HomeMy WebLinkAboutCED Northgate Town Square Project PPTNorthgate Town Square
City Council Meeting
December 2, 2024
INTRODUCTIONS &
ACKNOWLEDGMENTS 2
•Full complement of staff and consultants have been part of the review and
response of this project
•City representatives from Police Department, Fire Department, Department of
Public Works, Community and Economic Development Department, City
Attorney's Office, City Manager's Office, Finance Department
•City’s consultant team, including Burke Williams & Sorenson (legal), M-Group
(planning), LSA (environmental), Parametrix (traffic), Seifel Consulting (fiscal)
•Merlone Geier's team and their consultants
PURPOSE OF MEETING 3
•Review project entitlements and associated project Environmental Impact Report
(EIR)
•Three staff recommendations for Council consideration:(add all staff
recommendations that need Council action)
•Adopt a Resolution certifying the Final Environmental Impact Report
•Introduction of an Ordinance to approve a Zoning Amendment and adopt Findings of
Fact, Statement of Overriding Considerations, Mitigation Monitoring and Reporting
Program
•Resolution approving Project Entitlements, including Vesting Tentative Subdivision
Map, Master Use Permit, Environmental and Design Review Permit, and Master Sign
Program
PROJECT EVOLUTION
•Project has been presented at many public
and community meetings
•Several rounds of modifications and revisions
since initial submittal in 2021
•Revised plans submitted in June 2024
represent final proposed project
•Final project was presented to
the Planning Commission hearing in October
2024
•Only change to the project since Planning
Commission hearing in October is revisions to
the Master Sign Program 4
2021 2022 2023 2024
OVERALL PROJECT TIMELINE:
Formal
Application
Submitted
Draft EIR
Scoping
Session
Revised
Application
Submitted
Revised
Application
Submitted
PC/DRB
Study
Session
DRB Project
Review and
Comment
Notice of
Preparation /
Initial Study
PC Study Session
MAR-21 JAN -22 JAN -24
JUN-21 MAR-22 FEB-24
SEP-21 MAY-22
JUN-24
DEC-21 NOV-22
SEP-24
JUL-23 Revised
Application
Submitted
JUL-23 DRB review of
non-residential
SEP-23 DRB review of
residential
Draft EIR
Notice of
Availability
PC DEIR Meeting
Final Project
Modifications
Submitted
PC Study Session
MAY-23 Revised
Application
Submitted
NOV-23 Revised
Application
Submitted
OCT-24 PC
Recommendation
REVISED PROJECT 6
•Increase in size and enhancement of amenities in the Town Square
•Elimination of the stand-alone affordable housing component and moved to
10% inclusionary throughout the project
•Added 38 townhomes
•Added X units and increased building height to 6-stories to Residential 5 to
increase units to maintain 1,422 total; and
•Architectural changes to the cinema building
•Architectural refinements to add articulation and pedestrian level interest
•Withdrawal of the application for a Development Agreement
•Revised Master Sign Program
2025 Master
Plan – Phase 1
Demolition: 308,946 square feet of
existing retail
Construction: 44,380 square feet of
new retail
Construction: 864 residential units
(87 affordable units)
Construction: 56,975 square foot
town square and 9,604 square foot
bike hub with amenities
PH
A
S
E
1
OV
E
R
A
L
L
U
S
E
&
P
R
O
G
R
A
M
M
I
N
G
PH
A
S
E
1
OP
E
N
S
P
A
C
E
&
L
A
N
D
S
C
A
P
I
N
G
2040 Master
Plan – Phase 2
Demolition: 339,861 square feet
of existing retail
Construction: 57,300 square feet
of new retail
Construction: 558 residential
units (56 affordable units)
PH
A
S
E
2
OV
E
R
A
L
L
U
S
E
&
P
R
O
G
R
A
M
M
I
N
G
PH
A
S
E
2
OP
E
N
S
P
A
C
E
&
L
A
N
D
S
C
A
P
I
N
G
BLUE = RETAINED
RED = FULL OR PARTIAL DEMO (2025)
YELLOW = DEMO (2040)
Phase 1 Phase 2
OVERALL DEMOLITION PLAN (2025 & 2040)
ENVIRONMENTAL REVIEW 14
