HomeMy WebLinkAboutPW CIP FY2012-13CITY OFA/��IIi��I��'1�
Agenda Item No: 5a
Meeting Date: July 2, 2012
Z9 "IN INIT-111 KI of Ire I i •
Department: Public Works
Prepared by: City Manager Approval
pA,�LA
Director of Public Works
toile No.: Ul.U2.49
SUBJECT: ACCEPT REPORT APPROVING THE UPDATE OF SAN RAFAEL'S 5 -YEAR
CAPITAL IMPROVEMENT PROGRAM FOR FISCAL YEARS 2012/2013
THROUGH 2016/2017 AND AUTHORIZING THE REPROGRAMMING OF
SPECIFIC CAPITAL PROJECTS TO SUBSEQUENT YEARS
RECOMMENDATION
Staff recommends that the City Council accept the update of San Rafael's 5 -Year Capital Improvement
Program (CIP) and staff recommendation to reprogram specific capital projects to future years.
BACKGROUND
Council approved the first 5 -Year Capital Improvement Program formulated by the Department of Public
Works in FY 2009/2010. This is the fourth update of that document, encompassing the period from FY
2012/2013 through FY 2016/2017.
The current Department of Public Works budget is $32,600,000: $23,000,000 for capital projects and
$9,600,000 for operations. The Department has 44 full time employees, 8 of whom are in the
Engineering Division. That division is responsible for the following areas of service:
CIP Provide design and construction services for the City's Capital Improvement
Program, individual department project implementation, State and Federal Grant
management.
Traffic Manage traffic operations and on -street parking. Manage the city's 86 traffic
signals and 4,400 street lights. Coordinate with Police, Fire, and Parking
Services to address public complaints related to traffic issues. The division
utilizes traffic models and technical expertise to manage traffic flours and
perform development impact analyses.
Laird Development Provide subdivision, design review and building permit review services to
identify infrastructure improvements for private development within the City.
Coordinate with Planning and Building Inspection.
FOR CITY CLERK ONLY
w -
File No.:S -
Council Meeting: r ref
Disposition: _ f 0 t:, _ (_,4�-L7
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Pa2e: 2
Pen -nits Provide design review, construction review and assistance to utilities, property
owners and other entities performing work within the public right-of-way.
Administer and inspect grading, dredging, tideland, transportation and other
pen -nits. Manage mandated programs such the Marin County Stonmwater
Pollution Prevention Program (MCSTOPPP).
Public Service Address public concerns, provide over the counter services, property
investigation, maps and public assistance.
Administration Oversight of capital and operational expenditures, process department capital
project and operational invoices, participation on various City committees
including the ADA committee.
CAPITAL PROJECT FUNDING
San Rafael's infrastructure has deteriorated rapidly in recent years. Extensive ongoing maintenance and
large scale infrastructure repairs/upgrades are needed to prevent further deterioration. To support the
City's capital projects, Public Works utilizes funds from a variety of non -grant sources, such as Gas Tax,
Measure A, Construction Vehicle Impact Fees, Refuse Vehicle Registration Fees, Traffic Mitigation Fees,
state-wide propositions, property assessments. Here are the actual and projected funding levels for the
next three years:
• FY 2011/2012-$3,980,457 (actual)
• FY 2012/2013-$2,000,000 (actual and estimated)
• FY 2013/2014-$2,000,000 (estimated)
These funds, while significant, are wholly inadequate to address San Rafael's infrastructure needs,
especially as they relate to roadway deficiencies, aging City facilities and the City's extensive and rapidly
deteriorating storm drain system. To remedy this shortfall, Public Works aggressively seeks
supplemental grant funding for a wide array of Capital Improvement Projects.
We have received 100% of the grants applied for over the past several years due to our history of
completing projects on time and within budget, while meeting all regulatory requirements. It is important
to note that many grants carry strict deadlines which, if not met, can mean the loss of funds in the short
term and future grant eligibility. Over the past 5 years, these efforts have yielded $14,058,938 in grants
for 15 projects (see Exhibit A).
PROJECT UPDATE -FY 11/12 & FY 12/13
The Department completed 17 roadway, storm drain system, bicycle/pedestrian, ADA accessibility and
City building projects in FY 11/12, at a total cost of $3,809,434 (see Exhibit B).
Public Works is currently managing 32 capital improvement projects with a combined budget of
$12,548,373. All are scheduled for completion in FY 12/13 (see Exhibit C):
21 projects are mandatory with strict deadlines
6 address immediate safety concerns
5 will prevent further infrastructure or facility deterioration
Mandatory projects are those we are required to complete either through agreements with state or federal
grant sources, or other legal obligations such as the Department of Justice Settlement Agreement. Safety
projects are those that address an immediate threat to the public or City employees.
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Pa2e: 3
REPROGRAMMING
Securing funds and executing projects is a complex, multi-year process which requires considerable staff
resources. The Engineering Division had 13 employees at one time. There are now 8 employees, whose
productivity is further impacted by a reduction in work hours. But the number of grant funded projects,
project management obligations, and the demand for non -capital Public Works services has increased.
For example, the City has seen more development and related activity of late, requiring more engineering
time for land development, permits, traffic analysis and management, etc.
Regardless of staffing issues, the need for capital projects continues to grow. There are 13 new capital
projects scheduled to start in FY 2012/2013 (see Exhibit D) and 24 new capital projects scheduled to start
in FY 2013/2014 (see Exhibit E):
6 projects are mandatory with strict deadlines
21 projects address immediate safety concerns
10 projects are needed to prevent further infrastructure or facility deterioration
Federal and State constraints severely limit our ability to extend project deadlines. Many grants, even
those with small budgets, require significant staff time to complete studies, calculations and meet
regulatory requirements. Engineering Division staffing is no longer adequate to assure timely completion
of current grant funded projects.
We therefore recommend shifting the following 18 projects, a number of which are unfunded, to future
fiscal years to balance workload with existing staff resources:
Project Name
Current
Schedule
Reprogram
To
5 -Year CIP
Update Page #
5th & Garden Parking Lot Resurfacing
FY 13/14
FY 14/15
9
B St. Community Center Flooring Replacement*
FY 13/14
FY 14/15
13
Brookdale Avenue Retaining Wall*
FY 13/14
FY 14/15
45
Bungalow Avenue Reconstruction*
FY 13114
FY 14115
46
City Hall Irrigation 'Upgrades*
FY 13/14
FY 14/15
14
City Levee Study*
FY 12/13
FY 13/14
35
Fire Station Generator*
FY 13/14
FY 14115
24
Freitas Parkway/Las Gallinas Intersection Improvements
FY 13114
FY 14/15
51
Menzies Parking Lot Resurfacing
FY 13/14
FY 14115
8
North San Rafael Watershed Study*
FY 13/14
FY 14115
31
Park Pathways Resurfacing
FY 13/14
FY 14/15
44
Parking Structure Upgrade/Replacement Study
FY 13/14
FY 14/15
10
Pickleweed Synthetic Field*
FY 13114
FY 14/15
16
Rossi Purnp Station Reconstruction(partially funded
FY 13114
FY 14115
30
Santa Margarita Park Court Reconstruction*
FY 13/14
FY 14/15
15
Schoen Park Improvements*
FY 131'14
FY 14/15
12
Sea Level Rise Study*
FY 13/14
FY 14.°`15
33
Storm Drain System CMP Upgrades*
FY 13/14
FY 14/15
32
18 Projects
* - Unfunded
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 4
FISCAL IMPACT
Reprogramming will reduce the risk of losing $6,558,009 in capital improvement grants (see list below)
and will allow Public Works to concentrate staff resources on projects with immediate, non-negotiable
deadlines. These are projects with tangible benefits throughout the City. They are also among the
Department's most expensive and complex capital projects.
