HomeMy WebLinkAboutPW Service Level Agreement; Task Order No. 140; Construction Inspection Services for Francisco Blvd East Mid-Block Crossing ProjectCity of San Rafael
SERVICE LEVEL AGREEMENT
DATED JULY 8, 2024
WITH PARK ENGINEERING, INC.
TASK ORDER NO. 140
Subject title: Construction Inspection Services for Francisco Blvd East Mid -Block Crossing Project
Task Order Amount: $39,314.90
THIS TASK ORDER is entered into on Dec 13, 2024 between the City of San Rafael,
a municipal corporation ("City"), and Park Engineering, Inc., ("Contractor").
RECITALS
A. The City and Contractor (as may be identified as "Consultant" in the original Agreement) have
entered into a Service Level Agreement ("Agreement") dated July 8, 2024 under which
Contractor has agreed to perform certain contract services for the City; and
B. Pursuant to the terms of the Agreement, the City wishes Contractor to perform certain tasks as set
forth in this Task Order, which constitute the Work;
NOW, THEREFORE, City and Contractor agree as follows:
AGREEMENT
1. Scope of services. Contractor shall provide any and all of the services set forth in Exhibit A of
this Task Order, for an amount not to exceed the Task Order Amount, identified above, as directed by the
City.
Steve Patterson shall be the Project Manager for Contractor for this Task Order. Additional contract
services may be performed by other Contractor staff with prior notice and approval by City.
a. City's duties. The City will:
(1) Determine the scope of services, as set forth in Exhibit A.
(2) Make available work plans and specifications and other City data related to the project,
including full information as to the City's requirements.
(3) Designate Mariana Sanchez, or their designee as the person at the City responsible for
monitoring performance under this Task Order.
b. Contractor duties. The Contractor will:
(1) Provide and perform tasks identified in Exhibit A, Scope of Services.
(2) Provide miscellaneous services related to the Work and not stipulated elsewhere in this
Task Order, when requested by the City in writing. A Task Order Amendment is
required if these additional services cannot be performed within the Task Order budget.
2. Date of completion. Work hours estimate; Cost estimate and budget: Fee schedule: Costs are not -
Rev. March 2024
City of San Rafael Service Level Agreement
Task Order
to -exceed stated Task Order Amount in this Task Order. See Exhibit A for Work and fee schedule details.
3. Authorization to proceed.
The City will give Contractor authorization to proceed with the work specified in this Task Order only after
Contractor submits updated insurance certificates and endorsements, in accordance with the Agreement.
4. Service Level Agreement terms: Conflicts.
Except as expressly otherwise provided herein, all terms of the Agreement shall apply to Contractor in the
performance of work pursuant to this Task Order. If there is a conflict between this Task Order and the
Agreement, this Task Order shall control.
Amendment of Task Order: Conflicts.
Except as provided in Section 1(b)(2) above, this Task Order may not be modified except by an Amended
Task Order executed and approved in the same manner as the Task Order.
6. Siti1iiauires. The parties have executed this Task Order, as of the date first written above.
2
Rev March 2024
City of San Rafael Service Level Agreement
Task Order
CITY OF SAN RAFAEL
By: Cristine Alilovich (Dec 13, 202412:56 PST)
Cristine Alilovich, City Manager
Reviewed By
Robert P EDsl2tii�
By: Robert F. Epstein (Dec 1 , 202411:46 PST)
Robert F. Epstein, City Attorney
Exhibits:
A Scope of work
3
Rev. March 2024
CONTRACTOR
5, /�atto�ae.y
By:
Name: Steve Patterson
Title: Vice President
(if Contractor is a corporation, add signature
of second corporate officer)
By:
Name: Jaemin Park
Title: President/CEO/CFO
Exhibit A
City of San Rafael
Canal Alliance Crossing Project
City Project No. 11451 / City File No. 16.01.315
1. Rate includes vehicle, mobile phone, laptop and all equipment required to perform required duties.
2. Based on part-time inspection services for 40 working days.
Rates
Hours
Total
Total
Regular
Loaded Rate
Overtime
Rate
Construction
Uose out
Regular
Hours
Overtime
Hours
Cost
Pat Giles
Construction Inspector
$ 166.56
$ 249.84
160
16
176
0
$ 29,314.90
Applied Materials & Engineering
Materials Testing
As -needed see attached Rate Schedule )
