HomeMy WebLinkAboutCC Resolution 13862 (Housing Element Addendum)RESOLUTION NO. 13862
RESOLUTION OF THE SAN RAI' AEL CITY COUNCIL ADOPTING ADDENDUM
NO. 3 TO THE CERTIFIED SAN RAFAEL GENERAL PLAN 2020 FINAL
ENVIRONMENTAL IMPACT REPORT (FEIR) (SLIM 2003052031) PREPARED FOR
GENERAL PLAN ANIENDMENT GPA14-001
(HOUSING ELEMENT UPDATI_- 2015-2023)
The City Council of the City of San Rafael finds and determines that:
WfIEREAS, on November 15, 2004, the San Rafael City Council adopted Resolution
No. 11004, certifying the San Rafael General Plan 2020 Final Environmental Impact Report
(General Plan 2020 FEIR. The General Plan 2020 FEIR is comprised of the following:
r Draft EIR prepared by Nichol~-Berinan Environmental Consultants, February 2004:
r San Rafael General Plan 2020 Background Report prepared by the City of San Rafael,
April 2001 and updated ALILUst 2003;
i Response to Comments to I)raft HR prepared by Nichols -Berman Environmental
Consultants, August 2004: and
WIIF.REAS, the FEIR assessed the physical environmental impacts caused by
implementation of the San Rafael General Plan 2020. The General Plan 2020 FEIR concludes
that many of the significant environmental effects can be substantially lessened through adoption
of feasible nwivation measures and that some of these effects Would remain significant and
unavoidable despite the adoption of all feasible mitigation measure,. The certification of the
General Plan 2020 FEIR was supported by the following findings:
I. The FF.IR for the General Plan 2020 has been completed in compliance �t ith CEQA;
2. The FEIR is legally sufficient, not only for approval of General Plan 2020, but for all
subsequent actions such as Rez.oning.s. Pre -zonings, Annexations and revisions to the San
Rafael 1lunicipal Code and regulation~ as necessary to implement the provisions of the
General Plan 2020;
;. The FEIR reflects the independent judgment of the City of San Rafael and the City
Council of the City of San Rafael: and
WHEREAS, subsequent to certifying the General Plan 2020 FEIR, on November 15,
2004, the San Rafael City Council adopted Resolution No. 11665 adopting the San Rafael
General Plan 2020. The adoption of the San Rafael General Plan 2020 was supported by CEQA
Findings of Fact and a Statement of Overriding Consideration (Appendix C to Resolution 11665)
and approval of a Mitigation Monitoring and Reporting Program (MMRP. Appendix B to
Resolution 11665): and
WHEREAS, since 2004, the San Rafael General Plan 2020 has been amended numerous
times. In processing and adopting subsequent amendments, the City has relied on use of the
General Plan 2020 FEIR for environmental review and clearance. In 2009, the City prepared and
adopted an Addendum to the General Plan 2020 FEIR (Addendum No. 1), which assessed a
General Plan Amendment to change the Plan -adopted traffic level of service (LOS) standard at
the intersection of 3r1 and Union Streets; and
1
WHEREAS, in 2011, the City of San Rafael initiated a General Plan Amendment
(GPA l 1-001) which consisted of 1) amending the Housing Element for 2009-2014, 2)
incorporating a new Sustainability Element, 3) Amending Conservation Element Policy CON -3,
and 4) eliminating the Project Selection Process (PSP). The Addendum to the General Plan 2020
FEIR (Addendum No.2) encompassed these policies and actions; and
WHEREAS., in 2014, the City of San Rafael initiated a General Plan Amendment
(GPA ] 4-001) to update the Housing Element for the 2015-2023 planning period, requiring
Addendum No.3 to the General Plan 2020 FEIR; and
WHEREAS, as required by the California Environmental Quality Act (CEQA)
Guidelines, General Plan Amendment GPA 14-001 is defined as a `project' and is therefore
subject to environmental review. Given the components and scope of this project, it was
determined that "tiering" from the General Plan 2020 FEIR is appropriate and consistent with the
CEQA Guidelines Section 15152 in that:
1. The project and its environmental topic areas are broadly covered and analyzed in the
General Plan 2020 FEIR.
2. The project proposes a General Plan Amendment that is not site-specific or project -
specific; it addresses amendments to current policies that are applicable to the entire San
Rafael Planning Area. The level of detail contained in this tier need not be greater than
the program, plan or policy being analyzed.
WHEREAS, to further support "tierinL," from the General Plan 2020 FEIR, the Initial
Study has been prepared utili/.ing the most current CEQA Guidelines environmental checklist and
considered the following factors that constitute the "baseline" for review:
1. None of the components of the project result in any changes to land use assumptions or
projections currently presented in the San Rafael General Plan 2020 and analyzed in the
General Plan EIR.
2. No changes are proposed to land use designations or their respective density and intensity
parameters, nor are any changes proposed to adopted land use designations for individual
sites/properties.
3. The project proposes no changes to circulation (transportation/traffic) projections,
policies or implementing programs that would result in changes to level of service
conditions at intersections or along arterials.
