HomeMy WebLinkAboutPW St. Resurfacing Curb Ramps 2012; NOC Recordedin J®r '.14i. ' Agenda Item No: 3.g Meeting Date: November 5, 2012 1 SAN RAFAEL CITY COUNCIL AGENDA REPORT Department: Public Works Prepared by: City Manager Director of Public Works (LB) File No. 16.01.263 SUBJECT: ACCEPT COMPLETION OF THE CITYWIDE STREET RESURFACING 2012 CURB RAMPS, CITY PROJECT NO. 11204, AND AUTHORIZE THE CITY CLERK TO FILE THE NOTICE OF COMPLETION. RECOMMENDATION: Staff recommends that the City Council accept completion of the project and authorize the City Clerk to file the Notice of Completion. BACKGROUND: In June 2012, the City of San Rafael procured funding from Caltrans for roadway rehabilitation of approximately 3.1 miles of City streets. The following roadway segments will be resurfaced within the next year: ■ Fifth Avenue from B Street to H Street; ■ Bellam Boulevard from Woodland Avenue (City Limits) to 1-580 Ramps; ■ Bellam Boulevard from Kerner Boulevard to Windward Way; ■ D Street from Antonette Avenue to Second Street; and ■ Mission Avenue from Union Street to H Street. Current Americans with Disabilities Act (ADA) design standard mandates that altered (i.e. resurfaced) roads must include curb ramps or sloped areas at any intersection to provide access for pedestrians. Therefore, in anticipation of resurfacing the above noted streets, this project includes installation of 15 new compliant curb ramps, two driveways at Falkirk Cultural Center, a sidewalk extension on Bellam Boulevard at Vista Del Mar, and storm drainage improvements. The design of the project was completed by City of San Rafael Department of Public Works engineering staff. On May 21, 2012, the City Council adopted the plans and specifications. The project was advertised in accordance with the City of San Rafael's Municipal Code and policies on May 25, 2012. Bids were opened on June 14, 2012 at 10:00 AM and read aloud. On July 2, 2012, the City Council adopted a resolution authorizing the Public Works Director to enter into an agreement with the low bidder, Fieldstone Construction Company, and construction commenced on July 30, 2012. FOR CITY CLERK ONLY File No.: -1-G-2>L4 Council Meeting: Disposition: SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2 PROJECT UPDATE: Construction was completed on October 5, 2012. Due to the controversy of the tree removals included in the original project plans, the removal of the trees and installation of the ramp on the southwest comer of the intersection of D Street and Taylor Street was postponed to a point where it had to be removed from the construction contract. The City has therefore hired another contractor (Ghilotti Construction Company) to perform the removal of tree and install a new curb ramp at this location. The cost for this additional work is $17,900.00. The total construction cost, including utility relocations and reimbursable work for private property owners and including the cost for the second contract for the installation of the D/Taylor Curb Ramp is $219,590.42; after reimbursement for the utility and private property work, the total City cost is $211,824.42. This amount falls below the originally authorized construction budget of $250,000.00. PROJECT SUMMARY: Category Amount Construction July 2, 2012 Contract Amount based on Estimated Quantities $214,372.50 Actual Contract Amount based on Measured Quantities* $201,079.50 Additional Construction Contract for D/Taylor Curb Ramp $17,900.00 Change Orders* $610.92 Subtotal* $219,590.42 Anticipated Reimbursements from Utility Companies and Private Property Owners -7,766.00 Total Construction Cost T $211,824.42 *Includes the 5% retention to be paid 35 days after Notice of Completion is filed. The following summarizes the project milestones and working days: Working Item Date Days y Date of Contract July 2, 2012 Date of Notice to Proceed July 23, 2012 Construction Work Commencement July 30, 2012 - All Work Complete October 5, 2012 49 Working Days Allowed by Contract 30 Working Days Allowed by Change Order 12 Working Days Allowed