Project Name
Grant
Citywide Street Resurfacing 2012
$1,019,000
Lifeline Cycle 2 -Canal St. & Kerner Blvd. Pedestrian & Transit Improvements
$774,009
NTPP - Puerto Suello Hill Path to Transit Center Connector
$1,300,000
NTPP - Francisco Boulevard East Sidewalk Widening
$1,500,000
Safe Routes to School -Davidson
$565,000
BTA- Grand Avenue Pathway Connector Bride
$1,400,000
Total
$6,558,009
OPTIONS
The Council may authorize the reprogramming of the 18 capital projects referenced above. Doing so can
potentially save the City $6,558,009 in capital improvement grants.
Alternatively, the council may authorize staff to stop working on the referenced projects. Doing so will
mean a loss of $6,558,009 in capital improvement grants and will also jeopardize the City's eligibility for
future grants.
ACTION REQUIRED
Accept the updated 5 -Year Capital Improvement Program update and authorize the reprogramming of 18
projects from fiscal years 12/13 and 13/14 to subsequent years.
Enclosure: 5 -Year CIP Update Document- Attachment "A"
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Paye: 5
Exhibit A
Grant Sources (5 Years)
Source
CateLyory
Grant Amount
Association of Bay Area Governments
Roadway
$200,000
Caltrans Environmental Mitigation Grant
Roadway
$115,200
Community Development Block Grant
Roadway
$1,500,000
Department of Energy Federal Stimulus
Facilities
$575,400
Federal Highway Association Stimulus
Roadway
$1,188,000
Lifeline Transportation Program
Bike/Ped
$955,009
Metropolitan Transportation Commission
Bike/Ped
$900,000
Non -Motorized Transportation Pilot Program
Bike/Ped
$4,712,000
Safe Pathways to School
Bike/Ped
$250,000
Safe Routes to School — Federal
Bike/Ped
$928,179
Safe Routes to School — State
Bike/Ped
$1,242,811
Safe Routes to Transit
Bike/Ped
$600,000
State Transportation Program
Roadway
$640,339
Transportation Authority of Marin
Bike/Ped
$92,000
Transportation Fund for Clean Air
Bike/Ped
$160,000
15 Sources
Drainage
$14,058,938
Exhibit B
FY2011/2012 Completed Projects
Project Name
Category
Budget
3r'i Lootens Parking Lot Improvements
Facilities
$80,000
832 Tamarack Drive Drainage Improvements
Drainage
$15,000
Albert Park Lighting Improvements
Facilities
$10,000
Andersen Drive & DuBois Street Repairs
Roadway
$213,415
Bernard Hoffman Park Handrails ADA/DOJ)
Facilities
$17,695
City Attorney's Office Remodel
Facilities
$18,940
Citywide Street Resurfacing 10/11
Roadway
$1,518,640
Corporation Yard Fuel Station Island Lighting Installations
Facilities
$2,275
Falkirk Painting
Facilities
$148,535
Freitas Park Renovation Phase II
Facilities
$246,908
Freitas Parkway -Las Gallinas Avenue Resurfacing
Roadway
$623,474
Lifeline Cycle 1—Canal St. Pedestrian and Transit Improvements
Bike/Ped
$404,116
Olive Avenue and Acacia Roadway Reconstruction
Roadway
$100,000
Pickieweed Community Center Rodent Abatement/Electrical
Facilities
$25,540
Safe Pathways to School on Woodland Avenue
Bike/Ped
$250,000
San Quentin Marsh Pump Station Repairs
Drainage
$120,000 li
Terra Linda Community Gardens ADA Access Improvements
Facilities
$14,896
17 Projects i
( $3,809,434
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Pa2e: 6
Exhibit C
Current FY 11/12 & 12/13 Projects
Project Name
Need
Budget
3fd Street & Ci os Street Parking Lot Reconstruction
Mandatory
$250,000
400 Canal Street Pump Station Repair
Safety
$120,000
5`" Street & D Street Parking Lot Improvements
Facilities
$75,000
5' Street & Lootens Street Parking Lot Improvements
Facilities
$100,000
ADA/DOJ Curb Rams 11/12
Mandatory
$311,099
ADA/DOJ Curb Rams 12/13
Mandatory
$237,829
Bernard Hoffman Dugout Improvements
Facilities
$25,000
City Buildings Solar Upgrade Study
Facilities
$60,000
City Clerk Office Pass Thru Project
Safety
$15,000
City Hall HVAC Replacement
Mandatory
$1,389,000
Citywide Street Resurfacing 2012
Mandatory
$1,019,000
Citywide Street Resurfacing Curb Ramps 2012
Mandatory
$250,000
Corporate Center Pump Station Underground Connection
Mandatory
$30,000
Bicycle Parking Installations
Mandatory
$9,900
Downtown Pavement Safety Improvements
Safety
$100,000
Grand Avenue Pathway Connector Project
Mandatory
$1,400,000
H Street Drainage Improvements and Reconstruction (unfunded)
Safety
$1,000,000
LED Street Lighting Retrofits
Safety
$250,000
Lifeline Cycle 2—Canal St./Kerner Blvd. Pedestrian & Transit
Improvements
Mandatory
$774,009
NTPP — Francisco Boulevard East Sidewalk WideninR
Mandatory
$1,500,000
NTPP - Mahon Creek Path to Transit Center Connector
Mandatory
$350,000
NTPP — Puerto Suello Hill Path to Transit Center Connector
Mandatory
$1,300,000
Parking Structure/Garage Lighting Replacements
Mandatory
$113,045
Point San Pedro Road Median Landscaping Improvements
Mandatory
$227,491
Pt. San Pedro Road Resurfacing
Mandatory
$500,000
Puerto Suello Multi -Use Path Security Cameras
Mandatory
$92,000
Safe Routes to School -Coleman
Mandatory
$250,000
Safe Routes to School -Davidson
Mandato
$565,000
Santa Margarita Park Access Improvements
Mandatory
$10,000
Sea Way Bridge Replacement
Facilit .