•Final Environmental Impact Report (FEIR) was released on October 18, 2024,
includes analysis of the revised project
•Response to Comments for all comments received during 60-day public review
period were included in the FEIR
•Addendum to the Response to Comments Document was published on
November 22nd, 2024
•The City Council must certify the Final Environmental Impact Report , adopt
applicable findings, adopt the statement of overriding considerations, and
adopt the Mitigation Monitoring & Reporting Program in order to take action on
the project tonight
PURPOSE OF CEQA 15
Identify a project’s
significant
environmental
impacts
Evaluate potential
impacts against
“baseline”
conditions
according to
established
thresholds
Identify ways to
mitigate or avoid
project impacts
Identify a range of
reasonable
alternatives that
meet basic project
objectives and
avoid project
impacts
Inform the public
and decision-
makers of the
environmental
effects of a project
Impacts are direct physical
changes in the environment
and reasonably foreseeable
indirect physical changes
CEQA PROCESS AND TIMELINE
Milestone Date
Publication of Notice of Preparation (NOP)December 9, 2021
Draft EIR Scoping Session January 11, 2022
End of 30-Day NOP comment January 14, 2022
Publication of Draft EIR and Notice of Availability January 5, 2024
Draft EIR Comment Session February 13, 2024
End of 60-day Draft EIR Comment Period March 5, 2024
Publication of Response to Comments (RTC ) on Draft EIR October 18, 2024
Planning Commission Considers Recommendation to Certify Final EIR October 29, 2024
City Council Considers Certification of the Final EIR December 2024
OVERVIEW OF DRAFT EIR FINDINGS
SIGNIFICANT
UNAVOIDABLE
IMPACT
LESS THAN SIGNIFICANT
WITH MITIGATION
LESS THAN
SIGNIFICANT
IMPACT
NO IMPACT
•Greenhouse Gas
Emissions
•Noise (Operation
Period)
•Air Quality
•Cultural (Archeological) and
Tribal Resources
•Geology and Soils and
Paleontological Resources
•Hydrology and Water Quality
•Hazards and Hazardous
Materials
•Noise (Construction Period)
•Transportation
•Utilities and Services
•Cultural (Historic
Architectural)
Resources
•Energy
•Land Use and
Planning
•Population and
Housing
•Public Services and
Recreation
•Visual Resources
•Agriculture
and Forestry
Resources
•Mineral
Resources
•Wildfire
Significant
and
Unavoidable
Impacts
Greenhouse
Gas Emission
Impacts GHG-1
and GHG-2
Noise Impact
NOI-2
PROJECT ALTERNATIVES
Alternative Characteristics Impacts Reduced?Mitigation Measures Required
No Project •No modifications to
the project site
•All project impacts would
be avoided
•None
Reduced
Development
•501,941 sq. ft. of
commercial space
•922 residential units
•Incremental decrease in
air quality, energy,
greenhouse gas, and
noise impacts due to
reduced construction and
operation intensity
•Transportation noise
impacts increase
•All mitigation measures would
still be required
Reduced
Residential
•217,520 sq. ft. of
commercial space
•1,359 residential units
•Incremental decrease in
air quality, energy,
greenhouse gas, and
noise impacts due to
reduced operation
intensity
•All mitigation measures would
still be required
Final Environmental Impact Report
•Draft Environmental Impact Report
•Response to Comments (RTC) Document
Purpose and Organization of the Final EIR
Minor revisions to the project
List of agencies, organizations, and individuals who provided written and verbal comments
on the Draft EIR - approximately 270 comment letters were received
Reproduction of each comment letter received, and a transcript of verbal comments
provided at the Draft EIR Planning Commission hearing
Written responses to each substantive comment that addressed the adequacy of the
information and analysis in the Draft EIR
Revisions to the Draft EIR
