HomeMy WebLinkAboutCC Resolution 11971 (Village Loch Lomond Project)RESOLUTION NO. 11971
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN RAFAEL
AUTHORIZING THE INTERIM CITY MANAGER TO EXECUTE A SECOND
AMENDMENT TO THE AGREEMENT FOR PROFESSIONAL PLANNING SERVICES
WITH PAUL A. JENSEN FOR SERVICES AS PROJECT PLANNER FOR "THE
VILLAGE AT LOCH LOMOND MARINA" PROJECT, INCREASING THE BUDGET
FOR SERVICES
(Original Agreement Term: March 22, 2005 through March 21, 2007, with an amended budget
not to exceed $134,007.50)
WHEREAS, on March 21, 2005 the City Council authorized the City Manager to execute a
Professional Planning Services Agreement with Paul A. Jensen, AICP (Consultant) for services as project
planner for "The Village at Loch Lomond Marina" project, with a maximum budget amount of
$40,375.00; and
WHEREAS, on December 19, 2005 the City Council authorized the Interim City Manager to
execute a First Amendment to the March 21, 2005 Agreement, increasing the project budget by
$40,375.00 to a new maximum budget amount of $80,750.00; and
WHEREAS, as outlined in his June 1, 2006 request for a budget amendment, the Consultant
indicates that the original project budget is inadequate to cover charges for his services, as the project has
been subject to delays and the requirement for additional studies and analyses that were not anticipated in
the original budget and are beyond the control of the Consultant; and
WHEREAS, all costs associated with the Consultant's services as project planner will be
recouped from application and permit processing fees collected from the project developer during the
course of the development review process for the project.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of San Rafael does
hereby authorize the Interim City Manager to execute, on behalf of the City of San Rafael, a "Second
Amendment to Agreement for Professional Planning Services" with Paul A. Jensen, AICP, per his June
1, 2006 request for a budget amendment.
I, JEANNE M. LEONCINI, Clerk of the City of San Rafael, hereby certify that the foregoing Resolution
was duly and regularly introduced and adopted at a regular meeting of the City Council of said City held
on Monday, the 19th day of June, 2006 by the following vote, to wit:
AYES: COUNCILMEMBERS: Cohen, Heller, Miller and Mayor Boro
NOES: COUNCILMEMBERS: None
ABSENT: COUNCILMEMBERS: Phi 11 i p
ii..
JEAXNt M. LEONCINI, City Clerk
SECOND AMENDMENT TO AGREEMENT FOR
PROFESSIONAL PLANNING SERVICES
This second amendment to the Agreement for Professional Planning Services is made and
entered into this 19th day of June, 2006, by and between the CITY OF SAN RAFAEL (hereinafter
"CITY"), and PAUL A. JENSEN, AICP (hereinafter "CONTRACTOR").
RECITALS
WHEREAS, the CITY and CONTRACTOR executed an Agreement for Professional
Planning Services regarding project oversight of responsibilities related to the "The Village at Loch
Lomond Marina" development project on March 21, 2005 with an approved budget of $40,375.00,
with the Agreement term expiring on March 21, 2007, and
WHEREAS, on December 19, 2005, the CITY and CONTRACTOR executed a First
Amendment to the Agreement for Professional Planning services, increasing the approved budget
from $40,375.00 to $80,750.00, and
WHEREAS, the previously approved amended budget of $80,750.00 for professional
planning services is inadequate to cover the costs for CONTRACTOR's services, due to project
delays and the need for expanded studies and analysis beyond CONTRACTOR's control.
AGREEMENT
NOW, THEREFORE, the parties hereby agree to a second amendment to the original
Professional Services Agreement of March 21, 2005, as follows:
1. COMPENSATION
For full performance of the services described herein by CONTRACTOR, CITY shall pay
CONTRACTOR an hourly rate of $115.00 per hour. The billing amounts authorized under
this agreement shall not exceed $134,007.50.
Payment will be made monthly upon receipt by PROJECT MANAGER of itemized
invoices submitted by CONTRACTOR.
All other terms outlined in the March 21, 2005 Professional Services Agreement between
the CITY and CONTRACTOR are unchanged, and shall remain in full force and effect.
06/19/06 ]
Y
U ply
IN WITNESS WHEREOF, the parties have executed this Agreement as of the day, month
and year first above written.
CITY OF SAN RAFAEL
't, t') &4
RDHOFF, InteritCianager
ATTEST:
4.