$25,000
SMART
Mandatory
200,000
Traffic Signal Cabinet & Controller Upgrades 11/12
Safety
$100,000
32 Active Projects
$12,548,373
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Pa2e: 7
Exhibit D
New Proiects Scheduled for FY 12/13
Project Name
Need
Budget
City Bridge Repair Program
Mandatory
$135,000
City Building Solar Upgrades Study*
Facilities
$60,000
Emergency Facility Repair Projects
Safety
$100,000
Happy Lane Storm Drain Abandonment
Safety
$10,000
MCSTOPPP (annual)
Mandatory
$80,000
Miscellaneous Drainage Projects
Safety
$100,000
Miscellaneous Right -of -Way Projects
Safety
$100,000
Ramp Metering Study
Mandatory
$75,000
Street Resurfacing 12/13(partially funded)
Safety
$483,633
Street Resurfacing Curb Rams 12/13
Safety
$250,000
Traffic Signal Cabinet & Controller Upgrades 12/13
Safety
$100,000
City Levee Study*
Safety
$60,000
FEMA U dates*
Mandatory
$60,000
13 Projects
Safety
$1,613,633
Exhibit E
New Projects Scheduled for FY 13/14
Project Name
Need
Budget
5`" & Garden Parking Lot Resurfacing
Facilities
$50,000
B Street Community Center Flooring Replacement*
Facilities
$175,000
Brookdale Avenue Retaining Wall*
Safety
$250,000
Bungalow Avenue Reconstruction (partially funded)
Safety
$650,000
City Building Lock System Upgrades*
Safety
$60,000
City Hall Irrigation Upgrades*
Facilities
$100,000
City Library Carpeting Replacement*
Safety
$80,000
Emergency Facility Repair Projects
Facilities
$100,000
FEMA Updates*
Mandatory
$60,000
Fire Station Generator*
Safety
$60,000
Freitas Parkway/Las Gallinas Intersection
Improvements
Safety
$1,500,000
MCSTOPPP (annual)
Mandatory
$80,000
Menzies Parking Lot Resurfacing
Facilities
$120,000
Miscellaneous Drainage Projects
Safety
$100,000
Miscellaneous Right -of -Way Projects
Safety
$100,000
Park Pathways Resurfacing
Safety
$75,000
Parking Structure U rade/Replacement Stud v
Facilities
$200,000
Pickleweed Snthetic Field Construction*
Facilities
$4,000,000
Rossi Pump Station Reconstruction (partially
funded)
Safety
$120,000
Santa Margarita Park Court Reconstruction*
Facilities
$100,000 j
Schoen Park Improvements*
Facilities
$80,000
Sea Level Rise Study*
Safety
$50,000
Storm Drain System CMP Upgrades*
Safety
$2,000,000
Traffic Signal Cabinet & Controller Upgrades 13/14
r Safet
$100,000
24 Pra'ects
$10,214,000
* - Unfunded
ATTACHMENT A
CITY OF SAN RAFAEL
CAPITAL IMPROVEMENT PROGRAM
(CIP)
FISCAL YEAR 2012/13 TO 2016/17
.1110311 i! f f
July 2, 2012
Page 1 of 51
CAPITAL IMPROVEMENT PROGrTk,4T,1'
FISCAL YEAR 2012113 TO 2016/17
Table of Contents
INDEX
Table of Contents
Capital Improvement Program Summary 3
City Owned Property (COP) 4
Drainage
Road Right of Way (RMI) 36
Traffic
0 i i
CAPITAL IMPROVEMENT PROGRAM
2012/13 - 2016/17
Fund 12/13 13/14 14/15 15/16 16/17
Category
Type
General Fund Total (CIP) = 1,188,633 200,000 200,000 200,000 5,700,000
Other Funding Total (CIP) = 365,000 2,150,000 1 280,000 _ 2_80,000 280,000
Total (CIP) = 465,000 2,250,000 380,000 380,000 380,000
Un -Funded =
GF General Fund Contribution
Other Funding from other sources - Grants. Refer to attached backup information
U46nided Currently Not Funded
Page 3 of 51
DEPARTMENT OF PUBLIC WORKS
CITY OWNED PROPERTY (COP)
The objective of projects listed in the "City Owned Properties" category is to provide safe, accessible
and workable facilities for the City Staff and members of the public. The City has more than 20
facilities which occupy more than 200,000 square foot of space. These facilities require consistent
attention. Projects identified in this area are intended to maintain and improve current infrastructure
that facilitates the best level of service possible to City employees and the General Public who utilize
these facilities. Projects listed herein also include parking structures.
PROJECTS COMPLETED
The following projects related to City Owned Property were completed in Fiscal Year 2011/12
Albert Park Lighting
Bernard Hoffman Park Handrails (ADA -DOJ)
Freitas Park Renovations Phase 11
Pickleweed Rodent Abatement and Electrical Repair
City Attorney's Office Improvements
Corporation Yard Fuel Island Lights
Falkirk Mansion Repainting
Terra Linda Community Garden
Lootens Parking Lot Improvements I
ACTIVE PROJECTS
The following projects are currently active projects related to City Owned Property.
City Hall HVAC Project
City Clerk Pass thru Project
Sea Way Bridge Replacement (Unfunded)
Bernard Hoffman Dugout Improvements
Santa Margarita Park c P-,-, Improvemenvemen
3rd St. & Cijos Parking Lot Reconstruction
5th St. & D St. Parking Lot Improvements
Improvements5th St, & Lootens Parking Lot
Summary of Proposed 2012/17 City Owned Property (COP) Projects Expenditures
#
Project Description
Status
Tune
11
12/13
13/14
14/15
15/16
16/17
GF
100,000 100,000
100,000
100,000
100,000
Emergency_ Facilities
Design &
-
Other *
— - --
- -
-
----------
-
-
1
Repair
Construction
Total
100,000 100 000
100,000
100,000
100.000
G -F
-
-
-
-
-
Design &
Other
120,000
-
-
2
Menzies Resurfacing
Construction
Tota(
-
120,000
-
-
-
GF
-
-
-
-
Design &
I Other
50,000
-
-
-
3-1--t
5th & Garden Resurfacing
Construction
Total
50,000
-
-
_-------
Parking Structure
Design & I
Other
-
200,000
4
Upgrade/Reply ment Study
Construction
Total
Summary of Proposed 2012/17 City Owned Property (COP) Projects Expenditures
Floorin Re la rnt Constructionl
--GF
--
- 175,000 -
#
Project Description
Status
Tune
12/13
13/14
14/15
15/16
16/17
City Hall Irrigation
Design &f)te
6
Improvements
Construction
Total
-
80,000
Up rades
-
-
-
100,000
JCity Building Solar Design &
t r
�GF
5 U rades (Study) ConstructionTotal
60,000
- -
-
Santa Margarita Park - Design &
City Owned Property (COP) General Fund Subtotal =
100,000
100,000
100,000
100,000
100,000
City Owned Property (COP) Other Fund Subtotal =
-
370,000
-
-
City Owned Property (COP) Total =
100,000
470,000
_-_
100,000
100,000
100,000
City Owned Property (COP) UN -Fund Subtotal
Pickleweed Synthetic Field Design &r=
4ti00,
10 Construction Construction
Total
#
Project Description
Status
Tune
12/13
13/14
14/15
15/16
16/17
Victor Jones Park Path of
Design &
550;
K_ogB Street Community Cente Design & l7,7
Floorin Re la rnt Constructionl
--GF
--
- 175,000 -
Schoen Park
Design &
tt er *
-
80x
City Hall Irrigation
Design &f)te
6
Improvements
Construction
Total
-
80,000
Up rades
-
-
K_ogB Street Community Cente Design & l7,7
Floorin Re la rnt Constructionl
--GF
--
- 175,000 -
— _
— - -
-
City Hall Irrigation
Design &f)te
X00,
8
Up rades
Construction
Total
-
100,000
-
Santa Margarita Park - Design &
er *'
X00`
9
Court Reconstruction Construction
Total
- 100,000
-
-
-
GF
Pickleweed Synthetic Field Design &r=
4ti00,
10 Construction Construction
Total
- 4,000,000
GF
Victor Jones Park Path of
Design &
550;
11
Travellmprrovernents
Construction
Total
- -
350,000--------------
-
-
GF
-
-
-
-
-
Boyd Park Accessibility
Design &250,010
tE-
12
Improvements
- - - - - - -
Construction
Total
-
-
---- ---
-
250,000
-----
-
- -- -
- --
GF
- -
-
-
Gerstle Park Playground
Design &
_.