Categorized Responses
•Categorized responses address key issues:
#1: Draft EIR Public Review Period
#2: Project Merits
#3: Environmental Baseline
#4: Transportation Analysis Methodology
#5: Scope of Alternatives
#6: Speculation without Substantiation
#7: CEQA Mitigation Requirements
#8: Adequacy of the Draft EIR
Response to Comments:
Impact on Schools
•The project’s contribution to increased enrollment within the Miller Creek School
District (MCSD) is consistent with the enrollment projections outlined in the
2040 General Plan EIR
•The timeframe for full buildout of the project allows for the MCSD to plan for
enrollment increases
•State law specifies that the payment of development impact fees is deemed to
be full and complete mitigation for impacts to school facilities
•Traffic on surrounding roadways would be reduced compared to existing
conditions and the project would not substantially increase congestion during
pick up and drop off periods for area schools
Response to Comments:
Greenhouse Gas Emissions
•Prohibition of natural gas use in commercial kitchens is infeasible, inconsistent
with the City’s Municipal Code, and is legally indefensible
•All-electric commercial kitchen equipment may be available, but it is not
established that this equipment would be practical or feasible for the project
•All feasible mitigation measures are recommended – additional recommended
measures do not have a nexus to the use of natural gas and would not avoid or
reduce the identified impact
•Overall, the project has a net negative impact on operational GHG emissions
Revisions to the Draft EIR:
Revised Project
•The Final EIR fully documents and analyzes project revisions that were provided
in the June 4, 2024 re-submittal
•The minor increase in commercial space (1,860 square feet), expansion of Town
Square, and other minor project modifications do not change the construction
or operational impacts and related mitigation measures identified in the Draft
EIR
•The project revisions have been considered in the responses to comments on
the Draft EIR
Revisions to the Draft EIR:
Supplemental Air Quality Analysis
•Supplemental modeling updates the Health Risk Assessment utilizing
meteorological data from an air monitoring station that is closer to the project
area
•Another off-site emergency generator was added to the analysis of emission
sources
•The revised analysis determined that impacts would continue to be less than
significant with implementation of mitigation measures
•Applicable air quality emission reduction measures were modified for clarity and
are more stringent than presented in the Draft EIR
Mitigation Monitoring and Reporting
Program (MMRP)
•The MMRP identifies all feasible mitigation measures from the Final EIR that are
required to reduce the physical environmental impacts of the project
•The implementation strategy and timeline is identified, including by phase of
development
•The responsibility for implementation
•Entity that will oversee implementation and how the measure will be monitored
and enforced
CEQA Guidelines Section 15151:
Standards for Adequacy of an EIR
An EIR should be prepared with a sufficient degree of analysis to provide
decisionmakers with information which enables them to make a decision which
intelligently takes account of environmental consequences. An evaluation of the
environmental effects of a proposed project need not be exhaustive, but the
sufficiency of an EIR is to be reviewed in the light of what is reasonably feasible.
Disagreement among experts does not make an EIR inadequate, but the EIR should
summarize the main points of disagreement among the experts. The courts have
looked not for perfection but for adequacy, completeness, and a good faith effort at
full disclosure.