WHEREAS, in preparing the Initial Study, the project was reviewed against impacts
identified and mitigation measures included in the certified General Plan 2020 FEIR (2004). The
purpose of this review was to determine if the project would result in: new significant impacts: an
increase in the severity of impacts: or new or expanded mitigation measures from those analyzed
and determined in the General Plan EIR; and
WHEREAS, the project and the findings of the Initial Study were assessed to determine
whether an Addendum to the EIR, Supplemental EIR or Subsequent EIR would be appropriate to
address environmental review for General Plan Amendment GPA14-001. Public Resources Code
Section 21166 and CEQA Guidelines Section 15162 set forth limited situations in which a
Supplemental EIR or Subsequent EIR is required once an FEIR has been certified. Further.
CEQA Guidelines Section 15164 provides for preparation of an Addendum EIR if no
Supplemental EIR or Subsequent EIR is required; and
WHEREAS, as demonstrated in the preparation of an Initial Study and comparing the
project activities and actions against the impacts identified and mitigation measures included in
the General Plan 2020 FEIR, none of the conditions analyzed under the General Plan 2020 FEIR
have changed, nor does the proposed project meet the criteria for preparing a Subsequent EIR or
Supplemental EIR. Further, the project will not result in one or more significant effects not
discussed in the General Plan EIR, nor does the project create substantially more severe
significant effects than previously examined in the General Plan EIR. Therefore, the Initial Study
supports and recommends an Addendum versus the preparation of a Subsequent EIR or
Supplemental EIR. As a result, an addendum to the certified General Plan 2020 FEIR
(Addendum) was prepared; and
WHEREAS, on November 14, 2014, Addendum (No. 3) to the San Rafael General Plan
2020 FEIR was prepared for General Plan Amendment GPAl4-001; and
WHEREAS, on December 9, 2014, the Planning Commission reviewed and considered
Addendum No. 3 for General Plan Amendment GPA14-001, alone, with the previously certified
General Plan 2020 FEIR and all applicable mitigation measures therein. On a 6-0-1 vote
(Commissioner Schafer absent), the Planning Commission adopted Resolution 1408
recommending to the City Council the adoption of EIR Addendum No. 3; and
WHEREAS, on January 5, 2015, the City Council reviewed and considered the
Addendum No. 3 for General Plan Amendment GPA14-001, along with the previously certified
General Plan FEIR and all applicable mitigation measures therein; and
WHEREAS, the custodian of documents, which constitute the record of proceedings
upon which this decision is based, is the Community Development Department.
NOW, THEREFORE, BE IT RESOLVED, that the City Council adopts the
Addendum No. 3 to San Rafael General Plan 2020 FEIR for the General Plan Amendment
GPAl4-001 based on the following findings, and hereby reaffirms the findings made by the City
in adopting Resolution No. 11664 (listed above) certifying the General Plan 2020 FEIR:
CEQA Section 21166 and its corresponding CEQA Guidelines Sections 15162 and
15163, provide that once an EIR has been prepared, no subsequent or supplemental EIR
shall be required by the lead agency unless: (a) substantial changes are proposed in the
project, requiring major revisions in the EIR due to the involvement of new significant
environmental effects or a substantial increase in the severity of previously identified
significant effects; (b) substantial changes arise in the circumstances of the project's
undertaking, requiring major revisions in the EIR due to the involvement of new
significant environmental effects or a substantial increase in the severity of previously
identified significant effects; or (c) new information, which was not known and could not
have been known at the time the EIR was certified, shows any of the following:
The project will have one or more significant effects not discussed in the previous
EIR;
Significant effects previously examined will be substantially more severe than shown
in the previous EIR;
Mitigation measures or alternatives previously found not to be feasible would in fact
be feasible, and would substantially reduce one or more significant effects of the
project, but the project proponents decline to adopt the mitigation measure or
alternative; or
i Mitigation measures or alternatives which are considerably different from those
analyzed in the previous EIR would substantially reduce one or more significant
effects on the environment, but the project proponents decline the mitigation measure
or alternative.
2. CEQA Guidelines Section 15t64(a) provides that a lead agency shall prepare an
Addendum to a previously certified General Plan 2020 FEIR if some changes or
additions to the certified EIR are necessary but none of the conditions calling for the
preparation of a supplemental EIR have occurred. Based on the analysis and
documentation in Addendum No. 3 and the supportive Initial Study environmental
checklist prepared for the proposed project, none of the situations described in CEQA
Section 21166 and CEQA Guidelines Sections 15t62 and 15163 apply here. Based on
the results of the supportive Initial Study environmental checklist, the City has concluded
that the proposed project would not result in new significant adverse impacts nor an
increase in the severity of impacts identified and studied in the certified General Plan
2020 FEIR. None of the conditions requiring a supplemental or subsequent EIR exists
and the Addendum has been prepared in compliance with CEQA.
3. The Addendum has been prepared in accordance with CEQA, the CEQA Guidelines, and
the provisions of the City of San Rafael Environmental Assessment Procedures Manual.
4. The Addendum has been presented to the Planning Commission and City Council, who
have reviewed and considered the information in the Addendum and the certified General
Plan 2020 FEIR prior to approving the Project Approvals.
5. The Addendum No. 3 and the certified General Plan 2020 FEIR reflect the City's
independent judgment and analysis.
The foregoing resolution was adopted at a regular meeting of the San Rafael City Council held on
the 5th day of January 2015.
AYES: COUNCILMEMBERS: Bushey, Colin, Gamblin, McCullough, and Mayor Phillips
NOES: COUNCILMEMBERS:
ABSENT: COUNCILMEMBERS:
HUEUpdate.CCreso CEQA 1 5 15 (Adopted)
f -/
ESTHER C. BEIRNE, City Clerk
4