100,
13
Improvements
Construction
- ----- ---
Total
---
- -
-
100,000
-
GF
_
_-
TLCC Play Area & Access
Design &
0,
14
Improvements
------
- Construction
Total
---
-
-
—--
-
130,000 -
man raage - -
ernar o �n
- GF --
-
-
-
----------------------- -
and Irrigation Design &
Other, *
X50 0
15
improvements Construction
Total
-
-
-
250,000 -
Peacock Gap Playground
Design &er`
j
16
Upgrades
Construction
tal
-
-
800,000 -
MMM
Summary of Proposed 2012117 City Owned Property (COP) Projects Expenditures
# T
Project Description Status Fund 12/13 13/14 14/15 15/16 16/17
ype
GF
t
City Building Lock System Design & 0
---------pgrade Construction T
jo,
800�0
191 __U 7 t
otal 60,0001
Total City Owned Property Unfunded 1 4,666 00f 3W,000f j;6:�*
[GIF General Fund Contribution
OEOther Funding from other sources -Grants. Refer to attached backup information
Ot
ther Currently Unfunded
Page 6 of 51
Emergency Facilities Repair
COP 1
1. Proiect Description and Background
This annual amount is set aside to address emergency repairs that are necessary for the more than
20 City buildings. This can include plumbing, roofing and other building related issues that cannot
be addressed by the Facilities Repair group.
2. Proiect Obiectives
Maintain the existing City Building Facilities.
3. Cost Estimate
Funded annually through the General Fund = $ 100,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13 13/14 14/15
15/16
16/17
General -Fund
Other Funds
100,000 100,000 100,000
- - -
100,000
-
100,000
-
Project Total =
100,000 100,000 100,000
100,000
100,000
Annual amount set aside for emergency building repairs.
Page 7 of 51
1. Proiect Description and Background
2.
Menzies Resurfacing
This project consists of resurfacing and improving the referenced parking facility
Provide safe and accessible parking facility.
3. Cost Estimate
Recommended Funding = $ 120,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/15
16/16
.16/17
Other
12 000
Parking Services funds are utilized for this project
1. Proiect Description and Backaround
2.
5th & Garden Resurfacing
Provide improvements toaccessibility for the referenced parking lot.
Provide safe and accessible parking facility.
3. Cost Estimate
Recommended Funding = $ 50,000
4. Basis of Estimate
Staff Estimated Previously bid.
Funding Source
12/13
13/14
14/16
15/16
16/17
Parking Services funds are utilized for this projec
WOTJIW
Page 9 of 51
Parking Structure Upgrade/Replacement Study
t Proiect Description and Backaround
2.
This project involves resurfacing an existing parking facility and improvements to accessibility.
Provide accessible public facilities.
3. Cost Estimate
Recommended Funding = $ 200,000
4. Basis of Estimate
Staff Estimated
Funding Source
12113
13/14
14/16
15/16
.16/17
General Fund
Parking Services
-
Project Total
200,000
Parking Services funds are utilized for this project
City Building Solar Upgrades (Study)
COP 5
1. Proiect Description and Background
This project consists of a study to examine all the City Facilities to determine if solar panels and other
solar treatments can be added to our facilities to decrease the City's greenhouse gas footprint.
2. Proiect Obiectives
Provide more energy efficient systems.
3. Cost Estimate
Recommended Funding = $ 60,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13 13/14
14/15
15/16
16/17
General Fund
tnfcted
- -
-
-
-
Total this Project =
60,000 -
-
-
-
Funding for this project has not been identified to date.
Page 11 of 51
Schoen Park Improvements
rOT�T.W^-,,
1. Proiect Description and Background
This project involves improvements to Schoen Park. Accessibility and access improvements should be
considered.
2. Proiect Objectives
Improve the City's Parks and replace old and antiquated play equipment.
3. Cost Estimate
Recommended Annual Funding = $ 80,000
4. Basis of Estimate
Staff Estimated Previously bid.
Funding Source
12/13
13/14
14/15
16/16
16/17
General Fund
Unfunded
U f nded
-
-
80,000
-
-
-
Total this Project
80,000
Currently unfunded.
Page 12 of 51
B Street Community Center Flooring Replacement
COP 7
1. Project Description and Background
The B Street Community Center is a heavily utilized facility and its flooring is experiencing distress and
is in need of replacement.
2. Project Objectives
Provide a safe facility for the public.
3. Cost Estimate
Recommended Funding = $ 175,000
4. Basis of Estimate
Staff Estimated
Funding Source 12/13
13/14 14/15
15/16
16/17
General Fund -
Unfunded
- -
175,000
-
-
Total this Project
175,000
Currently unfunded
Page 13 of 51
City Hall Irrigation Upgrades
1. Project Description and Background
The existing City Hall irrigation system has failed several time over the last few years. This project
provides for replacing a majority of the existing system
2. Project Obiectives
Minimize damage to the existing building by repairing damaged facilities and provide a focal point for
the City Hall for the community.
3. Cost Estimate
Recommended Funding = $ 100,000
4. Basis of Estimate
Staff Estimated
Funding Source 12/13
13114
14/15 15/16
16/17
General Fund -
Unfunded
-
100,000
- -
-
-
Total this Project = -
100,000
- -
-
Currently unfunded.
Page 14 of 51
GontayWargardoPark-Court Reconstruction
1. Proiect Description and Background
2.
This project involves the reconstruction nfthe tennis courts and providing additional 00000a
improvement within the park.
Improve Park access and increase usage.
3. Cost Estimate
Recommended Funding = $ 100,000
4. Basis of Estimate
Staff Estimated Previously bid.
Funding Source
12/13
13/14
14/16
15/16
16/17
General Fund
Unfunded
-
100,000
Total this Project
100,000
Funding has not been identified for this improvement.
Page 15 of 51
Pickleweed Synthetic Field Construction
COP 10
1. Project Description and Background
This project includes the installation of a synthetic field and various improvements to the field area at
Pickleweed Park. Plans for the field have been completed and the project is waiting funding.
2. Proiect Obiectives
Provide a safe and new playing field.
3. Cost Estimate
Design Completed in 2010 - Design Cost = $ 110,000
Recommended Annual Funding = $ 4,000,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13 13/14
14/15 15/16
16/17
General Fund
Unfu ded
- -
4,000,000
- -
-
-
Total this Project =
- 4,000,000
- -
-
Supplemental grant funds have not been identified at this time; however staff will continue to aggressively
pursue grant funding.
Page 16 of 51
Victor Jones Park Path of Travel Improvements
COP 11
1. Prolect Description and Background
Provide accessibility improvements to Victor Jones Park.
2. Project Objectives
Improve the City's Parks and provide compliant paths of travel for the public.
