HomeMy WebLinkAboutPW San Quentin Pump Station Reconstruction Project; Thompson Builders; First AmendFIRST AMENDMENT TO THE PUBLIC WORKS CONTRACT WITH THOMPSON
BUILDERS CORPORATION FOR THE SAN QUENTIN PUMP STATION
RECONSTRUCTION PROJECT
THIS FIRST AMENDMENT to the Public Works Contract by and between the CITY
OF SAN RAFAEL (hereinafter “CITY”),and THOMPSON BUILDERS CORPORATION
(hereinafter “CONTRACTOR”),is made and entered into as of .
RECITALS
WHEREAS,the CITY and CONTRACTOR entered into a Public Works Contract
dated December 7,2022 for work in connection with CITY’S San Quentin Pump Station
Reconstruction Project,for an amount not to exceed $6,538,725 (the “Contract”);and
WHEREAS,the CITY and CONTRACTOR entered into seven (7)Change Orders to
the Public Works Contract between July 13,2023 and August 27,2024,to deduct and add
additional work in connection with CITY’S San Quentin Pump Station Reconstruction Project,
decreasing the total not to exceed under the Contract to $5,804,327;and
WHEREAS,under the terms of the Contract,the Contract Time was to expire on
December 7,2024;however CITY and CONTRACTOR,agreed informally that the Contract
Time would be extended,and now wish to ratify and memorialize that extension.
AMENDMENT TO CONTRACT
NOW,THEREFORE,the parties hereby agree to amend the Contract as follows:
Article 5 of the Contract,entitled “Time for Completion”is hereby amended,
effective as of December 7,2024,to extend the Contract Time by two (2)years
through December 7,2026.
Except as specifically amended herein,all of the other provisions,terms and
obligations of the Contract between the parties shall remain valid and shall be in
full force.
1.
3.
1
04/08/2025
IN VVITNKSS VVllERl'OF.ihc parlies have cxeculcd this l-'irsl Amendment on the day.
monih.and vear tlrsi abo\e wrillen.
CITY OF SAN RAFAF.L CONIRACIOI^
/
irv:„uC'RISTINE AI.II.OVICI I.Ciiv Manager
Name;
^'V
ATTEST:
I IfContractor is a eoiporaiion.add signalure of
second eoijjaralc olllcer]
LINDSAY I.ARA.Ciu Clerk
APPROVED AS TO 1‘ORM:Name:
nUe:
ANDREA VISVHSIIWARA.
Chief Assislanl Citv Auornes
Andrea Visveshwara (Apr 8, 2025 14:06 PDT)
Andrea Visveshwara
ris/ine A'i'*vih (Apr 8, 2025 16:т4 PDT)
indsa4
ara (Apr ш, 2025 12:25 PDT)
2indsa\ 2ara
CONTRACT ROUTING FORM
INSTRUCTIONS: Use this cover sheet to circulate all contracts for review and approval in the order shown below.
Step RESPONSIBLE
DEPARTMENT
DESCRIPTION COMPLETED
DATE
REVIEWER
Check/Initial
1 Project Manager
a. Email PINS Introductory Notice to Contractor
b. Email contract (in Word) and attachments to City
Attorney c/o Laraine.Gittens@cityofsanrafael.org
Click here to
enter a date.
1/27/2025
☐
☒SM
2 City Attorney
a. Review, revise, and comment on draft agreement
and return to Project Manager
b. Confirm insurance requirements, create Job on
PINS, send PINS insurance notice to contractor
1/29/2025
1/29/2025
☒ NT
☒ NT
3 Department Director Approval of final agreement form to send to
contractor
1/30/2025 ☒ AM
4 Project Manager
Forward three (3) originals of final agreement to
contractor for their signature
1/30/2025 ☒
5 Project Manager When necessary, contractor-signed agreement
agendized for City Council approval *
*City Council approval required for Professional Services
Agreements and purchases of goods and services that exceed
$75,000; and for Public Works Contracts that exceed $175,000
Date of City Council approval
☒ N/A
Or
Click here to
enter a date.
