HomeMy WebLinkAboutPW Francisco Boulevard East Sidewalk Improvements PPTFrancisco Blvd East Sidewalk Improvements
February 18, 2020
www.cityofsanrafael.org/DPW Slide 1
~RA/:..q "i,tf~ (C'< DEPARTMENT OF
1 l PUBLIC WORKS ~ a'
r,,.,.,..W•n•"'""'"
Francisco Blvd East Sidewalk Improvements
February 18, 2020
www.cityofsanrafael.org/DPW Slide 2
Project History and Limits of
WorkPHASE 2 -GRAND AVE
COMPLETED 2019
PROPOSED COMPLETION
SPRING 2021
-PHASE 1 (Ballam Blvd to Vivian St) -Sidewalk widening completed by Caltrans in 2010
-PHASE 2 (Grand Ave) -Sidewalk widening and pedestrian bridge completed in 2019
-PHASE 3 (Vivian St to Grand Ave) -Sidewalk widening with completion in 2021
DEPARTMENT OF
PUBLIC WORKS
Francisco Blvd East Sidewalk Improvements
February 18, 2020
www.cityofsanrafael.org/DPW Slide 3
Sidewalk Widening Concept
Before After
DEPARTMENT OF
PUBLIC WORKS
-_f-. =="_\ _____ _
----------
Francisco Blvd East Sidewalk Improvements
February 18, 2020
www.cityofsanrafael.org/DPW Slide 4
Potential Approach
-DAY-TIME WORK
-N IGHT-T IME WORK
-DETOUR (NORTHBOUND V IA FRONT STREET}
DEPARTMENT OF
PUBLIC WORKS
Francisco Blvd East Sidewalk Improvements
February 18, 2020
www.cityofsanrafael.org/DPW Slide 5
Project Impacts
–Transportation
•Traffic
•Temporary Closure/Relocation of one bus stop
–Environmental
•Noise (especially for night work)
Francisco Blvd East Sidewalk Improvements
February 18, 2020
www.cityofsanrafael.org/DPW Slide 6
Next Steps
–March 24th –Contractor Bids Due
–April 20th –Return to Council with a
Recommendation to Award a Construction
Contract
–June 2020 –Break Ground
Francisco Blvd East Sidewalk Improvements
February 18, 2020
www.cityofsanrafael.org/DPW Slide 7
Questions/Comments