3. Cost Estimate
Recommended Funding = $ 350,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/15
16/16
16/17
General Fund
Unfunded
-
-
-
350,000
-
-
Total this Project
350,000
Supplemental grant funds have not been identified at this time; however staff will continue to aggressively
pursue grant funding.
Page 17 of 51
Boyd Park Accessibility Improvements
FSTOOM
1. Proiect Description and Backaround
Accessibility and other improvements are necessary at Boyd Park. This project scheduled for 2014/15
addresses these concerns
2. Pro*ect Objectives
Provide accessible public facilities.
3. Cost Estimate
Recommended Funding = $ 250,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13114
14115
15/16
16/17
General Fund
Unfunded
-
-
-
-
250,000
-
Total this Project
250,000
Supplemental grant funds have not been identified at this time; however staff will continue to aggressively
pursue grant funding.
Page 18 of 51
Gerstle Park Playground Improvements
1. Proiect Description and Background
This project involves improvements to Gerstle Park Playground Equipment
2. Project Obiectives
Improve the City's Parks and replace old and antiquated play equipment.
3. Cost Estimate
Recommended Annual Funding = $ 100,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14 14/15
15/16
16117
General Fund
Unfunded
-
- -
-
100,000
-
Total this Project
100,000
Supplemental grant funds have not been identified at this time; however staff will continue to aggressively
pursue grant funding.
Page 19 of 51
TLCC Play Area & Access Improvements
COP 14
1. Proiect Description and Background
Access to the Terra Linda Community Center currently does not meet current code requirements. This
project would address a portion of these concerns.
2. Project Objectives
Improve access for the general public.
3. Cost Estimate
Recommended Funding = $ 130,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14 14/15 15/16
16/17
General Fund
Unfuded
-
-
- - -
130,000
-
Total this Project =
-
- - 130,000
-
Supplemental grant funds have not been identified at this time; however staff will continue to aggressively
pursue grant funding.
Page 20 of 51
Bernard Hoffman Drainage and Irrigation Improvements
1. Proiect Description and Background
Bernard Hoffman Park located in Terra Linda has several drainage and irrigation issues. This project
will identify the issues and implement modification to the park.
2. Proiect Obiectives
Minimize flooding and drainage issues as well and improve the existing drainage system.
3. Cost Estimate
Recommended Funding = $ 250,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/15
15/16
16/17
General Fund
Unfunded
-
-
-
-
250,000
-
Total this Project =
-
-
-
250,000
-
Supplemental grant funds have not been identified at this time; however staff will continue to aggressively
pursue grant funding.
Page 21 of 51
Peacock Gap Playground Upgrades
1. Proiect Description and Background
Peacock Gap Park's playground equipment is old and is in need of replacement. This upgrade project
will address modifications and accessibility issues.
2. Proiect Objectives
Provide updated play equipment for the community.
3. Cost Estimate
Recommended Funding = $ 800,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/15
15/16
16/17
General Fund
Unfunded
-
-
-
-
800,000
-
Total this Project
800,000
Supplemental grant funds have not been identified at this time; however staff will continue to aggressively
pursue grant funding.
Page 22 of 51
City Library Carpeting Replacement
1. Project Description and Background
This project consists of replacing the carpeting in the City Library. The existing carpet is unraveling and
may be a tripping hazard if not addressed.
2. Project Objectives
Provide safe services for the general public
3. Cost Estimate
Recommended Funding = $ 80,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13114
14/15
16/16
16117
General Fund
Unfunded
-
-
80,000
-
-
-
Total this Project
80,000
Funding for this project has not been identified to date.
Page 23 of 51
1. Proiect Description and Background
2.
Fire Station Generator
This project consists nfreplacing the generator system atFire Station 1which ioobsolete.
Provide alternative power source for essential service during emergencies.
3. Cost Estimate
Recommended Funding = $ 60,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/15
16/16
16/17
Unfunded
60,000
Total this Project
60,000
Funding for this project has not been identifiedto date.
CDP 18
Page 24 of 51
City Building Lock System Upgrade
1. Proiect Description and Background
2.
This project consists of replacing the existing lock system at the City Hall with Electronic locks and
proximity cards for employees.
Provide a secure lock system for the City.
3. Cost Estimate
Recommended Funding = $ 60,000
4. Basis of Estimate
Staff Estimated
Fundin_q Source
12/13 13/14
14/15
15/16
16/17
Unfunded
60,000
Total this Project
60,000
Funding for this project has not been identified todate. This project will improve the security control ofthe
City facilities such that remote operation and control is possible.
Page 25 of 51
DEPARTMENT OF PUBLIC WORKS
DRAINAGE
The objective of projects listed in the "Drainage" category is to provide safe and adequate drainage systems for the City
of San Rafael. The City has 12 Storm Water Pump Stations and extensive network of drainage culverts and open
channel facilities to control storm water. Projects identified in this area are intended to maintain and improve current
infrastructure that facilitates the best level of service possible and minimize flooding.
PROJECTS COMPLETED
(San Quentin Marsh Pump Station Repairs
832 Tamarack Drainage Improvements
H Street Drainage Improvements & Roadway Reconstruction (Unfunded)
1400 Canal Street Pump Station Repair
Corporate Center Pump Station Underground Connection
Summary of Proposed Drainage Projects and Expenditures
# Project Description Status Fund Type 12/13 13/14 14115 15/16 16117
GF
Miscellaneous Storm Drain, Slide Design & Other 100,000 100,000 100,000 100,000 100,000
1 Repair Projects Construction Total 100,0001 100,000 100,0001 100,000 100,000
-- GF--
Happy Lane Storm Drain Design & Other 10,000
2 — Abandonment Construction LTotal 1 10,000 -
Page 26 of 51
Marin County Storm Water Pollution
Design &
Other
80,000
80,000
80,000
80 000 80,000
3 Protection Program (MCSTOPPP)
Construction
I Total80
000
80,000
80 000 1
80,000 80,000
General Fund Subtotal (Drainage)
=-
Other Funding Subtotal (Drainage)
=
190,000
180,000
180,0001
180,000
180,000
Total (Drainage)
=
190,000
180,000
180,000
180.000
180 000
# Project Description Status
I Fund 1
12/13 1
13/14 1
14/15 1
15/16 116/17
Design &
tc��—
120000 '
S�t(i0ttRossi
Pump Station
Construction
120,000
550,000
1
-
--
GF
-
Design &
father * '
- "
80;000'
_ i
w
5
North San Rafael Watershed Study
Construction
Total
80,000
----------------
--------Storm
GF*
Storm Drain System CMP Design &
2001
2000
"000
6
Replacement/Upgrades Construction
Total T
2,000,0001
2,000,000
00
2,000,0OOQ000
T 2,
------ -- ----
-
-
Design &
90-1ry0
7
Sea Level Rise Study
Construction
Total50,000
--
-
- --
—
GF
Design &
.."
0101 i
_ . ;
8 _
FEMA Updates
- -p
Construction
—
Total
---
60,000
60,000
---
-
- --
-
GF-
Design &
�'
Z0, i3
941-
City Levee Study
Construction
Tota(
60.000
Unfunded Total (Drainage) _
" " 1ii)00 .:
2,310,000 ""
2,50,ti0i}
2x000, 2,000;
17 GF General Fund Contribution
Other IFunding from other sources - Grants. Refer to attached backup
information
er* ` Currently Unfunded
Page 26 of 51
Miscellaneous Storm Drain, Slide Repair Projects
1. Proiect Description and Background
This annual amount is set aside to address storm damage related repairs for drainage facilities,
slides and various drainage related issues.
