SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works
Prepared by: "`� 'ty Manager Approva X'
Director of Public Works (HY)
File No.: 18.10.17
SUBJECT: ADOPT PLANS AND SPECIFICATIONS FOR CONSTRUCTION OF THE
LIFELINE TRANSPORTATION PROGRAM (LTP) CANAL NEIGHBORHOOD
PEDESTRIAN AND TRANSIT ACCESS AND SAFETY IMPROVEMENTS
PROJECT PHASE II, CITY PROJECT NO. 11174, AND AUTHORIZE THE CITY
CLERK TO CALL FOR BIDS.
RECOMMENDATION: Adopt Plans and Specifications for the project.
4:10R&IIIN"I
The Lifeline Transportation Program (LTP) is administered by the Metropolitan Transportation
Commission (MTC) and is a state funded program that supports projects to improve mobility and
accessibility for residents in low-income communities. Transportation Authority of Marin (TAM), as the
Congestion Management Agency for Marin County, administers the Marin County component of the
regional program aimed at nine counties in the Bay Area.
In March 2007, the City applied for and received LTP funding for Phase I of the Canal Neighborhood
Transit and Pedestrian Access and Safety Improvements. Phase I, in which construction was completed in
June 2011, consisted of new sidewalk and transit improvements at four intersections on Canal Street
between Larkspur Street and Sonoma Street.
In October 2008, staff submitted a grant application for the Canal Neighborhood Transit and Pedestrian
Access and Safety Improvement Phase IL As the Golden Gate Bridge, Highway and Transportation
District (GGBHTD) is the only organization within the County of Marin that is eligible to receive LTP
funds, on February 22, 2011 the City Council approved Resolution No. 13112 authorizing the Public
Works Director to execute a Memorandum of Understanding (MOU) with GGBHTD, which allows the
City to receive the grant funds for the design and construction of the Phase 11 improvements.
In December 2011, the City Council approved Resolution No. 13273 authorizing the Public Works
Director to enter into a professional services agreement with Gannett Fleming for design and construction
support services of the proposed improvements. The plans and specifications have been approved by the
City Engineer and are available for review.
FOR CITY CLERK ONLY
File No.: -y t -
Council Meeting: P/
Disposition: '�i
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
ANALYSIS: Adoption of the project plans and specifications is necessary for the plans to go out to bid
and the construction of the project to begin. Construction is anticipated to begin in June 2013.
FISCAL IMPACT: The engineer's estimate for construction of the project is $480,000. The exact cost
for construction cannot be determined until bids have been received. The project sponsor, GGBHTD,
requires four percent of the grant funding to administer the State Transit Agency (STA) Proposition IB
funding. The STA Proposition 1B funding requires a local match of $155,000. Document reproduction
and available construction funds total $625,035.90.
"t, WIFUR111
Project Funding Sources Amount
Lifeline Transportation Program Grant $644,800.00
City of San Rafael Matching Funds $155,000.00
Total Available Funds 799,800.00
EXPENSES
Sponsor Project Adminitrat6n ;
GGBHTD Project Administration
(4% of UP Grant)
$25,792.00
Sponsor Project Administration Sub Total
$25,792.00
Design and Public Outreach Services
Gannett Fleming Design Services Contract
$148,703.00
Spanish Translation Services
$269.10
Design and Public Outreach Sub Total
$148,972.10
Construction Costs
Estimated City Project Management and Construction
Engineering (10%)
$79,980.00
Engineer's Estimate
$480,000.00
Construction Contingency (Approximately 10%)
$48,055.90
Allowances (Bus Shelter and Fire Hydrant Relocation)
$14,000.00
Document Reproduction
$3,000.00
Construction Sub Total
$625,035.90
Total Project Cost
$799,800.00
ACTION REQURED: Adopt Plans and Specifications for the Canal Neighborhood Transit and
Pedestrian Access and Safety Improvement Phase II Project, City Project No. 11174 on file with the City
Clerk, and authorize the City Clerk to call for bids.
CITY OF SAN RAFAEL 6
. . . , . . . • , 6 .
INSTRUCTIONS: USE THIS FORM WITH EACH SUBMITTAL OF A CONTRACT, AGREEMENT,
ORDINANCE OR RESOLUTION BEFORE APPROVAL BY COUNCIL / AGENCY.
SRRA / SRCC AGENDA ITEM NO.
DATE OF MEETING: April 15, 2013
FROM: Kevin McGowan
DEPARTMENT: Public Works
DATE: April 3, 2013
TITLE OF DOCUMENT:
ADOPT PLANS AND SPECIFICATIONS FOR CONSTRUCTION OF THE LIFELINE TRANSPORTATION PROGRAM
(LTP) CANAL NEIGHBORHOOD PEDESTRIAN AND TRANSIT ACCESS AND SAFETY IMPROVEMENTS PROJECT
PHASE 11, CITY PROJECT NO. 11174, AND AUTHORIZE THE CITY CLERK TO CALL FOR BIDS
Department Head (signature)
*** *** *** *** *** *** *** *** *** *** *** *** *** *** *** ***