☒
PRINT CONTINUE ROUTING PROCESS WITH HARD COPY
6 Project Manager Forward signed original agreements to City
Attorney with printed copy of this routing form
7 City Attorney Review and approve hard copy of signed
agreement
8 City Attorney Review and approve insurance in PINS , and bonds
(for Public Works Contracts)
9 City Manager / Mayor Agreement executed by City Council authorized
official
10 City Clerk Attest signatures, retains original agreement and
forwards copies to Project Manager
TO BE COMPLETED BY INITIATING DEPARTMENT PROJECT MANAGER:
Contracting Department: Public Works
Project Manager: Shannon Mackle (for Theo Sanchez) Extension: 3353
Contractor Name: Thompson Builders Corporation
Contractor’s Contact: Lee Jones Contact’s Email: leej@tbcorp.com
☐ FPPC: Check if Contractor/Consultant must file Form 700
First Amendment - Thompson Builders - SQ
Pump Station Reconstruction
Final Audit Report 2025-04-09
Created:2025-04-08
By:Shannon Mackle (shannon.mackle@cityofsanrafael.org)
Status:Signed
Transaction ID:CBJCHBCAABAAQ4OylSSsxnNPkjEaKQWG8IRdbI9Sr9Ap
"First Amendment - Thompson Builders - SQ Pump Station Rec
onstruction" History
Document created by Shannon Mackle (shannon.mackle@cityofsanrafael.org)
2025-04-08 - 8:39:50 PM GMT- IP address: 199.88.113.8
Document emailed to Nataly Torres (nataly.torres@cityofsanrafael.org) for approval
2025-04-08 - 8:41:29 PM GMT
Email viewed by Nataly Torres (nataly.torres@cityofsanrafael.org)
2025-04-08 - 8:55:57 PM GMT- IP address: 104.47.64.254
Document approved by Nataly Torres (nataly.torres@cityofsanrafael.org)
Approval Date: 2025-04-08 - 9:04:05 PM GMT - Time Source: server- IP address: 199.88.113.8
Document emailed to andrea.visveshwara@cityofsanrafael.org for signature
2025-04-08 - 9:04:09 PM GMT
Email viewed by andrea.visveshwara@cityofsanrafael.org
2025-04-08 - 9:05:53 PM GMT- IP address: 104.47.64.254
Signer andrea.visveshwara@cityofsanrafael.org entered name at signing as Andrea Visveshwara
2025-04-08 - 9:06:25 PM GMT- IP address: 199.88.113.8
Document e-signed by Andrea Visveshwara (andrea.visveshwara@cityofsanrafael.org)
Signature Date: 2025-04-08 - 9:06:27 PM GMT - Time Source: server- IP address: 199.88.113.8
Document emailed to city.clerk@cityofsanrafael.org for approval
2025-04-08 - 9:06:31 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2025-04-08 - 9:09:53 PM GMT- IP address: 199.88.113.8
Document approval delegated to Lindsay Lara (lindsayl@cityofsanrafael.org) by city.clerk@cityofsanrafael.org
2025-04-08 - 9:09:56 PM GMT- IP address: 199.88.113.8
Document approved by Lindsay Lara (lindsayl@cityofsanrafael.org)
Approval Date: 2025-04-08 - 9:10:29 PM GMT - Time Source: server- IP address: 199.88.113.8
Document emailed to cristine.alilovich@cityofsanrafael.org for signature
2025-04-08 - 9:10:32 PM GMT
Email viewed by cristine.alilovich@cityofsanrafael.org
2025-04-08 - 11:34:33 PM GMT- IP address: 104.47.65.254
Signer cristine.alilovich@cityofsanrafael.org entered name at signing as Cristine Alilovich
2025-04-08 - 11:34:54 PM GMT- IP address: 174.195.86.136
Document e-signed by Cristine Alilovich (cristine.alilovich@cityofsanrafael.org)
Signature Date: 2025-04-08 - 11:34:56 PM GMT - Time Source: server- IP address: 174.195.86.136
Document emailed to city.clerk@cityofsanrafael.org for signature
2025-04-08 - 11:35:00 PM GMT
Email viewed by city.clerk@cityofsanrafael.org
2025-04-09 - 7:25:21 PM GMT- IP address: 199.88.113.8
Signer city.clerk@cityofsanrafael.org entered name at signing as Lindsay Lara
2025-04-09 - 7:25:37 PM GMT- IP address: 199.88.113.8
Document e-signed by Lindsay Lara (city.clerk@cityofsanrafael.org)
Signature Date: 2025-04-09 - 7:25:39 PM GMT - Time Source: server- IP address: 199.88.113.8