$ 10,000.00
Total =
$ 39,314.90
1. Rate includes vehicle, mobile phone, laptop and all equipment required to perform required duties.
2. Based on part-time inspection services for 40 working days.
A1111E
980 41st Street Tel: (510) 420-8190
Oakland, CA 94608 FAX: (510) 420-8186
e-mail: info@appmateng.com
2024 RATE SHEET -
Various Improvement Projects
MATERIAL TESTING FEES - QUALITY ASSURANCE
A. HOURLY AND UNIT COSTS & BASIS OF CHARGES
The estimated fees are based on the following State and Federally mandated prevailing hourly inspection
rates and unit tests costs. Rates will be adjusted in accordance with DIR prevailing wage adjustments;
certified payroll, if required, will be billed at higher rates.
INSPECTION RATES Per Hour
1 HMA Sampling, Group 3 $125.00
2 Compaction Testing, Group 3 $125.00
UNIT TEST COSTS
Per Set
1 Concrete Compression, per set of 5 (includes pick-up)
$450.00
2 Sieve Analysis, each
$240.00
3 Sand Equivalent, each
$125.00
4 Cleanness Value, each
$280.00
5 Moisture Content, each
$55.00
6 Durability Index, each
$280.00
7 LA Abrasion
$750.00
8 Concrete Aggregate Tests (2 Sieves, 1 Cleanness value, 2 moisture content, 1 sand eq.)
$995.00
9 HMA JMF Verification or Production Startup, each
$8,000.00
10 HMA Production Testing, each
$4,500.00
11 Moisture -Density Curve or Cal Impact Test, each
$650.00
12 Core Density, each
$120.00
13 CIR IDT
$800.00
OTHER COSTS
1 Project Management, per hour $195.00
2 Final Affidavit, each $400.00
BASIS OF CHARGES
Minimum charge per call -out, show -up: 4 Hours
Work from 4-8 hours: Actual Time
Travel to job site: Portal -to -Portal
Mileage to shop & jobsite: $0.75 per mile
Parking: To be provided
Work over 8 and up to 12 hours per day, or on Saturday, per hour Time & One Half
Work over 12 hours per day, or on Sundays and Holidays, per hour Double Time
RAP,q�`
fW-4
z
y0
/rY W 1 T H P of 5
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Shannon Mackie (for Mariana Sanchez) Extension: 3353
Contractor Name: Park Engineering, Inc
Contractor's Contact: Steve Patterson Contact's Email: spatterson@park-eng.com
❑ FPPC: Check if Contractor/Consultant must file Form 700
Step
RESPONSIBLE
DESCRIPTION
COMPLETED
REVIEWER
DEPARTMENT
DATE
Check/Initial
1
Project Manager
a. Email PINS Introductory Notice to Contractor
Click here to
L7 -
enter
enter a date.
b. Email contract (in Word) and attachments to City
12/2/2024
City Attorney
Attorney c/o Laraine.Gittens@cityofsanrafael.org
12/4/2024
❑X SM
2
a. Review, revise, and comment on draft agreement
and return to Project Manager
12/4/2024
© NT
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
12/6/2024
® NT
3
Department Director
Approval of final agreement form to send to
© AM
contractor
12/6/2024
4
Project Manager
Forward three (3) originals of final agreement to
contractor for their signature
❑X N/A
5
Project Manager
When necessary, contractor -signed agreement
agendized for City Council approval *
*City Council approval required for Professional Services
❑
Agreements and purchases of goods and services that exceed
Or
$75,000; and for Public Works Contracts that exceed $175,000
Click here to
Date of City Council approval
enter a date.