by Extension 7 Non -Working Days Due to Weather 0 Actual Working Days Allowed 49 All work was completed within the amount of working days specified. We recommend acceptance of the project and recordation of a Notice of Completion. ANALYSIS: Pursuant to Civil Code Section 3093 the City, owner of the improvements, is required to record a Notice of Completion upon acceptance of the improvements by the City. This acceptance initiates a time period during which project sub -contractors may file Stop Notices seeking payment from the City out of the funds owed to the Contractor for the project work. SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 3 ACTION REQUIRED: Accept completion of the Citywide Street Resurfacing 2012 Curb Ramps, City Project No. 11204, and authorize the City Clerk to file a Notice of Completion. Enclosures: Notice of Completion Ail When recorded mail to: City of San Rafael Esther C. Beirne, City Clerk 1400 Fifth Avenue P. O. Box 151560 San Rafael, CA 94915-1560 20 1 2-00700 1 5 Recorded Official Records County of Marin RICHAIRD N. fish/SON Assessor -Recorder County Clerk 01:52PM 07 -Nov -21012 I REC FEE 0.00 a Page 1 of 1 SPACE ABOVE THIS LINE FOR RECORDER'S USE CITY OF SAN RAFAEL NOTICE OF COMPLETION OF IMPROVEMENT TO ALL PERSONS WHOM IT MAY CONCERN: NOTICE IS HEREBY GIVEN for and on behalf of the City of San Rafael, County of Marin, State of California, that there has been a cessation of labor upon the work or improvement and that said work or improvement was completed upon the 5th day of October, 2012 and accepted the 5th day of November 2012; that the name, address and nature of the title of the party giving this notice is as follows: The City of San Rafael, a municipal corporation, in the County of Marin, State of California, within the boundaries of which said work or improvement was made upon land owned by said City and/or over which said City has an easement; that said work or improvement is described as follows: CITYWIDE STREET RESURFACING 2012 CURB RAMPS CITY PROJECT #11204 and reference is hereby made for a further description thereof to the plans and specifications approved for said work or improvements now on file in the office of the City Clerk of said City, and said plans and specifications are hereby incorporated herein by reference thereto; and that the name of the Contractor who contracted to perform said work and make such improvement is FIELDSTONE CONSTRUCTION COMPANY I declare under penalty of perjury that the foregoing is true and f correct. Executed at San Rafael, California, on11W, % 201z.If - CITY OF SAN RAFAEL A Municipal Corporation 41� . By NADER MANSOURIAN Public Works Director STATE OF CALIFORNIA COUNTY OF MARIN On this 7;6k day of 20 (7, before me, Jeanne M. Leoncini, Deputy City Clerk of the City of Sari Rafael, County of Marin, State of California, residing therein, personally appeared NADER MANSOURIAN, (or proved to me on the basis of satisfactory evidence) to be the person whose name is subscribed to the within instrument and acknowledged to me that he executed the same in his authorized capacity, and that by his signature on. the instrument the person, or the entity upon behalf of which the person acted, executed the instrument. WITNESS my hand and official seal. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. • Signature NNE'11I.S,E01`cTCtI11D�uty City Clerk File: 16.01.263 Z] ORIGINAL CITY OF SAN RAFAEL INSTRUCTIONS: USE THIS FORM WITH EACH SUBMITTAL OF A CONTRACT, AGREEMENT, ORDINANCE OR RESOLUTION BEFORE APPROVAL BY COUNCIL / AGENCY. SRRA / SRCC AGENDA ITEM NO. -3g. DATE OF MEETING: 11/5/2012 FROM: NADER MANSOURIAN 191:19-11 Oat I LTA 1:42 DATE: 10/26/12 TITLE OF DOCUMENT: ACCEPT COMPLETION OF THE CITYWIDE STREET RESURFACING 2012 CURB RAMPS, CITY PROJECT NO. 11204, AND AUTHORIZE THE CITY CLERK TO FILE THE NOTICE OF COMPLETION. Department Head (signature) (LOWER HALF OF FORM FOR APPROVALS ONLY) APPROVED AS COUNCIL / AGENCY AGENDA ITEM: AA rWA IAJ City Manager (signature) APPROVED AS TO FORM: City Attorney (signage) 2154041aff-wellKW.