TRAFFIC ENVIRONMENTAL BASELINE
•Provides background and factual support for the use of the environmental baseline that assumes
full occupancy of the existing 766,507 square feet of gross leasable area
•The Mall maintained strong occupancy levels since 2017 when the owner purchased the property
and vacancy was at 3.2 percent in 2020, prior to the COVID-19 pandemic
•Institute of Transportation Engineers (ITE) trip generation rates for shopping malls assume some
amount of inherent rolling vacancy
•The existing gross leasable area of the Mall has been entitled and may be occupied for retail use
at any time
•Applying a conservative 5% vacancy, the Final EIR confirms that minor fluctuations in employment
data would not have any material effect on the analysis or conclusions presented in the Draft EIR
TRANSPORTATION ANALYSIS
METHODOLOGY
•Use of Institue of Transportation Engineers trip generation rates is an established
and widely used method for estimating existing and proposed trip generation
rates
•The methodology for collecting existing and projecting future traffic volume
data is consistent with the City’s Transportation Analysis Guidelines and is based
on TAM’s Demand Model for future 2040 conditions (and not one-time 2021
counts)
•Even if unleased space were subtracted from the 2021 traffic counts the project’s
PM peak hour trips show an overall reduction compared to existing conditions
•Residential uses generate fewer daily and PM peak trips than commercial uses
Transportation Improvements in
North San Rafael 30
•Roundabout project east side HWY 101: Construction 2025 by Caltrans
(https://www.cityofsanrafael.org/ada-mtf-101/)
•Freitas Pkwy HWY 101 Interchange project: Project Initiation Document
planning stage by TAM working with Caltrans and San Rafael
(https://tam101study.com/)
•Merrydale Northgate Promenade (Northgate to Civic Center)- Project
includes $500k from developer.Design anticipated 2025.
•South Merrydale- Civic Center Pathway Connector- Design to begin 2025 with
construction 2026-2027
•Freitas Parkway- Preliminary design Multi-use Pathway-currently in design
•Traffic signal inventory and upgrade plan
FIRE SERVICES &
EMERGENCY EVACUATION
•A recent study of fire and medical service adequacy and capacity in the
Northgate area found that no additional facilities or fire suppression and
emergency medical resources would be needed, based on the projected size,
density, and incident volume in the project area
•Further evaluation of wildfire risk and evacuation procedures determined that
the project would not create new or worsen existing conditions related to wild
land fires
•The Police & Fire Departments have confirmed that adequate procedures and
protocols are in place to evacuate the project area in the event of a natural
disaster
FISCAL ANALYSIS 32
•Summary of Findings
•Approach to Fiscal Impact Analysis
•Fiscal Revenues
•Fiscal Costs
•Fiscal Impact Analysis Results
33
Projected General Fund
Fiscal Impacts
See Exhibit 4 -Page 391 for Report
Libby to Add notes on Slide Explanation
and better version of chart (this version
pixelized)
SUMMARY OF FINDINGS FROM FISCAL
IMPACT ANALYSIS 34
•Projected net positive fiscal impact on City’s General Fund
at full buildout of Phase 1 (2025 Plan) and Phase 2 (2040
Plan) of the Proposed Project.
•New mixed-use development and the Town Plaza will
create an attractive centerpiece for new housing,
commerce and recreation.
•The project will stabilize and prevent further decline in
fiscal revenues from the property.
PLANNING COMMISSION
RECOMMENDATIONS
Planning Commission Recommended Approval of the Project, with the following
added conditions for:
•faux turf, modify the sign program, and submit a colors and materials board. Add the
additional ones...