2. Proiect Objectives
Maintain the existing drainage systems throughout the City and provide a funding mechanism for
repair slides and damages related to storms.
3. Cost Estimate
Funded annually= $ 100,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/15
15/16
16/17
General Fund
Other
-
100,000
-
100,000
-
300,000
-
300,000
-
300,000
Total =
100,000
100,000
300,000
300,000
i 300,000
Funding for this project in each fiscal year is supported by the annual Storm Water Fee.
Happy Lane Storm Drain Abandonment
1. Pro*ect Description and Backaround
2.
This project consists of backfilling and abandoning anexisting culvert system that has been
bypassed with the installation of the Happy Lane Drainage Systems several years ago.
Provide safe and adequate drainage facilities within the City.
3. Cost Estimate
Funded annually= $ 10.000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/15
15/16
16/17
Other
10,000
Total
10,000
This project is funded from the City's Storm Water fees
Marin County Storm Water Pollution Protection Program (MCSTOPPP)
MM
1. Proiect Description and Background
This project consists of complying with the latest requirements from the State Regional Water Quality
Control Board. These regulations are more stringent requiring testing.
2. Proiect Objectives
Provide safe and adequate drainage facilities within the City in compliance with State and Federal
Standards.
3. Cost Estimate
Funded annually = $ 80,000
4. Basis of Estimate
Staff Estimated
Source
GeneralFunding
.
Otherno
K.-Tell11
�•
�1 111'
:1 111
-MMK :1 111
It is anticipated that additional testing of construction sites and drainage outfall will be required
with the adoption of the latest Regional Water Quality Control Permit for our County.
Rossi Pump Station
1. Proiect Description and Background
iW
Rossi Pump Station is an older facility and is in need of structural repairs to the facility. Currently this
project is ready to construct with a plan in had for the work.
2. Proiect Obiectives
Provide adequate drainage facilities to minimize flooding to the City.
3. Cost Estimate
Construction Estimate = $ 670,000
4. Basis of Estimate
The Engineer's Estimate prepared by CSW Stuber Stroeh is 670,000 including contingency.
This project is recommended to be deferred to future years due to budgetary shorfalls. Original
funding has been moved to higher priority projects.
Page 30 of 51
North San Rafael Watershed Study
1. Proiect Description and Background
2.
This project is a collaborative project with the County of Marin to study and examine the North San
Rafael Watershed to determine if environmental improvements can be made to the current system.
Improve the City's waterways and streams.
3. Cost Estimate
Initial Study Cost = $ 80,000
4. Basis of Estimate
Staff Estimated
The initial study isanticipated hnidentify future improvements. Future estimated costs for these
improvements are identified above.
Page 31 of 51
Storm Drain System CMP Replacement/Upgrades
MW
1. Project Description and Background
Repair of deteriorated storm drainage culverts throughout the City.
2. Project Objectives
Improve the existing drainage facilities and prevent culvert collapses that can expand to roadway
failures and hazards.
3. Cost Estimate
Recommended Annual Funding = $
4. Basis of Estimate
Staff Estimated
Funding Source
Offe"Iffil "NOMM
MMMMMMMMM
MMNTITMRWI�.��
This project was identified in 2010 by the Public Works Director as a significant hazard to the general
public that needs to be addressed before additional deterioration is incurred.
Page 32 of 51
Sea Level Rise Study
1. Project Description and Background
This project involves working with regulatory agencies to determine the impacts that are predicted to
occur due to sea level rise.
2. Project Objectives
Provide safe and adequate drainage facilities within the City.
3. Cost Estimate
Estimated Study Cost $ 50,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13114
14/16
15/16
16/17
General Fund
Ott t
Othej
-
-
$0,000
-
-
-
Total
50,000
This project is currently not funded.
Page 33 of 51
FEMA Updates
1. Project Description and Background
FDIW.
This project involves working with the Federal Emergency Management Agency to update the
community regarding the new maps that FEMA will be producing. Many public meetings and much
staff time required for this project.
2. Project Obiectives
Provide public information.
3. Cost Estimate
Estimated Study Cost $ 60,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/16
15/16
16117
General Fund
-
-
-
-
-
Total =
60,000
60,000
This project is currently not funded.
City Levee Study
1. Project Description and Back -ground
This projects involves reviewing all City Levee systems to determine what measures need can be
implemented to deter flooding,
2. Proiect Objectives
Provide public information.
3. Cost Estimate
Estimated Study Cost $ 60,000
4. Basis of Estimate
Staff Estimated
Fundinq Source
12/13 13/14
14/15
15/16
16/17
General Fund
—6t67er—*
- -
-
-
-
Total =
60,000
This project is currently not funded.
MW
Page 35 of 51
DEPARTMENT OF PUBLIC WORKS
RIGHT-OF-WAY
The objective of projects listed in the "Road Right -of -Way" category is to provide safe and adequate road systems for
the incorporated area of the City of San Rafael. The City has over 177 miles of roadway and 86 traffic signals. Projects
identified in this area are intended to maintain and sometimes improve current infrastructure that facilitates the best level
of service possible for the traveling public.
