HomeMy WebLinkAboutPW Service Level Agreement; Task Order No. 133; Boyd Park Play Area DesignCity of San Rafael
SERVICE LEVEL AGREEMENT
DATED JULY 8, 2024
WITH DAVID L. GATES & ASSOCIATES, INC.
TASK ORDER NO. 133
Subject title: Boyd Park Play Area Design
Task Order Amount: $5,000
THIS TASK ORDER is entered into on Sep 24, 2024
between the City of San Rafael,
a municipal corporation ("City"), and David L. Gates & Associates, Inc., ("Contractor").
RECITALS
A. The City and Contractor (as may be identified as "Consultant" in the original Agreement) have
entered into a Service Level Agreement ("Agreement") dated July 8, 2024 under which
Contractor has agreed to perform certain contract services for the City; and
B. Pursuant to the terms of the Agreement, the City wishes Contractor to perform certain tasks as set
forth in this Task Order, which constitute the Work;
NOW, THEREFORE, City and Contractor agree as follows:
AGREEMENT
1. Scope of services. Contractor shall provide any and all of the services set forth in Exhibit A of
this Task Order, for an amount not to exceed the Task Order Amount, identified above, as directed by the
City.
Melonie Reynolds shall be the Project Manager for Contractor for this Task Order. Additional contract
services may be performed by other Contractor staff with prior notice and approval by City.
a. City's duties. The City will:
(1) Determine the scope of services, as set forth in Exhibit A.
(2) Make available work plans and specifications and other City data related to the project,
including full information as to the City's requirements.
(3) Designate Craig Veramay, or their designee as the person at the City responsible for
monitoring performance under this Task Order.
b.Contractor duties. The Contractor will:
(1) Provide and perform tasks identified in Exhibit A, Scope of Services.
(2) Provide miscellaneous services related to the Work and not stipulated elsewhere in this
Task Order, when requested by the City in writing. A Task Order Amendment is
required if these additional services cannot be performed within the Task Order budget.
2. Date of completion. Work hours estimate; Cost estimate and budget; Fee schedule: Costs are not -
Rev. March 2024
City of San Rafael Service Level Agreement
Task Order
to -exceed stated Task Order Amount in this Task Order. See Exhibit A for Work and fee schedule details.
Authorization to proceed.
The City will give Contractor authorization to proceed with the work specified in this Task Order only after
Contractor submits updated insurance certificates and endorsements, in accordance with the Agreement.
Service Level Agreement terms; Conflicts.
Except as expressly otherwise provided herein, all terms of the Agreement shall apply to Contractor in the
performance of work pursuant to this Task Order. If there is a conflict between this Task Order and the
Agreement, this Task Order shall control.
Amendment of Task Order; Conflicts.
Except as provided in Section 1(b)(2) above, this Task Order may not be modified except by an Amended
Task Order executed and approved in the same manner as the Task Order.
6. Signatures. The parties have executed this Task Order, as of the date first written above.
Rev. March 2024
City of San Rafael Service Level Ao eement
Task Order
CITY OF SSAN RAFAEL
By: -ItW-C�
April Miller, Public Works Director
Reviewed By
Rd-6e'�t P
By: Robert F, Epstein !Sep 23, 2024 19:07 PDT?
Robert F. Epstein, City Attorney
Exhibits:
A Scope of work
Rev. March 2024
CONTRACTOR
By: ca=R9� 11 ,202a1ia5ae-i
Name: Casey Case
Title: President
(if Contractor is a corporation, add signature
of second corporate officer)
By:
Name:
Title:
GATES
+ASSOCIATES LANDSCAPE ARCHITECTURE LAND PLANNING URBAN DESIGN
WORK AUTHORIZATION
Date: August 15, 2024
Project Title: Boyd Park —Play Area
To: Craig Veramay
Company: City of San Rafael
Craig.veramay@cityofsanrafael.org
SCOPE OF WORK:
Work with Ross Recreation to select play structure replacement for Boyd Park.
FEES FOR WORK:
T&M Not to Exceed $5,000
Please return one signed copy of this work authorization to Gates + Associates as soon as possible. If
you have questions or comments regarding this matter, please contact us at your earliest convenience.
ISSUED:
AUTHORIZATION CONFIRMED:
BY:......... ................. DATE:. zoza:o8-�s.. BY:.................................................. DATE:.....................
_ ONIE R NOLDS, ASSOCIATED PRINCIPAL
1655 N. MAIN STREET STE 365 1 WALNUT CREEK, CALIFORNIA 94596 1 T 925.736.8176 1 WWW. DGATES.COM
1. HOURLY FEES
HOURLY FEES FOR SERVICES OF:
Partner
Principal
Associate Principal
Senior Associate
Job Captain
Sr. Irrigation Designer
Community Outreach Facilitator
Marketing Coordinator
Administrative/Drafter
e EXPENSES (REIM S L E
RATE SCHEDULE
z- --EMBE
RATE PER HOUR:
$235.00 - $250.00
$220.00 - $235.00
$205.00 - $220.00
$185.00 - $205.00
$165.00 - $185.00
$200.00 - $210.00
$185.00 - $210.00
$135.00 - $185.00
$135.00 - $155.00
A. Consultants at approximately the same rates indicated above or on consultant fee schedules.
B. Other direct expenses at cost which may include:
1. Printing and reproduction costs.
2. Mileage and travel costs.
3. Miscellaneous
Hourly rates may be adjusted annually and shall apply for any services rendered after that date.