Planning Commission requested staff to evaluate: 1) privacy, 2) post construction
traffic studies,and 3) construction impacts
•Add language from staff report that says staff did so and found no more
studies were needed
PROPOSED CONDITIONS OF
APPROVAL 36
Some of the conditions specifically respond to public input and project refinement
including:
•Sustainability – above standard green building codes
•Contribution towards Merrydale pedestrian improvements
•Bike and pedestrian improvements, connecting development to existing community
•Construction Management Plan – advanced review of construction phasing and
community notification
•Town Square improvements – see next slide
TOWN SQUARE
•Increased in size
•Incorporated row of parking
•Maintained adjacent bike hub
•Retractable bollards
•Moved dog park
•Enhanced play area
•Eliminated synthetic turf
•Removed bollards from grass area
REQUESTED ENTITLEMENTS 38
The proposed Town Square Project requires the following City Council Approvals:
•Zoning Amendment – Plan Development Zoning District
•Vesting Tentative Subdivision Map
•Master Use Permit - includes affordable housing agreement
•Environmental and Design Review Permit includes Density Bonus
•Master Sign Program
STANDARDS FOR REVIEW
Project reviewed by staff for
compliance with:
•San Rafael Municipal Code
•San Rafael Subdivision Ordinance
•San Rafael General Plan 2040
•San Rafael Design Guidelines
•CEQA Guidelines
•Consistency matrices included in
packet and findings in resolutions
PROPOSED ZONING AMENDMENT
Staff recommends that the City Council
approve the following:
•Rezoning of Northgate Mall property from
General Commercial to Northgate Town
Square Planned Development
•Establish Northgate Town Square Planned
Development District and associated
standards
•Modify the Zoning Map to represent the
change from General Commercial to Planned
Development
40
PROPOSED NORTHGATE Planned
Development STANDARDS 41
Staff recommends that the City Council approve the proposed standards.
•The Proposed Northgate Planned Development includes provisions that deviate
from current zoning, including:
•Allows transfer of standards across the entire site
•Fencing provisions for different uses proposed
•Minimum 150 square feet for minimum of private usable open space for each residential unit
•Provisions for bicycle parking
•Temporary uses at the Town Square
•Compliance with Master Affordable Housing Agreement and Public Access, Use, and
Maintenance Agreement
PROPOSED VESTING TENTATIVE
SUBDIVISION MAP 42
Staff recommends that the City Council approve the following:
•The proposed vesting tentative map which subdivides six existing lots into 24
new lots AND provides for future subdivision for condo purposes on Lots 2 and 3
(Residential 1 and 2)
•Conditions include requirements for:
•Subdivision Improvement Agreement
•Public amenities and improvements
•Upsize sewer main
•Recycled water
•Erosion control and stormwater prevention plan
•Fire prevention infrastructure
PROPOSED MASTER USE PERMIT 43
Staff recommends that the City Council approve the following phased multi-unit
development which:
•Provides for all proposed uses on the site
•Includes conditions related to affordable housing, privately owned publicly
accessible open space areas
PRIVATELY OWNED PUBLICLY
ACCESSIBLE OPEN SPACE 44
Staff recommends that the City Council approve the:
•Privately Owned Publicly Accessible Open Space Agreement, which identifies
areas as part of project that are privately owned, but publicly accessible
•Elements of the agreement include specific improvements, maintenance, access
•Five areas specifically identified for public access:
•Town Square
•Bike Hub
•Restaurant Entry Plaza
•West Entry Rest Stop
•East Entry Rest Stop
PROPOSED ENVIRONMENTAL
AND DESIGN REVIEW PERMIT 45
Staff recommends that the City Council approve the Environmental & Design
Permit which approves architectural, site, and landscape design.
•Permit also includes specifications related to:
•Density Bonus and Building Height
•Inclusionary Housing
•Town Square and Public Amenities
•Drive through facilities
•Colors, Materials, and Landscaping
•Tree Removal and Protection
•Refuse Storage and Collection
PROPOSED MASTER SIGN
PROGRAM 46
Staff recommends that the City Council approve the
Master Sign Program which stablishes a uniform signage
approach across the site.
•Includes provisions for private tenant signs and
wayfinding signs
•The Planning Commission recommended a reduction
in the number of signs, which have been incorporated
into the final project
RECOMMENDATION
It is recommended that the City Council receive public input on the Project and
approve the following:
•Resolution certifying the FEIR
•Resolution approving a Zoning Amendment to establish the Northgate Town
Square PD District, approve the Northgate Town Square Development Plan, amend
the City’s Zoning Map, and rezone the 44.76-acre property from General
Commercial to the Northgate PD District and adopt findings of fact, a statement of
overriding considerations, and a mitigation monitoring and reporting program.
