THIRD STREET SAFETY PROJECT
CITY COUNCIL MEETING
Third Street Project
Project Limits
E STREETA STREETLINDAROC STREETB STREETD STREETLINCOLNSHAVERG STREETWEST STREETEAST STREETSafety Project: Federal & local funds
(Grand Ave to Lindaro St)
Rehabilitation Project: TAM & local funds
3rd Street from just east of Union St to 2nd St
2nd Street from West St to Shaver St
Third Street Project
Staff is asking the City Council to:
1.Award the Construction Contract to the lowest responsive and responsible bidder:Ghilotti
Bros.Inc.
2.Approve and authorize the execution of a professional services agreement with Park
Engineering for construction management,material testing,and inspection services.
3.Approve and authorize an amendment to the professional services agreement with Kimley
Horn to perform construction support services.
Tonight’s Objectives
Third Street Project
1.Improve safety for all users
2.Upgrade traffic signals and provide safety lighting
3.Improve pedestrian crossings and repair
sidewalks
4.Repair drainage
5.Expand and connect the communications network
6.Develop an economically viable project
Project Goals
Third Street Project
Lindaro/Lootens Intersection
Third Street Project
Lindaro/Lootens Intersection
THIRD STREET
WALGREENS
Third Street Project
Grand Avenue Intersection
Third Street Project
Construction Update
1.Construction (March 2022 to July 2023)
•Both projects
2.Lane closures during off peak periods
•Westbound:6 am to 3 pm
•Eastbound (Second Street):9 am to 6 pm
3.Miramar Sewer work:full closure 7am to 6pm
4.Night work:6pm to 6am
Third Street Project
Nightwork Hours
1.Night work:6pm to 6am
•Utility work east of Lincoln (Water line:Mid May to July 2022,Sewer TBD:3 weeks)
•Loudest operations from 6pm to 10pm (sawcutting,jack hammering,potholing)
•Paving and striping (Spring/Summer 2023)
**Current nightwork proposal.Times may vary
Third Street Project
Project Funding
Funding Source Funding Amount
Gas Tax Fund #206 $980,499
Traffic Mitigation Fund #246 $523,000
Federal HSIP grant $1,295,000
Total $2,798,499
Third Street Project
Additional Information
April Miller, P.E.
Assistant Director
April.Miller@cityofsanrafael.org
415-485-3409
www.cityofsanrafael.org/third-st-rehab/ Weekly emails: ThirdStreet@cityofsanrafael.org
Third Street Project
Thank you
Questions & Comments