PRINT
CONTINUE ROUTING PROCESS WITH HARD COPY
6
Project Manager
Forward signed original agreements to City
Attorney with printed copy of this routing form
Review and approve hard copy of signed
7
City Attorney
City Attorney
agreement
8
Review and approve insurance in PINS , and bonds
(for Public Works Contracts)
9
City Manager/ Mayor
Agreement executed by City Council authorized
official
10
City Clerk
Attest signatures, retains original agreement and
forwards copies to Project Manager
TO 140 - Inspection Services for Francisco Mid -
Block Crossing
Final Audit Report 2024-12-13
Created:
2024-12-06
By:
Shannon Mackle (Shannon.mackle@cityofsanrafael.org)
Status:
Signed
Transaction ID:
CBJCHBCAABAAjTxjYQOiS3Ph2nZZwlrX9712Jc2IXu00
"TO 140 - Inspection Services for Francisco Mid -Block Crossing"
History
Document created by Shannon Mackie(shannon.mackle@cityofsanrafael.org)
2024-12-06 - 11:04:26 PM GMT- IP address: 199.88.113.8
El Document emailed to Steve Patterson (spatterson@park-eng.com) for signature
2024-12-06 - 11:06:56 PM GMT
Email viewed by Steve Patterson (spatterson@park-eng.com)
2024-12-07 - 6:13:10 AM GMT- IP address: 172.225.89.33
Email viewed by Steve Patterson (spatterson@park-eng.com)
2024-12-12 - 5:48:31 PM GMT- IP address: 24.130.112.205
d© Document e -signed by Steve Patterson (spatterson@park-eng.com)
Signature Date: 2024-12-12 - 8:43:21 PM GMT - Time Source: server- IP address: 24.130.112.205
E'y Document emailed to Jaemin Park Qpark@park-eng.com) for signature
2024-12-12 - 8:43:24 PM GMT
Email viewed by Jaemin Park Qpark@park-eng.com)
2024-12-12 - 8:48:18 PM GMT- IP address: 24.130.112.205
6© Document e -signed by Jaemin Park Upark@park-eng.com)
Signature Date: 2024-12-12 - 8:49:12 PM GMT - Time Source: server- IP address: 24.130.112.205
L-► Document emailed to Laraine Gittens (laraine.gittens@cityofsanrafael.org) for approval
2024-12-12 - 8:49:14 PM GMT
Email viewed by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
2024-12-12 - 11:05:43 PM GMT- IP address: 104.47.64.254
SAN RAFAEL P__0dby
I Adobe
Acrobat Sign
6© Document approved by Laraine Gittens (laraine.gittens@cityofsanrafael.org)
Approval Date: 2024-12-12 -11:08:37 PM GMT -Time Source: server- IP address: 199.88.113.8
C'y Document emailed to rob.epstein@cityofsanrafael.org for signature
2024-12-12 - 11:08:40 PM GMT
Email viewed by rob.epstein@cityofsanrafael.org
2024-12-13 - 7:45:36 PM GMT- IP address: 73.15.82.184
d© Signer rob.epstein@cityofsanrafael.org entered name at signing as Robert F. Epstein
2024-12-13 - 7:46:02 PM GMT- IP address: 73.15.82.184
6© Document e -signed by Robert F. Epstein(rob.epstein@cityofsanrafael.org)
Signature Date: 2024-12-13 - 7:46:04 PM GMT - Time Source: server- IP address: 73.15.82.184
Document emailed to city.clerk@cityofsanrafael.org for approval
2024-12-13 - 7:46:06 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2024-12-13 - 8:07:34 PM GMT- IF address: 104.47.65.254
6o Signer city.clerk@cityofsanrafael.org entered name at signing as Brenna Nurmi
2024-12-13 - 8:07:43 PM GMT- IP address: 199.88.113.8
&G Document approved by Brenna Nurmi (city.clerk@cityofsanrafael.org)
Approval Date: 2024-12-13 - 8:07:45 PM GMT - Time Source: server- IP address: 199.88.113.8
'y Document emailed to cristine.alilovich@cityofsanrafael.org for signature
2024-12-13 - 8:07:47 PM GMT
Email viewed by cristine.alilovich@cityofsanrafael.org
2024-12-13 - 8:53:41 PM GMT- IP address: 104.47.65.254
6m Signer cristine.alilovich@cityofsanrafael.org entered name at signing as Cristine Alilovich
2024-12-13 - 8:56:53 PM GMT- IF address: 199.88.113.8
b© Document e -signed by Cristine Alilovich (cristine.alilovich@cityofsanrafael.org)
Signature Date: 2024-12-13 - 8:56:55 PM GMT - Time Source: server- IP address: 199.88.113.8
Agreement completed.
2024-12-13 - 8:56:55 PM GMT
PowereSAN RAFAEL I Adobe
"'s'' Acrobat Sign