•Resolution approving the Vesting Tentative Subdivision Map, Master Use Permit,
Environmental and Design Review Permit, and Master Sign Program for the
Northgate Town Square Project
BACK UP SLIDES
ENVIRONMENTAL REVIEW 50
To date:
•Notice of Preparation: December 9, 2021
•Scoping Meeting: January 11, 2022
•DEIR Notice of Availability: January 5, 2024
•DEIR Public Comment Period: January 5 – March 5, 2024
•Planning Commission meeting on DEIR: February 13, 2024
•Release of FEIR: October 18, 2024
•PC recommendation: October 29, 2024
•CC consideration of certification: December 2, 2024
DRB COMMENTS 51
•Consensus that the massing of the overall project is too big
•Increase visual interest on all elevations of each buildings (four sided
architecture)
•Provide additional awnings and other shade options
•Consider alternative design features on the east facing elevation of the cinema
building in lieu of the proposed mountain relief
•Consider providing a landscaped green screen or other design solution to break
up the rear façade of the cinema structure across from the townhomes
DRB COMMENTS 52
•Maximize use of shade trees where possible
•Increase level of detailing on the landscape plans versus what is shown on the
renderings
•Utilize permeable paving throughout the project to the extent possible
•Make the town square significantly larger
•Eliminate use of faux landscape materials (faux rocks/logs, synthetic turf, etc)
•Eliminate dog park from town square
•Eliminate rocks in town square
PH
A
S
E
1
S
I
T
E
A
C
C
E
S
S
,
C
I
R
C
U
L
A
T
I
O
N
,
CO
M
M
E
R
C
I
A
L
L
O
A
D
I
N
G
PH
A
S
E
1
V
E
H
I
C
L
E
A
N
D
B
I
C
Y
C
L
E
PA
R
K
I
N
G
C
O
M
M
E
R
C
I
A
L
&
RE
S
I
D
E
N
T
I
A
L
BLUE = SHORT-TERM BIKE PARKING
GREEN = LONG-TERM BIKE PARKING (RES)
PINK = LONG-TERM BIKE PARKING (COM)
VEHICLE PARKING BICYCLE PARKING
Total EV
Charger EV Ready Clean Air
Vehicle
ADA
Spaces
Compact
Spaces
Short
Term
Long
Term
3,453 410 1,242 223 119 22 240 860
PH
A
S
E
1
U
S
A
B
L
E
O
P
E
N
S
P
A
C
E
RE
S
I
D
E
N
T
I
A
L
1
,
2
,
3
,
4
RES 1 RES 2 RES 3
RES 4
Residential 1 7,314 s.f.
Residential 2 22,303 s.f.
Residential 3 42,979 s.f.
Residential 4 70,401 s.f.
DARK GREEN = PRIVATE AREA
LIGHT GREEN = COMMON OUTDOOR AREA
BLUE = COMMON INDOOR AREA
Residential Parcel Total Area
PH
A
S
E
2
S
I
T
E
A
C
C
E
S
S
,
C
I
R
C
U
L
A
T
I
O
N
,
CO
M
M
E
R
C
I
A
L
L
O
A
D
I
N
G
BLUE = SHORT-TERM BIKE PARKING
GREEN = LONG-TERM BIKE PARKING (RES)
PINK = LONG-TERM BIKE PARKING (COM)
VEHICLE PARKING BICYCLE PARKING
Total EV
Charger EV Ready Clean Air
Vehicle
ADA
Spaces
Compact
Spaces
Short
Term
Long
Term
3,887 646 2,080 306 155 33 260 1,452
PH
A
S
E
2
V
E
H
I
C
L
E
A
N
D
B
I
C
Y
C
L
E
PA
R
K
I
N
G
C
O
M
M
E
R
C
I
A
L
&
RE
S
I
D
E
N
T
I
A
L
PH
A
S
E
2
U
S
A
B
L
E
O
P
E
N
S
P
A
C
E
RE
S
I
D
E
N
T
I
A
L
5
,
6
Residential 5 54,688 s.f.
