HomeMy WebLinkAboutPW Pt. San Pedro Median Project; Plans and SpecsCITY OFIMOOO::54M
Agenda Item No: 3 f
Meeting Date: April 2, 2012
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works
Prepared by: _ City Manager Approva%
Director of Public Works (LB)
File No.: 03.01.180
SUBJECT: ADOPT PLANS AND SPECIFICATIONS FOR POINT SAN PEDRO MEDIAN
LANDSCAPING IMPROVEMENTS, AND AUTHORIZE THE CITY CLERK TO
CALL FOR BIDS.
RECOMMENDATION: Adopt Plans and Specifications for the project.
BACKGROUND: On June 22, 2011 the City Council adopted Resolution 13181 establishing the Pt. San
Pedro Road Median Landscaping Assessment District. On November 21, 2011 the City Council
authorized the Public Works Director to enter into an agreement with Abey Arnold Associates to design
the project. The completed project plans and specifications have been approved by the Public Works
City Engineer and a copy is available at the City Clerk's office for review.
The proposed improvements for the assessment district include the installation of irrigation, landscaping
and related median landscaping facilities along Point San Pedro Road between Union Street and
Biscayne Avenue. Hardscape features including river rock cobble and entrance monuments have been
incorporated into the design in areas that cannot accommodate landscaping. During the design of the
project, two public meetings were held. The comments received during these meetings have been
incorporated into the design.
There are currently twenty-nine existing median islands within the boundaries of the assessment district
that are proposed to be improved and maintained.
ANALYSIS: Adoption of the project plans and specifications is necessary for the plans to go out to bid
and the construction of the project to begin. Construction is anticipated to start in July 2012 and finish in
October 2012.
FISCAL IMPACT: The engineer's estimate for construction of the base bid project is $1,606,000. The
estimate to install the entrance monument signs is an additional $30,000. The exact cost for construction
will be determined after bids have been received.
To date, the City has obligated $146,995 for design services and public outreach. In addition, it is
anticipated that the City will need to hire a full-time inspector for this project, estimated to cost $100,000.
The total cost of the project is estimated to be approximately $1,883,000. The assessment district will
fund, through the purchase of bonds, $1,750,000 for design and construction of the project. The
FOR CITY CLERK ONLY
File No.: — f _ L-"° !
Council Meeting:1
Disposition: ilp rl")c o
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
remaining project cost will be taken from the operations and maintenance budget already collected from
the assessment district.
OPTIONS: The Council may choose tonot accept the report and direct the Public Works Lorevise
design concepts, hold more public meetings to receive additional comments and bring the matter back to
the City Council. If this option is pursued, construction will be delayed until summer of 2013.
ACTION REQUIRED: Adopt Plans and Specifications for the Point Sam Pedro Median Landscaping
Improvements Project (Project No. 111S3)onfile with the City Clerk, and authorize the City Clerk to call