ cityofsa n rafa e I . o rg )
2024-07-16 - 8:16:58 PM GMT- IP address: 199.88.113.8
Email viewed by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2024-07-16 - 9:03:00 PM GMT- IP address: 104.47.65.254
do Document approved by Laraine Gittens(laraine.gttens@cityofsanrafael.org)
Approval Date: 2024-07-16 - 9:06:27 PM GMT - Time Source: server- IP address: 199.88.113.8
E'-. Document emailed to rob.epstein@cityofsanrafael.org for signature
2024-07-16 - 9:06:30 PM GMT
Email viewed by rob.epstein@cityofsanrafael.org
2024-07-17 - 4:46:05 AM GMT- IP address: 104.28.123.163
&0 Signer rob.epstein@cityofsanrafael.org entered name at signing as Robert F. Epstein
2024-07-17 - 4:46:26 AM GMT- IP address: 104.28.123.163
4e Document e-signed by Robert F. Epstein (rob.epstein@cityofsanrafael.org)
Signature Date: 2024-07-17 - 4:46:28 AM GMT - Time Source: server- IP address: 104.28.123.163
SAN RAFAEL I by
Adobe
TW :!ry v. in a r.ni« n•r Acrobat Sign
P' + Document emailed to city.clerk@cityofsanrafael.org for approval
2024-07-17 - 4:46:30 AM GMT
Email viewed by city.clerk@cityofsanrafael.org
2024-07-17 - 4:58:43 PM GMT- IP address: 104.47.65.254
60 Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi
2024-07-17 - 4:58:51 PM GMT- IP address: 199.88.113.8
60 Document approved by Brenna Nurmi (city.clerk@cityofsanrafael.org)
Approval Date: 2024-07-17 - 4:58:53 PM GMT - Time Source: server- IP address: 199.88.113.8
El Document emailed to cristine.alilovich@cityofsanrafael.org for signature
2024-07-17-4:58:55 PM GMT
Email viewed by cristine.alilovich@cityofsanrafael.org
2024-07-17 - 7:45:33 PM GMT- IP address: 104.47.64.254
60 Signer cristine.alilovich@cityofsanrafael.org entered name at signing as Cristine Alilovich
2024-07-17 - 7:46:03 PM GMT- IP address: 199.88.113.8
60 Document e-signed by Cristine Alilovich (cristine.alilovich@cityofsanrafael.org)
Signature Date: 2024-07-17 - 7:46:05 PM GMT - Time Source: server- IP address: 199.88.113.8
C'-► Document emailed to city. clerk@cityofsanrafael.org for signature
2024-07-17 - 7:46:06 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2024-07-17 - 7:58:14 PM GMT- IP address: 104.47.65.254
60 Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi (for)
2024-07-17 - 7:58:27 PM GMT- IP address: 199.88.113.8
de Document e-signed by Brenna Nurmi (for)(city.clerk@cityofsanrafael.org)
Signature Date: 2024-07-17 - 7:58:29 PM GMT - Time Source: server- IP address: 199.88.113.8
Agreement completed.
2024-07-17 - 7:58:29 PM GMT
SAN RAFAEL Adobe
I Acrobat Sign