Residential 6 43,617 s.f.
Residential Parcel Total AreaDARK GREEN = PRIVATE AREA
LIGHT GREEN = COMMON OUTDOOR AREA
BLUE = COMMON INDOOR AREA
RES 5 RES 6
TOWN SQUARE 59
RESIDENTIAL PARCEL 1 60
ORIGINAL
REVISED
RESIDENTIAL 1
•Replaced 96 unit
EAH building
•38 for-sale three-
story townhomes
•Similar Residential
2
•Shifted approach
to inclusionary
housing to
distribute 10%
BMR units on each
residential parcel
•Maintain 1,422
total residential
units
RESIDENTIAL PARCEL 5 62
RESIDENTIAL 5
•Increased by 58 units
•Maintained 1,422 total
residential units
•Increased massing to 6-
stories
•Other changes to modify
location of common
recreation areas
CINEMA BUILDING 64
CINEMA
•Eliminated mountain motif
•Addition of trellis
•More robust tree planting
along east and south
elevations
•Addition of windows and
sunshades on south
elevation
FENCING
66
SIGNAGE
67
RESIDENTIAL
68
SHOPS AND PADS
69
PROJECT EVOLUTION 70
SITE DEVELOPMENT CATEGORIES MAR-24 JUN-21 MAR-22 JUL-23 JUN-24
Total Residential 1,356 1,320 1,320 1,422 1,422
Total Affordable Residential --138 147 143
Residential Density (dwelling units per acre)30.3 29.5 29.5 31.8 31.8
Total Retail/Commercial (square feet)246,677 250,200 225,100 217,520 219,380
Non-residenital Intensity (floor area ratio)0.13 0.13 0.12 0.11 0.11
Landscaping Concept 334,138 360,299 328,785 324,870
Usable Open Space Concept 299,510 225,500 328,785 329,142
Town Square -35,000 47,818 48,075 56,975
Bike Hub Open Space/Plaza --14,025 12,934 9,604
Residential Parking 2,311 2,225 2,314 2,524 2,586
Retail Parking 1,776 1,445 1,402 1,325 1,303
Long-Term Bicycle Parking (Residential)--Concept 1,396 1,356
Short-Term Bicycle Parking (Entire Site)--138 198 210
Long-Term Bicycle Parking (Retail)--47 96 96
PH
A
S
E
1
C
O
M
M
E
R
C
I
A
L
S
P
A
C
E
Space Floor Plans Category Existing
(sq ft)
Demolished
(sq ft)
Existing
to Remain
(sq ft)
New
(sq ft)
Total
(sq ft)
Sears --Full Demolition 134,976 134,976 ------
HomeGoods --Full Demolition 29,538 29,538 ------
Mall RT-16 Partial
Demolition 199,792 144,432 55,360 --55,360
Macy’s --Preserved 254,015 --254,015 --254,015
Major 1 RT-8 Preserved 79,051 --79,051 --79,051
Rite Aid --Preserved 17,340 --17,340 --17,340
Shops 1 RT-13 Preserved 6,795 --6,795 --6,795
Cinema RT-2 Preserved/New 45,000 --45,000 20,000 65,000
Ounces --New ------480 480
Shops 3 RT-2 New ------5,000 5,000
Shops 4 RE-50 New ------6,200 6,200
Pad 1 RT-22 New ------8,400 8,400
Pad 2 RT-26 New ------4,300 4,300
Total 766,507 308,946 457,561 44,380 501,941
PH
A
S
E
1
C
O
M
M
E
R
C
I
A
L
S
P