N
ANNE M. LEOIlVI, City Clerk
.y Attorney
06/12/06 2
CONTRACTOR
By:od&z Q
Name: Paul A. Jens?-1911�
Title: Sole Proprietor
PAUL A. JENSEN, AICP
Policy/Environmental Planning and Processing
77 Mark Drive, Suite 32 San Rafael, California 94903
(4151479-9438 FAX (415( 472-3187
June 1, 2006
Bill Meeker, Principal Planner
Community Development Department
City of San Rafael
1400 Fifth Avenue
P.O. Box 151560
San Rafael, CA 94915-1560
Subject: Loch Lomond Marina Development, San Rafael; budget amendment
to professional services agreement (Job No. 244)
Dear Mr. Meeker:
In March 2005, the City of San Rafael approved a Professional Services Agreement,
which authorized my contract planning services for managing the Village at Loch
Lomond Marina project. As outlined in my letter to you dated February 21, 2005, the
services agreement covers project planning and management through the all processing
phases of this project. The budget for this service was set at $40,375.00. In December
2005, a budget amendment was proposed and authorized, establishing a new, not -to -
exceed budget amount of $80,750.00.
The project is approximately 50% through the review process. The next major milestone
is the completion of the Final Environmental Impact Report, which is scheduled to be
completed this summer. When the services agreement was approved, it was expected
that this review process would be completed by the end of 2005. However, there have
been a number of delays as a result of additional studies commissioned by the project
sponsor and/or required of the EIR consultant. It is not expected that the project review
process to be completed until fall 2006. The delays in the process and the need for
expanded study have caused me to exhaust much of my current service budget. Given
the high profile nature of this project, the pace and extended study that has been
experienced to date is expected to continue.
As of this date, there is a remaining budget of $13,442.50 under my current services
agreement. As we have yet to complete the environmental review process or analysis
of project merits, I respectfully request an amendment to my services budget at an
updated hourly billing rate of $115.00 per hour as follows:
➢ Amend Phase II services (Environmental Review Process) for an additional 130
hours.
Bill Meeker, Principal Panner
May 22, 2006
Page 2
➢ Add a new Phase II -A to incorporate a budget of 85 hours for completing
additional studies and tasks related to dry dock boat storage, grocery store
market study and parking (Planning Commission study sessions).
➢ Amend Phase III services (Project Merits Review) to 280 hours.
➢ Amend Phase IV (Attendance at Public Hearings and Meetings) to 70.
➢ Retain Phase V (Post Action Processing) at 15 hours.
Attached Exhibit A provides a breakdown of the tasks and services. The total for this
amended budget is an additional $53,257.50, less the remaining budget under the
current agreement.
Thank you for considering this budget amendment to my services agreement. If you
have any questions, please feel free to contact me at 415.479.9438 or e-mail at
iensenaicr)(cDaol.com.
Sincerely,
Paul A. Jensen, AICP
C:/Ich1mnd.prps13
EXHIBIT A
CONTRACT PLANNING SERVICES BUDGET AMENDMENT NO.2
June 1, 2006
TASKISERVICE I ESTIMATED HOURS I
Phase H Services —Environmental Review Process
Meetings with RBF Consulting and City Staff
30
IAssist RBF Consulting in Preparing FEIR/Responses to Comments
40
Coordinate distribution of ADFEIR/Response to Comments for City staff review
20
Review ADFEIR/Response to Comments
30
Coordinate distribution of FEIR/Response to Comments
10
Phase II Services — Total Hours
130
Phase II -A Services — Special Studies and Tasks
15
Complete additional dry dock boat storage surveys and research
20
Prepare Summary of dry dock boat storage
10
Prepare notices and staff report for Planning Commission Workshop - Market Study
30
Attend Planning Commission Workshop — Market Study
5
Prepare notices and staff report for Planning Commission Workshop - Parking
15
Attend Planning Commission Workshop - Parking
5
Phase III -A Services — Total Hours
85
Phase III Services — Proiect Merits Review
Complete review of project for consistency with San Rafael General Plan 2020
40
Coordinate and review comment and conditions from City departments, services, etc.
20
Prepare draft findings including CEQA findings; coordinate review by City Attorney
1 50
Prepare draft conditions of approval and MMRP
75
Prepare staff reports - Design Review Board, Planning Commission & City Council
80
Prepare and coordinate distribution of public hearing notices; posting notices
15
Phase III Service — Total Hours
280
Phase IV Services — Preparation and Attendance at Public Hearings
Design Review Board Meeting (2 meetings)
20
Planning Commission (3 meetings)
30
City Council (2 meetings)
20
Phase IV Services — Total Hours
70
Phase V Services — Post Action Processing
Ordinances and Resolutions
5
IFinalize
Prepare and file Notice of Determination
15
Close out City files
15
Phase V Services — Total Hours
15
Total Hours for Proposed Budget Amendment
580
Total Budget Amendment (aD, $115.00 per hour I $66,700.00
Remaining Budget Amount Under Current Contract Agreement [$13,442.50]
Total Additional Budget = $53,257.50