COMPLETED PROJECTS (2011/12)
RepairsAndersen/Dubois Street
Freitas Avenue Resurfacing
Las Gallinas Avenue Resurfacing
Safe Pathways to School Woodland
Citywide Street Resurfacing 2010/11
Lifeline Cycle 1 Canal Pedestrian & Transit Improveme
Olive & Acacia Road Reconstruction I
ACTIVE PROJECTS
ADA -DOJ Curb Ramps 2011/12
ADA -DOJ Curb Ramps 2012/13
Citywide Street Resurfacing 2012
Downtown Bicycle Parking Installation
Downtown Pavement Safety Improvements
Grand Avenue Pathway Connector Project
Lifeline Phase 2 - Canal and Kerner Pedestrian & Transit Improvements
NTPP Mahon Creek Path to Transit Connector Project
NTPP Porto Suello Path to Transit Connector Project
Safe Routes to School - Coleman
Safe Routes to School - Davidson
SMART
Citywide Street Resurfacing Curb Ramps 2012
Point San Pedro Resurfacing
Point San Pedro Median Landscaping Improvements
NTPP-Francisco Blvd, East Improvements
Downtown Pavement SafetyImprovements
Summary of Proposed Road Right -of -Way Projects Expenditures (FY12/17)
# Project Description Status Tune 12/13 13/14 14/15 15/16 16/17
Page 36 of 51
GF
-
-
-
-
©
Design &
-Other
100,000
_
100,000
100,000
100,000 100,000
1
Miscellaneous Right of Way
Construction
Total
100,000
100,000
100.000
100,000 100.000
Page 36 of 51
-Downtown
©
Pavement Safe
Design &
s
•• ��t
MMMM
City Bridge Repair Proqra�
Construction
•
•• it•
-
-
Page 36 of 51
-Downtown
©
Pavement Safe
�-
s
•• ��t
MMMM
-e -
Resurfacing • ►i
• r
•
•• it•
-
-
Page 36 of 51
-Downtown
Pavement Safe
Desi n &
g
r
hm
120,0404
_tY
Im rovements
Constructionota{
120.000
-
-
Page 36 of 51
Summary of Proposed Road Right -of -Way Projects Expenditures (FYI 2/17)
# Project Description Status Tune 12/13 13/14 14115 15/16 16/17
General Fund Subtotal (Road RNV) _ - - - -
Other Funding Subtotal (Road RNV) = 974,000 100,000 100,000 100,000 5,600,000
Total (Road RNV) = 974,000 100,000 100,000 100,000 5,600,000
# Project Description Status Tune 12/13 13/14 14115 15/16 16/17
GF - - - - -
Brookdale Avenue Retaining Design & "Other
r �
8 wall Construction Total - 250,000 _
GF
- -
-
- -
Street Resurfacing Curb Ramps
Design &Other
Design &
Other
- -
-
- 5,500,000
5
Aerial Undergrounding
Construction
Total
- -
-
- 5,500,000
General Fund Subtotal (Road RNV) _ - - - -
Other Funding Subtotal (Road RNV) = 974,000 100,000 100,000 100,000 5,600,000
Total (Road RNV) = 974,000 100,000 100,000 100,000 5,600,000
# Project Description Status Tune 12/13 13/14 14115 15/16 16/17
GF - - - - -
Brookdale Avenue Retaining Design & "Other
r �
8 wall Construction Total - 250,000 _
GF
I -
1
Street Resurfacing Curb Ramps
Design &Other
250,000
- - -
6
2012/13
Construction
Total 250,0001
-
_
- - -
General Fund Subtotal (Road RNV) _ - - - -
Other Funding Subtotal (Road RNV) = 974,000 100,000 100,000 100,000 5,600,000
Total (Road RNV) = 974,000 100,000 100,000 100,000 5,600,000
# Project Description Status Tune 12/13 13/14 14115 15/16 16/17
GF - - - - -
Brookdale Avenue Retaining Design & "Other
r �
8 wall Construction Total - 250,000 _
GF
I -
1
-
-
Design &
Other
-
75,000
-
-
77 -
7
Parks Pathways ResurfacingConstruction
Total
-
75,000
-
-
-
General Fund Subtotal (Road RNV) _ - - - -
Other Funding Subtotal (Road RNV) = 974,000 100,000 100,000 100,000 5,600,000
Total (Road RNV) = 974,000 100,000 100,000 100,000 5,600,000
# Project Description Status Tune 12/13 13/14 14115 15/16 16/17
GF - - - - -
Brookdale Avenue Retaining Design & "Other
r �
8 wall Construction Total - 250,000 _
M
I GF
Design &_ *;
Construction Total
Un -Funded (Road RNV) _
GF General Fund Contribution
Other Funding from other sources -Grants. Refer to attached backup information
Other * Currently Not Funded
Page 37 of 51
GF
- - - -
-
Design &t
9
Bungalow Ave Reconstruction
Construction
Total
- 650,000 - -
-
M
I GF
Design &_ *;
Construction Total
Un -Funded (Road RNV) _
GF General Fund Contribution
Other Funding from other sources -Grants. Refer to attached backup information
Other * Currently Not Funded
Page 37 of 51
Miscellaneous Right of Way
1. Promect Description and Back -ground
2.
in�
Curb and Gutter repairs and replacements including sidewalks sdvarious locations throughout the
City.
Improve accessibility for the public and minimize hazards.
3. Cost Estimate
Funded annually= $ 100,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/15
16116
16/17
Gas Tax
100,000
100,000
100,000
100,000
100,000
Total this Project
100,000
- 100,000
100,000
100,000
100,000,
Gas Tax, Measure /\ and Vehicle Impact Fees support this budget center and the referenced
City Bridge Repair Program
1. Project Description and Background
Repair existing bridges maintained by the City as identified by the State of California's annual inspection
2. Proiect Obiectives
Maintain the City's existing infrastructure.
3. Cost Estimate
Preliminary Engineer's Estimate $ 135,000
4. Basis of Estimate
Funding Source
12/13
13/14
14/16
15/16
16/17
General Fund
Other Funding
-
135,000
-135,000
Total this Project =
1
A total of 4 City Maintained bridges were identified as needing improvements. The improvements
range from deck treatment to foundation improvements. The complexity of the repair will depend
on man factors including but not limited to permitting, traffic control and many others.
Street Resurfacing 2012/13
R/W 3
1. Project Description and Background
This project consists of resurfacing various streets throughout the City. The severity of the street
condition based on each Streets Pavement Condition Index and engineering review determines which
streets are to be resurfaced based on the budget available.
2. Proiect Obiectives
Improve the existing pavement condition, access and safety aspects of the City's infrastructure.
3. Cost Estimate
Engineer's Estimate = $ 369,000
4. Basis of Estimate
Funding Source
12/13
13/14
14/15
15/16
16/17
General Fund
Other Funding
-
369,000
-
-
-
-
-
-
-
-
Total this Project =
369,000
-
-
-
-
This project is funded through Gas Tax. The project is generally designed in house with
general assistance for construction inspection.
Page 40 of 51
Downtown Pavement Safety Improvements
1. Prolect Description and Backaround
2.
Grind and resurface several areas within highly traveled City roads with pavement raveling issues and
undulations.
Maintain the City's existing infrastructure
3. Cost Estimate
Engineer's Estimate = $ 120.000
4. Basis of Estimate
Engineer's Estimate
Fundina Source
12/13
13/14
14/16
15/16
16/17
Other Funding
120,000
Total this Project
120,000
This project issupported through Gas Tax, Measure A.and the Vehicle Impact Fee's collected
annually.
Page 41 of 51
Aerial Undergrounding
RAN 5
1. Proiect Description and Background
Underground existing aerial utilities along a main City corridor.
2. Project Objectives
Provide a safer and healthier environment for residents of the City.
3. Cost Estimate
Funded annually through the General Fund = $ 5,500,000
4. Basis of Estimate
Engineers Estimate
Funding Source 12/13
13/14 14/15
15/16
16/17
General Fund
Rule 20A Funding
-
-
-
-
5,500,000
Total this Project = -
- -
-
5,500,000
This is a Rule 20A project supported by funds accumulated by PG&E to underground facilities
within the City.
Page 42 of 51
Street Resurfacing Curb Ramps 2012/13
•Gid
1. Project Description and Background
This project consists of installing curb ramps on the streets that are scheduled to be resurfaced this
year in compliance with current accessibility standards
2. Proiect Obiectives
Provide accessible access along City streets.
3. Cost Estimate
Total Project Budget Estimate $ 250,000
4. Basis of Estimate
Engineer's Estimate
Funding Source
12/13
13/14
14/15
15/16
16/17
General Fund
-
-
-
-
-
Other Funding
250,000
-
-
-
-
Total this Project =
250,000
-
-
-
-
Gas Tax currently funds this project.
Page 43 of 51
Parks Pathways Resurfacing
�1
1. Project Description and Background
This project consists of resurfacing a portion of the City's bicycle paths that have deteriorated to a point
that they are now a safety concern. The actual locations of the repairs will be determined at upon
review by staff.