A
C
E
Space Floor Plans Category Existing
(sq ft)
Demolished
(sq ft)
Existing to
Remain
(sq ft)
New
(sq ft)
Total
(sq ft)
Macy’s --Full Demolition 254,015 254,015 ------
Major 1 --Full Demolition 79,051 79,051 ------
Shops 1 --Full Demolition 6,795 6,795 ------
Mall RT-16 Preserved (Pre-existing)55,360 --55,360 --55,360
Rite Aid --Preserved (Pre-existing)17,340 --17,340 --17,340
Cinema RT-2 Preserved (Phase 1)65,000 --65,000 --65,000
Ounces --Preserved (Phase 1)480 --480 --480
Shops 3 RT-2 Preserved (Phase 1)5,000 --5,000 --5,000
Shops 4 RE-50 Preserved (Phase 1)6,200 --6,200 --6,200
Pad 1 RT-22 Preserved (Phase 1)8,400 --8,400 --8,400
Pad 2 RT-26 Preserved (Phase 1)4,300 --4,300 --4,300
Major 3 RE-70 New ------10,000 10,000
Major 4 RE-88 New ------25,000 25,000
Shops 5 RE-70 New ------3,500 3,500
Shops 6 RE-88 New ------5,000 5,000
Pad 3 RT-40 New ------5,000 5,000
Pad 4 RT-43 New ------3,800 3,800
Pad 5 RT-46 New ------5,000 5,000
Total 501,941 339,861 162,080 57,300 219,380
PH
A
S
E
1
R
E
S
I
D
E
N
T
I
A
L
U
N
I
T
S
Housing
Type Units Low-Income Units Unit Sizes
(square feet)
Floor
Plans
Residential 1 For-sale
Townhomes
38 Total Units:
6 one-bed
18 two-bed
8 three-bed
6 four-bed
4 Low-Income
1 one-bed
1 two-bed
1 three-bed
1 four-bed
1 bed: 470
2 bed: 1,503 – 1,575
3 bed: 1,441 – 2,019
4 bed: 2,107 – 2,124
RE-3 to
RE-5
Residential 2 For-sale
Townhomes
100 Total Units
10 one-bed
40 two-bed
30 three-bed
20 four-bed
10 Low-Income
1 one-bed
4 two-bed
3 three-bed
2 four-bed
1 bed: 470
2 bed: 1,503 – 1,575
3 bed: 1,441 – 2,019
4 bed: 2,107 – 2,124
RE-15 to
RE-17
Residential 3 Rental
Apartments
280 Total Units
63 studio
164 one-bed
53 two-bed
28 Low-Income
6 studio
17 one-bed
5 two-bed
Studio: 620
1 bed: 680 – 1,315
2 bed: 1,130 – 1,655
RE-32 to
RE-38
Residential 4 Rental
Apartments
446 Total Units
41 studio
310 one-bed
95 two-bed
45 Low-Income
4 studio
32 one-bed
9 two-bed
Studio: 620
1 bed: 680 – 1,415
2 bed: 908 – 1,970
RE-48 to
RE-56
Total 864 87 --
PH
A
S
E
2
R
E
S
I
D
E
N
T
I
A
L
U
N
I
T
S
Housing Type Units Low -Income Units Unit Sizes
(square feet)
Floor
Plans
Residential 5 Rental
Apartments
309 Total Units
52 studio
190 one-bed
67 two-bed
31 Low-Income
5 studio
19 one-bed
7 two-bed
Studio: 620
1 bed: 680 – 830
2 bed: 1,130 – 1,150
RE-3 to RE-
5
Residential 6 Rental
Apartments
249 Total Units
36 studio
160 one-bed
53 two-bed
25 Low-Income
4 studio
16 one-bed
5 two-bed
Studio: 620
1 bed: 680 – 830
2 bed: 1,130 – 1,150
RE-15 to
RE-17
Phase 2 (2040)
Total 558 56 --
Buildout Total 1,422 143 --