These adjustments are not limited to the rate per hour ranges listed above, and will not affect the
total amount of compensation for services.
GATES
ASSOCIATES
RAP
5 2
�O
WtTH P'�y
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
Step
RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor
Click ,ere to
❑
enter a date.
b. Email contract (in Word) and attachments to City
8/29/2024
Attorney c/o Laraine.Gittens@cityofsanrafael.org
❑X SM
2
City Attorney
a. Review, revise, and comment on draft agreement
9/10/2024
and return to Project Manager
9/10/2024
❑X NT
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
❑X NT
3
Department Director
Approval of final agreement form to send to
9/11/2024
❑x AM
contractor
4
Project Manager
Forward three (3) originals of final agreement to
9/12/2024
contractor for their signature
5
Project Manager
When necessary, contractor -signed agreement
❑X N/A
agendized for City Council approval *
*City Council approval required for Professional Services
❑
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
Click mere to
Date of City Council approval
ester a da`e.
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
9/12/24
SM
Attorney with printed copy of this routing form
7
City Attorney
Review and approve hard copy of signed
agreement
8
City Attorney
Review and approve insurance in PINS , and bonds
(for Public Works Contracts)
9
City Manager / Mayor
Agreement executed by City Council authorized
official
10
City Clerk
Attest signatures, retains original agreement and
forwards copies to Project Manager
TO 133 - Boyd Park Play
Final Audit Report
Area Design
2024-09-24
Created:
2024-09-23
By:
Shannon Mackie (shannon.mackle@cityofsanrafael.org)
Status:
Signed
Transaction ID:
CBJCHBCAABAA_7wiW8hAWTifL6p2dSsYQscRNH5usvl
"TO 133 - Boyd Park Play Area Design" History
Document created by Shannon Mackie (shannon.mackle@cityofsanrafael.org)
2024-09-23 - 8:37:02 PM GMT- IP address: 199.88.89.34
Document emailed to Laraine Gittens (laraine.gittens@cityofsanrafael.org) for approval
2024-09-23 - 8:37:51 PM GMT
Document shared with Jonathan Schellin Qonathans@cityofsanrafael.org) by Shannon Mackie
(shannon.mackle@cityofsanrafael.org)
2024-09-23 - 8:55:41 PM GMT- IP address: 199.88.89.34
Document shared with Nataly Torres(nataly.torres@cityofsanrafael.org) by Shannon Mackie
(shannon.mackle@cityofsanrafael.org)
2024-09-23 - 8:55:41 PM GMT- IP address: 199.88.89.34
Email viewed by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2024-09-23 - 9:07:20 PM GMT- IP address: 104.47.64.254
Jo Document approved by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
Approval Date: 2024-09-23 - 9:11:10 PM GMT - Time Source: server- IP address: 199.88.113.8
E-+ Document emailed to rob.epstein@cityofsanrafael.org for signature
2024-09-23 - 9:11:12 PM GMT
Email viewed by rob.epstein@cityofsanrafael.org
2024-09-24 - 2:07:33 AM GMT- IP address: 104.28.123.163
Signer rob.epstein@cityofsanrafael.org entered name at signing as Robert F. Epstein
2024-09-24 - 2:07:49 AM GMT- IP address: 104.28.123.163
""' Document e-signed by Robert F. Epstein (rob.epstein@cityofsanrafael.org)
Signature Date: 2024-09-24 - 2:07:51 AM GMT - Time Source: server- IP address: 104.28.123.163
Powered
. SAN RAFAEL i Adobesr
Acrobat Sign
Document emailed to city.clerk@cityofsanrafael.org for approval
2024-09-24 - 2:07:53 AM GMT
Email viewed by city.clerk@cityofsanrafael.org
2024-09-24 - 2:33:51 PM GMT- IP address: 104.47.64.254
Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi
2024-09-24 - 2:34:00 PM GMT- IP address: 199.88.113.8
Document approved by Brenna Nurmi (city.clerk@cityofsanrafael.org)
Approval Date: 2024-09-24 - 2:34:02 PM GMT - Time Source: server- IP address: 199.88.113.8
Document emailed to APRIL MILLER (april.miller@cityofsanrafael.org) for signature
2024-09-24 - 2:34:05 PM GMT
Email viewed by APRIL MILLER (april.miller@cityofsanrafael.org)
2024-09-24 - 3:25:47 PM GMT- IP address: 104.47.65.254
t�'o Document e-signed by APRIL MILLER (april.miller@cityofsanrafael.org)
Signature Date: 2024-09-24 - 3:26:13 PM GMT - Time Source: server- IP address: 199.88.89.34
Agreement completed.
2024-09-24 - 3:26:13 PM GMT
P
l � AN RAPA,EL Adobe
Powered MJ
S' ,Adobe
Acrobat Sign