2. Project Obiectives
Provide accessible access along City pathways
3. Cost Estimate
Total Project Budget Estimate $ 75,000
4. Basis of Estimate
Engineer's Estimate
Funding Source
12/13
13/14
14/15
15/16
16/17
General Fund
Other Funding
-
-
-
75,000
-
-
-
-
-
-
Total this Project =
-
75,000
-
-
-
Gas Tax currently funds this project.
Page 44 of 51
1. Proiect Description and Backaround
2.
BmokdaleAvenue Retaining Wall
RM 8
This project consists ofrepairing aslide adjacent 0oBmukdaleAvenue. The projects involves work within anexisting
creek such that there may bainvolvement with regulatory agencies.
Repair the existing road and prevent future erosion and sliding caused by the creek.
3. Cost Estimate
Engineers Estimate = $ 250,000
4. Basis of Estimate
Engineer's Estimate
Funding Source
12/13
13114
14/15
16/16
16/17
General Fund
Other Fu
250,000
Total this Project
250,000
This project is currently unfunded.
Page 45 of 51
Bungalow Ave Reconstruction
1. Project Description and Background
Reconstruction of Bungalow street from Woodland to Picnic. Work includes the reconstruction of a
failing drainage systems as well as removing older style curb and gutter to provide access to adjacent
properties.
2. Proiect Objectives
Provide a safer and healthier environment for residents of the City.
3. Cost Estimate
Total Project Budget Estimate $ 650,000
4. Basis of Estimate
Engineer's Estimate
Funding Source
12/13
13/14
14/15
15116 .16/17
General Fund
Other Funding
-
-
650,000
-
- -
Total this Project
650,000
This project is currently partially funded such that there is insufficient funding to complete.
1. Proiect Description and Background
2.
Mahon Path Landscaping
The pathway long Mahon Creek is sparse and it is anticipate that improvements to the landscaping will
be needed.
Provide improved landscaping
3. Cost Estimate
Recommended Funding = $ 250,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14
14/16
15/16
J 6/17
Unfunded
250,000
Total this Project
250,000
Supplemental grant funds have not been identified at this time; however staff will continue to aggressively
pursue grant funding.
Page 47 of 51
DEPARTMENT OF PUBLIC WORKS
TRAFFIC
The objective of projects listed in the "Traffic" category is to provide safe traffic facility systems for the City of San
Rafael. The City has over 86 traffic signals and over 4,400 street lights. Some of these systems are antiquated such
that maintenance of these facilities is difficult. Projects identified in this area are intended to maintain and improve
current infrastructure facilitates to the best level of service possible and improve safety.
Traffic Cabinet Signal & Controller Upgrades 2011/12
LED Street Lighting Retrofits
Puerto Suello Multiuse Pathway Security Cameras
Summary of Proposed Traffic Projects Expenditures
# Project Description Status Type 12/13 13/14 14115 15/16 16117
GF
C 1
Traffic Cabinet 2 12i1 !ler Upgrades DesiConstruction gOther
otal 100,0001 100,000 100,000 100,000 100,000
Freitas/Las Gallinas Intersection
Improvements
Design &
General Fund Subtotal (Traffic) _ _ _
Other Funding Subtotal (Traffic) = 175,000 1,600,000 100_000 100,000 100_000
Total (Traffic) = 175,000 1,600,000 100,000 100_000 100,000
GF General Fund Contribution
Other Funding from other sources -Grants. Refer to attached backup information
Otl1er- Currently Unfunded
GF -
- - - -
Design &
---
Other 75,000
----- --
2
Ramp Metering Study_
Construction
Total 75,000
Freitas/Las Gallinas Intersection
Improvements
Design &
General Fund Subtotal (Traffic) _ _ _
Other Funding Subtotal (Traffic) = 175,000 1,600,000 100_000 100,000 100_000
Total (Traffic) = 175,000 1,600,000 100,000 100_000 100,000
GF General Fund Contribution
Other Funding from other sources -Grants. Refer to attached backup information
Otl1er- Currently Unfunded
Traffic Cabinet Controller Upgrades 2012/13
1. Proiect Description and Background
This project consists of upgrading older traffic controller equipment to meet current standards
2. Puerto Suello Multiuse Pathway Security Camera
Provide safer and improved signal systems within the City.
3. Cost Estimate
Recommended Funding = $ 100,000
4. Basis of Estimate
Staff Estimated - Grant Amount Available
Funding Source
12/13 13/14 14/15
15/16
16/17
General Fund
Other
- - -
100,000 100,000 100,000
-
100,000
-
100,000
Total this Project =
100,000 100,000 100,000
100,000
100,000
This project is funded by Gas Tax?
Page 49 of 51
Ramp Metering Study
1. Project Description and Background
IIWJ
This project is initiated by the State of California to study the effect of installing ramp metering systems
on the on ramps for City Streets that have access to the Highway system.
2. Puerto Suello Multiuse Pathway Security Camera
Provide a safer Highway system, work collaboratively with the State.
3. Cost Estimate
Recommended Funding = $ 75,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13 13/14 14/15
15/16
16/17
General Fund_
Other
- - -
75,000
-
-
Total this Project =
75,000 - -
-
-
This project is funded by Gas Tax.
Page 50 of 51
Freitas/Las Gallinas Intersection Improvements
T 3
1. Project Description and Background
This project consists of widening the Intersection of Las Gallinas and Freitas Parkway. In particular the
left turn pocket onto Las Gallinas from Freitas Parkway heading south should be expanded to
accommodate the current traffic. This work also involves work over a creek.
2. Puerto Suello Multiuse Pathway Security Camera
Provide a safe roadway systems at this intersection.
3. Cost Estimate
Recommended Funding = $ 1,500,000
4. Basis of Estimate
Staff Estimated
Funding Source
12/13
13/14 14/15
15/16
16/17
General Fund
Other
-
-
- -
1,500,000 -
-
-
-
-
Total this Project =
-
1,500,000 -
-
-
This project currently supported by traffic mitigation fees.
Page 51 of 51
CITY OF SAN RAFAEL
i1q,wff 11 1 lk -kvii
A 1 1 1
INSTRUCTIONS: USE THIS FORM WITH EACH SUBMITTAL OF A CONTRACT, AGREEMENT,
ORDINANCE OR RESOLUTION BEFORE APPROVAL BY COUNCIL / AGENCY.
SRRA / SRCC AGENDA ITEM NO. S`� -
DATE OF MEETING: 7/2/2012
FROM: Nader Mansourian
DEPARTMENT: Public Works
DATE: 6/26/12
TITLE OF DOCUMENT:
ACCEPT REPORT APPROVING THE UPDATE OF SAN RAFAEL'S 5 -YEAR CAPITAL IMPROVEMENT
PROGRAM FOR FISCAL YEARS 2012/2013 THROUGH 2016/2017 AND AUTHORIZING THE
REPROGRAMMING OF SPECIFIC CAPITAL PROJECTS TO SUBSEQUENT YEARS
Department Head (signature)
(LOWER HALF OF FORM FOR APPROVALS ONLY)
APPROVED AS COUNCIL AGENCY APPROVED AS TO FORM:
AGENDA ITEM:
City Manager (signature) City Attorney (signature)
09119NNUMM
File No.: 01.02.49