HomeMy WebLinkAboutPresentation from Caltrans on the Manuel T. Freitas and Highway 101 Roundabout PPTADA Improvements and
Roundabout at the Manuel T Freitas
Parkway / Route 101 Interchange
City Council Presentation
February 3, 2025
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Project Overview
Need and Purpose
•Pedestrian safety
•ADA compliance
•Consistency with Caltrans Strategic Plan
& Complete Street Policy
Benefit to City of San Rafael
•Improved safety
•Improved traffic operation on local street
•Improved bicycle and pedestrian mobility
•Increased accessibility to bus stops
•Reduced emissions
•Reduced long-term maintenance
•Compatibility with San Rafael’s plan for
roundabout on west side of the freeway
Scope
•Reconstruct curb ramps and sidewalk
•Remove stairs and bus stop access
across loop ramps
•Relocate NB bus stop to Redwood Hwy
•Construct roundabout at Redwood Hwy/
Civic Center Dr intersection
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Project Cost and Schedule
Anticipated Construction Cost
•$7.15 Million (2024 Dollars)
Schedule
•Bid Opening – 11/20/2024
•Begin Construction – Spring 2025
•Finish Construction – Fall 2025
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Public Information Plan
Traffic advisories
•The Caltrans’ Public Information Officer
will write traffic advisories when there
are upcoming traffic disruptions within
the project limits. The advisories are sent
to a distribution list that includes other
agencies as well as city and elected
officials.
•The traffic advisories are shared on
Caltrans’ social media channels (X,
Facebook and Instagram), and city
officials are encouraged to share them
on Nextdoor. The advisories are also
posted on Caltrans’ District 4 web page.
Other outreach
The Caltrans’ Public Information Officer will
respond to public and media inquiries
involving the project. For questions email
matt.odonnell@dot.ca.gov
Elected officials should email
William.Butkus@dot.ca.gov
For more
https://dot.ca.gov/caltrans-near-me/district-
4/d4-projects/d4-roundabout-project-us101-
san-rafael
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Existing Conditions
Manuel T Freitas Parkway / US-101 Interchange
Manuel T Freitas Pkwy
Ci
v
i
c
C
e
n
t
e
r
D
r
.
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Proposed Improvements (West Side)
Manuel T Freitas Pkwy / Southbound Ramps
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Proposed Improvements (East Side)
Manuel T Freitas Pkwy / Northbound Ramps / Frontage Roads
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Project Construction
Staging
•7 Stages
•Frontage road and ramp closures
required for some stages
•Approximately 5.5 months total
Intersection Closure Benefits
•Increased safety
•Shorter construction duration
•Reduced impact to travelling public
•Reduced construction costs
Traffic Handling
•Detailed plans for each stage
•Advanced signage
•Positive protection
•Detours for road closures
•Continuous bus stop access
•Continuous pedestrian access
•Continuous access to 5000 Civic
Center Dr
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Proposed Construction Staging
DURATION: ~2 MONTHS
WEST SIDE:
•Nothing
EAST SIDE:
•Retaining
Walls
•Median
Removal
•Sidewalk
DETOURS:
•Pedestrians
on Civic
Center
Detoured via
Merrydale
DURATION: 52 HOURS
WEST SIDE:
•Nothing
EAST SIDE:
•Private
Driveway
Paving
DETOURS:
•Driveway
Closed
Access
Through
Scettrini Dr
DURATION: 3 WEEKS
WEST SIDE:
•Median
EAST SIDE:
•Median
•SB Bike Lane
•Bus Stop
Removal
DETOURS:
•EB Manuel
Freitas Pkwy
Traffic
Detoured to
Lucas Valley
IC
DURATION: ~2 WEEKS
WEST SIDE:
•Final Striping
EAST SIDE:
•Grind &
Overlay
•Final Striping
DETOURS:
•None
1 2 3 4 7
DURATION: ~2 MONTHS
WEST SIDE:
•Nothing
EAST SIDE:
•Roundabout
•New Bus Stop
•NB Slip On-
Ramp
DETOURS:
•Redwood Hwy
/ Civic Center
Dr Intersection
Closed
•Adjacent IC’s
and local roads
DURATION: 52 HOURS
WEST SIDE:
•Curb Ramps &
Sidewalks
•SB Loop On-
Ramp
EAST SIDE:
•Nothing
DETOURS:
•SB Loop On-
Ramp Closed
Detour to SB
Slip On-Ramp
5
DURATION: ~1 WEEK
WEST SIDE:
•Curb Ramps &
Sidewalks
•Traffic Signals
•SB Off-Ramp
EAST SIDE:
•Nothing
DETOURS:
•SB Off-Ramp
Closed at Night
Detour to Next
IC
6
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Proposed Stage 3 (East Side)
Manuel T Freitas Pkwy / Northbound Ramps / Frontage Roads
~2 MONTHS
Frontage road
intersection closed
Bike/Ped/Vehicle
access to 5000
Civic Center Dr
maintained
Pedestrian route
between Manuel
Freitas Pkwy to
Redwood Hwy and
bus stops
maintained.
Full access to/from
Manuel Freitas
Pkwy to US-101
On/Off-Ramps
Manuel T Freitas Parkway / US-101 Interchange Improvements CALTRANS DISTRICT 4 | 04-0K800
Proposed Stage 3 Detours
Northbound Civic Center to NB US-101
Multiple detailed
detour scenarios
in plans
Traffic diverted to
Merrydale Rd
Overcrossing,
Lucas Valley Rd or
N San Pedro Rd
Interchanges
Thank you